KOP PERUSAHAAN
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN : REHABILITASI BANGUNAN GEDUNG NEGARA PADA BALINGTAN PATI
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO. URAIAN PEKERJAAN B I A Y A
I REHABILITASI BANGUNAN GEDUNG NEGARA
a. RENOVASI MESS 1 LANTAI Rp.
b. RENOVASI RUANG PERTEMUAN GEDUNG PENELITI Rp.
c. RENOVASI BANGUNAN KANTOR ( R. MAKAN MESS ) Rp.
d. RENOVASI RUANG PERTEMUAN GEDUNG KEBUN PERCOBAAN Rp.
e. RENOVASI PAGAR DEPAN KP Rp.
f. LANDSCAPING ( TAMAN AIR GEDUNG UTAMA ) Rp.
g. REHABILITASI POS SATPAM Rp.
Rp.
JUMLAH TOTAL Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
Page 2
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 2/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI MESS 1 LANTAI
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN
1 Uitzet / bouwplank 128.00 m'
2 Barak Kerja 28.00 m2
3 Administrasi & Dokumentasi 1.00 set
4 Listrik & Air Kerja 1.00 set
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Belah & Rolaag 299.42 m3
2 Urugan Tanah Kembali 237.48 m3
3 Urugan Sirtu Dibawah Lantai t : 15cm 80.75 m3
4 Urugan Sirtu Dibawah Pondasi Batu Belah t : 20cm 61.94 m3
5 Urugan Pasir Dibawah Rolaag Batu Belah t : 5cm 0.78 m3
6 Urugan Tanah Dipadatkan utk Peninggian Lantai t : 25cm 134.58 m3
III PEKERJAAN PASANGAN
1 Aanstamping 61.94 m3
2 Pasangan Batu Belah 1 : 6 130.07 m3
3 Pasangan Batu Belah Rolaag 1 : 6 7.80 m34 Pasangan Batu Bata 1: 5 461.14 m2
5 Pasangan Batu Bata 1: 3 120.60 m2
6 Plesteran Dinding 1: 5 922.27 m2
7 Plesteran Dinding Trasraam 1: 3 241.20 m2
8 Plesteran Beton 67.50 m2
9 Plesteran Sudut 1157.94 m'
10 Acian Dinding 1230.97 m2
IV PEKERJAAN BETON BERTULANG
Mutu Beton Struktur K250
Mutu Beton Non Struktur K175
a Sloof
1 Sloof Praktis 12x20 2.93 m3
2 Sloof Struktur 15x30 146 kg/m3 13.03 m3
b Kolom
1 Kolom Praktis 2.76 m3
2 Kolom Type K1 30x30 316 kg/m3 0.72 m3
3 Kolom Type K2 25x30 374 kg/m3 0.60 m34 Kolom Type K3 20x30 189 kg/m3 5.28 m3
5 Kolom Type K4 15x40 195 kg/m3 6.96 m3
6 Kolom Type K5 25x25 118 kg/m3 0.50 m3
c Balok Atap
1 Balok Atap Type B1 25x50 184 kg/m3 1.88 m3
2 Balok Atap Type B2 25x60 232 kg/m3 2.25 m3
3 Balok Atap Type B3 15x30 209 kg/m3 5.04 m3
4 Balok Atap Type B4 15x30 255 kg/m3 6.73 m3
5 Balok Atap Type B5 15x30 255 kg/m3 0.18 m3
6 Balok Atap Type B6 15x30 186 kg/m3 1.62 m3
d Plat Atap
1 Beton Plat Lantai 1 ht : 6cm 32.30 m3
2 Beton Plat Atap ht : 10cm 57.18 m3
3 Beton Plat Level 3.03 m3
e Ringbalk
1 Ringbalk Praktis & Balok Latei 4.89 m3
V PEKERJAAN PLAFON1 Plafond Gypsumboard 9mm rk Hollow Metal GB 299.80 m2
