-
'
VIETSOVPETRO VIETSOVPETRO
Document No. : BK14-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014
Page : 1 of 14 1F01
VIETSOVPETRO JOINT VENTURE
PROJECT TITLE : THE GASLIFT BK14-BT7 EXTENSION LOCATED AT "WHITE
TIGER" FIELD
DOCUMENT TITLE : PAINTING SPECIFICATION
DOCUMENT NO. : BK14-BT7-S-SP-001
esk ...
-
VIETSOVPETRO
NO Revision Document No : BK14-BT7-S-SP-001
No : 0 Date : 04/03/2014 Page : 2 of 14 VIETSOVPETRO
4113141M-13nE
TABLE OF CONTENT 1.0 PURPOSE 3
2.0 SCOPE 3
3.0 DEFINITIONS 3
4.0 SURFACE PREPARATION 4
7.0 SPRAY APPLICATION 8
8.0 BRUSH AND ROLLER APPLICATION 9
9.0 REPAIR OF COATING/PAINT DAMAGE 9
10.0 COATING/PAINTING AFTER WELDING 9
11.0 INSPECTION 10
12.0 SAFETY 11
13.0 APPENDIX A DETAILED COATING SYSTEMS 12
14.0 APPENDIX B 14
-
Document No : BK14-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014
VIETSOVPETRO 14I:SWVPETRO Page : 3 of 14 1.0 PURPOSE This
procedure is served as a guideline for the surface preparation and
painting / coating application of facilities.
2.0 SCOPE The procedure covers the methods, equipments and
materials to be used for carrying out surface preparation and
painting/ coating application of facilities including structural
steel works, tanks, vessels, piping systems, etc. Specialized
equipment supplied by vendors such as valves, pumps, compressors,
etc. will be coated in compliance with the User's respective
functional specification; as such they are not covered under this
procedure.
3.0 DEFINITIONS 3.1 General definitions
The Company is a joint venture established by and between two
governments Russia and Vietnam, carrying out of exploration and
production of petroleum resources in the OPERATION AREA. The
Contractor is the party, which carries out all or part of the
design, engineering, procurement, construction and commissioning or
management of the project or operation of a facility. Paint
Contractor is a sub-contractor employed to carry out the part of
the project which includes surface preparation and application of
the paint coating system. The Manufacturer/Supplier is the party,
which manufactures or supplies equipments and services to perform
the duties specified by the Contractor. The word shall indicate a
requirement. The word should indicate a recommendation.
3.2 Specific definition The Painting System is a term intended
to include, with equal emphasis, not only the well accepted
components of a system such as surface preparation and paint
materials, but also the application, inspection, and safety
functions. The Coating System is a term which refers to the applied
and cured multilayer film or to the components of a system based on
non-paint type coating. The Paint is the material in the general
sense, includes primers, enamels, varnishes, emulsions, catalyzed
coatings, bituminous coatings, and other organic coatings.
Inorganic coatings, which are applied in the same manner as paints,
are included in this definition. The Work is a term, which refers
to all works associated with the selection of the painting and
coating systems, surface preparation, paint application, and
inspection. The Initial painting is the painting of new
construction projects or complete recoating of existing facilities
during major maintenance. The Maintenance painting is the Periodic
painting (repair/touch up of corroded areas or deteriorated
paintwork) after initial painting.
