YEAR:2008-09 Block Village Approved Revised(if available) 1 2 3 4 5 6 7 8 9 10 A SINGHAT BLOCK i) General a) Communication (IVR) 1 Constn. Of IVR from Lanchah to Mongjang SGT Lanchah 4.00 4.00 4.00 4.00 Completed 2 Constn. Of IVR from Theigotang to Hiangtam (V) do Theogotang 3.00 3.00 3.00 3.00 Completed 3 Constn. Of IVR from Hengjang to Hiangtam (K) do Hengjang 4.00 4.00 4.00 4.00 Completed 4 Constn. Of IVR from Suangdai to Ngaljang do Suangdai 4.00 4.00 4.00 4.00 Completed 5 Impvt. Of Link Road between L. Kanan & Behiang do L. Kanan 3.00 3.00 3.00 3.00 Completed 6 Constn. Of IVR from Hengjang to Songjang do Hengjang 4.00 4.00 4.00 4.00 Completed 7 Cosntn. Of IVR from Suangdoh to Sialbu via Chingai Suangdoh 10.00 10.00 10.00 10.00 Completed b) BRIDGES 8 Constn. of S/Bridge over Tuilak river between Lungthul(L)& Sialbu SGT Lungthul (L) 7.32 7.32 7.32 7.32 Completed 9 Constn. of S/Bridge over Tuivel river between Pakmual and Behiang (V) SGT Pakmual & Behiang 6.00 6.00 6.00 6.00 Completed 10 Constn. of S/Bridges over Kangkap river between Kangkap and Ngaljang SGT Kangkap & Ngalzing 6.00 6.00 6.00 6.00 Completed 11 Constn. of S/Bridges over Tengkhol stream between Tongjang and Lungjang SGT Tongjang & Lungzing 6.00 6.00 6.00 6.00 Completed c) Community Building BORDER AREA DEVELOPMENT PROGRAMME(BADP) (Rs. in lakhs) Name of the District:CHURCHANDPUR Sl.No. Name of the schemes/projects Location COMPLETED SCHEMES/PROJECTS TAKEN UP UNDER BADP (YEAR-WISE/DISTRICT-WISE/BLOCK-WISE/DEPTT-WISE/SECTOR-WISE) Amount released by MHA Amount utilised Remarks Project Cost Amount Sanctioned
22
Embed
BORDER AREA DEVELOPMENT PROGRAMME(BADP ... 2008-09.pdf22 improvement of M.I. Dam at Ngasuan river near Tonjang Tonjang 5.00 5.00 5.00 5.00 Completed g) Health & sanitation 23 Provision
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
YEAR:2008-09
Block Village Approved Revised(if available)
1 2 3 4 5 6 7 8 9 10A SINGHAT BLOCKi) Generala) Communication (IVR)1 Constn. Of IVR from Lanchah to Mongjang SGT Lanchah 4.00 4.00 4.00 4.00 Completed
2 Constn. Of IVR from Theigotang to Hiangtam (V)
do Theogotang 3.00 3.00 3.00 3.00 Completed
3 Constn. Of IVR from Hengjang to Hiangtam (K)
do Hengjang 4.00 4.00 4.00 4.00 Completed
4 Constn. Of IVR from Suangdai to Ngaljang do Suangdai 4.00 4.00 4.00 4.00 Completed
5 Impvt. Of Link Road between L. Kanan & Behiang
do L. Kanan 3.00 3.00 3.00 3.00 Completed
6 Constn. Of IVR from Hengjang to Songjang do Hengjang 4.00 4.00 4.00 4.00 Completed
7 Cosntn. Of IVR from Suangdoh to Sialbu via Chingai
Suangdoh 10.00 10.00 10.00 10.00 Completed
b) BRIDGES
8 Constn. of S/Bridge over Tuilak river between Lungthul(L)& Sialbu
SGT Lungthul (L) 7.32 7.32 7.32 7.32 Completed
9 Constn. of S/Bridge over Tuivel river between Pakmual and Behiang (V)
SGT Pakmual & Behiang
6.00 6.00 6.00 6.00 Completed
10 Constn. of S/Bridges over Kangkap river between Kangkap and Ngaljang
SGT Kangkap & Ngalzing
6.00 6.00 6.00 6.00 Completed
11 Constn. of S/Bridges over Tengkhol stream between Tongjang and Lungjang
SGT Tongjang & Lungzing
6.00 6.00 6.00 6.00 Completed
c) Community Building
BORDER AREA DEVELOPMENT PROGRAMME(BADP)
(Rs. in lakhs)Name of the District:CHURCHANDPURSl.No. Name of the schemes/projects Location
COMPLETED SCHEMES/PROJECTS TAKEN UP UNDER BADP (YEAR-WISE/DISTRICT-WISE/BLOCK-WISE/DEPTT-WISE/SECTOR-WISE)
Amount released by MHA
Amount utilised
RemarksProject Cost Amount Sanctioned
Block Village Approved Revised(if available)
