Top Banner

of 66

Basic_Surveying.pdf

Jun 02, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/11/2019 Basic_Surveying.pdf

    1/66

    1

    UNESCO-NIGERIA TECHNICAL &

    VOCATIONAL EDUCATION

    REVITALISATION PROJECT-PHASE II

    YEAR I- SEMESTER 2

    THEORY

    Version 1: December 2008

    NATIONAL DIPLOMA IN

    BUILDING TECHNOLOGY

    BASIC PRINCIPLES IN SURVEYING II

    COURSE CODE: SUG102

  • 8/11/2019 Basic_Surveying.pdf

    2/66

    2

    BASIC PRINCIPLES IN SURVEYING II (TSL 102)

    THEORETICAL COURSE INDEX

    WEEK 1. 1.0 TACHEOMETRIC SURVEYING

    1.1 Introduction to Tacheometry.1

    WEEK 2. 1.2 Calibration of Instrument...7

    WEEK 3. 1.3 Sources of error in Stadia

    Tacheometry....11

    1.4 Application of Stadia

    Tacheometry....12

    WEEK 4. 2.0 THE THEODOLITE

    2.1 Theodolites and Uses... .17

    2.2 Theodolites Resolutions.. 17

    2.3 Basic Components of an optical

    Theodolite18

    WEEK 5. 3.0 GLOBAL POSITIONNING SYSTEM

    3.1 Introduction G.P.S....23

    3.2 Space Segment of the G.P.S...............243.3 G.P.S. Positionning Methods.26

    WEEK 6. 3.4 How G.P.S. Works..28

    WEEK 7. 3.5 G.P.S. Instrumentation..30

    3.6 Application of the G.P.S. .32

    WEEK 8. 4.0 THE TOTAL STATION

    4.1 Introduction to Total Station.394.2 Angle Measurement ..43

    4.3 Distance Measurement.43

    4.4 Power Supply.45

    WEEK 9. 5.0 THEODOLITE TRAVERSING.

    5.1 Theodolite Traversing.................46

    5.2 Types of Traversing.............46

  • 8/11/2019 Basic_Surveying.pdf

    3/66

    3

    5.3 Traverse Specification

    and Accuracy .......48

    WEEK 10. 5.4 Traverse Field Work ...50

    5.5 Station Markings 51

    WEEK 11. 6.0 SETTING OUT IN CIVIL ENGINEERING

    6.1 Introduction to Setting Out53

    6.2 Aims of Setting Out......53

    6.3 Stages in Setting Out54

    WEEK 12. 6.4 Equipment for Setting

    Out Buildings....56

    WEEK 13. 6.5 Setting Out a Simple Building

    Plan626.6 Setting Out Subsidiary Lines...63

    WEEK 14. 7.0 TRIANGULATION AND TRILATRATION

    7.1 Triangulation and Trilatration65

    7.2 Triangulation and Trilatration Field

    Work....67

    WEEK 15. 7.3 Distance Measurement..70

    7.4 Angle Measurement..70

  • 8/11/2019 Basic_Surveying.pdf

    4/66

    4

    WEEK ONE

    Introdution toTachoemetry.

    1.1 Tacheometry is a branch of surveying where heights and distances are determined

    from the instrumental readings alone; these readings are usually taken with a specially

    adopted theodolite known as a Tacheometer. Chaining operation is eliminated and

    tacheometry is therefore very useful in broken terrain e.g. land cut by ravines, river valley,

    over standing crops etc. where direct linear measurement would be difficult and inaccurate.

    All that is needed is that the surveying assistant, who carries a levelling staff on which the

    tacheometer is sighted shall be able to reach the various points to be surveyed and levelled

    and that a clear line of sight exists between the levelling staff and the tacheometer must not

    exceed a maximum, beyond which error due to inaccurate reading becomes excessive,

    normally, 50m.

    The field work in tachometry is rapid compared with direct levelling and measurement and it

    is widely used therefore to give contoured plans of areas, especially for reservoir and hydro

    electric project tipping site, road and railway reconnaissance, housing sites etc. With

    reasonable precautions, the results of tachometry obtained can be of the same order of

    accuracy as, or even better than the results obtained by direct measurement in some cases.

    In stadia tachometry, a levelling staff is held vertically at one end of the line being measured

    and a level or theodolite is set up above or below the other. The staff sighted and readings

    taken using lines engraved on the telescope diaphram as shown in figure below. The vertical

    angle along the line of sight can be either horizontal or inclined as shown in the below figure.

    The vertical compensating system of the theodolite must be in correct adjustment since

    vertical angles are read on face only.

  • 8/11/2019 Basic_Surveying.pdf

    5/66

    5

    RLx

    Figure1.0 Inclined line of sight in stadia tacheometry.

    With reference to the above figure;

    Horizontal distance P x = D = KS cos2 + C cos (i)

    Vertical distance V = K S sin 2 + C sin (ii)

    Reduced level of X = RLX= RLP+ hi V m (iii)

    Where;

    K = the multiplying constant of instrument, usually 100

    C = the additive constant of the instrument, usually 0

    S = the difference between the two stadia readings

    = the vertical angle along the line of sight

    hi = the height of trunnion axis above point p

    m = the middle staff reading at X

    Stadia linesM

    X

    hi

    D

    P

    S

    V

  • 8/11/2019 Basic_Surveying.pdf

    6/66

    6

    +v = used if there is an angle of elevation

    - v = used if there is an angle of depression

    Example 1.

    A theodolite having a multiplying constant of 100 and additive constant of 0.00was centred

    and levelled at a height of 1.48m above a point C, of reduced level 46.87m.

    A levelling staff was held vertically at points D and L in turn and the readings shown in table

    1.1 below were taken.

    Required:

    calculate;

    a. The reduced levels of points D and L

    b.

    The horizontal distances; DCDand DCL

    Table 1.0 : Stadia readings.

    Staffposition

    Staff readings(m)

    Vertical circlereadings

    Horizontal circlereadings

    D 3.240, 3.047, 2.853 02021

    07

    56

    049

    31

    L 2.458, 2.230, 2.002 020

    2136

    98

    007

    18

  • 8/11/2019 Basic_Surveying.pdf

    7/66

    7

    SOLUTION

    Figure 1.2 tacheomeyric Exercise.

    (a) The reduced levels of points D and L are obtained as follows;

    From equation (ii)

    VCD = KS sin 2 + C sin

    = (100) (3.240 2.853) sin 2(02021

    07

    ) + 0

    = 50 (0.387) sin (4.703890)

    = 1.587m

    VCL = KS sin 2 + C sin

    = (100) (2.458 2.002) sin 2(02021

    36

    ) + 0

    = 50(0.456) sin (4.7200)

    = 1.876m

    Using equation (iii)

    Reduced level at point D = RLD.

    RLD = RLC+ hi + VCD m

    = 46.87 + 1.48 + 1.587 3.047= 46.89m

    RLL = RLC+ hi VCD m

    = 46.87 + 1.48 1.876 2.230

    = 44.24m

    (b) The horizontal distance DL = KS cos2 + C cos

    VCL

    m C

    D

    VCD

    m

    1.48m

    L

    02021

    36

    020

    21

    07

    DCL DCD

  • 8/11/2019 Basic_Surveying.pdf

    8/66

    8

    From equation (i)

    Horizontal distance DCD= 100 (3.240 2.853) cos2(02

    021

    07

    ) +0

    = 38.7 (0.998315911)

    = 38.635m

    Horizontal distance = 100 (2.458 2.002) cos2(0202136)

    = 45.60 (0.998304362)

    = 45.523m

    Slope = Difference in RL = 46.89 44.24

    Total distance 38.635 + 45.523

    = 2.650 = 0.0315

    84.158

    = tan-10.0315 = 1.8040

  • 8/11/2019 Basic_Surveying.pdf

    9/66

    9

    WEEK TWO

    1.2 CALIBRATION OF INSTRUMENT.

    Figure 2.1 A Theodolite.

