1 GTC Presentation Bored Pile and Driven H-Pile Construction (24 June 2011) Christopher Leung (Geotechnics)
Sep 18, 2014
1
GTC Presentation
Bored Pile and Driven H-Pile Construction
(24 June 2011)
Christopher Leung(Geotechnics)
2
Secondment at Tysan Foundation Limited
Oct 2011 – Jan 2011 (3 months)Construction of Public Rental Housing at Kai Tak Site 1B(~1100 Nos. of mixed driven H-pile and sockettedH-pile)
Jan 2011 – Jun 2011 (6 months)Piling Works for the Proposed Industrial Building at No. 6-28 Chai Wan Kok Street, Tsuen Wan(33 Nos. of bored piles and 53 Nos. of driven H-pile)
3
Bored Pile Construction- Procedures, plants and equipment
4
Bored Pile Construction – Typical Procedures
1. Pre-drilling (at each pile location) 2. Setting out3. Casing driving through soft layer and excavation4. Rock socket and bell-out forming (by RCD)5. Air-lifting6. Koden test7. Steel cage installation8. Concreting9. Interface/ full-depth concrete coring
5
Determination of rockhead level before constructionAt each pile locationContinuous 5m of Grade III or better rock with TCR over 85%Double or triple-tube (for fragmented rock) core-barrelT2/TN size barrel
Bored Pile Construction – Pre-drilling
6
General site arrangementCasing driving RCDSteel cage fabricationAir liftingConcreting
Chai Wan Kok Street (Feb 2011)
7
Casing drivingWelded Splice/ Bolted JointCommon size: 2.0m, 2.5m & 3.0mCommonly by oscillatorDown to bedrock/hard stratum
8
Other common methods for casing driving
VibratorRotator
9
By crawler crane simultaneously with casing drivingBy hammer grab and rock chisel
Excavation
10
Rock socket forming
Reverse Circulation Drill (RCD)Vertical drill-bitRock sample inspection at rockhead, founding andpile base levels
11Cutter
Drum Stabilizer
Stabilizer
Drill Rod
Swivel Head
Drilling PlatformClamping Collar
Drill Bit
Water Tank Air Comp Power Pack
Rock socket forming by RCD
12
Bell-out tools
Reverse Circulation Drill (RCD)Replaced with bell-out bitNo further drilling downwards but only extending the arms“Travel” calibration
Founding Level
Pile Base Level
13
Air-lifting
Tremie Pipe
Air Hose
Recycle water / Fresh Water
Flush out to Sedimentation Tank
Air Compressor
14
Koden Test
Common acoustic device to verify verticality & bell-out sizeRequire sufficient clarity of waterDO NOT expect very exact values
15
Steel cage installationAware of possible cage collapse
Use crawler crane with sufficient powerAware of design with heavier top reinforcement
Ensure sufficient lapping length
Sufficient nos. of reservation pipes (150mm dia.)
16
Concreting
Ramp
Skip
Tremie Pipe
Concreting Platform
17
Concreting
Simultaneous with casing extraction and removal and tremie pipeCasing supported securely by oscillator/crawler crane
18
Quality Problems in Association with Construction Technology and Design
Quality Problems
Pile Inclination and Off-CentreNecking Pile ShaftThermal Cracking of ConcreteAir Voids and Honeycomb in ConcreteSediments at Pile Base
Unknown underground condition!
19
Design ConsiderationDimension
Avoid Very Large, Extremely Long Piles (e.g. 3m diameter more than 80m deep) and Large Bell-Out (e.g. 4.8m)
Concrete and reinforcementUse High Grade Concrete with Care (e.g. Grade 50)Maintain Sufficient Clear Spacing between Reinforcing BarsEnsure Sufficient Stiffness of the Reinforcement Cage
Ground conditionUse Permanent Casing in Very Soft Ground or Subject to Tidal Effect and Underground Stream
Quality Problems in Association with Construction Technology and Design
20
Tests on Bored Pile ConstructionInterface Coring
Coring through reservation pipesOn each bored pile after concreting for a certain periodVisual inspection on the contact of the pile base and the founding rock
Example of good contact
21
Tests on Bored Pile ConstructionFull-depth Concrete Coring
Coring from the top of pile into the founding rockNos. subject to criteria of completion (e.g. 5%)Concrete cores selected for compressive testAs alternative to interface coring
22
Interface and full-depth concrete coring
Common imperfectionsConcrete core
Thermal jointAir voids and honeycomb in concrete
Interface contactNo recovery (inferred as soil inclusion) due to sediment at pile toeLoss of contact at the interface due to inaccessibility of concrete mix into rock fragments
23
Process control to minimize the occurrence of segregation
Introduce grout/bentonite in advance of concrete dischargingUse high slump concreteUse of additional retarder to enhance workability
Interface and full-depth concrete coring
24
1. Additional coreholes2. Clean the pile toe with high pressure water jet3. Pressurized cement grout4. Verification cores
As specified by RSE to which extent of remedial works should be performed
Remedial Actions for Pile Base Imperfections
25
Remedial Actions for Pile Base Imperfections
Caution!!!This method may only work in intact rocksituation with confined defects
In highly fractured rock zones, high-pressure water jetting and grouting may induce more collapses and aggravate the situation⇒ progressive creation of cavity ⇒ induce further collapses at pile toe
26
Driven H-Pile Construction- Procedures, plants and equipment
27
Driven H-Pile Construction – Typical Procedures
1. Pre-drilling (piles covered by 5m radius) 2. Setting out3. H-pile section inspection4. Pitching of 1st section5. Splice more sections and welded joint inspection
(Visual, some with non-destructive test)6. Final set (some with PDA)7. Load test
28
H-pile inspectionMill cert, stocklist, s/n recordLength measurement (VERYimportant especially for sections cut from other piles)Pile tip inspection
29
Pile pitching/drivingHydraulic HammerOffset control
Limit power in the first few blowsClose monitoring by pile workerPile extraction if necessary
Noise permit
Hydraulic hammer
30
Better co-ordination and recording for large site• KT1B Site with over 1000 nos. of H-piles of average 5,6 sections
31
Splice sections by welding
Better arrangement of welding period/ weldersAllow certain time of cooling before drivingVisual inspection by RE
32
Non-destructive test on welds
Ultrasonic testRequired for a certain ratio of pilesBy pulse reflection of transducerDiscontinuity of weld
33
Final set
Use of drop hammer of specified weightSpecified drop height for 10 blowsFinal set graph
Cp+Cq
sFinal set process
34
Calibration
Weight of drop hammer, helmet & followerTemporary compression of helmet (Cc)Coefficient of restitution (e)Hammer efficiency (k)
Hiley’s formula
)(*)(
*)(5.0
* 2
PWWWePWWW
CCCsEkRu
fhr
fhr
qpc +++
+++
+++=
Depending on the specification requirement
35
Pile Driving Analysis (PDA)
For a certain ratio of piles specified (e.g. 5%)Can be done simultaneously with final setWave signal analysis during drivingWave equation modelInduced pile capacity as additional verification
36
Post-construction drilling
In case the pile founding level is higher than designed level from pre-drillingMinimum nos. as specifiedProcess similar to pre-drilling
Rockhead/SPT
37
Load TestLoading to ultimate pile capacityKentledge with sufficient loadingFour dial gauge extensometerAllowable maximum and residual settlement
Kentledge and hydraulic jack
38
Conclusion
Typical procedures for Bored Pile and Driven H-Pile constructionExamples from the projects involved
END