Biovail Project Name Biovail Technologies, Dublin Project Size 2,500 m² Project Value €1.8 million Project Duration 6 months Client Biovail Cleanroom Classification Class C, ISO 6 Class D, ISO 7 & ISO 8 This negative pressure tablet manufacturing and coating facility includes a number of 6.7m high rooms, low-level extract ducts and stainless steel service panels. Ceilings – 1,900m² of fully flush long-span walk-on plank ceiling panels. Partitions – 2,500m² of metal faced fully flush FM approved paneling 50mm thick. Doorsets – Provision of approx 35 fully flush non rated doorsets and 10 fi re rated units. Furniture – Design, manufacture and installation of an integrated step over bench. Structural – Design, supply and installation of a subgrid structure above entire ceiling including integrated handrails to the perimeter. Interlocking – Design, supply, installation and commissioning of interlocking to 6 doorsets. HVAC – Low-level cleanroom paneled extract ducts. Miscellaneous – Stainless steel service plates and magnetic service panels.
1

Biovail - asgardcleanrooms.com

Feb 22, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Biovail - asgardcleanrooms.com

BiovailProject Name

Biovail Technologies,

Dublin

Project Size2,500 m²

Project Value €1.8 million

Project Duration 6 months

ClientBiovail

Cleanroom Classification Class C, ISO 6

Class D, ISO 7 & ISO 8

This negative pressure tablet manufacturing and coating facility includes a number of 6.7m high rooms, low-level extract ducts and stainless steel service panels.

Ceilings – 1,900m² of fully flush long-span walk-on plank ceiling panels.

Partitions – 2,500m² of metal faced fully flush FM approved paneling 50mm thick.

Doorsets – Provision of approx 35 fully flush non rated doorsets and 10 fi re rated units.

Furniture – Design, manufacture and installation of an integrated step over bench.

Structural – Design, supply and installation of a subgrid structure above entire ceiling including integrated handrails to the perimeter.

Interlocking – Design, supply, installation and commissioning of interlocking to 6 doorsets.

HVAC – Low-level cleanroom paneled extract ducts.

Miscellaneous – Stainless steel service plates and magnetic service panels.