  • 8/11/2019 Basic_Surveying.pdf

    10/66

    10

    Figure 2.2 Observing through the Instrument.

    The tacheometer at every time has two constants namely;

    The multiplying constant, denoted by K.

    Additive constant denoted by C.

    These constant can be determined for any instrument whose either are not known or need to

    be recalibrated.

    Finding K and C for an instrument

    The instrument to be calibrated or recalibrated is centred at a point on a horizontal ground;

    the eyepiece focusing is used for stadia measurements of two staff positions placed at

    different distances away from the instrument say 100m and 200m with the staff held

  • 8/11/2019 Basic_Surveying.pdf

    11/66

    11

    vertically upright. The staff is sighted with the telescope at a horizontal line of sight. The

    lower and upper staff readings are carefully read and recorded as illustrated in the figure

    below.

    Fiigure: 2.3 Calibration of Equipment

    We know that horizontal distance = KS cos2 + C cos

    Since the line of sight is horizontal, it follows that = 0.This implies that horizontal distance,

    D = KS + C . (iv)

    Equation (iv) is used to determine the constants for any instrument whose readings are taken

    as explained previously.

    Example 2.

    The table below shows the observations (readings) taken to determine the two constants for

    an instrument.

    TheodoliteUpper Stadia

    reading

    Lower Stadia

    reading

    Upper Stadia

    reading

    Lower Stadia

    reading

    100m

    200m

    Staff

  • 8/11/2019 Basic_Surveying.pdf

    12/66

    12

    Table 2.0 : Stadia readings

    Required:

    Find the values of these constants

    Using equation (iv)

    D = KS + C

    For staff 1, D1= KS1+ C

    => 30 = K (0.3) + C .. (1)

    For staff 2, D2= KS2+ C

    => 90 = K (0.9) + C .. (2)

    Subtracting equation (1) from (2)

    90 = K (0.9) + C

    - 30 = K (0.3) + C

    60 = 0.6K + 0

    K =60

    /0.6= 100

    K = 100

    Horizontal distance

    (m)

    Reading on staff.

    ( m)

    Lower wire Upper wire

    30 1.133 1.433

    90 1.452 2.352

    Theodolite 1.433

    1.13

    2.352

    1.452

    30m

    90m

    Staff 1Staff 2

  • 8/11/2019 Basic_Surveying.pdf

    13/66

    13

    Substituting the value of K into equation (1)

    30 = 100 (0.3) + C

    30 30 = C

    => C = 0

    Hence, the values of these constants are;

    K = 100 and C = 0

    Questions:

    A theodolite is to be used in tacheometric survey to pick the details of up and down stream

    features of a new dam. It was tested on known bases as follows;

    Table 2.2 Stadia readings.

    Horizontal distance

    (m)

    Vertical angle Staff reading

    (m)

    Upper Lower

    30.00 90000

    00

    1.433 1.183

    89.98

    90000

    00

    2.247 1.542

    Required: Find the multiplier and additive constants of the instrumentThe instrument above was used to generate the following data;

    Upper stadia reading = 1.330m

    Lower stadia reading = 1.100m

    What is the horizontal distance between the instrument and the staff?

    The instrument height = 1.210m and the reduced level at the instrument position = 39.47m

  • 8/11/2019 Basic_Surveying.pdf

    14/66

    14

    WEEK THREE

    1.3 SOURCES OF ERROR IN STADIA TACHEOMETRY

    The accuracy of basic stadia tacheometry depends on two categories of error; instrumental

    and field errors.

    (A) INSTRUMENTAL ERRORS

    An incorrectly assumed value for K, the multiplying constant, caused by an error in the

    construction of the diaphragm of the theodolite or level used.

    Errors arising out of the assumption that K and C are fixed when strictly, both K and C arevariable.

    The possible errors due to 1 and 2 above limit the overall accuracy to distance measurement

    by stadia tachometry to 1 in 1000.

    (B) FIELD ERRORS

    These can occur from the following sources.

    when observing the staff, incorrect readings may be recorded which result in an error in the

    staff intercept S. Assuming K = 100, an error of 1mm in the value of S results in an error of

    10mm in D.

    Since the staff reading accuracy decreases as D increases, the maximum length of a

    tachometric sight should be + 50mm.

    2. Non verticality of the levelling staff can be a serious source of error. This and

    poor accuracy of staff readings form the worst two sources of error.

    The error in distance due to the non verticality of the staff is proportional to both the angle

    of elevation of the sighting and the length of the sighting. Hence, a large error can be caused

    by steep sightings, long sighting or a combination of both. It is therefore advisable not to

    exceed = 100for all stadia tachometry.

    3. A further source of error is in reading the vertical circle of the theodolite. If the line of

    sight is limited to 100, errors arising from this source will be small. Usually, it is

    sufficiently accurate to measure the vertical angle 1and although it is possible to improve

  • 8/11/2019 Basic_Surveying.pdf

    15/66

    15

    this reading accuracy, it is seldom worth doing so due to the magnitude of all the other errors

    previously discussed.

    Considering all the sources of error, the overall accuracy expected for distance measurement

    is 1 in 500 and the best possible accuracy is only 1 in 1000.

    The vertical component V is subject to the same sources of error described above for

    distances and the accuracy expected is approximately 50mm.

    The precision of stadia tachometry is of paramount importance for best results.

    1.4 APPLICATIONS OF STADIA TACHEOMETRY

    Vertical staff tacheometry is ideally suited for detail surveying by radiation techniques. This

    method of survey is best restricted to the production of contoured site plans since the bestpossible accuracy obtainable is only 1 in 1000 and should not be used to measure distances

    where precision better than this are required.

    Example 3.

    The following readings were taken on a vertical staff with a tacheometer fitted with an

    anallatic lens and having a constant of 100.

    Table 3.0 : Stadia readings.

    Staff

    station

    Bearing Stadia Reading (m)

    Lower middle Upper

    Vertical angle

    A.

    B.

    27030

    00

    20703000

    1.000, 1.515, 2.025

    1.000, 2.055, 3.110

    +80000

    00

    - 500000

    Required: Calculate the relative levels of the ground at A and B, and the mean slope between

    the two points (A & B).

  • 8/11/2019 Basic_Surveying.pdf

    16/66

    16

    Solution

    Figure 3.0 Tacheo metric Exercise.

    From Equation (ii)VA= KS Sin 2 + C sin

    = (100) (2.025-1.000) Sin 2(8000

    00

    ) + 0

    = 50(1.025) sin (16000

    00

    )

    = 14.13m

    VB= KS sin 2 + C Sin

    = (100) (3.110-1.000) sin 2(50 00I00II)

    = 50 (2.110) Sin (100

    0000

    )

    = 18.32m

    For horizontal distances HAand HB, equation (i) is applicable.

    Hence, HA= Ks cos2 + C cos

    = 100 (1.025) cos2(8

    000

    00

    ) + 0

    = 100.51m

    HB = Ks cos2 + C cos

    = (2.110) cos2(5

    000

    00

    )

    V2

    m C

    A

    V1

    m

    hi

    B

    -500000

    +800000

    H2 H1

  • 8/11/2019 Basic_Surveying.pdf

    17/66

    17

    = 209.40m

    Let x be the height of instrument above datum;

    Level of A = 14.12 + x 1.515

    = x + 12.61

    Level of B = 18.32 x 2.055

    = x 16.27

    The difference in level from A and B;

    Level of A level of B

    = (x + 12.61) (x 16.27)

    = x + 12.61 x + 16.27

    = 12.61 + 16.27

    = 28.89m

    The bearings slow that A, B and the instrument lie on a straight line

    (207030

    00

    27

    030

    00

    =18

    000

    00)

    => Mean slope = Difference in level

    HA+ HB

    = 28.89

    (100.15 + 209.40)

    = 28.8

    309.91

    = 0.093220

    = tan-10.093220 = 5.33

    0

    ASSIGNMENT 1

    Q1. Tachometric survey conducted to pick the details of the up and down stream features

    of a proposed new dam generated the following data;

    Table 3.1 :Stadia readings.