3.3 Abbreviations RH Relative Humidity DFT Dry Film Thickness
WFT Wet Film Thickness QC Quality Control
-
VIETSOVPETRO
OWi 4 Document No : BK14-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014 Page : 4 of 14 VIETSOVPETRO 4111:1143;-3P IM
HSE
Health, Safety and Environment EQA Environmental Quality Act
ASTM American Society for Testing & Material ISO
International Organization for Standardization
3.4 Applicable codes and standards SSPC SP 1 SSPC SP 2 SSPC SP 3
SSPC SP 5/NACE 1 SSPC SP 10/NACE 2 SSPC SP 6/NACE 3 NACE Standard
RP0287
BS EN ISO 14713
BS EN ISO 12944 ISO 8401: 2007
ISO 8501-1:1998
BS 7079 Pt.A1
ASTM D 3359 ASTM D 4541
4.0 SURFACE PREPARATION 4.1 General
Solvent cleaning Hand tool cleaning Power tool cleaning White
metal blast cleaning Near white blast cleaning Commercial blast
cleaning Field measurement of surface profile of abrasive blast
cleaning surface using Replica Tape Zinc coatings, guidelines and
recommendations for the protection against corrosion of iron and
steel in structure
Protective paint system Metallic coatings. Review of methods of
measurement of ductility Preparation of steel substrates before
Application of paint and related Products-Visual Assessment for
Surface Cleanliness Preparation of steel substrates before
Application of paint and related Products Measuring Adhesion by
Tape Test Pull-off strength of coating using portable Adhesion
Testers
For optimum paint coating performance, surfaces to be painted or
coated shall be completely dry and free from burrs, weld spatter,
flux, rust, loose scale, dirt, grease, oil and other foreign matter
before any coat is applied. After preparation of the substrate
surface, any grit, dust etc. shall be removed and a layer of primer
applied before any corrosion or recontamination occurs, normally
within 4 hours after blasting. Surface preparation shall be carried
out by dry blast-cleaning wherever possible. The surface
preparation grades shall be as specified for the various painting
and coating systems. Surface preparation shall be subjected to
inspection before the prime coat is applied to ensure all traces of
dust and foreign matter have been removed by brushing, blowing with
dry clean
-
VIETSOVPETRO
MIM
VIETSOVPETRO 413141G1-3PUEC
Document No : BK14-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014 Page : 5 of 14
compressed air, or vacuum cleaning. 4.2 Pre-cleaning of surfaces
and solvent cleaning
This cleaning procedure is mandatory before further cleaning or
surface preparation. Prior to the actual cleaning operation,
surface contaminants such as oil, grease, hydrocarbon, etc. shall
be removed preferably by degreasing with suitable degreaser or
solvent cleaning. The degreased surface shall be further washed
with fresh water to remove all traces of the chemicals. The surface
shall be allowed to dry thoroughly before proceeding with any
further coating work. This procedure also applies to all metal
surfaces to be coated that do not require blast cleaning or power
tool cleaning. The procedure shall be cleaned in accordance with
the SSPC SP-1. Excessive rust scale shall be removed by impact
cleaning tools or high pressure water jetting. Before abrasive
blast cleaning, all equipment which could be damaged by blast, dust
or particulate matter shall be suitably protected by masking,
wrapping, tapping, or other means to prevent damage. The equipment
shall include, but not necessarily be limited to, the
following:
- Bearings - Control panels - Control valves - Conduit -
Instrument dials - Expansion joint bellows - Machined surfaces -
Shafts - Push buttons - Tags - Screws - Exposed moving parts
4.3 Surface preparation by abrasive blasting 4.3.1 General
Surface preparation by abrasive blasting shall be to a near
white metal. Surface preparation by abrasive blasting shall be
cleaned in accordance with the SSPC SP-10 or ISO 8501-1: 1988, Sa
2.5. The fmish visual standard in accordance with SSPC-SP-5, Sa 2.5
at the time of coating. The surface profile after blasting shall be
from 40 to 70 microns.
4.3.2 Preparation for abrasive blasting Prior to abrasive
blasting, all joints are to be continuously welded, and all
corners, edges shall be rounded to a 1.6mm minimum radius. Welds
must be free of pinholes, and all weld spatter shall be removed
prior to blasting. Before and after abrasive blasting, all
weldments shall be closely inspected for the presence of welding
flux, spatter, slivers, inclusions, lamination and underlying mill
scale. Imperfections shall be removed and the immediate area
re-blasted. Prior to blasting, all oil, grease, varnish, soil, salt
and other contaminants shall be removed by solvent cleaning, and/or
wet steam and detergent cleaning.
-
VIETSOVPETRO
MIi M id, Document No : BKI4-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014 Page : 6 of 14 VIETSOVPETRO 4131041M-WiqE
4.3.3 Materials and condition does abrasive blasting Abrasive
material shall be dry, clean and free from contaminates. It shall
be of a type and size adequate to give required surface profile.