2 Plafond Calsiboard 4.5mm rk Hollow Metal KSB 145.15 m2
3 Plafond Beton Ekspose BE 69.49 m2
4 Polycarbonate Rangka Besi Hollow PC 14.70 m2
5 Plafond Drop Ceiling Gypsumboard 9mm rk Hollow Metal 26.80 m'
6 List Tepi Plafon Gypsum Profil 550.10 m'
Page 3
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 3/20
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
VI PEKERJAAN PINTU & JENDELA
1 Kusen & Pintu Jendela + Ass Terpasang - Type PJ1 8.00 unit
2 Kusen & Pintu Jendela + Ass Terpasang - Type PJ2 1.00 unit
3 Kusen & Pintu + Ass Terpasang - Type P1 9.00 unit
4 Kusen & Pintu + Ass Terpasang - Type P2 3.00 unit
5 Kusen & Pintu UPVC + Ass Terpasang - Type P3 9.00 unit
6 Kusen & Pintu + Ass Terpasang - Type Ps 8.00 unit
7 Kusen & Pintu + Ass Terpasang - Type Pt 8.00 unit
8 Kusen & Pintu + Ass Terpasang - Type P 8.00 unit
9 Kusen & Jendela Loket & Counter + Meja + Ass Terpasang - Type Lk 1.00 unit
10 Kusen & Jendela + Ass Terpasang - Type J1 1.00 unit
11 Kusen & Jendela + Ass Terpasang - Type J2 1.00 unit
12 Grill Besi + Ass Terpasang - Type G1 2.00 unit
13 Grill Besi + Ass Terpasang - Type G2 2.00 unit
14 Grill Besi + Ass Terpasang - Type G3 1.00 unit
15 Grill Besi + Ass Terpasang - Type G4 1.00 unit
16 Grill Besi + Ass Terpasang - Type G5 1.00 unit
17 Grill Besi + Ass Terpasang - Type G6 1.00 unit
18 Grill Besi + Ass Terpasang - Type G7 10.00 unit
19 Kusen + Kaca Sekat Kamar Mandi 10.00 unit
VII PEKERJAAN LANTAI & PELAPIS
1 Granite Tile 60x60 Polished ( A ) 208.80 m2
2 Granite Tile 60x60 Un Polished ( B ) 129.28 m2
3 Granite Tile 60x60 Un Polished Pasang Pola Khusus ( C ) 73.00 m2
4 Border Granite Tile 20x60 ( D ) 5.20 m25 Granite Tile 30x60 Dengan Alur Mesin ( Bevel ) ( E ) 33.00 m2
6 Trap Granite Tile 30x60 Un Polished ( F ) 11.64 m2
7 Keramik 40x40 ( G ) 32.25 m2
8 Keramik 40x40 Texture ( H ) / ( KT ) 89.48 m2
9 Pav ing Type Holland Pasang Model Sirip Ikan + Border Pav ing ( I ) 175.20 m2
10 Keramik Dinding 25x40 ( KD ) 197.35 m2
11 Border Keramik Aksen Warna 25x40 ( BK ) 72.30 m2
11 Plint Lantai Granite Tile 10x60 ( A ) 240.20 m'
12 Plint Lantai Keramik 10x40 ( B ) 75.30 m'
13 Kansteen Beton 72.90 m'
14 Rabat Beton 58.20 m2
15 Plat Beton Bawah Lantai 1 tebal 10cm 58.26 m3
VIII PEKERJAAN CAT-CATAN
1 Pekerjaan Cat Dinding Dalam / Interior 800.13 m2
2 Pekerjaan Cat Dinding Luar / Exterior 430.84 m2
3 Pekerjaan Cat Plafon Gypsumboard, Kalsiboard & Beton Ekspose 527.84 m2
4 Pekerjaan Waterproofing Atap & KM/WC Lantai 2 38.40 m2
IX PEKERJAAN MEKANIKAL & ELEKTRIKAL
a PEKERJAAN LISTRIK
1 Titik lampu dan stop kontak+ konduit 134.00 titik