1 2 3 4 5 6 7 8 9 10
Sl.No. Name of the schemes/projects Location Amount released by MHA
Amount utilised
RemarksProject Cost Amount Sanctioned
12 Constn. Of Community Hall at Tuima (Kangkap) SGT Tuima (Kangkap)
5.00 5.00 5.00 5.00 Completed
13 Constn. Of Community Hall at Tuikuimuallum do Tuikuimuallum 5.00 5.00 5.00 5.00 Completed
14 Constn. Of Community Hall at Sialbu do Sialbu 5.00 5.00 5.00 5.00 Completed
15 Constn. Of VA house at Hiangtam (V) do Hiangtam (V) 3.00 3.00 3.00 3.00 Completed
d) Education/ Playground
16 Constn. Of Tribal Girl Hostel at Singngat HQ do Singngat HQ 20.00 20.00 20.00 20.00 Completed
17 Constn. Of Playground at Suangphu do Suangphu 3.00 3.00 3.00 3.00 Completed
18 Constn. Of Playground at Theigotang do Theigotang 3.00 3.00 3.00 3.00 Completede) Agriculture & Allied
19 Community Fishery farm at Hengjang do Hengjang 2.00 2.00 2.00 2.00 Completed
20 Banana Plantation at Tonjang do Tonjang 3.50 3.50 3.50 3.50 Completed
f) MI DAMS
21 Constn. Of B/S Dam at Tengkol stream at Jangnuam for Nengkhanmang Lourup
do Jangnuam 3.00 3.00 3.00 3.00 Completed
22 improvement of M.I. Dam at Ngasuan river near Tonjang
Tonjang 5.00 5.00 5.00 5.00 Completed
g) Health & sanitation
23 Provision for treatment & purchase medicine etc in medical emergencies in remote border areas.
do 5.00 5.00 5.00 5.00 Completed
h) WATER SUPPLY
24 Constn. Of RWS at L.Kanan do L.Kanan 3.00 3.00 3.00 3.00 Completed
25 Constn. Of RWS at Mongjang do Mongjang 3.00 3.00 3.00 3.00 Completed
i) BEHIANG CLUSTER
COMMUNICATION :
26 Construction of IVR from Songjang to Aishi do Songjang 5.00 5.00 5.00 5.00 Completed
27 Constn. Of IVR from L. Kanan to Behiang(V) do L.Kanan 5.00 5.00 5.00 5.00 Completed
AGRICULTURE & ALLIED
Block Village Approved Revised(if available)
1 2 3 4 5 6 7 8 9 10
Sl.No. Name of the schemes/projects Location Amount released by MHA
Amount utilised
RemarksProject Cost Amount Sanctioned
28 Plantation of Lemon at Pakmual do Pakmual 3.00 3.00 3.00 3.00 Completed
29 Plantation of Ginger at Suangdoh do Suangdoh 2.00 2.00 2.00 2.00 Completed
SUANGDOH CLUSTER
j) COMMUNICATION :
30 Constn. Of IVR from Sialbu to Lungthul (L) with 4m.span slab culvert over Sialbu stream
do Sialbu & Lungthul
6.00 6.00 6.00 6.00 Completed
Total (Singhat): 146.82 0.00 146.82 146.82 146.82 0.00
B THANLON BORDER BLOCK
a) Infrastructure
COMMUNCIATION
31 Constn. Of IVR from Thuangtam to Umtal Thanlon Thuangtam & Umtal
6.00 6.00 6.00 6.00 Completed
32 Constn. Of IVR from Umtal to Mualkui do Umtal & Mualkui
5.00 5.00 5.00 5.00 Completed
33 Construction of road from Mong-on to Vaipheimual
do Mong-on & Vaipheimual
6.00 6.00 6.00 6.00 Completed
b) BRIDGES/SLAB CULVERT
34 Constn. Of S/Bridge over Tuikui river between Pangmual and Khuanggin
do Pangmual & Khuanggin
7.00 7.00 7.00 7.00 Completed
c) Social sectorCOMMUNITY DEVELOPMENT
35 Constn. Of VA House at Songtal do Songtal 6.00 6.00 6.00 6.00 Completed
36 Constn. Of VA House at Thuangtam do Thuangtam 6.00 6.00 6.00 6.00 Completed
37 Constn. Of VA House at Tongkham do Tongkham 5.00 5.00 5.00 5.00 Completed
38 Constn. Of Community Hall at Sumtuh do Sumtuh 8.00 8.00 8.00 8.00 Completed
39 Constn. Of VA House at Phailenbung do Phailenbung 4.00 4.00 4.00 4.00 Completed
40 Cosntn. Of VA House at Phaitong do Phaitong 5.00 5.00 5.00 5.00 Completed
41 Cosntn. Of Community Hall at Thuangtam do Thuangtam 4.50 4.50 4.50 4.50 Completed
42 Construction of V.A. House at Pamjal do Pamjal 5.00 5.00 5.00 5.00 Completed
