Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS BHEL, TRICHY -14 Welcome
38

Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Dec 17, 2015

Download

Documents

Harriet Ellis
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Fluidized Bed Combustion SystemsBy

M.RAJAVEL, SDGM / R&D/PCPSBHEL, TRICHY -14

Welcome

Page 2: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

What is Fluidization ?

When

Buoyancy Force

balances

Gravity Force

Buoyancy Force

FLUIDISED BED BOILER

Fluidized Bed

FUEL AIR

ASH

Gravity Force

Page 3: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Light object Floats ; Heavier ones Sink

(Fixes Fuel Size)

AIR AIR

Why call it Fluidized Bed ?

Page 4: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Horizontality Maintained

(Fixes Ash drain mechanism from Bed)

Why call it Fluidized Bed ?

ASH

ASH

ASH

Fixed Bed Fluidised Bed

Page 5: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

AIRAIR

Flow / Velocity

P

A

B A B

Pressure drop is Bed Height

(Fixes Fan Power)

Umf

Why call it Fluidized Bed ?

Page 6: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

What is Fluidization ?

When

Gravitational Force

is predominant

Buoyancy

Force

STOKER FIRED BOILER

Fixed Bed

FUEL

AIR

ASH

Upto 25mm

Page 7: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Why call it Fluidized Bed ?

FLUIDISED BED BOILER

FUEL AIR

A Bed of Solid Particles exhibit the

properties of a FLUID namely: Lighter objects float heavier ones sink

Pressure drop is Bed Height

Horizontality maintained

hence termed as Fluidized Bed

ASH

Page 8: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

How does a Fluidized Bed work ?

FLUIDISED BED BOILER

FUEL AIR

The Bed of solid particles have to be retained at that size:

Combustion Temperature has to be well below ash fusion temperature

Heat transfer walls are enclosed

Ash does not fuse - no slagging

Heat transfer by Gas / Particles Convection & Radiation

Fuel size upto 10mm - No PULVERISING

Ash soft amorphous state - less erosion

ASH

Page 9: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

How does a Fluidized Bed work ?

FLUIDISED BED BOILER

FUELAIR

When Fuel is injected into a Fluidized Bed of solid particles which is heated to Ignition Temperature of Fuel, it burns imparting heat to the entire bed

Fuel Combustion takes place due to the heat available in the Bed Ash - millions of

IGNITORS

Fuel of any Quality can be fired

ASH

Page 10: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

FLUIDISED BED BOILER

FUEL AIR

Combustion of Solid Fuel leaves

behind Ash. Finer fraction carried by

flue gas, coarser fraction replenishes

the bed solid inventory and excess is

drained out by drain pipes

Ash is dry and granular and is easily

handled.

How does a Fluidized Bed work?

ASH

Page 11: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Summary of Combustion Technologies

GAS FLOW/VELOCITY

PR

ES

SU

RE

D

RO

P

FIXED BED

FLUIDIZED BED

PNEUMATIC TRANSPORT

Page 12: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Technology Comparison

2.3 - 3 m/s 1.2 - 6 m/s 4.6 - 6.1 m/sVel

6000 m 300 - 1000 m 50 mPar

FUEL FUEL

STOKER

(FIXED BED)

FLUIDISED – BED FIRING

FBC

PULVERISED FIRING

(ENTRAINED BED)

AIR ASHASH ASH

FUELFUEL

AIRAIR

AIR

GAS GAS

GAS

Temp 1600 C 850 C 1600 C

Page 13: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Advantages of Fluidized Bed Combustion Boilers

Low combustion temperature- <900 DegC lead to less Nox emission.

Sulphur present in coal can be recovered in-situ by adding limestone. SOx emission can be reduced >90%

S + O2 SO2

CaO + SO2 +1/2 (O2) --> CaSO4

Poor quality coal/lignite, coal washery rejects, containing ash >70%, can be used.

Biomass fuel can be fired either independently or in combination with fossil fuels.

Page 14: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Advantages of Fluidized Bed Combustion Boilers

FBC Boilers can be operated in all loads without sacrificing combustion efficiency.