2 Lampu TL 2x36 armature RM,300 2.00 bh
3 DL .D 175-ESS.18 W 51.00 bh
4 Lampu TL 1x18 armature 8.00 bh
5 Lampu baret 22 W 4.00 bh
6 Exhaust ceilling fan 9.00 bh
7 Stop kontak, 1 p 60.00 bh
8 Saklar tunggal 14.00 bh
9 Saklar ganda 20.00 bh
b PEKERJAAN PANEL
PANEL PP 1
1 Box Panel PP.1 Lt. 1,( 80x60x25cm) 1.00 unit
2 MCCB 50A/10kA/3p 1.00 bh
3 MCB 6A/5kA/1p 5.00 bh
4 MCB 10A/5kA/1p 10.00 bh
5 MCB 16A/6kA/3p 1.00 bh
6 MCB 20A/6kA/3p 1.00 bh
7 Pilot lamp 3.00 bh
8 petanahan/arde 2 Ohm 1.00 ls
9 kabel NYY 4x16 mm2 dari SDP Asrama 6.00 m
10 Kabel try stu 300x50 66.00 m
Page 4
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 4/20
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
PANEL SDP
1 Box Panel SDP.Asrama 1.00 unit
2 MCCB 200A/25kA/3p 1.00 bh
3 MCCB 50A/10kA/3p 2.00 bh
4 MCCB 25A/10kA/3p 2.00 bh
5 MCB 25A/5kA/1p 3.00 bh
6 Pilot lamp 3.00 bh
7 petanahan/arde 2 Ohm 1.00 ls
8 kabelLVTC 3X70mm2+50 mm2 dari MDP2 145.00 m9 Kabel try stu 300x50 30.00 m
PANEL AC
1 Box Panel P.AC.1 Lt. 1,( 70x50x25cm) 1.00 unit
2 MCCB 25A/10kA/3p 1.00 bh
3 MCB 10A/5kA/1p 4.00 bh
4 MCB 16A/5kA/1p 8.00 bh
5 Pilot lamp 3.00 bh
6 petanahan/arde 2 Ohm 1.00 ls
7 Instalasi kabel NYM 3x2.5mm2 19.00 ttk
8 kabel NYY 4x16 mm2 dari SDP Asrama 6.00 m
c PEKERJAAN TATA UDARA
ACSplit Unit lengkap pipa refrigerant,pipa drain
bracket,kabel, bobokan dan testing
1 Wall type (1 pk) 1.00 unit
2 Wall type (1.5 pk) 8.00 unit
d PEKERJAAN TELEPHONE & LAN
1 instalasi kabel telphone utp cat 6 +konduit 8.00 ttk
2 socket telephone,RJ11 8.00 bh
3 pesawat telp. Analog 1.00 bh
4 Instalasi kabel datautp cat6 +konduit 1.00 ttk
5 socket LAN,RJ45 10.00 unit
X PEKERJAA PLUMBING
Instalasi Pipa ,lengkap sleave, penggantung,
dudukan dan testing
1 Pipa Air Bersih PVC-AW ( 10 kg/cm2)
- dia 1.5'' 65.00 m
- dia 1'' 65.00 m
- dia 1/2'' 220.00 ls
- fitting 1.00 bh
- ball valve 1.5'' 1.00 bh
2 Pipa Air Bekas, Air Kotor dan Vent,PVC-AW
- dia 6'' 65.00 m
- dia 4'' 70.00 m
- dia 3'' 110.00 m
- dia 2'' 40.00 m
- fitting 1.00 ls
- CO 4'' 4.00 bh
3 Pompa Transfer/dist ribusi ais listrik otomatis 1.00 unit
H=40m,kap.35 lpm,setara Shimizu PS130BT
4 WLC dan kabel kontrol setara Radar 1.00 unit
5 foot valve 1'' 1.00 bh
6 pipa PVC-AW dia. 1'' dari r.pompa ke tower 30.00 m
7 PAH (Pipa Air Hujan)
- RD (Roof Drain) dia 3'' 16.00 bh
- PVC -AW 3'' 130.00 m
8 Tangki atas kap 3 m3 2.00 bh
9 Ground Tank Kapasitas 24m3 1.00 unit10 Septicktank & Peresapan 2.00 unit
XI PEKERJAAN SANITAIR
1 Kloset Duduk ex TOTO CW 661 JT1/SW 661 JP + Ass Terpasang 9.00 unit
2 Washtafel Gantung ex TOTO LW 230 CJ + assesories terpasang 9.00 unit
