Aaron Organ – Director / Principal Ecologist Adelaide, Brisbane, Melbourne, Geelong Ph (07) 3221 3352, Mob. 0425 873 159
Jun 14, 2015
Aaron Organ – Director / Principal Ecologist
Adelaide, Brisbane, Melbourne, Geelong
Ph (07) 3221 3352, Mob. 0425 873 159
Biodiversity offset policies (State comparison)
Key Issues
Brief examples
Solutions
Concluding thoughts
Overview
6
Hierarchy
Development proposals need to demonstrate:
◦ Avoidance of impacts
◦ Minimisation of impacts
◦ Mitigation of impacts
Residual (unavoidable) negative environmental impacts from a development are subject to offsets
Introduction
7
Queensland Government Environmental Offset Policy (2008) (QGEOP) – overarching framework for environmental offsets in QLD.
Four specific offset policies support the QGEOP:
1. Policy for Vegetation Management Offsets;
2. Mitigation and Compensation for Works or Activities Causing Marine Fish Habitat Loss;
3. Offsets for Net Benefit to Koalas and Koala Habitat (2010); and
4. Queensland Biodiversity Offsets Policy (2011).
Each policy specifies the manner in which offsets can be provided (i.e. a land based offset and/or a monetary contribution).
Offset Policies - Qld
8
A biobanking statement obtained for development assessed under Parts 4 or 5 of the EP&A Act, also Part 3A applications
Precludes the need for additional assessment of impacts to threatened species
Limited implications under the TSC Act - voluntary offset scheme (no requirement to source any offsets using the scheme or register offsets under the scheme)
Methodology highly complex
BioBanking and Offset Scheme - NSW
9
Two types of biodiversity credits – species credits and ecosystem credits
Small number of projects have been finalised (offsets have been achieved in other ways)
Cost of offsets and funding for management of offset sites are negotiated
Offsite offsets are managed by landowner not the developer
BioBanking and Offset Scheme - NSW
10
Victoria’s policy on native vegetation is the document, Victoria’s Native Vegetation Management – A Framework for Action (2002)
Primary goal is the reversal of decline in extent and quality of native vegetation i.e. Net Gain
BushBroker Scheme administered by Department of Sustainability and Environment
Offsets need to be quality ‘like for like’
Net Gain calculator, 10yr OMP (although needs to be permanently secured)
Currently being reviewed (incorporate risk and proportionality, increasing options to offset on site or pooling multiple small offsets at larger sites through over-the-counter offset schemes)
Net Gain - Victoria
11
NSW - no assessments for threatened species when using BioBanking
NSW - consent authority includes the conditions of the biobanking statement in the development consent – differs to Vic where it states an approved Offset Management Plan (OMP), Qld Offset Area Management Plan (ceases when mapped as remnant native veg.)
Vic - emphasis on vegetation offsets, minimal focus/process and options for threatened species offsets
Qld - lack of empirical data on species distribution and accuracy of RE mapping (large State), offsets cannot be remnant vegetation
Qld - exemptions for certain projects, also and doesn't apply to all vegetation communities or species (typically only State significant biodiversity values)
Main differences between the States
12
Inaccurate advice - overestimating or understating ecological values
Currently high expectation of level of survey effort for offset analysis
Project size and complexity (multiple values across a larger area)
Poor communication and negotiation with regulators
Project Risks - ‘the issues’
13
Poor negotiation between broker and landowner
Duplication of offset process
Security of offset site prior to commencement
Land based offset requirements restrictive
Complex and evolving legislation and policies
Practical management of offset site(s) (in perpetuity)
Project Risks - ‘the issues’
Problems
Understating the impact
Overstating the impact
Messing up offsets
No problems
Pre-empting problems
Working with regulators
Ornamental snakes and genetic fragmentation ◦ Vulnerable EPBC Act / NC Act
◦ Why genetic fragmentation is difficult to cause for such a species
◦ Whole reason for the project being a ‘controlled action’ under the Act
◦ Project delays, conditions placed on approval leading to additional costs
◦ Large habitat offsets required
16
Clearing of vegetation prior to offsets and ecological equivalence ◦ Automatic scores of 100 for cleared vegetation
◦ The vegetation would have only scored ~60 if properly surveyed
◦ No vegetation in offset area scores >70
◦ If surveys had been completed (with a realistic score) the total offset liability would have been less
18
19
I’m concerned about the costs and delays for my mining, energy and infrastructure projects, what are the solutions?
Get the right advice early
Locate and secure offsets prior to the lodgement of EIS/DA
Look for legal precedents associated with offset requirements (ratios, areas)
Don’t be afraid to work with regulators
Get the lawyers involved (ensure you check the finer details under the State and Commonwealth conditions of approval)
Ensure specialist botanists and zoologists undertake assessments and review the draft conditions (peer review of reports)
Issues with combined offsets from the clients perspective (timing, compliance)
Don’t try and circumvent the process!
Solutions
20
Are offsets hear to stay – yes, they are.
Increased complexity – although all Governments are attempting to streamline the process
Difficult for regulators to validate the offset areas (rely on their consultants and spatial data)
Harder to locate offsets – habitat recreation/revegetation
Practical management – who manages and audits the offset (compliance). Developer often doesn’t have the desire or expertise to manage the offset in the short term and in perpetuity
Future Considerations
21
Use of spatial and satellite data to improve your confidence in potential offset sites prior to field
Environmental loss is immediate – restoration/rehabilitation outcome is not as certain and has inherent difficulties
Early investment by Government - lack of funding?
Large offsets can be facilitated in a coordinated way (strategic approach)
Future Considerations
22
23
Aaron Organ Director / Principal Ecologist
0425 873 159
Adelaide - (08) 8372 7829 Brisbane – (07) 3221 3352 / Geelong – (03) 5221 8122 / Melbourne – (03) 9377 0100
www.ehpartners.com.au