    Levelling staff

    station

    Upper stadia

    reading (m)

    Middle stadia

    reading(m)

    Lower stadia

    reading (m)

    Vertical angle

  • 8/11/2019 Basic_Surveying.pdf

    18/66

    18

    A 1.433 1.308 1.183 20015

    00

    B 2.247 1.849 1.452 - 12030

    00

    The instrument has a multiplying constant of 100 and an additive constant of 0, whose height

    is 1.47m and centred at point x of reduced level 39.85m.

    Required:

    Calculate the reduced levels of stations A and B.

    Determine the horizontal distance from station A to B.

    Q2. A theodolite whose height of instrument level is 182.56m has a multiplier constant of

    100 and an additive constant of 1.00

    If the angle of elevation is 10000

    00

    and upper, middle and lower stadia readings

    are 5.00, 3.50 and 2.00 respectively.

    What is the horizontal distance of the staff from the station of instrument if the instrument is

    levelled at 1.42m height?

    What is the reduced level at the staff?

    Q3. Given the following data, determine the two constants for the instrument used and

    distance x

    Station of

    Instrument

    Staff distance

    (m)

    Staff reading (m)

    Lower

    Stadia

    Upper stadia

    A 100 3.620 4.610

    200 2.980 4.970

    X 1.830 2.100

  • 8/11/2019 Basic_Surveying.pdf

    19/66

    19

    WEEK FOUR

    2.1 THEODOLITES AND USES.

    Theodolites are telescopic instruments used basically for measuring both vertical and

    horizontal angles. They are also useful in determining horizontal and vertical distances by

    stadia prolonging straight lines and low order differential levelling.

    Figure 4.0 : Detailed sketch of a Theodolite.

    Theodolites are precision instruments used extensively in construction work for measuring

    angles in the horizontal and vertical planes.

    Many different theodolites are available for measuring angles and they are often classified

    according to the smallest reading that can be taken with the instrument known as the

    Theodolite Resolution

  • 8/11/2019 Basic_Surveying.pdf

    20/66

    20

    2.2 TheodoliteResolution.

    This can vary from 1to 0.1and for example, a 1theodolite is one which can be used read

    to 1directly without any estimation.

    At this point, it is worth noting that a full circle is 3600and a reading system capable of

    resolving to 1directly shows the degree of precision in the manufacture of theodolites.

    In order to measure horizontal and vertical angles, the theodolite must be centred over a point

    using a plumbing device and must be levelled to bring the angle reading systems of the

    instrument into appropriate planes.

    All types of optical theodolites are similar in construction and the general features of the

    SOKKIA TM20H are shown in figures below.

    The various parts of a theodolite and their functions are given as follows;

    Figure 4.2 : Parts of a Theodolite.

    2.3 BASIC COMPONENTS OF AN OPTICAL THEODOLITE

    Alidade level

  • 8/11/2019 Basic_Surveying.pdf

    21/66

    21

    Transparent tube that contains liquid and an air bubble; it serves as a guide for positioning the

    alidade on the vertical axis.

    Illumination mirror

    Adjustable polished glass surface that reflects light onto the circles so that the angles can be

    read.

    Leveling head

    Platform serving as a support for the theolodite.

    Horizontal clamp

    Knob that locks the alidade to prevent it from rotating.

    Leveling head locking knob

    Knob that locks the alidade to the leveling head.

    Leveling head level

    Transparent tube that contains liquid and an air bubble; it serves as a guide for positioning the

    leveling head on the horizontal axis.

    Base plate

    Plate to which the leveling head is attached by means of three leveling screws.

    Leveling screw

    Screw that adjusts the theodolites leveling head level on the horizontal plane.

    Telescope

    Optical instrument composed of several lenses; it can be adjusted in the horizontal and

    vertical planes and is used to observe distant objects.

    Optical sight

  • 8/11/2019 Basic_Surveying.pdf

    22/66

    22

    Device with an eyepiece that precisely aims the telescope at the target whose angles are to be

    measured.

    Adjustment for horizontal-circle image

    Knob that adjusts the sharpness of the image of the horizontal circle (graduated from 0 to

    360) in order to read the angles on the horizontal axis.

    Micrometer screw

    Knob that adjusts the micrometer to give a very precise reading of the circles measurements.

    Adjustment for vertical-circle image

    Knob that adjusts the sharpness of the image of the vertical circle (graduated from 0 to 360)

    in order to read the angles on the vertical axis.

    Alidade

    Part of the theodolite that rotates on a vertical axle to measure angles by means of the

    telescope.

    The trivets stage

    This forms the base of the instrument and in order to be able to attach the theodolite to the

    tripod, most tripods have a clamping screw which locates into a5/8inch threaded centre on

    the trivet. This enables the instrument to move on the tripod head and allows the theodolite to

    be centred. The trivet also carries the feet of three threaded levelling foot screws.

    The tripod

    This is used to provide support for the theodolite, the tripod may be telescopic i.e. it has

    sliding legs or may have legs of fixed lengths.

  • 8/11/2019 Basic_Surveying.pdf

    23/66

    23

    Figure 4.3 A tripod stand.

    The Tribrach

    This is the body of the instrument carrying all other parts. It has a hollow slightly conical

    shape socket into which fits the reminder of the instrument. The tribrach can be levelled

    independently of the trivet stage.

    The lower plate

    This carries the horizontal circle. The term glass arc has been used to describe optical

    theodolites because the horizontal and vertical circles on which the angle graduations are

    photographically etched are made of glass. Many types of optical theodolite are available,

    varying in reading precision from 1to 0.1although 20and 6reading theodolites are most

    commonly used in engineering surveying.

  • 8/11/2019 Basic_Surveying.pdf

    24/66

    24

    The focusing screw

    This is fitted concentrically with the barel of the telescope and diaphram can be illuminated

    for night or tunnel wok. When the main telescope is rotated in altitude about the trunnion axis

    from one direction to face in the opposite direction, it has been transmitted. The side of the

    main telescope, viewed from the eyepiece, containing the vertical circle is called the face.

    Standards

    This is the frame mounted directly on the cover plate carrying the telescope.

    Transit axis or trunnion axis

    This axis rests on the limbs of the standard and is securely held in position by a lock nut.

    Attached to the transit are the telescope and the vertical circle.

    Plate Bubble

    When this is levelled, that is at the centre of its run, the line of sight is horizontal.

    Optical plummet

    This assists the centering of the instrument particularly in windy weather.

  • 8/11/2019 Basic_Surveying.pdf

    25/66

    25

    WEEK FIVE

    3.1 GLOBAL POSITIONING SYSTEM (G.P.S.)

    The global positioning system is one of the available systems used for satellite positioning. It

    is also another method of determining horizontal and three dimensional positions for

    engineering surveys by processing measurements from artificial Earth satellites.

    The development of GPS (also known as NAVSTAR for navigation system using timing and

    ranging) began in 1973. Designed primarily for military users, GPS is managed and is under

    the control of the U.S. department of Defence. It is developed so that a user at any point on

    near the Earth can obtain three dimensional coordinates instantaneously. These fixes can be

    taken at any time of the day or night and in the any weather conditions.

    The GPS consists of three segments called the space segment, the control segment and user

    segment.