Page 5
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 5/20
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
3 Kran Air 9.00 unit
4 Jet Washer 9.00 unit
5 Floor Drain 9.00 unit
6 Kaca Cermin 60x100 9.00 unit
XII PEK. SALURAN KELILING & BAK PENAMPUNG AIR KAP 64 m3
1 Saluran Keliling U30 138.00 m'
2 Bak Kontrol 6.00 bh
3 Galian Tanah 124.36 m34 Urugan Tanah Kembali 33.81 m3
5 Urugan Pasir 3.70 m3
6 Lantai Kerja Beton K100 1.85 m3
7 Balok Beton Tutup - B1 20x35 243 kg/m3 0.29 m3
8 Balok Beton Tutup - B2 20x30 168 kg/m3 1.51 m3
9 Balok Beton Lantai - B3 20x35 243 kg/m3 0.29 m3
10 Balok Beton Lantai - B4 20x30 168 kg/m3 1.51 m3
11 Kolom Beton - 25x25 266 kg/m3 0.90 m3
12 Plat Lantai Beton - tebal 20cm 102 kg/m3 6.89 m3
13 Plat Dinding Beton - tebal 15cm 133 kg/m3 7.44 m3
14 Plat Tutup Beton - tebal 12cm 138 kg/m3 8.06 m3
15 Tutup Lubang Manhole - Plat Besi Stainless Steel 1.00 unit
16 Tangga Baja Mantenance - Pipa dia 1" Stainless Steel 1.00 unit
17 Lapis Waterproofing 80.00 m3
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 6
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 6/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI MESS 1 LANTAI
LOKASI : KABUPATEN PATITAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN TANAH Rp.
III PEKERJAAN PASANGAN Rp.
IV PEKERJAAN BETON BERTULANG Rp.
V PEKERJAAN PLAFON Rp.
VI PEKERJAAN PINTU & JENDELA Rp.
VII PEKERJAAN LANTAI & PELAPIS Rp.
VIII PEKERJAAN CAT-CATAN Rp.
IX PEKERJAAN MEKANIKAL & ELEKTRIKAL Rp.
X PEKERJAA PLUMBING Rp.
XI PEKERJAAN SANITAIR Rp.
XII PEK. SALURAN KELILING & BAK PENAMPUNG AIR KAP 64 m3 Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A
Page 7
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 7/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI RUANG PERTEMUAN GEDUNG PENELITI
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN1 Listrik & Air Kerja 1.00 set
II PEKERJAAN BONGKARAN
1 Bongkar Plafond Existing 41.00 m2
2 Pembersihan dan Buang Puing 1.00 ls
III PEKERJAAN PLAFON
1 Plafond Gypsumboard 9mm rk metal furing full system 41.00 m2
2 List Tepi Plafon Gypsum Profil 28.20 m'
IV PEKERJAAN CAT-CATAN
1 Pekerjaan Cat Plafon Gypsumboard 41.00 m2
V PEKERJAAN ELEKTRIKAL
1 Bongkar dan Pasang Kembali Lampu Existing 1.00 ls
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 8
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 8/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI RUANG PERTEMUAN GEDUNG PENELITI
LOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN BONGKARAN Rp.
III PEKERJAAN PLAFON Rp.
IV PEKERJAAN CAT-CATAN Rp.
