Binamare Sub-Health Post Building Construction Support Project Binamare VDC- 4, Baglung, Nepal Funding Organisation: Rotary Stiftung – Rheine, Germany Implementing Organisation: Social Welfare Association Of Nepal (SWAN)
34

Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Apr 16, 2018

Download

Documents

trinhtruc
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Binamare Sub-Health Post Building

Construction Support Project

Binamare VDC- 4, Baglung, Nepal

Funding Organisation:

Rotary Stiftung – Rheine,

Germany

Implementing Organisation:

Social Welfare Association Of Nepal

(SWAN)

Page 2: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Nepal Political

Baglung District

Page 3: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Baglung political

Binamare SHP Building

Construction Site

Page 4: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Introduction of Village and Health Service

� Binamare VDC is situated in the southern part, about 25 km far from district

headquarters of Baglung.

� There are 9 wards and population more than 3,500 in this VDC.

� The area is composed with various ethnic community inhabitants, such as,

Brahmins, Magars, Chettris, Sarkis, Damai, Newar, and other castes.

� This community life is based on farming and livestock.

� The sub-health post is the only health service institution for people in this area.

� The current sub health post is situated in a building which is a part of a

secondary school and is in a ruined and poor condition, which is not at all

suitable to carry out the task of providing health care facilities.

� In order to get out of this difficult situation to provide the health services to the

people, it was an urgent need to have a sub-health post building being

constructed in order to provide health services to the local community.

Page 5: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

SHP Organogram

There are 4 staff in Binamare Sub-health post provided by the government

SHP

Management

Committee

Incharge -

Auxiliary Health

Worker(AHW)

Village Health

Worker (VHW)

Maternal & Child

Health Worker

(MCHW)

Office Helper

Page 6: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Old Sub-health post house provided by the school

Page 7: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

All SHP staff working in one room office Dispensary in the same room

Page 8: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Program introductory workshop

A workshop on project work was conducted, and the SWAN representatives,

Village Development Committee members, all political party representatives,

representatives of various groups of the village and Binamare Sub-health Post

Management committee member and staff participated.

The Binamare Sub-health post construction site was observed by

SWAN President Mr. Krishna Karki, Project manager, Mr. Sakas G. C., together

with the Sub-health Post Management Committee and the site was finalized.

Page 9: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project
Page 10: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

The following are the major activities that have been carried out during the

project period:

� Formation of a SHP construction committee

� Coordination with District Development Committee, District Health Office,

and Village Development Committee

� Constructed 6 rooms for SHP building

� Constructed a toilet

� Fences to be constructed

� Making furniture has been started

� Equipment to be supplied

� Drinking water supply to be constructed

Major activities

Page 11: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Formation of SHP construction committee

A Construction Management Committee was formed with 11 members and they

were briefed about the project by the SWAN project Manager. The following are

the members in the committee:

1. Mr. Krishna Bahadur Hamal President

2. Mr. Prabanna B. K. Vice-President

3. Mr. Tanka Bahadur K. C. Secretary, SHP In-charge

4. Mr. Prem Bahadur Thapa Treasurer

5. Mr. Khum Bahadur Roka Member

6. Ms. Manaka Roka Member

7. Mr. Krishna Paudel Member

8. Mr. Prem Bahadur Malla Member

9. Ms. Pabitra Paudel Member

10. Mr. Bhanu Bhakta Pandey Member

11. Mr. Lal Bahadur Thapa Member

Page 12: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Members and Chairperson, Mr Krishna Bahadur Hamal (Right) of the Building

Construction Committee commencing the construction work

Page 13: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

SHP building construction site

Page 14: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

SHP building construction committee chairperson, Mr. Krishna Bahadur

Hamal (left) and SHP incharge, Mr. Tanka Bahadur K. C., carrying out the

measurement work of the SHP construction site and planning other work

Page 15: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

District Health Officer,

Mr. Arjun Adhikari (centre)

participated the

foundation

laying ceremony

First phase Activities“A Laying of foundation stone event”

Page 16: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

“First Phase of construction work”

Page 17: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Second phase Activities

Building of tie beam and walling

Page 18: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Completion of walling

Page 19: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Wood work for preparation of doors and windows and roofing

Page 20: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Third phase Activities

Preparation of the roof fixing

Page 21: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

A supervision work was carried out by SWAN President, Krishna Bahadur Karki,

Project Manager, Sakas G. C and staff

Page 22: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Completion of roofing

Page 23: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

View from east side of the Binamare SHP Building under construction

Page 24: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Fourth phase Activities

Front view of the Binamare SHP Building under construction

Page 25: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Side view of the Binamare SHP Building under construction

Page 26: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Rooms and partial side views

Page 27: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Corridor

Page 28: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project
Page 29: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Estimated Budget

Amount

Requested

from Donors

To be funded

by District

Development

Committee

To be funded

by

District Health

Office

To be funded

by Village

Development

Committee

Community

contribution Total Budget

Rs.1,548,406 Rs.100,000 Rs.100,000 Rs.300,000 Rs.500,000 Rs. 2,548,406

Euro : 16,507 Euro:1,066 Euro:1,066 Euro: 3,198 Euro :5,330 Euro: 27,168

Page 30: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

ROTARY STIFTUNG – RHEINE,

BINAMARE SUB HEALTH POST CONSTRUCTION PROJECT

(SWAN 2011/12)

1 Fund received from Rotary Stiftung - Rheine Feb 13, 2011 € 3.980,00

2 Fund received from Rotary Stiftung - Rheine June 27, 2011 € 3.980,00

3 Fund received from Rotary Stiftung – Rheine October 13, 2011 € 3.980,00

4 Fund received from Rotary Stiftung – Rheine February 02, 2012 € 4.567,00

Total fund received from Rotary Stiftung - Rheine, € 16.507,00

Page 31: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Community Contributions and VDC Support

PROJECT

BINAMARE SUB HEALTH POST CONSTRUCTION

SWAN 2011/12

1 Fund received from Binamare Village Development Committee Rs. 400,000

2 Community Contributions:

(a) Provided land for building construction

(b) Construction site leveling work

© Provided stone for wall

Rs. 300,000

Rs. 50,000

Rs. 200,000

Total Community Contributions and VDC support in Nepali Rupees

Total Community Contributions and VDC support in Euro

Rs. 950,000

€ 10,128

Page 32: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Expenditure Report

BINAMARE SUB HEALTH POST CONSTRUCTION

SWAN 2011/12

Descriptions

First Phase

Expenses

Second Phase

Expenses

Third Phase

Expenses

Fourth

Phase

Expenses

Total

1 Program Introductory

Cost 26,735 0 0 0 26,735

2 Wages 204,100 329,350 250,200 145,680 933,085

3 Construction Materials,

Transportation and other

costs

256,250 133,205 259,153 315,879 960,732

Total in Nepalese Rupees 487,085 462,555 509,353 461,559 1,920,552

Page 33: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

Binamare VDC and the mountains in the background

Page 34: Binamare Sub-Health Post Building Construction …rotary1870.de/.../Downloads/binamare_shp_building_construction....pdfBinamare Sub-Health Post Building Construction Support Project

See You in October!

Namastey