Abrasive material shall be selected in accordance with surface
preparation method and hazardous area classification of project.
Blasting is not permitted if the relative humidity is greater than
85 percent, or if the surface temperature is less than 3C above the
air dew point. The compressed air supply for blasting shall be free
of detrimental amount of oil and water. Adequate separators and
traps shall be provided, and shall be frequently checked, cleaned
and emptied. Stainless steel surfaces which are to be coated shall
be cleaned by solvent. Care shall be taken to ensure aluminum,
stainless steel, and all dissimilar metals are segregated form the
surface preparation operations of carbon steel material.
4.4 Surface preparation by hand and power tool cleaning Surface
preparation by hand and power tool cleaning shall be cleaned in
accordance with the SSPC SP-3 or ISO St3. The most technically
effective surface preparation method is abrasive blasting. Manual
preparation shall only be used when abrasive blasting is either not
feasible or not strictly required. Manual cleaning shall be
performed using hand wire brushes or mechanically operated tools
(grinders, chippers or wire brushes). The surface shall be left
roughly and a burnished surface shall be avoided. Where welds occur
within these areas or when these areas cannot accommodate a power
disc, power impact tools shall be applied (vibratory and rotary
hammers, needle guns, chisels) followed by brush cleaning. If the
surface being prepared lies adjacent to a coated surface, which is
not to be refurbished, the power tool cleaning shall overlap the
coated surface by at least 25 mm. Care shall be taken to ensure
that the substrate surface does not become polished during power
tool cleaning.
4.5 Test plan Paint materials should be reviewed and checked
their quality before application. Paint qualification can be done
on suitable steel panels (1 mx 1 mx 10 mm) that are cleaned to the
specified requirement and surface profile before application of
painting systems in accordance with the instructions of the paint
manufacturer(s). The coatings on the panels shall be checked after
complete dry with the minimum following parameters:
Dry film thickness. Defects. Appearance (runs, sags, colors...).
Holiday test shall be performed in accordance with the standard
NACE RP
0188 88 anywhere if necessary. Criteria for acceptable coatings
are no holiday. Adhesion test shall be performed in accordance with
the standard ASTM D
4541. Criteria for acceptable coatings are that adhesion
strength is minimum 2.5 MPa for the coatings
epoxy/polyurethane.
The test results should be recorded in the suitable inspection
report.
-
Document No : BK14-BT7-S-SP-001
Revision No : 0
Date : 04/03/2014 VIETSOVPETRO
VIETSOVPETRO 4C::IMIG1FJM Page : 7 of 14 4.6 Quality Record
The Contractor shall generate quality records from the
inspection and test activities and in accordance with the approved
inspection and test plan(s). The records shall be compiled and
reviewed by the Contractor following the completion of each
inspection and test. Note: The records for qualification of paint
materials that are in accordance with the above technical
requirements also can be reviewed and accepted. 5.0 COATING
MATERIAL
5.1 Material supplier Coating materials for the project should
be supplied by approved paint manufacturers (such as PV Paint, ADP,
Jotun, Sigma, Hempel...).
5.2 Packing and storage All paint and coating materials shall be
furnished in the manufacture's unopened containers, which shall be
identifiable and protected. Lot number and date of manufacture
shall be clearly marked on the containers. The recommended shelf
life and the use by date shall be clearly identified. All materials
shall be stored out of direct sunlight in well-ventilated areas and
away from heat source, in accordance with manufacture's
recommendations.
5.3 Visual check Prior to painting work, the paint shall be
visually checked confirming that the paint is in suitable condition
for application.
5.4 Mixing Coating system All components shall be thoroughly
mixed by mechanical means. This mixing shall be done in cleaned
containers, free from traces of grease, other paint or
contaminants. Multi-component coating, such as inorganic zinc,
epoxy and urethane, the components shall be measured accurately
under the manufacturer's directions.
5.5 Thinner Thinner/paint ratio will be confirmed to the limits
recommended by the manufacturer.
5.6 Pot life The coating manufacture's recommended pot life
shall not be exceeded. When this limit is reached, the spray pot
shall be emptied and cleaned, and new materials shall be mixed.