Block Village Approved Revised(if available)
1 2 3 4 5 6 7 8 9 10
Sl.No. Name of the schemes/projects Location Amount released by MHA
Amount utilised
RemarksProject Cost Amount Sanctioned
43 Construction of V.A. House at Mong-on do Mong-on 5.00 5.00 5.00 5.00 Completed
44 Construction of Community Hall at Mualkui do Mualkui 5.00 5.00 5.00 5.00 Completed
45 Construction of Community Hall at Kaihlam do Kaihlam 4.50 4.50 4.50 4.50 Completed
46 Construction of Villaga Authority House at Phaipheng
do Phaipheng 4.50 4.50 4.50 4.50 Completed
MARKET SHED
47 Cosntn. Of Market shed at Songtal do Songtal 8.00 8.00 8.00 8.00 Completed
b) Education Sector
48 Constn. Of Tribal Girl Hostel Building at Thanlon HQ
do Thanlon 20.00 20.00 20.00 20.00 Completed
c) Agriculture & Allied Sector
MI DAM
49 Cosntn. Of MI Dam at Sumtuh do Sumtuh 6.00 6.00 6.00 6.00 Completed
50 Constn. of Community Fishery pond at Sumtuh
do Sumtuh 6.00 6.00 6.00 6.00 Completed
51 Constn. of Community Fishery pond at Khajang
do Khajang 6.00 6.00 6.00 6.00 Completed
d) Health & sanitation Sector
52 Provision for treatment & purchase medicine etcin medical emergencies in remote border areas.
do Whole Bolck 5.28 5.28 5.28 5.28 Completed
Water Supply
53 RWS at Umtal do Umtal 3.00 3.00 3.00 3.00 Completed
54 RWS at Khajang do Khajang 3.00 3.00 3.00 3.00 Completed
Total (Thanlon): 143.78 143.78 143.78 143.78
Total (Churachandpur District): 290.60 290.60 290.60 290.60
YEAR:2008-09
Block Village Approved Revised(if available)
1 2 3 4 5 6 7 8 9 10
I:TENGNOUPAL BLOCK :A. Education Sectors
Constn of Hostel Building1 Constn. Of Girls Dormitory for
Moreh Govt. High SchoolTPL Moreh 6.00 6.00 6.00 6.00 Completed
Constn. Of Library Building:1 Constn. Of Library cum Recreation
Centre at Moreh Ward No. 3TPL Moreh 8.00 8.00 8.00 8.00 Completed
Constn. Of Playground2 Constn. of Play ground at Angbrasu
VillageTPL Angbrasu 5.00 5.00 5.00 5.00 Completed
3 Constn. of Play ground at Sairel Shaisim
TPL Sairel Shaisim
5.00 5.00 5.00 5.00 Completed
4 ,-do- at New Mongjang/ Khomunnom
TPL New Mongjang
5.00 5.00 5.00 5.00 Completed
5 ,-do- at Khudengthabi TPL Khudengthabi
4.00 4.00 4.00 4.00 Completed
B. Agricultural & Allied Sectors6 Construction of MI Dam across
Phaisan stream for Phisan LoubukTPL Lamlong
Khunou5.00 5.00 5.00 5.00 Completed
7 Constrn. Of MI Dam 7 canal across Kangoitong stream for kangoitong Loubuk
TPL Lamlong Khunou
5.00 5.00 5.00 5.00 Completed
Amount utilised
Remarks
BORDER AREA DEVELOPMENT PROGRAMME(BADP)COMPLETED SCHEMES/PROJECTS TAKEN UP UNDER BADP (YEAR-WISE/DISTRICT-WISE/BLOCK-WISE/DEPTT-WISE/SECTOR-WISE)
Name of the District:CHANDEL (Rs. in lakhs)Sl.No. Name of the schemes/projects Location Project Cost Amount
SanctionedAmount released by MHA
8 MI Dam across Anchapso river for M Piba Loubuk
TPL Saibol 2.00 2.00 2.00 2.00 Completed
9 -do- Mangkarok Lok for AS Piba Loubuk
TPL Saibol 4.00 4.00 4.00 4.00 Completed
10 -do- Ngachan Lok to Mayonmi Loubuk
TPL Yangkhul 4.00 4.00 4.00 4.00 Completed
11 -do- Tuiphei Lok for Kochai and Angkham Loukon
TPL Kharou Khunou
5.00 5.00 5.00 5.00 Completed
Plantation12 Banana Plantation at Rilram Centre TPL Rilram
Centre3.00 3.00 3.00 3.00 Completed
C. Health & SanitationConstruction of Water Reservoir at:
36 Dev. Of playground at Jessami Chingai Jessami 3.00 3.00 3.00 3.00 Completed37 Constn. of playground at Challou Chingai Challou 3.00 3.00 3.00 3.00 Completed38 Constn. of Public Convenience at