  • 8/11/2019 Basic_Surveying.pdf

    26/66

    26

    Figure 5.1 : A hand held skygolf-slycaddie-sg4-gps-system

  • 8/11/2019 Basic_Surveying.pdf

    27/66

    27

    3.2 Space segment

    Figure 52 :SPACE_GPS_NAVSTAR_IIA_IIR_IIF_Constellation.

  • 8/11/2019 Basic_Surveying.pdf

    28/66

    28

    Figure 5.3 : A 748px-GPS_Satellite_NASA,

    When fully operational, the space segment will consist of 24 satellites all of which will be it

    orbits at an altitude of 20200km. at this altitude, each satellite will orbit the Earth every 12

    hours and this, together with a suitable choice of orbital plane for each satellite, ensure that at

    least four (the minimum needed for a position fix) will be in view at any time.

    All satellites in the constellation transmit two L band signals known as L1and L2of

    frequencies 1575.42MHZand 1227.60MHZrespectively. L1is modulated with two binary

    codes known as the C/A (course acquisition) and p (precise) codes and a data message.

    The data message consists of an almanac giving the approximate position of all the satellites

    in the system, the satellite ephemeris which contains; precise information about the position

    of the host satellite and subsidiary information such as clock corrections and the status of the

    system. The L2carrier is modulated with the p code and data message only.

    The coarse acquisition code allows access to the standard position service which has an

    intended accuracy for single point positioning of the order of 150m and the precise code

    allows the precise positioning service which has an intended accuracy of about 15m. By

    giving an approximate position, the C/A code is able to help a receiver acquire code for more

    precise measurement of position.

    Control and user segments

  • 8/11/2019 Basic_Surveying.pdf

    29/66

    29

    Five monitor stations form the control segment of global positioning system; a master control

    station situated at Colorado Springs and four other stations at Hawaii, Kwajalein, Diego

    Garcia, and Ascensio Island. Each station tracks all the GPS satellites and this information is

    relayed to the master control station (at Colorado) where it is used to predict future orbits for

    all satellites. In addition, the clock on board each satellite is monitored and comparison is

    made with the GPS clock at Colorado Springs to enable corrections to be computed to keep

    satellite clocks in step with the GPS time. The ephemeris predictions and clock corrections

    are loaded to the satellites regularly and the data message transmitted by each satellite

    changes every hour. In case problems arise with the tracking network, each satellite stores

    sufficient data to be able to predict and transmit orbit data 14days without any update.

    The GPS user segment consists of all civil and military users of the system. In addition to

    land surveyors, the number of other civilian users of GPS is considerable since it is capable

    of dynamic positioning and has applications in hydro graphic surveying, setting out, civil

    engineering construction, vehicle navigation and all forms of navigations.

    3.3 GPS POSITIONING METHODS

    Pseudo ranging: by this method, GPS positioning is carried out with a single receiver

    determining Pseudo ranges

    Both the C/A and P codes transmitted by each GPS satellites are digital Pseudo random

    timing codes. The C/A code has a frequency of 1.023MHZand repeats every 1ms, whereasthe p code has a frequency of 1.023HMZ, but is 38 weeks long. At a frequency of

    1.023HMZ, the spacing between binary digits on the C/A code is about 300m and for the p

    code, the spacing is about 30m. These spacing (or the frequency of the codes) dictate what

    accuracy is possible from Pseudo range measurements with GPS. Since the C/A code

    repeats every 1ms, it is easy for a ground receiver to acquire without knowing the pseudo

    random sequence.

    However, unless a user has prior knowledge of the p code, it is impossible to decode

    because of the long pseudo random sequence involved.

    When a receiver locks into a satellite, the incoming signal triggers the receiver to generate a

    C/A code identical to that produced by the satellite. The replica code generated by the

    receiver is then compared with the satellite code in a process known as cross correlation in

    which the receiver code is shifted until it is phase with the satellite code. The amount by

    which the receiver generated code is shifted is equal to the transit time of the signal between

    satellite and receiver, multiplied by the speed of light; this gives the distance between the

  • 8/11/2019 Basic_Surveying.pdf

    30/66

    30

    satellite and receiver. If measurements are to be taken using the p code, the receiver repeats

    all cross correlation process and the so called hand over word instructs the receiver

    which portion of the p code to generate.

    All GPS satellites are fitted with very accurate caesium clocks which are all kept

    synchronised in GPS time by applying frequent corrections. On the other hand, receiver

    clocks are of power quality and are not usually synchronised with GPS time.

    Consequently, the receiver generated codes contain a clock error which affects transit times.

    Because of this, all ranges measured by receiver will be biased and are called pseudo

    ranges.

    As well as pseudo range measurement, a receiver will also decode the data message and

    from this computes the position of the satellite at the time of measurement.

    ii. Carrier phase measurement: Although the equipment and methods used in EDM are

    very different to GPS, the GPS receivers also use phase comparison to measure distances to

    satellites but this is carried out by comparing the phase of an incoming satellite signal with a

    similar signal generated by the receiver. These phase measurements are taken on the L1and

    L2carrier waves with a resolution of about 10and because the carriers have very short wave

    lengths of 0.19m (L1signal) and 0.24m (L2signal) it is possible to observe a range with

    millimetre precision.

    At the start of a measurement, a GPS receiver must first remove the codes from the L1

    and L2signals so that it can access the carrierwave.

  • 8/11/2019 Basic_Surveying.pdf

    31/66

    31

    WEEK SIX

    3.4 How GPS Works

    Figure 6.1 G.PS. Configuration.

    When people talk about "a GPS," they usually mean a GPS receiver. The Global Positioning

    System (GPS) is actually a constellation of 27 Earth-orbiting satellites (24 in operation and

    three extras in case one fails). The U.S. military developed and implemented this satellite

    network as a military navigation system, but soon opened it up to everybody else.

    Each of these 3,000- to 4,000-pound solar-powered satellites circles the globe at about 12,000

    miles (19,300 km), making two complete rotations every day. The orbits are arranged so that

    at any time, anywhere on Earth, there are at least four satellites "visible" in the sky.,

  • 8/11/2019 Basic_Surveying.pdf

    32/66

    32

    A GPS receiver's job is to locate four or more of these satellites, figure out the distance to

    each, and use this information to deduce its own location. This operation is based on a simple

    mathematical principle called trilateration. GPS receiver calculates its position on earth based

    on the information it receives from four located satellites. This system works pretty well, but

    inaccuracies do pop up. For one thing, this method assumes the radio signals will make their

    way through the atmosphere at a consistent speed (the speed of light). In fact, the Earth's

    atmosphere slows the electromagnetic energy down somewhat, particularly as it goes through

    the ionosphere and troposphere. The delay varies depending on where you are on Earth,

    which means it's difficult to accurately factor this into the distance calculations. Problems can

    also occur when radio signals bounce off large objects, such as skyscrapers, giving a receiver

    the impression that a satellite is farther away than it actually is. On top of all that, satellites

    sometimes just send out bad almanac data, misreporting their own position.

    Differential GPS (DGPS) helps correct these errors. The basic idea is to gauge GPS

    inaccuracy at a stationary receiver station with a known location. Since the DGPS hardware

    at the station already knows its own position, it can easily calculate its receiver's inaccuracy.

    The station then broadcasts a radio signal to all DGPS-equipped receivers in the area,

    providing signal correction information for that area. In general, access to this correction

    information makes DGPS receivers much more accurate than ordinary receivers.

  • 8/11/2019 Basic_Surveying.pdf

    33/66

    33

    WEEK SEVEN

    3.5 GPS INSTRUMENTATION

    Figure 7.1 G.P.S. Instrumentation.