6.0 GENERAL APPLICATION 6.1 Application
Painting shall be carried out by airless spray, air spray, brush
or roller according to paint manufacturer's recommendation.
6.2 Environmental conditions Painting or coatings shall not be
applied when any of the following conditions exist: Painted surface
is wetted.
-
Document No : BK14-BT7-S-SP-001 * Revision No
: 0 Date : 04/03/2014
VIETSOVPETRO VIETSOVPETRO 411:20011091M Page : 8 of 14
Relative humidity exceeds the manufacturer's recommendation or
85% whichever is the lower. Steel surface temperature is less than
3C above the dew point Ambient or surface temperature is above or
below the manufacture's recommended temperature for application.
Whenever painting is carried out in the field, and poor weather
conditions prevail, adequate precautions shall be taken to protect
the activity from adverse effects of wind and rain.
6.3 Dust Every possible precaution shall be taken to eliminate
dust before and during painting process. Cleaning down prior to
painting is recommended by manufacturer following long periods
between coats and following inclement weather. Cleaning down may be
done by fresh water spraying, sanding paper or by other approved
methods.
6.4 Primer coating Blasting cleaned surfaces shall be coated
with one complete application of primer as soon as is practically
possible, but in no case later than 4 hours after blasting.
6.5 Dryness Each coat shall be in a proper state of cure prior
to the application of succeeding coats. Materials shall be
considered dry for re-coating when manufacture's technical
representative has accepted the coat and the additional coat can be
applied without the development of any detrimental film
irregularities, such as lifting or loss of adhesion of the
undercoat. The dry time as specified in the manufacture's data
sheets, will be observed at all times.
6.6 Re-coating The maximum and minimum re-coating interval in
the manufacture's data sheets will be observed before successive
coats are applied. The only exception to this may be after
application of a mist coat where the recommended re-coat interval
may be reduced in accordance with the coating manufacturer's
recommendations. Any thin spot or area missed in the application
shall be re-coated and permitted to dry before the next coat is
applied.
6.7 Masking All nameplates, manufacture's identification tags,
machine surfaces, finished flange faces, control valves etc., shall
be masked before painting to prevent painting contamination.
7.0 SPRAY APPLICATION Spray coating shall comply with the
followings:
Coating manufacturer's recommendations. Spray equipment
manufacturer's recommendations for the coating material and This
procedure.
7.10perators Operators shall be skilled in the proper
application technique for each coating.
7.2 Spray application Prior to application, all coating material
shall be vigorously stirred in spray pot until pigments,
-
VIETSOVPETRO eN VIETSOVPETRO 410111G3IPIM
Document No : BK14-BT7-S-SP-001
Revision No : 0 Date : 04/03/2014 Page : 9 of 14
vehicles, and catalysis are mixed thoroughly. Prior to add new
material, lines, pots and guns shall be thoroughly cleaned
following each application. Solvent left in the equipment shall be
removed completely before coating the prepared surfaces. For
optimum spraying effectiveness, the pressure on the material in the
pot and of the air at the gun shall be adjusted and maintained to
deliver the material at the rate specified by the manufacturer. Air
pressure and volume shall be minimum required to properly atomized
the coating material. The spray gun shall be hold perpendicular to
the surface at all times and a maximum distance of 300mm from the
surface and no closer than 200mm to the surface that will ensure
depositing a fully wet layer of coating material on the surface.
Arching of the gun is not permitted. Parallel, even passes shall be
made that overlap the previous spray coating by 50 percent. Large
continuous surfaces shall be coated by two passes made at right
angles to each other. All runs, air bubbles, sags and other
imperfections shall be brushed out immediately or the coating shall
be removed and re-sprayed.
7.3 Equipment cleaning Spray guns, lines and pressure pots shall
be cleaned prior to adding a new material. The air caps, nozzles
and needles shall be those recommended by the coating manufacturer
for the material being sprayed.
7.4 Compressed Air Compressed air shall be free from water and
oil. Suitable air filters, separators and traps shall be provided
and installed in the coolest part of the system , they shall be
regularly emptied to prevent carrying over of water and oil.
