Page 1: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Bidding Made Easy: Better Bidding for Better Projects

Page 2: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Better Bidding for Better ProjectsMSA is a Full-Service Consulting

Firm

Sixteen Offices in Six States

Teresa Anderson, P.E.

Municipal Engineer/Team Leader

Page 3: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Using bidding to get the desired results

Page 4: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Bidding Made Easy•Identify public works projects for which bidding is required•Recognize opportunities for flexibility

◦ Bid Format, Alternates, Allowances, Splitting the Contract, Monetizing Time

•Discuss pre-qualification of bidders

Page 5: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Things to keep in mind•Focus on public owners•Local procurement policies/ordinances vary•Specific project issues need specific analysis•Make use of engineers and architects•Check with your attorney, if you have questions

Page 6: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

When is bidding required?• “All public construction, the estimated cost of which

exceeds $25,000, shall be let by contract to the lowest responsible bidder…”oPublic Construction is understood to be:

• Cannot split project to avoid bidding - $25,000

• Between $5,000 and $25,000 – Class 1 Notice

Public improvements that combine materials, supplies, and labor

Page 7: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

When is bidding not required?•Equipment for more than a single project•Emergency situation •Donated materials or labor•Professional services (Qualifications Based Selection)•Other exceptions in statutes

Page 8: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Pre-Qualification of Bidders•Why Pre-Qualify?•Addresses concerns about contractor

qualifications• Incentivizes pre-qualified contractors•Quicker turn-around between bid and award

Page 9: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

Bidding Made Easy•Identify Public Works Projects for which Bidding is Required

•Recognize Opportunities for Flexibility

•Discuss Pre-Qualification of Bidders

•Better Bidding = Better Project

Combine materials, supplies, and labor > $25,000

Bid Format Allowances Alternates

Multiple Contracts Monetize Time Pre-Qualification

Page 10: Better Bidding for Better Projects

MSA PROFESSIONAL SERVICES

www.msa-ps.com

Questions?

Contact Teresa Anderson at [email protected]