    *** The weld GPS system 200 from Leica has a 9 - channel dual frequency

    receiver which means that it can track 9 satellites simultaneously and can take measurements

    on both L1and L2signals. It uses a reconstructed carrier in phase measurements but should

    the p code becomes encrypted, it can switch to the signal squaring method. The system 200

    supports all the measurement modes used for precise GPS surveying and with their SKI post

    processing soft ware, the accuracy quoted by Leica for baseline measurements is 5mm x

    1ppm of the baseline length. For single point positioning with pseudo ranges the accuracy

    is 15m subject to SA.

  • 8/11/2019 Basic_Surveying.pdf

    34/66

    34

    *** The 400 SSE Geodetic surveyors from Trimble navigation is also a dual

    frequency of 9 - channel receiver. Normally, it uses p codes measurements on both L1and

    L2frequencies ambiguity resolution but during periods of p code encryption the receiver

    measures the cross correlation of the encrypted by either reconstructing the original carrier

    or by using a signal squaring technique. In order to be able to reconstruct the original

    carrier, an exact knowledge of pseudo random binary codes (usually the p code) is

    required.

    Squaring techniques, on the other hand, require no knowledge of codes (this is known as the

    codeless approach) and give a carrier with codes eliminated at twice the original frequency.

    Because of this, the squaring technique is capable of being more accurate since phase

    measurements are taken at half the original wavelength. Unfortunately this method suffers the

    disadvantage that the squaring process destroys the data message and an external ephemeris

    must be used to obtain satellite positions.

    P Codes in conjunction with the C/A codes instead. This combination of observables

    according to the manufacturer, provides faster ambiguity resolution than squaring techniques

    when used for static positioning, the 4000 SSE has a quoted accuracy of 5mm + 1ppm times

    the baseline length and when used in the various kinematic surveying mode sit has a quoted

    accuracy of 200mm + 1ppm of the base-line length.Data processing for the 400 SSE is

    carried out with a software package known as GPSurvey.

    *** The Ashtech Z 12 is a 12 channel GPS receiver that uses the p code on both L1

    and L2frequencies and the C/A code to obtain carrier phase and pseudo range

    measurements. These are all combined to resolve carrier phase ambiguities when anti

    spoofing (AS) is turned on, the instrument automatically activates its Z Tracking mode

    which enable the cancellation of the effects of AS. The Z 12 has an accuracy quoted in

    millimetres, the exact figure depending on observation times and operating mode.

  • 8/11/2019 Basic_Surveying.pdf

    35/66

    35

    3.6 APPLICATIONS OF GPS

    The GPS is a rather complex system that can be used in so many ways. For basic point

    positioning and navigation, hand held receivers with an accuracy at the 100m level have

    found wide spread use while at the other end of the GPS spectrum, geodetic receivers with a

    computer and post processing software are now starting to be used for routine survey work

    at the centimetre level.

    Although the accuracy of GPS is important, some surveyors feel that the main advantage of

    the instrument compared with conventional surveys is that it can be used in any weather

    condition day or night. This enables GPS surveying to be carried out over extended periods at

    any time of the year without restrictions such as rain, fog and poor visibility delaying work.

    Another advantage when surveying with GPS is that inter visibility between stations orpoints surveyed is not necessary. This allows control stations to be placed where convenient

    and not at locations which may be difficult to get to in order to establish lines of sight.

    At the moment, the full potentials of GPS has not been realised even though the accuracy

    required for engineering surveys can be achieved. One of the reasons for this is the cost of

    GPS surveying which can be uneconomical compared with conventional surveying. These

    high costs are caused by firstly the receivers which are between five and ten times more

    expensive than total stations and secondly the fact that GPS is not fully kinematics and there

    are problems with satellite coverage, both of which can result in long occupation times.

    Added to these, there are difficulties in defining heights above survey datums such as mean

    sea level and with real time data processing and control.

    Despite these draw backs, GPS has been very successfully used for control surveys where it

    has joined traversing triangulation and trilateration as a method for coordinating stations in a

    network.

    The best application identified so far for GPS have been for improving existing national

    control networks and for surveys in remote areas. GPS is also used on engineering projects

    that extend over large areas, especially where a high degree of precision is required, e.g. in a

    tunnel network surveying.

    Another application where GPS has been successfully utilised in engineering surveying is in

    providing control for a number of major route location and highway maintenance schemes. In

    these examples, GPS provided what is known as the primary control or points with height

    precision spread out over relatively long distances. These were used as reference points for

  • 8/11/2019 Basic_Surveying.pdf

    36/66

    36

    providing further control, for example link traversing was carried out between the GPS

    reference points using total station or combined theodolite and EDM systems. This may well

    be the best use for GPS in future where it is integrated with other methods of surveying rather

    than trying to compare with them.

    As far as detail survey and setting out are concerned, GPS is not used extensively in Civil

    Engineering and construction as it can not compete with conventional large scale surveying

    systems at present, particularly regarding costs. However, the possible applications in

    engineering surveying f0r low cost, small size GPS black box capable of high precision,

    real time surveys are enormous. Such surveying system would be integrated with or even

    replace existing methods for control surveys, detail surveys and setting out and would

    completely change surveying as it is known today. Much research is being carried out to

    achieve this and developments in receiver technology and associated software.

  • 8/11/2019 Basic_Surveying.pdf

    37/66

    37

    WEEK EIGHT

    4.1 INTRODUCTION TOTOTAL STATIONS

    The total station otherwise known as electronic tachometer is an instrument used in surveying

    which is capable of measuring angles and distances electronically. Just as is common withother electronic surveying instruments, the total station is operated using a multi function

    key board which is connected to a micro processor built into the instrument. The micro

    processor not only controls both the angle and distance measuring systems but also used as a

    small computer that can electronically calculate slope corrections, vertical components, and

    rectangular co ordinates and in some cases, can also store observations directly using an

    internal memory.

    Figure 8.1: A Detailed sketch of the Total Station.

    Below is a figure showing the NIKON DTM A 5LG, SOKKIA SET3C and the Zeiss Elta 5,

    a sample of total station from the extensive range now available.

  • 8/11/2019 Basic_Surveying.pdf

    38/66

    38

    Figure 8.2 : A KTS-442R-445R-Total-Station.

  • 8/11/2019 Basic_Surveying.pdf

    39/66

    39

    Figure 8.3 : A 76e%20TotalStation

  • 8/11/2019 Basic_Surveying.pdf

    40/66

    40

    Figure 8.4 : A TOTAL STATION

    The table below shows the technical specifications in summary of the types given

    Table 8.1: Specifications of some examples of total station.

  • 8/11/2019 Basic_Surveying.pdf

    41/66

    41

    Instrument Type. Nikkon DMT

    A5LG

    SOKKIA SET 3C ZEISS ELTA 5

    Angle measurement

    - H accuracy

    - V accuracy

    2

    2

    3

    3

    5

    5

    Distance measurement

    - to one prism

    - to three prisms

    Accuracy

    2.3km

    3.1km

    (2mm + 2ppm)

    2.2km

    2.9km

    (3mm + 3ppm)

    1.0km

    1.5km

    (5mm + 3ppm)

    Measurement time 3.0 seconds 3.2 seconds 3.4 seconds

    Data displayed

    - H and V angles

    - SD, HD and VD

    - X, Y and Z co ords

    - setting out data

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Yes

    Data recording Data recorder field

    computer

    Data recorder field

    computer memory

    card

    Data recorder field

    computer

    Compensator battery Singleaxis Ni

    cad 7.2v

    Dual axis Ni cad

    6.0v

    Single axis Ni cad

    4.8v

    4.2 Angle measurement

    This exercise is done using an electronic theodolite .All features associated with the

    electronic theodolite (a theodolite that produces a digital output of direction or angle) is

    appliance to all total stations.