Accumulations of oil and moisture shall be removed from the air
receiver by regular purging. Air compressor shall not deliver air
at a temperature in excess of 110C. 8.0 BRUSH AND ROLLER
APPLICATION Coating may be applied with a brush and roller in areas
that can not be spray coated. Brushes shall be of a style, quality
and composition that enable proper coating application. Round or
oval brushes are the most suitable for coating rivets, bolts, and
irregular surfaces. Wide flat brushes are suitable for large flat
surfaces. A brush width greater than 125mm is not acceptable.
Successive coats shall be applied by crosshatching the previous
coat. Runs, air bubbles and sags shall be brushed out immediately.
Coating shall be worked into all crevices, and corners. Surfaces
not accessible to brushes shall be coated with daubers.
9.0 REPAIR OF COATING/PAINT DAMAGE Surface preparation for
damaged areas shall be performed using hand wire brushes,
galvanizing damaged method or mechanically operated tools
(grinders, chippers or wire brushes). The surface shall be left
roughly and a burnished surface shall be avoided. All damaged
areas, before and after erection, shall be repaired, using the
original coating system. Where paint has been damaged or is loosely
adhering, the paint shall be removed and the surface shall be
thoroughly cleaned prior to applying the new coating. If repair to
the coating of vendor supplied equipment is necessary, it shall be
carried out in accordance with the vendor's recommendations and
only after Company approval.
10.0 COATING/PAINTING AFTER WELDING This is achieved by approved
methods, but is generally used where paint surfaces were
damaged
-
VIETSOVPETRO eN VIETSOVPETRO 4C11)4:11r1P91E3
Document No : BK14-BT7-S-SP-001 Revision No : 0
Date : 04/03/2014 Page : 10 of 14
during the fabrication and welding operations. The method for
coating/painting in these areas shall be the same as the method of
repairing the painting damage.
11.0 INSPECTION 11.1 General.
To ensure the quality control inspection requirements are
maintain during the abrasive blast cleaning and painting
operations. Inspection will be carried out by Inspector and project
Engineer in accordance with the requirements of this procedure. As
a minimum following requirements for each coating system, the
following aspects shall be recorded in a coating inspection
record:
Ambient condition (at each occasion of abrasive blast cleaning
or coating application) including ambient temperature, surface
temperature, relative humidity.
Coating batch number, cure time, thinner to be used, and ratio
between thinner and coating material.
Quality of surface preparation/ surface profile. Dry film
thickness of each coat. Dry film thickness of the total system.
Visual aspects of the coating. Production Test: pull-off, adhesion,
holiday testing.
11.2 Visual inspection Each coat and complete coating shall be
visually inspected for appearance. The coating shall be flatness,
under coat not be seen, free from excessive sagging, pinholes and
blisters, cracks, extensive over dripping, etc.
11.3 Dry Film thickness 11.3.1 Dry Film Thickness
Measurement
The dry film thickness of each coat shall be spot checked by
using means of a magnetic type thickness gauge or comparable
instrument.
11.3.2 Zero Setting The gauge shall be set to scale zero on a
flat section of steel with surface finish prepared in accordance
with this procedure.
11.3.3 Dry Film Thickness (DFT) Value Each 10 square meters of
area of painted/ coated surface shall be measured with at least
five (5) separate spots spaced evenly. Each spot shall be measured
and recorded with three readings. The average of DFT of 5 spot
measurements for each such 10 square metres area shall not be less
than specified thickness. No single spot measurement value in any
10 square metres area shall be less than 80 % of specified
thickness. No measurement of DFT will normally be made on
machinery, equipment, small bore pipes with nominal diameter less
than 50 mm, pipe supports, machinery seats, small fittings and pipe
supports where the geometrical surface limits practical inspection.
DFT values shall be recorded on Coating inspection Report/
Record
-
VIETSOVPETRO
Miiii Document No : BK14-BT7-S-SP-001 Revision No : 0 Date :
04/03/2014 Page : 11 of 14 VIETSOVPETRO 41C1141M-30715Z
12.0 SAFETY All Coating Contractors using this standard, shall
have a section in their Safety Management System devoted to
industrial coating applications. This shall include, but not be
limited to the following sections.
