Blue Grass Chemical Agent- Destruction Pilot Plant Quarterly Update June 11, 2014 Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Chemical Destruction Community Advisory Board Presented by: Jeff Brubaker Doug Omichinski Site Project Manager Project Manager
15
Embed
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11, 2014
Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Chemical Destruction Community Advisory Board
Presented by: Jeff Brubaker Doug Omichinski Site Project Manager Project Manager
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update
June 11, 2014
Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Chemical Destruction Community Advisory Board
Presented by:
Jeff Brubaker Doug OmichinskiSite Project Manager Project Manager
A Partnership for Safe Chemical Weapons Destruction
2
Agenda
Aerial Overview Blue Grass Update Photos: Main Processing Facilities, Support Facilities and
Infrastructure Moving Forward Explosive Destruction Technology Facility Laboratory Testing Cyanide Treatment National Research Council Studies Safety Performance Community Involvement Update Community Partnerships and Events
A Partnership for Safe Chemical Weapons Destruction
3
Northwestern Corner - Observation Point
1 2
1
3
5
2
6
Hydrolysate Storage Area
Control and Support Building
Munitions Demilitarization Building (MDB) Filter Banks
MDB
Utility Building
Supercritical Water Oxidation Building (not visible in photo)
Laboratory Building (not visible in photo)
7 65
4
3
7
4
Blue Grass Chemical Agent-Destruction Pilot Plant Construction Site (June 2014)
A Partnership for Safe Chemical Weapons Destruction
4
Blue Grass Updates
Construction now more than 82 percent complete
Systemization activities now more than 18 percent complete
Excavation for Container Handling Building
Excavation and installation of utilities for Medical Facility and Personnel Maintenance Building
Heat trace and insulation of Hydrolysate Storage Area tanks
Continuing installation of Munitions Demilitarization Building filter area ductwork including connection to the Clean-Air Exhaust Stacks
Sheet metal workers get their ducts in a row on the Munitions Demilitarization Building filter banks. Facility air will be cleaned and monitored here before being released to the environment.
A Partnership for Safe Chemical Weapons Destruction
Main Processing Facilities
5
Control and Support Building Facility Control System consoles become operational.
Supercritical Water Oxidation Processing Building
tank construction.
Pipe welding inside the Agent Neutralization System room.
Munitions Demilitarization Building munitions handling conveyor installation.
A Partnership for Safe Chemical Weapons Destruction
Support Facilities and Infrastructure
6
Hydrolysate Storage Area tanks coatings are complete, heat tracing installation begins.
Electrical work continues at the bulk chemical storage area.
Utility Building construction is complete and systemization work begins.
Utility Power Center cable pulling.
A Partnership for Safe Chemical Weapons Destruction
7
Start of Container Handling Building construction Start of Medical Facility and Personnel Maintenance Building
construction Construction of Supercritical Water Oxidation Processing Building
effluent tanks Start-up of boiler system in the Utility Building Start of Entry Control Facility construction Continued installation of Munitions Demilitarization Building major
electrical, piping and instrumentation
Moving Forward
Left, boilermakers install one of the Supercritical Water Oxidation waste tanks. Center, an electrician marks the route for a course of wiring. Right, workers begin excavation for the Container Handling Building.
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technology (EDT) Facility
8
Completed successful 30 percent design review with the Kentucky Department for Environmental Protection in March – 60 percent design review anticipated to
take place in June– 90 percent design review by the end of
July Shared 30 percent design information
with EDT Working Group members Resource Conservation and Recovery
Act permit application March 2014– Initial public comment period closed
mid-May
Above, Robert Blythe, Chemical Destruction Community Advisory Board member, observes the Anniston Static Detonation Chamber (SDC) in action destroying conventional munitions. Right, a 30-percent design architectural image of the Blue Grass SDC facility.
A Partnership for Safe Chemical Weapons Destruction
Laboratory Testing
9
This summer, the Laboratory will start receiving dilute mustard agent for testing
BGCAPP’s plan is to inform stakeholders at least four to six weeks prior to the arrival of dilute agent
The Laboratory Building is systemized and staff are preparing to receive dilute agent for testing.
A Partnership for Safe Chemical Weapons Destruction
10
Cyanide Treatment
BGCAPP is focusing on engineering controls and treatment to provide better protection for workers during plant operations
Enhancing Munitions Demilitarization Building (MDB) heating to Energetics Neutralization Reactors (ENRs) to increase operating temperature
– Safely and efficiently destroys more than 95 percent of cyanide
– Does not change neutralization process– Does not alter Supercritical Water Oxidation
process– Does not impact weapons destruction baseline
schedule
MDB systems enhancements
– Insulating jacket placed around reactors– Heat exchanger added to increase temperatures– Heat exchanger added to cool sampling line
Above, a graphic of the Energetics Neutralization Reactors in the Munitions Demilitarization Building. Below, a representative heat exchanger.
A Partnership for Safe Chemical Weapons Destruction
National Research Council (NRC) Studies
11
NRC will conduct a study to determine an alternative approach to hydrolysate treatment at PCAPP and BGCAPP– Prior to the study, NRC members will conduct a meeting in
Colorado and Kentucky– BGCAPP’s study will be completed summer 2015– The project will share data and previous studies with NRC
CAC/CDCAB chairs reviewed Statement of Task Opportunity for community engagement with NRC as the study
continues (January 2015)
A Partnership for Safe Chemical Weapons Destruction
3.2
1.10.98
0.07
Recordable Injuries Lost-Time Injuries
Construction IndustryBechtel Parsons
12
Safety Performance
12-month rolling rate
Accidents per 200,000 job hours
Safety remains a core value of the project workforce
Occupational Safety and Health Administration Voluntary Protection Program (VPP) Star Status site
Three-year VPP reassessment in August 2014
Lost-time injury rate is 98 percent lower and recordable injury rate is 69 percent lower than industry average
As of April 30, 2014, the project has completed 1,877,720 hours and 230 days without a lost-time accident
Safety remains a core value of the project workforce
Occupational Safety and Health Administration Voluntary Protection Program (VPP) Star Status site
Three-year VPP reassessment in August 2014
Lost-time injury rate is 98 percent lower and recordable injury rate is 69 percent lower than industry average
As of April 30, 2014, the project has completed 1,877,720 hours and 230 days without a lost-time accident
A Partnership for Safe Chemical Weapons Destruction
Community Partnerships/Events
13
A Partnership for Safe Chemical Weapons Destruction
Community Involvement Update
14
Raised $7,500 for Big Brothers Big Sisters at Bowl for Kids’ Sake event
Habitat for Humanity 100th home build in Richmond
Raised $3,000 for American Heart Association Walk
Raised $7,500 for American Diabetes Association duringStep Out walk
Raised $100,000 for United Way; received 2014 Commitment to Community award
Other fundraising efforts
Bowl for Kids’ Sake.
Habitat for Humanity 100th home build.
A Partnership for Safe Chemical Weapons Destruction
Questions/Discussion
15
For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office at (859) 626-8944.