    Typically, a total station can record angles with resolution of between 1and 20

    and all

    instruments incorporate some form of compensator, the more expensive using dual axis and

    the less sophisticated, single axis compensator.

  • 8/11/2019 Basic_Surveying.pdf

    42/66

    42

    4.3 Distance measurement

    Currently, most total stations use a Ga As infra red carrier source and phase comparison

    techniques in order to measure distances. However, compared to theodolite mounted systems

    nearly all total stations use coaxial optics in which the EDM transmitter and receiver are

    combined with the theodolite telescope. This makes the instrument much more compact and

    easier to use on site. Normally a total station will measure a slope distance and the micro

    processor uses the vertical angle recorded by the theodolite along the line of sight (line of

    distance measurement) to calculate the horizontal distance. In addition, the height difference

    between the trunnion axis and prism centre is also calculated and displayed. All instruments

    use some form of signal attenuations to protect the receiver.

    Three modes are usually available for distance measurement namely;

    Standard (or coarse) mode: This has a resolution of 1mm and a measurement time of 1 2

    seconds.

    Precise (or refine) mode: This has a resolution of 1mm but a measurement time of 3 4

    seconds. This is more accurate than the standard mode since the instrument repeats the

    measurement and refines the arithmetic mean value.

    Tracking (or fast): Mode in which the distance measurement is automatically replaced at

    intervals of less than one second. Normally, this mode has a resolution of 10m and is used

    extensively when setting out since readings are updated very quickly and vary in response to

    movements of the prism which is usually pole mounted.The range of a total station is typically 1 3km to a single prism assuming visibility is

    good and up to a range of 500m which covers 90 percents of the distance measured on site,

    the precision of a typical total station is about 5mm. Most instruments allow for the input of

    temperature and pressure which enables the distance readings to be automatically corrected

    for atmospheric effects. Also, any value of prism constant can be entered into the instrument

    via the alpha numeric key board.

    If a code is entered from the key board to define the feature being observed, the data can be

    processed much more quickly by downloading it into approximate software.

    On numeric key boards codes are represented by numbers and/or letters which give greater

    versatility and scope. The alpha- numeric control panel of the Topcon GTS 6 is shown in

    figure below.

  • 8/11/2019 Basic_Surveying.pdf

    43/66

    43

    Figure 8.5 A sketch of the Alpha Numeric key board of the Total Station.

    4.4 Power supply

    Rechargeable nickel cadmium (Nicad) batteries are now standard for surveying instruments

    and these are connected directly to the total station without using cables. For angle and

    distance measurements, between two and ten hours use can be obtained from a battery,

    depending on the instrument. Most total stations are capable of giving a battery power

    indication and some have an auto save feature which switches the instrument off or into

    some standby mode after it has not been used for a specified time. It is a good practice, no

    matter what assurances a manufacturer may give about the life of a battery to have a fully

    charged spare with the instrument at all times.

    The micro processor of the total station apart from controlling the angle and distance

    function, it is also programmed to perform coordinate and other calculations.

    Even though a total station can perform many of the calculations often done manually on site,

    this does not mean that the surveyor or engineer should lose this ability. Thus, this

    opportunity should be seen as a method and not a substitute for other surveying principles.

    GTS-6

    REC BAT MENU

    F1 F2 F3 F4 F5 F6

    DISPLY SREEN

  • 8/11/2019 Basic_Surveying.pdf

    44/66

    44

    WEEK NINE

    5.1 THEODOLITE TRAVERSING

    A traverse is a continuous framework of lines connecting a number of points, lengths of the

    lines and their angular relationship to each other being measured. The lines are known as legs

    and the points as stations.

    A traverse is a means of providing horizontal control in which rectangular coordinates are

    determined from a combination of angle and distance measurements along lines joining

    adjacent stations.

    USES

    Traverse surveys are used where site conditions make the chain triangulation method

    impossible, i.e. a wood, built up factor blocks, long winding river or where the survey is of

    large area and details are required.

    The main purpose of theodolite traversing is to establish the bearing and lengths of a series of

    adjoining lines which together form the framework for the survey of a particular area. The

    bearings and distances are then plotted with protractor or by triangular co ordinate.

    5.2 TYPES OF TRAVERSING

    We have two major types;Open traverse

    Close traverse

    OPEN TRAVERSE

    A traverse whose starting and finishing stations do not coincide or are not both fixed or

    known is called an open traverse. This type of traverse is used to survey rivers, roads or

    railway routes.

    Open traverse commences at a known point and finishes at unknown point or station and

    therefore are not close. Since open traverse are used only in exceptional circumstances, there

    is no external check on the measurement.

  • 8/11/2019 Basic_Surveying.pdf

    45/66

    45

    CLOSE TRAVERSE

    When a framework form a close figure (or when the traverse connects station which position

    are known) it is known as a closed traverse, such a traverse is easily checked, as a surveying

    start and finishes at a fixed point or points.

    In the figure below, a traverse has been run from station A (of known position) to stations 1,

    2, 3 and another known position B. Traverse A ,1, 2, 3,B is therefore; closed at B. This type

    of traverse is called a link, connecting or close route traverse.

    Figure 9.1 :Closed Traverse Network.

    The figure shown below is a framework of a closed traverse known as a polygon traverse it

    started and ended at a common point x.

    Figure 9.2 : Closed Traverse Network.

    A

    1

    2

    3

    B

    N

    X

  • 8/11/2019 Basic_Surveying.pdf

    46/66

    46

    5.3 TRAVERSE SPECIFICATION AND ACCURACY

    The accuracy of a traverse is governed largely by the type of equipment used and the

    observing and measuring techniques employed. These are basically dictated by the purpose of

    the survey work.

    Many types of traverse are possible but three broad groups can be defined and are given in

    table 2.1 below.

    The most common type of traverse for general engineering work and site surveys would be of

    typical accuracy 1 in 10, 000.

    An important factor when selecting traverse equipment is that the various instruments should

    produce roughly the same order to precision, that is, it is pointless using a 1theodolite to

    measure traverse angles if the lengths are being measured with a synthetic tape.

    Table 9.1 : General traverse specifications

    Type Typical Purpose Angular

    measurement

    Distance

    measurement

    Geodetic or

    precise

    1 in 50, 000 or

    better

    1. Major control

    for mapping

    large circles

    2. Provision of

    very accurate

    reference points

    for engineering

    surveys.

    0.1 EDM

    General 1 in 5, 000 to 1

    in 50, 000

    1. General

    engineering

    survey that is,

    setting out and

    site surveys

    2. Secondary

    control for

    mapping large

    areas

    1or 2

    theodolite

    EDM, steel taps

  • 8/11/2019 Basic_Surveying.pdf

    47/66

    47

    Low accuracy 1 in 500 to 1 in

    5, 000

    1. Small scale

    detail surveys.

    2. Rough large

    scale detail

    surveys.

    3. preliminary

    or

    reconnaissance

    surveys

    20or 1

    theodolite

    Synthetic tapes,

    stadia

    tacheometry

  • 8/11/2019 Basic_Surveying.pdf

    48/66

    48

    WEEK TEN

    5.4 Traversing field work: Reconnaissance

    This is one of the most important aspects of any survey and must always be undertaken

    before any angles or lengths are measured. The main aim of the reconnaissance is to locate

    suitable positions for traverse stations and a poorly executed reconnaissance can result in

    difficulties at later stages in a survey leading to waste of time and inaccurate work.

    To start a reconnaissance, an over all picture of the area us obtained by walking all over the

    site keeping in mind the requirements of the survey. If an existing map or plan of the area is

    available, this is a useful aid at this stage.

    When sitting station, an attempt should be made to keep the number of stations to a minimum

    and the lengths of traverse legs should be kept as long as possible to minimise the effect of

    any centring errors.