12.1 General A safe area shall be established and clearly
identified for handling and storage of all flammable materials and
for waste disposal. No source of ignition shall be permitted within
the safe area at any time. The Contractor shall take proper
precautions before and during work in confined areas and/or in
areas with the potential for fire or explosion. If possible, all
electrical equipment shall be located remote from the hazardous
work area in a well-ventilated, non-hazardous space. All electrical
equipment intended for such areas shall be of an approved type in
accordance with the area classification requirements established by
the relevant IEC codes. The Contractor shall provide and maintain
fire extinguishers approved for the expected fire hazard near or in
all work areas. The Contractor shall provide and install sufficient
scaffolding and staging for easy access during surface preparation,
coating application, and inspection of all surfaces. The supporting
structure and the surface or item being worked on shall be
constructed so that workers will have free use of body and arms.
The structures shall be provided with safety features that will
help prevent accidents. The structures shall comply with all
applicable OSHA requirements. The Contractor shall exercise extreme
care and caution when working in the vicinity of in-service
facilities. All valves, switches, and controls shall remain unmoved
and undisturbed.
12.2 Handling of Chemicals Material Safety Data Sheets (MSDS's)
shall always be available for review during transport and prior to
the application of the product. Manufacturer's instructions for the
safe handling of products shall be followed to minimize the risk of
injury or creation of health hazards to personnel. Handling of
coatings and chemicals shall be carried out with due care and
diligence. The correct use of personal protection equipment (PPE)
shall be employed during the coating preparation and application.
Disposal of chemicals must be treated with due regard to
environmental protection.
12.3 Spray and blasting operations Abrasive blasting and spray
coating shall be performed with approved equipment by experienced
operators. The Contractor shall provide all operators with hoods
for protection against abrasives and with paint masks that are OSHA
approved for extended service. The hoods and masks shall be worn at
all times when work is being done. Pressure vessels, such as sand
hoppers and compressed-air volume tanks, shall be protected from
over-pressurization with automatic pressure relieving devices.
Pressure nozzle controls shall be of the fail-safe, dead-man type.
Pressure hose connections shall incorporate a positive locking
mechanism to prevent accidental disconnection (For example,
quick-connect connections shall have safety wire in place).
Adequate ventilation shall be provided in confined areas with
blowers capable of a minimum of 12 air changes per hour.
-
VIETSOVPETRO eIM VIETSOVPETRO C:041M-IF
Document No : BK14-BT7-S-SP-001
Revision No : 0 Date : 04/03/2014 Page : 12 of 14
Spray and blasting equipment in confined areas shall be securely
grounded to dissipate static electrical charges. Hand tool shall be
made of spark-proof materials.
12.4 Pressure Equipment The safe operation of all pressure
equipment shall be detailed in the Contractors Safety Management
System and show how, when and records for the inspection of such
equipment. The equipment and associated connections shall be
regularly inspected and well maintained.
12.5 Earthing All equipment, particularly nozzles, tanks, piping
and cable trays and cable ladders shall be earthed to prevent
sparking and electric shocks from static electricity.
12.6 Breathing Apparatus Appropriate air-fed masks should be
used during blasting and coating operations. Other personnel in the
vicinity shall wear suitable protective masks or respirators when
necessary. Adequate ventilation must be provided in confined spaces
and when using air-fed masks in these areas, attention should be
paid to the possibility of explosive vapor build-up. As a minimum,
dust, rust and vapors should be directed away from the operator by
wind or extraction fan.
13.0 APPENDIX A DETAILED COATING SYSTEMS
Surface to be coated Operating Temp. System Remark
Structure steel, carbon steel equipment, piping, valves, vessels
etc.
