Top Banner
BERTSCHenergy Power Plants Process Equipment TRADITION, QUALITY, KNOW-HOW. SINCE 1925. www.bertsch.at Boiler feed water (BFW) preheater in ammonia production Reference Sheet
2

Boiler feed water (BFW) preheater in ammonia production...» BFW preheater » Gas mixing and control device » Refratory lining High pressure process gas coolers which have to be re-vamped

Aug 03, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Boiler feed water (BFW) preheater in ammonia production...» BFW preheater » Gas mixing and control device » Refratory lining High pressure process gas coolers which have to be re-vamped

BERTSCHenergyPower PlantsProcess Equipment

TRADITION, QUALITY, KNOW-HOW. SINCE 1925.

www.bertsch.at

Boiler feed water (BFW) preheater in ammonia production

Reference Sheet

Page 2: Boiler feed water (BFW) preheater in ammonia production...» BFW preheater » Gas mixing and control device » Refratory lining High pressure process gas coolers which have to be re-vamped

» Boiler feed water (BFW) preheater in ammonia production «

» Boiler feed water (BFW) preheater in ammonia production

TECHNICAL DATA

» Gas side mass flow 161,500 kg/h

» Water side mass flow 303,000 kg/h

» Heat duty 22.8 MW

» Design pressure gas side 35.4 barg

» Design pressure water side 131 barg

SCOPE OF SUPPLY

» BFW preheater

» Gas mixing and control device

» Refratory lining

High pressure process gas coolers which have to be re-vamped because of reaching end of lifetime are always very critical system components for the owner, no mat-ter if they are acting as evaporators or boiler feed water preheaters as illustrated in this reference example.Not only the 131 barg design pressure on the water side but also the pressurized H2/CO rich process gas de-mands sophisticated detail design and manufacturing know-how. As operators have to minimize the risk of unplanned shut downs suppliers have to offer the new equipment with the absolute shortest delivery time.

BERTSCH is proud to executed such projects in compe-titive time together with no compromises in quality.

Alexandria, Egypt | Delivery date: Q4/2020