    If the traverse is being run for a detail survey then the method which is to be used for the

    subsequent operation must be considered. For most sites a polygon traverse is usually sited

    around the area at points of maximum visibility. It should be possible to observe across

    checks or lines across the area to enable other points inside the area to be fixed and also to

    assist in the location for angular errors. Traverse for read works and pipelines generally

    require a link traverse. Since these sites tend to be long and narrow. The shape of the read or

    pipe line dictation the shape of the traverse.

    If distance measurements are to be carried out using tapes the ground conditions between

    stations should be suitable for this purpose, steep slopes or badly broken ground along the

    traverse lines should be avoided and it is better if there are as few changes of slopes as

    possible. Roads and paths that have been surfaced are usually good for ground measurements.

    Stations should be located such that they are clearly inter visible, preferably at ground level,

    that is, with a theodolite set up at one point, it should be possible to see the ground marks at

    adjacent stations and as many others as possible. This eases the angular measurement process

    and enhances its accuracy.

    Stations should be placed in firm level ground so that the theodolite and tripod are supported

    adequately when observing angles at the stations. Very often stations are used for a sited

    survey and at later stage for setting out. Since some time elapse between the site survey and

    the start of the construction, the choice of firm ground in order to prevent the stations moving

    in any way becomes even more important. It is sometimes necessary to install semi

    permanent stations.

  • 8/11/2019 Basic_Surveying.pdf

    49/66

    49

    Owing to the effects of lateral refraction and shimmer traverse ,lines of sight should be well

    above ground level (greater than 1m) for most of their length to avoid any possible angular

    errors due to rays passing close to ground level (grazing rays). These effects are serious in hot

    weather.

    When are stations have been sited a sketch of the traverse should be prepared approximately

    to scale. The stations are given reference letters or numbers. This greatly assists in the

    planning and checking of fieldwork.

    5.5 STATION MARKING

    When a reconnaissance is completed, the stations have to be marked for the duration or

    longer of the survey. Station markers must be permanent, not easily disturbed and they should

    be clearly visible. The construction and type of station depends on the requirements of the

    survey.

    For general purpose traverse, wooden pegs are used which are hammered into the ground

    until the top of the peg is almost flushed with the ground level (see figure below).

    300-500mm

    Figure 10.1 ; station peg.

    If it is not possible to drive the whole length of the peg into hard ground the excess above the

    ground should be sawn off. This is necessary since a long length of peg left above the ground

    is liable to be knocked down. A nail should be tapped into the top of the peg to define the

    exact position of the station as shown in figure above.

    Stations in roadways can be marked with 75mm pipe nail driven flush with the surface. The

    nail surround should be painted for easy identification. These marks are fairly permanent, but

    it is usually prudent to enquire if the road is to be resurfaced in the near future.

    A more permanent station would be normally required on marks set in concrete, typical

    station designs are shown in the figure below.

    50mm square

    wooden peg

    Nail

  • 8/11/2019 Basic_Surveying.pdf

    50/66

    50

    A reference or witnessing sketch of the features surrounding each stations should be

    prepared, especially if the stations are to be left for any time before being used, or if they will

    be required again at a much later stage.

    Measurements are taken from the station to nearby permanent features to enable it to be

    relocated. A typical sketch is shown in figure below.

    Metal

    post

    Station

    14

    (Iron Bar in Concrete)

    Building

    Man hole

    3.4m 3.8m

    N

    Figure 10.2: Witnessing Sketch

  • 8/11/2019 Basic_Surveying.pdf

    51/66

    51

    WEEK ELEVEN

    6.1 SETTING OUT

    The International Organization for Standardization (ISO) in their publication ISO/DP 7078

    Building construction defines setting out as the establishment of the marks and lines to define

    the positions and levels of the elements for the construction work so that works may proceed

    with reference of them.

    Setting out can also be defined as the process whereby the positions and levels of new works

    already recorded on a working plan are transferred to the ground.

    A definition often used for setting out is that, it is the reverse of surveying. This definition

    means that whereas surveying is the process of producing a plan or map of a particular area

    or site, setting out begins with the plan and ends with the various elements of a particular

    engineering project correctly positioned on the ground in the area.

    However, as in surveying, setting out must be arranged so that the work at hand can be

    properly checked. Every peg placed must be proved to be in its correct position as provided

    in the plan within allowable limits.

    6.2 AIMS OF SETTING OUT

    There are two main aims when undertaking setting out operations;

    The various elements of the scheme or work must be correct in all three dimensions both

    relatively and absolutely, that is each element must be in its correct size, in its correct

    position and at its correct deduced level.

    Once setting out begins, it must proceed quickly and with little or no delay in order that the

    works can proceed smoothly and the costs can be minimized.

    In practice, there are many techniques, which can be used to achieve these two aims.

    However, they are all based on three general principles

    Points of knownE, Ncoordinates must be established within or near the site from which thedesign point can be set out in their correct plan positions. This involves horizontal control

    techniques

    Points of known elevation relative to an agreed datum are required within or near the site

    from which the design points can be set out at their correct reduced levels. This involves

    vertical control technique.

  • 8/11/2019 Basic_Surveying.pdf

    52/66

    52

    Accurate methods must be adopted to establish design points from these horizontal and

    vertical controls. This involves positioning techniques

    6.3 STAGES IN SETTING OUT.

    As the work proceeds, the setting out falls into two broad stages;

    Initially, techniques are required to define the site, to set out the foundations and to monitor

    their construction. Once this has been done, emphasis changes to the above ground

    elements of the scheme and methods must be adopted which will ensure that they are fixed at

    their correct levels and positions. These two stages are explained as follows

    FIRST STAGE SETTING OUT.

    The first stage when setting out any work is to locate the boundaries of the works in their

    correct position on the ground surface and to define the major elements. In order to achieve

    this, horizontal and vertical control points must be established on or near the site as explained

    earlier. These are then used not only to define the perimeter of the site which enables fences

    to be erected and site clearance to begin but also to set out critical design points on the

    scheme and to define slopes, directions and so on. For example; in a structural project, the

    main corners and sites of the building will be located and the required depths of dig to

    foundation level will be defined. In a road project, the centre line and the extent of the

    embankments and cuttings will be established together with their required slopes.

    When the boundaries and major elements have been pegged out, the top soil is stripped off

    and excavation work begins. During this period, it may be necessary to relocate any peg(s)

    that are accidentally disturbed by the plant and equipment. Once the formation level is

    reached, the foundations are laid in accordance with the drawings and the critical design

    points located earlier.

    Setting out techniques is used to check that the foundations are in their correct three

    dimensional positions. The first stage ends once construction to ground floor level, sub base

    level or similar levels has been completed.

  • 8/11/2019 Basic_Surveying.pdf

    53/66

    53

    WEEK TWELVE

    SECOND STAGE SETTING OUT.

    This continues from the first stage, beginning at the ground floor slab, road sub base level

    or similar levels. Up to this point, all the controls will still be outside the main construction,

    for example, the pegs defining building corners, centre lines and so on will have been

    knocked out during the earth moving work and only the original control will be

    undisturbed. Some off set pegs may remain but these too will be set back from the actual

    construction itself.

    The purpose of second stage setting out therefore is to transfer the horizontal and vertical

    controls used in the first stage into the various elements of the scheme.

    6.4 EQUIPMENT FOR SETTING OUT OF BUILDING.

    The nature and complexity of the building or any engineering work like; bridges, dams, roads

    etc. determine the accuracy that need to be achieved, which in turns, defines or determines

    which types of equipment will be selected for the task e.g. dumpy level or theodolite, fibre

    glass tape or steel tape, plumb bob and line or optical plummet etc.

  • 8/11/2019 Basic_Surveying.pdf

    54/66

    54

    Figure 12.1 : A MEASURING TAPE.