Ambient up to 110C I
Galvanized and aluminum alloy surfaces Ambient bien t II
Ladders, cages, stairs, handrails and where nominated
Stainless steel Ambient to 100C III Where nominated
Earthing connections Ambient IV
COATING SYSTEM I
SCOPE: Structural steel, carbon steel equipment, piping,
vessels, valves, motors, guards with surface operating temperature
up to 110C
PREPARATION: Abrasive Blast Cleaning
-
VIETSOVPETRO eN VIETSOVPETRO 4341311-11PIED
Document No : BK14-BT7-S-SP-001 Revision No : 0
Date :04/03/2014 Page : 13 of 14
COAT PRODUCT DESCRIPTION MN DRY FILM THICKNESS (microns)
PRIMER
INORGANIC ZINC SILICATE (Note 1)
75
INTERMEDIATE HIGH BUILD EPDXY
150
FINISH
POLYURETHANE
50
TOTAL MINIMUM DRY FILM THICKNESS
275
NOTE: One layer of tie coat epoxy or mist coat epoxy with about
35 microns DFT is to be applied after inorganic zinc silicate
primer ._
COATING SYSTEM II
SCOPE: Galvanized and aluminum surfaces (where nominated)
PREPARATION: Sweep Blast Cleaning before applying primer
COAT PRODUCT DESCRIPTION MIN DRY FILM THICKNESS (microns) PRIMER
ETCH PRIMER 10(Max)
INTERMEDIATE HIGH BUILD EPDXY 150
FINISH POLYURETHANE 50
TOTAL MINIMUM DRY FILM THICKNESS 210
COATING SYSTEM III SCOPE: Stainless steel surfaces up to 100C
(where nominated) PREPARATION: Sweep Blast Cleaning before applying
pnmer
COAT PRODUCT DESCRIPTION MN DRY FILM THICKNESS (microns) PRIMER
ZINC PHOSPHATE EPDXY PRIMER 50 - 75
FINISH POLYURETHANE/ ACRYLIC POLYSILOXANE
50
TOTAL MINIMUM DRY FILM THICKNESS 100 - 125
NOTE: Stainless steel surfaces shall not be coated unless either
specifically nominated or the component is to be insulated.
-
VIETSOVPETRO MIN VIETSOVPETRO 401n4131.-X3 1M
B0K14-BT7-S-SP-001 RDeovciumsioennNt No o :: Date : 04/03/2014
Page : 14 of 14
COATING SYSTEM IV SCOPE: Following installation of equipment and
connection of earth leads
to earth bosses, all exposed carbon steel on the earth
connection shall be coated with the following system
COAT PRODUCT DESCRIPTION MIN DRY FILM THICKNESS (microns) PRIMER
ZINC RICH EPDXY 50 75
TOTAL MINIMUM DRY FILM THICKNESS 50 - 75
NOTE: 1. Prior to touch up coating of exposed carbon steel, the
surface shall be prepared. 2. In addition, the earth connection
shall be wrapped with Denso tape.
COLOR
1. Process Gas and Blow down: SIGNAL YELLOW 2. Instrument air:
BLUE 3. Water spray pipe: RED 4. Steel structure: DARK GREEN
NOTE: The color of previous fmal coat should be different to,
but corresponding to final coat
14.0 APPENDIX B Form of Painting Inspection Report
-
APPENDIX B
INSPECTION'S DAILY REPORT ANTICORRODING WORKS
PROJECT: Date: .... / / Location: Date of the week: Sun / Mon /
Tue / Wed / Fri / Sat
Sheet No.:
Contract No Client Contractor
Weather condition N/C Criteria Air Temperature Ta, C RH, % RH
< 85% Steel Temperature Ts, C 0 C < Ts < 50 C Dew Point
Td, C AT = Ts Td, C AT>3C
Acceptance q Accepted q Not Accepted
q Accepted q Not Accepted
q Accepted q Not Accepted
q Accepted q Not Accepted
Surface preparation Start time End time Method q Abrasive Blast
Cleaning q Power Tool Cleaning q Hand Tool Cleaning Degree of
cleanliness q Sa2.0 q Sa2.5 q Sa3.0 q St3 q St2 Surface profile
Paint Application l coat 2nd coat 3' coat 4th coat Remark Start
time End time
Method q Airless spray
q Brush q Airless spray q Brush
q Airless spray q Brush
q Airless spray q Brush
WFT, micron DFT, micron
Paint Technical Data Batch number of Base
Batch number of Hardener Batch number of Thinner
Comment:
Review by: Inspector's Signature QC Engineer Date
Page 1Page 2Page 3Page 4Page 5Page 6Page 7Page 8Page 9Page
10Page 11Page 12Page 13Page 14Page 15