V PEKERJAAN ELEKTRIKAL Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)Direktur
NO URAIAN PEKERJAAN H A R G A
Page 9
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 9/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI BANGUNAN KANTOR ( R. MAKAN MESS )
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN
1 Uitzet / bouwplank 59.00 m'
II PEKERJAAN BONGKARAN
1 Bongkaran Bangunan Lama 138.00 m2
2 Pembersihan & Buang Puing Bongkaran 1.00 ls
III PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Belah 49.80 m3
2 Urugan Tanah Kembali 14.15 m3
3 Urugan Pasir Dibawah Lantai 9.88 m3
4 Urugan Sirtu Dibawah Pondasi Batu Belah 9.31 m3
5 Urugan Tanah Dipadatkan untuk Peninggian Lantai 39.51 m3
IV PEKERJAAN PASANGAN
1 Aanstamping 7.45 m3
2 Pasangan Batu Belah 1 : 6 17.67 m3
3 Pasangan Batu Bata 1: 5 97.96 m2
4 Pasangan Batu Bata 1: 3 14.10 m2
5 Plesteran Dinding 1: 5 195.91 m2
6 Plesteran Dinding Trasraam 1: 3 28.20 m2
7 Plesteran Beton 12.00 m2
8 Plesteran Sudut 151.65 m'
9 Acian 120.74 m2
V PEKERJAAN BETON BERTULANG
Mutu Beton Struktur K250
Mutu Beton Non Struktur K175
1 Sloof Praktis 12x20 1.22 m3
2 Kolom Praktis 1.16 m3
3 Kolom Type K1 20x20 1.55 m3
4 Beton Plat Atap KM/WC 0.40 m3
5 Beton Plat Level 0.19 m3
6 Beton Plat Meja Pantry & Washtafel 0.48 m3
7 Ringbalk Praktis & Balok Latei 3.38 m3
V PEKERJAAN BESI
1 Rangka Atap Baja Ringan 194.31 m2
2 Railing Besi Hollow Finish Cat 19.50 m'
VI PEKERJAAN ATAP
1 Penutup Atap Zincalume 194.31 m2
2 Bubungan/Nok Atap Zincalume 19.50 m'
3 Insulation System 194.31 m2
4 Penutup Atap Kanopy Polycarbonat Rangka Hollow 57.02 m2
5 Listplank Atap GRC Termasuk Rangka Finish Cat Exterior 151.20 m2
6 Flashing Atap Zincalume t : 0.4mm 19.20 m'
7 Atap Seng Penutup Belakang Listplank GRC 94.50 m2
8 Talang Atap 41.00 m'
VII PEKERJAAN PLAFON
1 Plafond Gypsumboard 9mm rk metal furing full system 154.16 m2
2 Plafond Calsiboard 4mm rk metal furing full system 7.50 m2
3 Plafond Drop Ceiling Gypsumboard 9mm rk metal furing full system 20.56 m'
4 List Tepi Plafon Gypsum Profil 118.50 m'
Page 10
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 10/20
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
VIII PEKERJAAN PINTU & JENDELA
1 Kusen & Pintu Jendela + Ass Terpasang - Type PJ1 1.00 unit
2 Kusen & Pintu + Ass Terpasang - Type P1 1.00 unit
3 Kusen & Pintu + Ass Terpasang - Type P2 1.00 unit
4 Kusen & Pintu + Ass Terpasang - Type P2' 1.00 unit
5 Kusen & Pintu UPVC + Ass Terpasang - Type P3 2.00 unit
6 Kusen & Pintu Besi + Ass Terpasang - Type P4 1.00 unit
7 Kusen & Pintu Besi + Ass Terpasang - Type P5 1.00 unit
8 Kusen & Jendela + Ass Terpasang - Type J1 1.00 unit
9 Kusen & Jendela + Ass Terpasang - Type J2 2.00 unit
10 Kusen & Jendela + Ass Terpasang - Type BV1 2.00 unit
11 Kusen & Jendela + Ass Terpasang - Type BV2 1.00 unit
IX PEKERJAAN PELAPIS LANTAI & DINDING
1 Rabat Beton Bawah Lantai 197.13 m2
2 Keramik 40x40 Polished 182.16 m2