Fuel of size less than 6 m.m. is used in FBC boilers and hence need not be pulverised as does in P.F. Boilers.

No moving grate or burners in FBC boilers.

Ash does not fuse at 900 DegC and hence soot blowers are not required.

High combustion efficiency of fuel due to higher residence time and entire surface area of fuel in contact with air.

Page 15: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Stoker fired boiler

Page 16: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Stoker Fired Boilers

Moving Component (Travelling Grate) in the high temperature Furnace zone

Combustion temperature 1400 - 1600°C; heat transfer in furnace by Flame Radiation

Fuel Ignited by the already burning Fixed Bed

Fuel Combustion time limited to grate travel length - hence fuels of poorer quality than design do not burn fully

Due to grate cooling requirements a minimum air quantity is required - hence excess air is high at part loads

Very low relative movement between Fuel and Air

Page 17: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Fluidised Bed Combustion Boilers

Atmospheric pressure Fluidised Bed Combustion Boilers (AFBC)

Pressurised Fluidised Bed Combustion Boilers (PFBC)

I

Page 18: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Atmospheric Fluidised Bed Combustion Boilers

Bubbling Fluidised Bed Combustion Boilers (BFBC)

Circulating Fluidised Bed Combustion Boilers (CFBC)

I

Page 19: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

10 t/hr BFBC Prototype Boiler - 1977

FBC Test FacilitiesFBC Test Facilities

Combustion Test Rig-1979

BFBC Test Facility-1986

(90 t/hr Hot water)

Page 20: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

AFBC Technology DevelopmentAFBC Technology Development

1981 : First 12 t/h Commercial Boiler commissioned

1984 : First 10 MW power plant for Washery Rejects

1987 : First 10 MW power plant for Straw

1992 : First 20 MW (100 t/h) power plant for Rejects and Char

2000 : Largest boiler in operation of 180 t/h (45 MW)

2002 : Export of 17 MW Boilers to PT IBR Indonesia

2003 : Largest Boiler (300 t/hr) offered

2006 : Design of 120 MW Boiler ready

2008 : 3x18 MW Order from PT KPP, Indonesia

2009 : 2 X 180 t/hr BFBC Boiler order from JSPL, Angul

66 Boilers Contracted Over 2.5 million operating hours

Page 21: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

CoalBunker

Feeder

P A Fan

E S P

Air Heater

EcoS H I

S H II EVA

Drum

Schematic of AFBC Boiler

I D Fan

AirDistributor

F D Fan

MainSteam Ash

DESH

Page 22: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

AFBC ComponentsAFBC Components

1 Steam Drum2 Bed Superheater3 Bed Evaporator4 Convection Superheater5 Economiser6 Windbox7 Air Distributor Plate8 Hot Air Duct9 Cold Air Duct10 Air Preheater

1

2

3

4

5

6

78

9

10

Page 23: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Compartment – Unique Operational feature Compartment – Unique Operational feature

Page 24: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Page 25: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Flow Diagram of CFBC Boiler - Separate FBHE

ID Fan

SpiessValve

DRUM

SECONDARY AIR

Page 26: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

CFB Process Advantages

Page 27: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Page 28: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Major Milestone -CFBC Technology DevelopmentMajor Milestone -CFBC Technology Development

1995 : First CFBC boiler of capacity 175 TPH contracted

1995 : Utility size 2x125 Mwe capacity plant order received from

Surat Lignite plant (SLPP)

2003 : RVUNL, Rajasthan -2x125 Mwe plant using high sulphur content

lignite (6%)

2005 : First 2x250 MW CFBC power plant order received from

NLC,Neyveli.

