Top Banner
KANSAS STATE BRIDGE DESIGN WORKSHOP OCTOBER 9, 2015 Mark E. Hoppe, P.E. BSGS OFFICE UPDATE
20

BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

Aug 21, 2018

Download

Documents

NguyễnNhân
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

KANSAS STATE BRIDGE DESIGN WORKSHOP

OCTOBER 9, 2015

Mark E. Hoppe, P.E.

BSGS OFFICE UPDATE

Page 2: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BSGS OFFICE UPDATE

PERSONNEL CHANGES

NEW LOCATIONS

T-WORKS

CURRENT INITIATIVES & ISSUES

3D CADD

Asbestos Abatement of Bridges

FHWA Revision of Design Standard Specifications

Page 3: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BSGS PERSONNEL CHANGES

STAFF LOSSES

STAFF IN NEW POSITIONS

Page 4: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BUREAU CHIEF, BSGS

Loren Risch

Retired in April

35+ years of experience

Page 5: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

ENGINEERING ASSOCIATE

Brandy Sutherland

Chris Meyer’s Squad

Returned to Transportation

Planning

Page 6: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

ET SPECIALIST

Clem Boos

Bridge Inspection

Retired in March

Started at KDOT in 1987

Page 7: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

ET SPECIALIST

Dee Jay Estes

Brad Rognlie’s Squad

Retired in March

Started at KDOT in 1970

Page 8: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

ET SENIOR

Corey Jennings

Mark Hoppe’s Squad

Moved to Nebraska

Started at KDOT in 1992

Page 9: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BUREAU CHIEF, BSGS

Mark Hoppe

Started at KDOT in 1989

26+ years of experience in

the Bridge Section.

Page 10: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

SENIOR BRIDGE SQUAD LEADER

Shawn Schwensen

Started with KDOT in 1995

20+ years of experience in

the Bridge Section.

Page 11: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BRIDGE SQUAD LEADER

Kelly Carlton

Started at KDOT in 2006

8+ years of experience in

the Bridge Section.

Page 12: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

BRIDGE DESIGN SQUAD CHANGESCalvin Reed

Brad Rognlie

Mike Orth

Shawn Schwensen

Jeff Ruby

Michelle LaRoche

Charlene Morris

Colby Farlow

Mark Hurt

Travis Malone

Kelly Carlton

Steve Burnett

Dan Wadley

Andrew Spencer

Chris Meyer

Karen Peterson

Dominique Shannon

Peter Tobaben

John Jones

Page 13: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

NEW OFFICE LOCATIONS

Bridge Management moving to the 13th Floor of the ESOB.

Bridge Inspection moving to the 7th Floor of the ESOB

Lawrence Geology Office

Moving to the Geology Shop in Topeka

Page 14: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

T-WORKS UPDATE Currently almost 65% of T-Works has been completed since the

start of the program.

We have a pool of prioritized projects that are currently under development. Multiple factors, including emerging needs and available funding, play a part in determining which will be approved for future construction.

Similarly, we have a pool of prioritized bridge projects that are currently under development. Multiple factors, including emerging needs, progressing bridge condition and available funding, play a part in determining which will be approved for future construction.

http://kdotapp.ksdot.org/TWorks/About

Page 15: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

GATEWAY I-435/I-35

Page 16: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

GATEWAY K-10E/I-435N

Page 17: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

POST T-WORKS

Local Consult

Meetings held last fall.

Needs will continue to be identified through next year with

additional Local Consult Meetings in late 2016.

Development of a new program will begin in the near

future.

Initial plans are to develop a multiyear program to follow

the completion of T-Works.

Page 18: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

CURRENT INITIATIVES - 3D CADD

Transition to 3D Modeling to start later this year.

Phase 1 - 3D Analysis and Implementation Plan.

Funding has be secured and this phase is scheduled to be completed Spring

2016.

Additional Phases to follow dependent on funding with full

implementation within 2-3 years after completion of Phase 1.

Future BSGS direction could include.

Modeling the bridge structure and bridge berms for inclusion in the

overall 3D project model.

The occasional development of a 3D PDF detail model to clarify

complex 2D plan details for fabricators and field construction staff.

Page 19: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

CURRENT ISSUES - ASBESTOS

EPA issued a regulatory interpretation of the Asbestos

NESHAP as it applies to concrete bridges in 2014.

Applies to the demolition, reconstruction, rehabilitation, or

deck repairs of existing span bridges.

Asbestos containing materials (ACM) is defined as material

containing more than 1% asbestos.

Bridge concrete is considered Category II non-friable AMC if it

contains more than one percent asbestos.

Special Provision and testing protocol currently being

developed.

Page 20: BRIDGE OFFICE UPDATE - cpb-us-e1.wpmucdn.com · Will replace the current reference to AASHTO LRFD Bridge design Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

CURRENT ISSUES – 23 CFR 625

FHWA requested comments in June on a proposed revision to

design standards and standard specification that applies to work

on the National Highway System. Comments are currently

under review.

Will replace the current reference to AASHTO LRFD Bridge design

Specification, First Edition 1994 with the AASHTO LRFD Bridge Design

Specification, 7th Edition, 2014.

Will replace the current reference to Standard Specification for Structural

Supports for Highway Signs, Luminaries and Traffic Signals, 1994 with the

Standard Specification for Structural Supports for Highway Signs,

Luminaries and Traffic Signals, 6th Edition, 2013.

Currently reviewing BSGS standards.