BATA’S SUBMARINE OUTFALL FO Emissário... · Bata’s Submarine Outfall – Equatorial Guinea The outfall is included on the project of water supply and sanitation of Bata and included

Feb 10, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BATA’S SUBMARINE OUTFALL FO Emissário... · Bata’s Submarine Outfall – Equatorial Guinea The outfall is included on the project of water supply and sanitation of Bata and included

www.etermar.pt

BATA’S SUBMARINE OUTFALL1.280 m length, Ø 1.100mm

SOMAGEC GE / Min. des Trav. Pub. de la République de Guinée EquatorialCLIENT

Page 2: BATA’S SUBMARINE OUTFALL FO Emissário... · Bata’s Submarine Outfall – Equatorial Guinea The outfall is included on the project of water supply and sanitation of Bata and included

Bata’s Submarine Outfall – Equatorial Guinea

The outfall is included on the project of water supply and sanitation of Bata and included the following works: - Project design and supervision; - Trench dredging for outfall installation; - Construction of two sheet piling curtains with 2 x 200 m of length; - Production, assembling and installation of ballasting rings, stabilizers and diffuser

protection blocs in reinforced concrete. - Assembling by thermic welding of the PEHD pipe; - Installation of the pipe at sea; - Installation of the diffuser; - Trench covering; - Supply and installation of signalization buoy; - Final tests to the outfall.

Outfall main characteristics: Length 1.280m ....................................................Internal diameter 1.000 mm ................................External diameter 1.100 mm ...............................Diffusers 8 duckbill valves ..................................Pipe HDPE, PE100, SDR 22, PN 7.7 .................

12 MONTHS

DESCRIPTION

CONSTRUCTION TIME