2008 : Export order received from New Calidonia to supply 405 TPH

steam generator

28 CFBC Boilers Contracted .

Page 29: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Proximate   

Moisture % 4.50Volatile Matter % 39.58Ash % 3.77Fixed Carbon % 52.15HHV kcal/kg 7792

Ultimate   

Carbon % 78.36Hydrogen % 5.04Sulphur % 2.57Nitrogen % 0.98Moisture % 4.50Ash % 3.77Oxygen % 4.78

Typical Fuel analysis ( Assam Coal)

Page 30: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Assam Coal Lime Stone

Silica (SiO2) % 56.70 4.90

Aluminium Oxide(Al2O3) % 15.0 1.20

Iron Oxide (Fe2O3) % 17.90 1.00

Titanium Oxide (TiO2) % 0.80 1.00

Calcium Oxide (CaO) % 1.70 53.70

Magnesium Oxide (MgO) % 1.60 0.50

Sodium Oxide (Na2O) % 3.50 1.00

Potassium Oxide (K2O) % 2.60 0.10

Carbon di Oxide (CO2) % - 37.00

Chemical composition of fuel ash (Assam Coal) and limestone:

Page 31: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

C. ASH ANALYSIS

1.Silica (SiO2)

(%)51.08 48.42 52.38 48.15 52.56

2. Alumina (Al2O3) (%) 14.83 13.84 15.73 13.66 15.97

3. Iron Oxide (Fe2O3) (%) 18.60 25.16 15.31 26.14 14.36

4.Titania (TiO2)

(%)1.30 1.04 1.42 0.96 1.49

5. Phosphoric Anhydride(P2O5) (%) 0.26 0.19 0.32 0.16 0.37

6.Lime (CaO)

(%)2.04 1.73 2.18 1.68 2.25

7. Magnesia (MgO) (%) 0.51 0.41 0.65 0.37 0.73

8. Sulphuric Anhydride(SO3) (%) 8.82 7.08 9.09 6.81 9.91

9. Sodium Oxide (Na2O) max (%) 0.16 0.10 0.26 0.10 0.31

10. Potassium Oxide (%) 2.41 2.03 2.66 1.97 2.76

D. ASH FUSION RANGE (under reducing atmosphere)

1. Initial Deformation Temp.(IDT) oC 1075 1050 1100 1050 1100

2. Hemispherical Temp. oC 1125 1100 1150 1100 1150

3.FusionTemp.

oC1175 1150 1200 1150 1200

Page 32: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Page 33: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Page 34: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Supercritical 600 MWe CFBC Boiler- Baima, China Research on supercritical CFB

was started in 2003. A demonstration of 600MWe supercritical CFB was initiating in 2006 supported by government.

The first demonstration in Baima was approved in 2008, that shall be commissioned in 2011

Steam T : 571 /569℃ ℃Steam P : 25.4MPaSteam Flow: 1900t/h,Boiler efficiency: 92%SO2 : <300mg/Nm3,Nox : <200mg/Nm3,Generation efficiency:42%

Page 35: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Design features:

Vertical tube design with partial rifle

tube ;

Mass flow rate is 1400kg/m2s

6 cyclones with 6 external heat

exchangers (EHEs);

Bottom ash drained from both two

side walls through roller type ash

cooler;

Design of 600MWe Supercritical CFB Boiler ,

Page 36: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Design Feature:

Benson vertical tube water membrane, mass flow 800kg/M2S.

Twin furnace (with total cross section 15x28m2 and 55 m height) divided by

a partition water wall.

Six cyclones with inner diameter 9m.

six external heat exchanger (EHE).

In furnace superheater panels.

The LT SH and LT RH in second pass.

The HT RH , the MT SH located in EHEs.

There are two options for the cyclone selection –steam cooled and insulated.

Water jacketed rotary ash cooler is used bed ash 2011.

Page 37: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Arrangement of 600MWe supercritical CFB Boiler of Tsinghua’s Design

Page 38: Bharat Heavy Electricals Limited TIRUCHIRAPALLI Presentation on FBC Boilers 28 th August 2012 Fluidized Bed Combustion Systems By M.RAJAVEL, SDGM / R&D/PCPS.

Bharat Heavy Electricals Limited TIRUCHIRAPALLI

Presentation on FBC Boilers

28th August 2012

Take Care of Our Environment

Thanks for Your Patient Listening