3 Keramik 40x40 Motif kayu 7.47 m2
4 Keramik 40x40 Texture 7.50 m2
5 Keramik 25x40 Meja Pantry 6.37 m2
6 Keramik Dinding 25x40 56.18 m2
7 Border Keramik Aksen Warna 25x40 8.50 m2
8 Plint Lantai Keramik 10x40 17.40 m'
9 Plint Lantai Granit Tile 10x60 39.80 m'
10 Batu Andesit 44.97 m2
11 Rabat Beton 8.33 m3
X PEKERJAAN CAT-CATAN
1 Pekerjaan Cat Dinding Dalam / Interior 308.69 m2
2 Pekerjaan Cat Dinding Luar / Exterior 154.75 m2
3 Pekerjaan Cat Plafon Gypsumboard & Kalsiboard 174.00 m2
4 Pekerjaan Waterproofing 78.19 m2
XI PEKERJAAN MEKANIKAL & ELEKTRIKAL
A PEKERJAAN LISTRIK
1 Titik lampu dan stop kontak+ konduit 47.00 titik
2 Lampu TL 2x36 armature RM,300 2.00 bh
3 DL .D 175-ESS.18 W 32.00 bh
4 Exhaust ceilling fan 3.00 bh
5 Stop kontak, 1 p 10.00 bh
6 Saklar tunggal 6.00 bh
7 Saklar ganda 6.00 bh
B PEKERJAAN PANEL
1 Box MCB R.Makan 1.00 unit
2 MCB 6A/5kA/1p 3.00 bh
3 MCB 10A/5kA/1p 3.00 bh
4 MCB 16A/5kA/1p 1.00 bh
5 MCB 20A/5kA/1p 1.00 bh
6 Pilot lamp 1.00 bh
7 petanahan/arde 2 Ohm 1.00 ls
8 kabel LVTC 2x10 mm2 125.00 m
XII PEKERJAAN PLUMBING
Instalasi Pipa ,lengkap sleave, penggantung,
dudukan dan testing
1 Pipa Air Bersih PVC-AW ( 10 kg/cm2)- dia 1.5'' 10.00 m
- dia 1'' 25.00 m
- dia 1/2'' 12.00 ls
- fitting 1.00 bh
Page 11
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 11/20
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
- ball valve 1.5'' 1.00 bh
2 Pipa Air Bekas, Air Kotor dan Vent,PVC-AW
- dia 6'' 4.00 m
- dia 4'' 4.00 m
- dia 3'' 4.00 m
- dia 2'' 8.00 m
- fitting 1.00 ls
- CO 4'' 2.00 bh
3 Pompa Transfer/distribusi ais listrik otomatis 1.00 unitH=40m,kap.35 lpm,setara Shimizu PS130BT
4 WLC dan kabel kontrol setara Radar 1.00 unit
5 foot valve 1'' 1.00 bh
6 pipa PVC-AW dia. 1'' dari r.pompa ke tower 10.00 m
7 Ground Tank Kapasitas 6m3 1.00 unit
8 Septicktank & Peresapan 1.00 unit
XIII PEKERJAAN SANITAIR
1 Kloset Duduk ex TOTO CW 661 JT1/SW 661 JP + Assesories Terpasang 2.00 unit
2 Washtafel Gantung ex TOTO LW 230 CJ + assesories terpasang 2.00 unit
3 Kran Air 2.00 unit
4 Jet Washer 2.00 unit
5 Floor Drain 2.00 unit
6 Kaca Cermin 60x100 2.00 unit
XIV PEKERJAAN LAIN-LAIN
1 Saluran Drainase
- Saluran U30 Terbuka 44.00 m'
2 Tanaman
- Gebalan Rumput Gajah Mini 37.44 m2
- Urugan tanah Merah + Pupuk 3.74 m3
3 Counter Saji 6.00 m'
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 12
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 12/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI BANGUNAN KANTOR ( R. MAKAN MESS )
LOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN BONGKARAN Rp.
III PEKERJAAN TANAH Rp.
IV PEKERJAAN PASANGAN Rp.
V PEKERJAAN BETON BERTULANG Rp.
V PEKERJAAN BESI Rp.
VI PEKERJAAN ATAP Rp.
VII PEKERJAAN PLAFON Rp.
VIII PEKERJAAN PINTU & JENDELA Rp.
IX PEKERJAAN PELAPIS LANTAI & DINDING Rp.
X PEKERJAAN CAT-CATAN Rp.
XI PEKERJAAN MEKANIKAL & ELEKTRIKAL Rp.
XII PEKERJAAN PLUMBING Rp.
XIII PEKERJAAN SANITAIR Rp.
