Top Banner
Beltline Highway ITS – Ramp Beltline Highway ITS – Ramp Metering Project Metering Project ODOT Planners Meeting April 25, 2012
11

Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Dec 10, 2015

Download

Documents

Kayla Rodriguez
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Beltline Highway ITS – Beltline Highway ITS – Ramp Metering ProjectRamp Metering Project

ODOT Planners MeetingApril 25, 2012

Page 2: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Beltline ITS Project Beltline ITS Project BackgroundBackground

• Funded through HB2001: Jobs and Transportation ACT for $2 million

• Goal: Identify near-term, lower cost ITS treatments to help address existing traffic congestion and safety concerns along the Beltline and Delta Highways. – Ramp Metering– Variable Speed Limits– ITS Integration (VMS Signs, Other Opportunities)

• Schedule: Implement by Fall 2012

Page 3: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Study AreaStudy Area

• Examine Beltline Highway from Interstate 5 to Barger Interchange

Page 4: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Study Area ObjectivesStudy Area Objectives

• Determine feasibility of ramp metering

• Document simulated levels of impact to Beltline Highway (with & without ramp metering)

• Identify conceptual geometric improvements to facilitate ramp metering

• Estimate construction costs for the preferred metering strategy

Page 5: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Beltline Ramp Metering – System Beltline Ramp Metering – System Opportunities and ConstraintsOpportunities and Constraints

• Heaviest traffic volume between River Road and Delta Highway Focus for Metering

Beltline Highway 2008 Average Daily Traffic

Page 6: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Recommended Ramp Meter Recommended Ramp Meter LocationsLocations

2 lanes2 lanes

2 lanes

1 lane

Page 7: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Ramp Metering BenefitsRamp Metering Benefits

• Traffic Operations increased freeway capacity, speeds; reduced travel times and system delay

• Safety reduced side friction and increased gaps for merging

• Environmental reduction of stop and go freeway conditions reduces fuel consumption and air pollution

* Note ramp metering increases ramp delay & queuing

Page 8: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Ramp Metering ConcernsRamp Metering Concerns• Local System

– Beltline Operations vs. Local System Operations

• Alternate Routes– Had to meter both eastbound ramps to

avoid over use and possible impact to River Avenue

• Environmental– Increased delay & emissions on ramps

(offset by savings along freeway)

Page 9: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Westbound Westbound

Key Outcomes• Coburg Road On-Ramp and Green Acres Road

On-Ramp

• P.M. Peak Period: 3:00-6:45

• Travel Time Savings ~ 270 Vehicle Hours/Day

• Total Cost ~ $870,000

Page 10: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Eastbound Eastbound

Key Outcomes• River Avenue On-Ramp and River Road On-

Ramp

• A.M. Peak Period: 6:30-9:30

• Travel Time Savings ~ 90 Vehicle Hours/Day

• Total Cost ~ $790,000

Page 11: Beltline Highway ITS – Ramp Metering Project ODOT Planners Meeting April 25, 2012.

Next StepsNext Steps

• Ramp Meters Installation Fall 2012

• Variable Speeds on Delta Highway (south of Beltline Highway)– Speeds reduced during peak periods– Safety benefit– Need additional funding– Need Enforcement