Idaho State Capitol Restoration 2007 through 2010 Andrew Erstad, Chairman, Idaho Capitol Commission C.L. “Butch” Otter Governo Jan Frew Executive Project Manager Dep. Administrator, Idaho Div of Public Works
Jan 14, 2015
Idaho State Capitol
Restoration
2007 through 2010
Andrew Erstad, Chairman, Idaho Capitol Commission
C.L. “Butch” Otter Governor
Jan FrewExecutive Project Manager Dep. Administrator, Idaho Div of Public Works
Andrew ErstadBoise
Chairman
Janet GallimoreBoise
EvanFrasurePocatello
Stephen HartgenTwin Falls
Sandra PatanoCoeur d’Alene
JeffYoutzBoise
Idaho Capitol Commission
DoloresCrowNampa
Mike Gwartney, SecretaryBoise
Idaho Capitol CommissionCapitol License Plate Program
Capitol License Plate Revenue
$0.00
$10,000.00
$20,000.00
$30,000.00
$40,000.00
$50,000.00
$60,000.00
$70,000.00
$80,000.00
FY2002 FY2003 FY2004 FY2005 FY2006 FY2007
FY
Re
ce
ipts
$80,710.00FY2007
$65,710.00FY2006
$49,050.00FY2005
$36,570.00FY2004
$29,585.00FY2003
$6,095.00FY2002
$80,955.00FY2008
Total $313,940.00
Idaho Capitol Restoration and Expansion
Restoration $85 Million
Idaho Capitol Restoration, CMAR Jacobson Hunt Joint
Venture (JHJV)
WHY WHY RESTORE IT?RESTORE IT?
Idaho Capitol Exterior
Concrete deterioration
Peeling paint
Idaho Capitol Interior
Four types of marbleHouse column with cracks
Idaho Capitol Restoration and Expansion Priorities
Preservation, Restoration and Rehabilitation of the Idaho State
Capitol Building•Restore and Refinish Windows •Repair Marble Flooring •repair decorative plaster •restore wood floors •refinish wood doors and restore hardware •replace/refurbish light fixtures •upgrade electrical •complete smoke and fire detection system •install fire sprinkler system throughout •improve exterior lighting •add emergency power generator
Preservation, Restoration and Rehabilitation of the Idaho State
Capitol Building•install new HVAC system •replace sewer piping •replace hot water system •improve exiting from basement •provide vertical circulation cores from the Legislative chambers level to the new garden-level wings •safer access to roof domes •add egress hardware •provide accessible toilet rooms •install accessible elevator (gurney size)
WHY EXPAND WHY EXPAND IT?IT?
Idaho Capitol Expansion
Idaho Capitol Expansion
“Packing 'em in”
Idaho Capitol Expansion
“Packing 'em in”
New Construction Garden Level Wings
New Construction
Idaho Capitol Expansion $35 Million
Idaho Capitol Expansion
Idaho Capitol Expansion
ChallengesChallenges
Idaho Capitol Restoration & Expansion
Moving Trees-Moving Tenants
Idaho Capitol Restoration and Expansion
April 2008
Idaho Capitol Restoration and Expansion
April 2008
Idaho Capitol Restoration and Expansion
April 2008
Connecting Main Section to Wings
•Concrete cuts for connecting wings expansion & Capitol building•Auditorium sloped floor concrete poured•Marble cleaning•Senate Caucus room mock up
Idaho Capitol Restoration and Expansion
May 2008
Idaho Capitol Restoration and Expansion
•Cut openings for new stairs in NE and NW corners of Capitol•Structural steel housings completed •Hoisted one set of stairs into the building
May 2008
Idaho Capitol Restoration and Expansion
May 2008
Idaho Capitol Restoration and Expansion
June 2008
Idaho Capitol Restoration and Expansion
Design/Build contractor:•Enclosed the East wing•Completed bulk of mechanical ductwork, electrical, plumbing (MEP), fire sprinkler rough-in work•Flood testing the waterproofing in both wings•Installed West Wing air handler unit•Completed hydronic piping underneath garden level
June 2008
Idaho Capitol Restoration and Expansion
June 2008
Idaho Capitol Restoration and Expansion
July 2008
July 2008
Capitol Restoration
August 2008
Capitol Restoration
Idaho Capitol Restoration and Expansion
August 2008
Idaho Capitol Restoration and Expansion
August 2008
Idaho Capitol Restoration and Expansion
September 2008
August 2008
Capitol Restoration
September 2008
Capitol Restoration
October 2008
Capitol Restoration
Idaho Capitol Restoration and Expansion
October 2008
Capitol Restoration
Capitol RestorationNovember 2008
December 2008
Capitol Restoration
December 2008
Capitol Restoration
Capitol Restoration
Capitol RestorationJanuary 2009
Capitol RestorationFebruary 2009
Capitol RestorationMarch 2009
Capitol RestorationApril 2009