BLOCK B - O MON PIPELINE OPERATING COMPANY PROJECT BLOCK B – O MON GAS PIPELINE PHASE EPC NUMBERING PROCEDURE 0 29/02/12 Issued For Approval Rev. Date Description PVE VSP Approval BPOC Approval CA Approval EPC CONTRACTOR (VSP-PVC-PTSC) Document number: BB.G-VSP-PVE-ED-00-PM-PRO-008 Number of pages: 28 (including this page)
18
Embed
Bb.g Vsp Pve Ed 00 Pm Pro 008 Numbering Procedure Rev 0
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
BLOCK B - O MON PIPELINE OPERATING COMPANY
PROJECT BLOCK B – O MON GAS PIPELINE
PHASE EPC
NUMBERING PROCEDURE
0 29/02/12 Issued For Approval
Rev. Date Description PVEVSP
ApprovalBPOC
ApprovalCA
Approval
EPC CONTRACTOR (VSP-PVC-PTSC)
Document number: BB.G-VSP-PVE-ED-00-PM-PRO-008
Number of pages: 28 (including this page)
PROJECT BLOCK B – O MON GAS PIPELINE
PHASE EPC
NUMBERING PROCEDURE
0 29/02/12 Issued For ApprovalN.N.T.A Izaham JB IAJ
Rev. Date Description
Preparedby
Checked by
EM PM DisciplineTeam
LeaderSPMB
Sub-Contractor EPC Contractor
EPC CONTRACTOR(VSP-PVC-PTSC CONSORTIUM)
PV ENGINEERING J.S.CDocument number:
BB.G-VSP-PVE-ED-00-PM-PRO-008
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE
1. PROJECT OVERVIEW
PetroVietnam Gas Corporation Block B - O Mon Pipeline Operating Company
(BPOC) is responsible for the development of the Block B - O Mon Gas Pipeline.
This project will be implemented to transport natural gas from a proposed Central
Processing Platform (CPP) located in Block B fields to Ca Mau, O Mon and
Neighboring Industrial Zones in provinces along the pipeline route.
The Block B-O Mon Gas Pipeline Project includes the following facilities:
Approximately 246.4km subsea pipeline with DN 700 (28”)
Mui Tram, Ca Mau Landfall station (LFS)
Approximately 152.4km onshore pipeline with DN 750 (30”) from Mui Tram
LFS to O Mon GDC
Nine Line Block Valve Stations (LBV)
A pipeline lateral section from LBV#2 to Ca Mau GDS: approximately
400m DN 250 (10”)
Ca Mau Gas Distribution Station (GDS)
A pipeline section from O Mon Gas Distribution Centre (GDC) to each O
Mon Power Plant
The project investment objective is to contribute to the economic development in
Southwest provinces and to secure gas/power supply in Vietnam.
2. GENERAL INFORMATION AND REQUIREMENTS
The role of the EPC Contractor for the Block B – O Mon Gas Pipeline Project
shall be undertaken by VSP-PVC-PTSC Consortium and VSP shall be the
Leader of Consortium.
PV Engineering J.S.C (SUB-CONTRACTOR) is the nominated Contractor to
carry out the Detailed Design of Offshore and Onshore Pipelines and Stations.
2.1 Language and Units of Measurement
The content, references, attachments and any supplementary information for all
engineering documents shall be in English unless specified otherwise. After the
engineering package has been approved, Vietnamese translations of the
approved engineering documents will be provided.
BB.G-VSP-PVE-ED-00-PM-PRO-008 Rev. 0 Page 4/14
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE
Units of measurement for all engineering documents shall be in the System
International (SI).
2.2 Purpose of Document
This document provides the instruction of numbering procedure for project
documents/ drawings including the procedures, technical documents, for Block B
– O Mon Gas Pipeline Project at Detailed Design stage. This procedure is
applied for Detailed Design Sub-Contractor (PVE)
2.3 Definitions and Abbreviations
2.3.1 Definitions
BPOC Block B - O Mon Pipeline Operating Company (Client)
DNV Det Norske Veritas (Certify Agent)
EPC CONTRACTOR A consortium of Vietsovpetro (VSP), PetroVietnam Construction Joint Stock Corporation (PVC), Petroleum Technical Services Corporation (PTSC). (VSP as the alliance leader)
SPMB Service Project Management Board - a subsidiary of VSP who will work full time on the project
PVE PV Engineering J.S.C - An entity subcontracted by VSP to perform the detailed engineering design.
2.3.2 Abbreviations
If not applicable please put NOT APPLICABLE
2.4 Codes and Standards
ISO 9001: 2008 Quality Management System Requirements
2.5 Reference Documents
BB.G-VSP-SPMB-LT-00-PM-PRO-003
Document Numbering Procedure (by SPMB/ VSP)
BB.G-VSP-PVE-ED-00-PM-PRO-001 Procedure for Coordination Detail Design of onshore & offshore pipelines and stations
BB.G-VSP-PVE-ED-00-PM-PRO-008 Rev. 0 Page 5/14
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE
3. DOCUMENT NUMBERING SYSTEM
All documents of Block B – O Mon Gas Pipeline Project shall be numbered uniquely as shown below:
- - - - - - -
Where:
a. Project Code:
Project Code for Block B – O Mon Gas Pipeline Project is BB.G.
b. Contractor Code:
Contractor Code is included Main-Contractor and Sub-contractor codes.
This code is VSP-PVE.
c. Phase Code:
The two-character code identifies the executing stage of the project and shall be the following:
BD Basic Design
ED Engineering Design
AB As Built
d. Area Code:
This code is used to separate the areas of the project. For projects where no area number is required “00” is used as a default.
For Block B – O Mon Gas Pipeline Project:
BB.G-VSP-PVE-ED-00-PM-PRO-008 Rev. 0 Page 6/14
Project Code
Contractor Code
Phase Code
Area Code
Discipline Code
Document Indentifier
Serial Number
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE
00 General (Excluding Line Block Valve Station)
10 Offshore Pipeline
20 Landfall Station (LFS)
30 Gas Distribution Station at Ca Mau
40 Gas Distribution Centre at O Mon
60 Onshore Pipeline (including Line Block Valve Stations)
e. Discipline Code:
PM Project Management IC Instrumentation & Control
AR Architectural ME Mechanical
CI Civil/ Structural PI Piping/ Layouts
CR Anti-corrosion PL Onshore Pipelines
ES Estimating PR Process
EL Electrical SU Subsea Pipelines/ Facilities
HS Health & Safety TE Telecommunications
HV HVAC OT Other (if any)
f. Document Identifier:
PCR Project Change Request IDX Drawing/ Document Index
PRO Procedure LST Line/ Equipment/ Valve/ etc. List
REP Report MAN Manuals & User Guides
SCH Project Schedule MTO Material Take-off/ Bill of Materials
TPD Third Party Supplied Document PHL Philosophy
BOD Basis of Design REF Reference
CAL Calculation REG Register
CHK Checklist REQ Requisition
CRT Design Criteria SPC Engineering Specification
BB.G-VSP-PVE-ED-00-PM-PRO-008 Rev. 0 Page 7/14
BLOCK B – O MON GAS PIPELINE PROJECTEPC PHASE-NUMBERING PROCEDURE