XIV PEKERJAAN LAIN-LAIN Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A
Page 13
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 13/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI RUANG PERTEMUAN GEDUNG KEBUN PERCOBAAN
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN
1 Uitzet / bouwplank 1.00 ls
II PEKERJAAN BONGKARAN
1 Bongkaran Dinding Lama 73.50 m2
2 Bongkar Kusen Pintu & Jendela Existing 1.00 ls
3 Pembersihan & Buang Puing Bongkaran 1.00 ls
III PEKERJAAN PASANGAN
1 Pasangan Batu Bata (Eks. Kusen Existing) 1: 5 11.61 m2
2 Plesteran Dinding 1: 5 23.22 m2
3 Plesteran Sudut 173.80 m'
4 Acian Dinding 23.22 m2
IV PEKERJAAN PINTU & JENDELA
1 Kusen & Pintu + Ass Terpasang - Type P1 1.00 unit
2 Kusen & Pintu + Ass Terpasang - Type P2 2.00 unit
3 Kusen & Pintu UPVC + Ass Terpasang - Type P3 1.00 unit4 Kusen & Jendela + Ass Terpasang - Type J1 2.00 unit
5 Kusen & Jendela + Ass Terpasang - Type J2 4.00 unit
6 Kusen & Jendela + Ass Terpasang - Type J3 2.00 unit
7 Kusen & Bouvenligt + Ass Terpasang - Type BV1 1.00 unit
V PEKERJAAN LANTAI & PELAPIS
1 Keramik 30x30 Polished 118.40 m2
2 Keramik 20x20 Texture 3.00 m2
3 Keramik Dinding 20x25 10.85 m2
4 Border Keramik Aksen Warna 10x20 0.62 m2
VI PEKERJAAN CAT-CATAN
1 Pekerjaan Cat Dinding Dalam / Interior 210.43 m2
VII PEKERJAAN SANITAIR
1 Kloset Jongkok ex TOTO + Ass Terpasang 1.00 unit
2 Kran Air 1.00 unit
3 Jet Washer 1.00 unit4 Floor Drain 1.00 unit
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 14
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 14/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI RUANG PERTEMUAN GEDUNG KEBUN PERCOBAAN
LOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN BONGKARAN Rp.
III PEKERJAAN PASANGAN Rp.
IV PEKERJAAN PINTU & JENDELA Rp.
V PEKERJAAN LANTAI & PELAPIS Rp.
VI PEKERJAAN CAT-CATAN Rp.
VII PEKERJAAN SANITAIR Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A
Page 15
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 15/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI PAGAR DEPAN KP
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN1 Listrik & Air Kerja 1.00 set
II PEKERJAAN TANAH
1 Galian Tanah Pondasi Batu Belah 7.00 m3
2 Urugan Tanah Kembali 3.09 m3
3 Urugan Sirtu Dibawah Pondasi Batu Belah 1.40 m3
III PEKERJAAN PASANGAN
1 Pasangan Batu Belah 1 : 6 2.35 m3
2 Pasangan Batu Bata 1: 5 9.60 m2
3 Plesteran Dinding 1: 5 19.20 m2
4 Plesteran Beton 0.90 m2
5 Plesteran Sudut 43.20 m'
6 Acian Dinding 20.10 m2
IV PEKERJAAN BETON BERTULANG
1 Sloof Praktis 12x20 0.15 m3
2 Kolom Praktis 0.23 m3
3 Beton Plat 0.05 m3
V PEKERJAAN BESI
1 Pintu Pagar Besi Tempa Finish Cat 2.00 unit
VI PEKERJAAN PELAPIS
1 Pasang Batu Andesit 7.48 m2
VII PEKERJAAN CAT-CATAN
1 Pekerjaan Cat Dinding Luar / Exterior 3.70 m2
VIII PEKERJAAN LAIN-LAIN
1 Pasang Logo 2.00 unit
JUMLAHPPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 16
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 16/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : RENOVASI PAGAR DEPAN KPLOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN TANAH Rp.
III PEKERJAAN PASANGAN Rp.
IV PEKERJAAN BETON BERTULANG Rp.
V PEKERJAAN BESI Rp.
VI PEKERJAAN PELAPIS Rp.
VII PEKERJAAN CAT-CATAN Rp.
