Best Practices Best Practices The Fantasy Island Story The Fantasy Island Story Richard Wainio Port Director and CEO Tampa Port Authority [email protected]
17

Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Oct 14, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Best PracticesBest PracticesThe Fantasy Island StoryThe Fantasy Island Story

Richard WainioPort Director and CEOTampa Port Authority

[email protected]

Page 2: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Environmental RoleEnvironmental Role

Port has a longPort has a long--standing commitment to standing commitment to the environmental integrity of the Tampa the environmental integrity of the Tampa Bay regionBay regionPort engages in many environmental Port engages in many environmental projects and initiativesprojects and initiativesPort works with environmental agencies, Port works with environmental agencies, like EPC, Audubon Society, Tampa Bay like EPC, Audubon Society, Tampa Bay Estuary Program, etc.Estuary Program, etc.

Page 3: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Background . . .Background . . .

Late 70sLate 70s--early 80searly 80s–– 4 acre island 4 acre island constructed of dredge material during constructed of dredge material during Tampa Harbor Deepening ProjectTampa Harbor Deepening ProjectOver time, nonOver time, non--native, invasive/exotic native, invasive/exotic plant life made the island inhospitable to plant life made the island inhospitable to visitorsvisitors20002000–– a coalition began to discuss a coalition began to discuss restoring the island as onrestoring the island as on--thethe--water water educational and environmental project educational and environmental project for Tampa Bayfor Tampa BayCritical partnerships formedCritical partnerships formed

Page 4: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Background, cont.Background, cont.

Port engaged in planning and funding Port engaged in planning and funding effortseffortsDevelopment drawings and plans, and Development drawings and plans, and permitting procedures for constructionpermitting procedures for constructionRemoval and treatment of nonRemoval and treatment of non--native, native, invasive/exotic vegetationinvasive/exotic vegetationMore than 7,000 plants transported and More than 7,000 plants transported and plantedplantedMay 2006May 2006–– TPA and its partners opened TPA and its partners opened Fantasy Island to the publicFantasy Island to the public

Page 5: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Overgrown IslandOvergrown IslandBefore DevelopmentBefore Development

Page 6: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

BIG Three FactorsBIG Three Factors

Partnerships, Partnerships, Partnerships, Partnerships, Partnerships!Partnerships!•• Committed stakeholdersCommitted stakeholders

Funding SourcesFunding Sources•• Grants, inGrants, in--kind serviceskind services

Research and PlanningResearch and Planning•• Development of facilities, ongoing Development of facilities, ongoing

maintenance, school curriculummaintenance, school curriculum

Page 7: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Key Port PartnersKey Port Partners

The Florida AquariumThe Florida Aquarium

Tampa Electric CompanyTampa Electric Company

U.S. Coast GuardU.S. Coast Guard

Page 8: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Delivery of PlantsDelivery of Plants& Equipment& Equipment

Page 9: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Volunteers Volunteers –– Lots of them!Lots of them!

Page 10: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

School CurriculumSchool CurriculumHillsborough County school teachersHillsborough County school teachers

Florida Aquarium Staff MembersFlorida Aquarium Staff Members

Florida Fish and Wildlife Research Institute Florida Fish and Wildlife Research Institute Representative/FL Fish & Wildlife Representative/FL Fish & Wildlife Conservation CommissionConservation Commission

Page 11: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Equipped for EducationEquipped for Education

Informational KiosksInformational Kiosksand Educational Signsand Educational Signs

PavilionPavilion““ClassroomClassroom””

Boat Dock/PierBoat Dock/Pier(ADA Compliant)(ADA Compliant)

Restoration/Shoreline Protection ProjectsRestoration/Shoreline Protection Projects(Reefballs, oyster shell bars, salt marsh plantings)(Reefballs, oyster shell bars, salt marsh plantings)

Rainwater Recovery SystemRainwater Recovery System(Fresh water for plants)(Fresh water for plants)

Page 12: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

EcotoursEcotours

Page 13: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Maintenance ChallengesMaintenance Challenges

Maintenance of facilitiesMaintenance of facilities•• Every 2Every 2--3 months, volunteers help maintain 3 months, volunteers help maintain

trailstrails•• Maintenance dredging around boat berthing areaMaintenance dredging around boat berthing area

Care of habitat/plant lifeCare of habitat/plant life•• Control of invasive plantsControl of invasive plants•• Litter clean upLitter clean up

Vandalism/security issuesVandalism/security issues•• Theft and destruction of signsTheft and destruction of signs•• Dock and pier damageDock and pier damage

Page 14: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Read AllRead AllAbout It!About It!

Page 15: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

AwardsAwards

2002 Gulf of Mexico 2002 Gulf of Mexico Program, EPCProgram, EPC•• 11stst Place in Place in

Partnership CategoryPartnership Category

2004 Florida Native 2004 Florida Native Plant SocietyPlant Society2004 Tampa Bay 2004 Tampa Bay Regional Planning Regional Planning Environmental Environmental AwardAward

Page 16: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

More to Come!More to Come!

General visitor programs

More Teacher workshops

Completion of grant-funded programs for Hillsborough County Marine Science classes

Addition of other grade levels and counties

Page 17: Best Practices for Environmental Projects · 2007. 10. 12. · Background . . . Late 70s-early 80s– 4 acre island constructed of dredge material during Tampa Harbor Deepening Project

Thank You!Thank You!