BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Dec 17, 2015

Download

Documents

Rosanna Cannon
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.
Page 2: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

2

BIDDERS’ CONFERENCE IT-3981Dismantling, Refurbishment, Replacement and Supply of Electrical

Overhead Travelling Cranes Over 10 Tons Capacity

January 14th-15th 2014 Handling Engineering Group

Site Visits

Page 3: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 3

Visit Schedule - January 14th

January 14th-15th 2014

 

Bonfanti / Meloni+

J.P. Granchelli / H. Lourenço / R. Rinaldesi

Brunnhuber / Brun-Mech+

O. Boettcher / G. Roche / A. Kertesz

14.30 – 16.00 PR712 in building SD4 PR68, PR76 and PR82 in Meyrin

16.30 – 18.00 PR68, PR76 and PR82 in Meyrin PR712 in building SD4

Page 4: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 4

Visit Schedule - January 14th

January 14th-15th 2014

Crane PR Building Location / extent of visit Installation type

A PR712 SD4Surface hall, access on cranes for inspection

Building with space constraints

C PR68 167Surface hall, no access on crane foreseen

Building without space constraints

B PR76 201Surface hall, no access on crane foreseen

Building with space constraints

E PR82 168Surface hall, no access on crane foreseen

Building with space constraints

Page 5: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 5

Visit Schedule - January 15th

January 14th-15th 2014

 

Bonfanti / Meloni+

J.P. Granchelli / H. Lourenço / R. Rinaldesi

Brunnhuber / Brun-Mech+

O. Boettcher / A. Kertesz / G. Roche

9.00 – 10.00 PR720 in cavern UX85 PR725 in building SX8

10.30 – 11.30 PR725 in building SX8 PR720 in cavern UX85

Page 6: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 6

Visit Schedule - January 15th

January 14th-15th 2014

Crane PR Building Location / extent of visit Installation type

D PR720 UX85Cavern crane, no access on crane foreseen

Underground areas

F PR725 SX8Surface hall, access on cranes for inspection

Building without space constraints

Page 7: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 7

Hazards• Access to railways and cranes at ~10 from

the ground

• Underground areas

• Access to radiation areas

January 14th-15th 2014

Page 8: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.

Handling Engineering Group 8

Measures• Personal Protective Equipment: safety

shoes, helmet• Fall-arrest harness (with lanyard)• Dosimeters (escort only)• All visitors shall be authorized by their

employer to work in height and use a harness

• All visitors shall be authorized by their employer to work in radioactive areas

January 14th-15th 2014

Page 9: BIDDERS’ CONFERENCE IT-3981 Dismantling, Refurbishment, Replacement and Supply of Electrical Overhead Travelling Cranes Over 10 Tons Capacity January.