Page 1: BIM for Building Sitework

4/24/2012

1

Implementing VDC

for Building SiteworkJohn Prince, P.E.

April 24, 2012

2012 San Antonio, TX

Page 2: BIM for Building Sitework

4/24/2012

2

VDC for Building Sitework

Introduction

Results, Lessons Learned, Suggestions

Internal Impacts of VDC Implementation

External Impacts of VDC Implementation

Page 3: BIM for Building Sitework

4/24/2012

7

3D Laser Scanning

3DSite Survey

3D Surveying

Miramar College Interim Library Topo

• Traditional Surveying with3D Processing

• Site Features Generated Automatically

• Accurate Surface Model Readyfor VDC

• Detailed Site Culture to Meet Needs

Page 4: BIM for Building Sitework

4/24/2012

8

• Various Reference Sources

• Ready for VDC

• Embedded System Information

3D Laser Scanning

3DSite Survey

3D ExistingUtility

Modeling

3D Surveying

Page 5: BIM for Building Sitework

4/24/2012

9

−Dynamic 3D Environment

−Detailed Surface Integral with Site Plan

−Data-Rich Utilities and Structures

3DSurveying

3DSite Design

Alpine Blvd Widening

Miramar College Student Union

RBF Experiences/Services

Page 6: BIM for Building Sitework

CSUSM Ballfields

Mesa College SBSB

3D Site Design

Fire Science/EMT Training Facility

Page 7: BIM for Building Sitework

3D Site Design

Page 8: BIM for Building Sitework

3DSite Design

3DSurveying

Camp Pendleton

BEQ 8Conversion Modeling

−Model any Site Utility System

−Phase Utilities or Grading to meet Contractors Need

−Staking of Dry Utilities

−Up-To-Date Model with Construction Changes/As-Built

RBF Experiences/Services

Page 9: BIM for Building Sitework

.NWDfrom each Discipline

.NWDfrom each Discipline

.NWFMaster Model

.NWFMaster Model

Clash Analysis

Clash Analysis

BIM Coordination

Meeting

BIM Coordination

Meeting

Design Revisions and Coordination

Design Revisions and Coordination

RepeatRepeat

3DSite Design

3DSurveying

Site BIM Management

Conversion Modeling

RBF Experiences/Services

Page 10: BIM for Building Sitework

― Real-World Coordinates― Tied by existing conditions/constraints― Design includes existing and proposed conditions, not just all new― Different authoring software than building design― Authoring software is geared more toward public works type projects― Less prefabricated elements or “system” components― Site BIM Management techniques differ

Civil Engineering Design & TechnologyKey Differences with Sitework

Page 11: BIM for Building Sitework

VDC for Building Sitework

Introduction

Results, Lessons Learned, Suggestions

Internal VDC Implementation Impacts

External VDC Implementation Impacts

Page 12: BIM for Building Sitework

Key Differences of SiteworkSo, Why VDC for RBF?

Page 13: BIM for Building Sitework

― Better documentation of existing utility conditions― Detailed surface improves fine grading and ADA design― Model Based/Dynamic Design and Plan Production = Increased

Efficiency, Fewer Errors, and Better Quality End Product

So, Why BIM for RBF?Internal Impacts

Page 14: BIM for Building Sitework

Complete shift in QA/QC process using collaboration software― General Visual QC/Layers― Utility Clashes― Utility Cover― Utility Structure at Grade

Internal Impacts

Page 15: BIM for Building Sitework

Complete shift in QA/QC process using collaboration software― Grading Impacts on Existing Utilities or Early Install Utilities― Water/Sewer/Recycled Water separation― Pipe/Structure Connections

Internal Impacts

Page 16: BIM for Building Sitework

VDC for Building Sitework

Introduction

Results, Lessons Learned, Suggestions

Internal Impacts of VDC Implementation

External Impacts of VDC Implementation

Page 17: BIM for Building Sitework

Increased Project Understanding through more comprehensive model

External Impacts

Page 18: BIM for Building Sitework

― Tighter/More Detailed Design = Less RFI’s― Increased Clarify of Design Changes

― Use of different authoring software between site and building consultants requires some traditional 2D coordination (for now)…

External Impacts

Page 19: BIM for Building Sitework

Coordination Using VDC Methods(collaboration software, BIM tools, etc.)

NEXT

External Impacts

―Vertical Utility Coordination―Grading Impacts to Early Utilities

Page 20: BIM for Building Sitework

Grading Impacts to Early Utilities

External Impacts

Page 21: BIM for Building Sitework

Coordination Using VDC Methods(collaboration software, BIM tools, etc.)

NEXT

External Impacts

―Vertical Utility Coordination―Grading Impacts to Early Utilities―Formation/Soil Layer Analysis

Page 22: BIM for Building Sitework

Formation/Soil Layer Analysis

External Impacts

Page 23: BIM for Building Sitework

Coordination Using VDC Methods(collaboration software, BIM tools, etc.)

NEXT

External Impacts

―Vertical Utility Coordination―Grading Impacts to Early Utilities―Formation/Soil Layer Analysis―Utility Equipment Sizing―Structural Footing Conflicts―Structural Load Influence Conflicts

Page 24: BIM for Building Sitework

Structural Load Influence Conflicts

External Impacts

Page 25: BIM for Building Sitework

Coordination Still Using Traditional Methods(overlays, coordination print review)

External Impacts

―Architectural Site Plan―Horizontal Site Utility Coordination―Building Utility POC Info―Discipline References across Plan Sheets―Pavement Types and Sections―Existing Utility Accuracy and Potholing―Dissemination of Changes

Page 26: BIM for Building Sitework

VDC for Building Sitework

Introduction

Results, Lessons Learned, Suggestions

Internal Impacts of VDC Implementation

External Impacts of VDC Implementation

Page 27: BIM for Building Sitework

Results, Lessons Learned, Suggestions

― File/Building Alignment is Very Important― Need Building Consultants Align with Civil Site

― Building/Site Coordination Tools― Efficient/Repetitive File Sharing/Overlay― Building Doors and Utility POC’s― Site Utilities― Surfaces― Confident Alignment in Collaboration

Page 28: BIM for Building Sitework

VDC Implementation has proven beneficial

The effect of VDC on Sitework needs attention

The VDC Process needs to follow the Design Process/Schedule

Full Buy-in from all consultants is needed for success

Well developed processes/execution are necessary for benefits to be realized

Take-Aways

Page 29: BIM for Building Sitework

Implementing VDC for Building SiteworkJohn Prince, P.E.

Thank You, Any Questions?