VIII PEKERJAAN LAIN-LAIN Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A
Page 17
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 17/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : LANDSCAPING ( TAMAN AIR GEDUNG UTAMA )
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN1 Uitzet / bouwplank 26.00 m'
2 Listrik & Air Kerja 1.00 set
II PEKERJAAN TANAH
1 Galian Tanah 38.24 m3
2 Urugan Tanah Kembali 9.56 m3
3 Urugan Pasir Dibawah Plat Lantai tebal 5cm 3.48 m3
III PEKERJAAN PASANGAN
1 Pasangan Batu Belah 1 : 6 4.82 m3
IV PEKERJAAN BETON BERTULANG
Mutu Beton Struktur K250
Mutu Beton Non Struktur K175
1 Lantai Kerja Beton K100 3.48 m3
2 Beton Plat Lantai tebal 10cm 83 kg/m3 6.95 m3
3 Beton Plat Dinding tebal 13cm 78 kg/m3 3.13 m3
V PEKERJAAN LANTAI & PELAPIS
1 Granite Tile Un Polish 60x60 46.98 m2
2 Batu Andesit ( Kasar ) 30x30 11.34 m2
3 Floor Hardener 3.48 m2
4 Batu Koral Sikat Halus 16.13 m2
5 Pekerjaan Waterproofing 77.85 m2
VI PEKERJAAN AIR MUNCRAT
1 Nozzle Jet Spray ( Air Muncrat ) Type I 15.00 bh
2 Nozzle ( Air Muncrat ) Type 2 + Lampu 5.00 bh
3 Spraying gardens pump lengkap accessories strainer, 1.00 unit
house coupling, pipe, kapasitas 8 Lpm, head 30 kg/cm2
daya 3/4 HP, 220 V, 1420rpm,50 Hz,1p, LS906
4 Instalasi Plumbing / Pipa PPR-PN10 dia 1/2" 30.00 m'
5 Instalasi Listrik Kabel NYYHY 30.00 m'
6 Saluran Sirkulasi 24.00 m'
7 Bak Kontrol 1.00 unit8 Bak Tandon / Balance Tank 1.00 unit
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 18
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 18/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : LANDSCAPING ( TAMAN AIR GEDUNG UTAMA )
LOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN TANAH Rp.
III PEKERJAAN PASANGAN Rp.
IV PEKERJAAN BETON BERTULANG Rp.
V PEKERJAAN LANTAI & PELAPIS Rp.
VI PEKERJAAN AIR MUNCRAT Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A
Page 19
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 19/20
RENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : REHABILITASI POS SATPAM
LOKASI : KABUPATEN PATI
TAHUN : 2014
NO URAIAN PEKERJAAN VOL. SAT. HARGA SAT. H A R G A JUMLAH HARGA
Rp. Rp. Rp.
I PEKERJAAN PERSIAPAN1 Listrik & Air Kerja 1.00 set
II PEKERJAAN PLAFON
1 Plafond Calsiboard 4mm rk metal furing full system 18.02 m2
- R. Ganti, Dapur, R. Sholat, KM/WC
2 Pekerjaan Cat Plafon Gypsumboard, Kalsiboard & Beton Ekspose 18.02 m2
I II PEKERJAAN LANTAI & PELAPIS
1 Keramik 40x40 Polished 46.52 m2
2 Keramik 20x20 Texture 2.31 m2
JUMLAH
PPN 10%
JUMLAH TOTAL
JUMLAH ( DIBULATKAN )
Page 20
8/18/2019 BQ Rehabilitasi
http://slidepdf.com/reader/full/bq-rehabilitasi 20/20
KOP PERUSAHAAN
REKAPITULASIRENCANA ANGGARAN BIAYA
PAKET : REHABILITASI BANGUNAN GEDUNG NEGARA
PEKERJAAN : REHABILITASI POS SATPAM
LOKASI : KABUPATEN PATI
TAHUN : 2014
I PEKERJAAN PERSIAPAN Rp.
II PEKERJAAN PLAFON Rp.
III PEKERJAAN LANTAI & PELAPIS Rp.
JUMLAH Rp.
PPN 10% Rp.
JUMLAH TOTAL Rp.
JUMLAH DIBULATKAN Rp.
…………….,…………………20…
Yang menawar,
PT/CV……………………..
(…………………………….)
Direktur
NO URAIAN PEKERJAAN H A R G A