    Figure 12.2 : A STEEL MEASURING TAPE.

    Figure 12.3 : A DIGITAL MEASURING TAPE.

    PEGS

    :These are usually made of two materials;

  • 8/11/2019 Basic_Surveying.pdf

    55/66

    55

    Figure 12.4 : Wooden Pegs.

    i.

    Timber pegs 50mm section of variable length but having a pointed end to

    facilitated driving into the ground by hammering. A timber peg may have a nail

    fixed to its top at the centre to locate exactly the station point. All setting out pegs

    should be clearly marked with a 50mm deep and red paint and should have a

    board of blue paint.

    ii.

    Steel pegs they are usually formed from lengths of steel reinforcement rods, cut to

    a suitable lengths and may have one edge sharpened to facilitate careful driving

    positions have been checked, they are normally surrounded by concrete.

    Identification works may be made into the surface of the concrete before it sets

    hard

    Lines:

    They are strings, wire, nylon etc. the weather condition plays a very vital role in selecting

    which material to be used so that the line is safe from damage, stretch, sag in prevailing

    working conditions of the weather. The lines provides straight out lines from a peg to

    another. They define straight lines from points or stations.

    PROFILE BOARDS:

    These are used in conjunction with pegs so that extended lines positions may be marked by

    using profile boards, the string or wire lines can be removed in the knowledge that when they

    are required again, they can be positioned exactly as they were originally. Normally, a profile

    boards is erected near each off set peg and used in exactly the same way as a sight rail, a

    traveler are being used between profile boards to monitor excavation

  • 8/11/2019 Basic_Surveying.pdf

    56/66

    56

    FIGURE 12.5 : SHOWING PROFILE BOARD

    SITE SQUARE:

    This is an optical device used for setting out right angles whereby unskilled labour can attain

    an accuracy of 5mm in 30m.

    The instrument is basically of two telescopes mounted one above the other and with their

    lines of sight set at 900to each other. The site square is supported on a tripod stand, which

    can be set over a fixed mark on the ground. The lower telescope is aimed along the line from

    which the right angle is to be established being brought to bear on any site mark in the line bymoving the telescope:

    In the vertical plane

    Laterally by means of a fine turning screw. Once the adjustment of the lower telescope is

    complete, the upper telescope will trace out a line at right angles to the original line and a

    further site mark can be positioned as required by moving this telescope in the vertical plane

    only.

  • 8/11/2019 Basic_Surveying.pdf

    57/66

    57

    Figure 12.6 : Travelers used in setting out slopping ground

  • 8/11/2019 Basic_Surveying.pdf

    58/66

    58

    WEEK THIRTEEN

    6.5 SETTING OUT OF BUILDING

    Setting out the base line: The base line adopted in setting out a building is usually the

    building line, although on extensive factory layouts are centre lines of buildings are

    sometimes runs of machinery. In either case, the location of such lines is reacted to the

    physical features of the site. The building line is the line of the front face of the building as

    indicated in figure below (line AB).

    Figure 13.1 : Setting out a simple building plan.

    The position of the building line may be defined on the working plan by measurements from

    any of the following;

    The property boundary

    The edge of the road kerb

    The centre line of the road.

    It is important to note that

    Proposed building (structure)EXISTING

    BUILDING

    EXISTING

    BUILDING

  • 8/11/2019 Basic_Surveying.pdf

    59/66

    59

    Where there is no indication of the building line, its position must be agreed on site with the

    local authority-building inspectors.

    Where there is an obvious line of existing building frontages, this line is usually adopted as

    the building line.

    The building line is first ranged by eye and pegs are placed at the two front corners of the

    outer face of the proposed building. Critical measurements are made from the boundary to the

    building corners as shown in figure above or defined by local regulations and along the face

    of the proposed building by nails hammed into the pegs.

    6.6 B. Setting out the subsidiary lines:

    From the two front pegs, A and B, angles are set out in accordance with the building plan to

    follow the outer face of the flank walls. This could be done with a theodolite, setting up over

    each peg in turn and turning off the required angle from the building line in each case. As the

    angle of the flank wall is most often 900this could be set out without a theodolite using the

    following;

    a. A 3:4:5 taped triangle

    b. A builders square, which is a 3:4:5-ratio triangle made out of timber

    c. An optical square

    d. A site square, which is a proprietary instrument consisting of two small telescopes

    fixed rigidly at right angles on a small stand.

    e. A level incorporating a horizontal circle like a theodolite, but reading by venire toabout 5only. When the two rear pegs; C and D are placed and nail marked, they are

    checked by measuring between them and by measuring the diagonals.

    In a rectangle building, the two diagonals must be equal to prove the positioning of

    the pegs.

    After the main outline has been pegged ,any minor extensions or returns from the

    main figure are pegged and checked, such as the pegs at e, f, g, h, j and k, when the complete

    outline of the outer face of the building has been pegged and checked.

    Setting out the reference marks: The pegs now placed will be destroyed as the

    foundations are excavated and the reference system must be adopted. This can be achieved by

    the use of profile boards, illustrated in the above figure.

    Profile boards are constructed of 150 or 200mm by 25mm, boards supported on 50mm

    square posts hammered firmly into the ground, well clear of the working area. On well

    organized sites, the boards are placed at one level, usually finished floor level or dam proof

    course level. The advantages of these are as follows;

  • 8/11/2019 Basic_Surveying.pdf

    60/66

    60

    They help to keep the tape horizontal when making measurements.

    They provide a level datum around the site so that less check leveling is needed subsequently.

    Disturbance of the boards can easily be noted visually.

    Levels of work below ground can be controlled by travelers using the profile boards as sight

    rails.

    Approximate levels can be obtained by direct vertical measurements up or down from lines

    strung between the profile boards.

    Once all boards have been placed in position, all at one level, lines are strung between

    them and positioned vertically above the nail markers defining the building outline. If the line

    is some distance above the peg, the peg position must be plumbed upward, using plumb line

    in reference to the less accurate brick layers spirit level. When the lines have been accurately

    strung across the profile boards, positions are marked with a nail or saw cut so that they

    may be replaced at any time. The intersections of the various strung lines will then define the

    peg positions when they are removed for excavations. Profile boards for minor buildings or

    projections are not always erected or needed. Full foundation width is marked on the boards

    and two lines strung between these points to define the width of the foundation trench to be

    dug. Once the trench has been started, the lines are removed.

    Alternatively, the lines may be temporarily defined along the ground by means of

    strips of lime or sand to guide excavation of the trench.

  • 8/11/2019 Basic_Surveying.pdf

    61/66

    61

    WEEK FOURTEEN

    7.1 TRIANGULATION AND TRILATERATION.

    Like traversing, triangulation and trilateration are surveying methods used to locate

    control points or stations which form a network.

    A triangulation network consists of a series of single or overlapping triangles as

    shown below, the points (vertices) of each triangle forming control stations. Position is

    determined by measuring all the angles in the network and by measuring the length of one or

    more base lines such as XY or IB, with the base line, application of the Sine Rule in each

    triangle throughout the network enables the lengths of all triangle sides to be calculated.

    These lengths when combined with the measured angles enable the coordinates of the stations

    to be computed.

    Figure 14.1 : Triangulation Network.

  • 8/11/2019 Basic_Surveying.pdf

    62/66

    62

    Figure 14.2 A map.

    7.2 TRIANGULATION AND TRILATERATION: FIELDWORK.

    The methods that can be used to establish and observe a combined network vary

    considerably with its size and it is emphasized the following sections are concerned solely

    with civil engineering and construction sites where distances between control stations seldom

    exceed 1km.

  • 8/11/2019 Basic_Surveying.pdf

    63/66

    63

    Figure 14 3:TRIANGULATION NETWORK

    A trilateration network is a series of singles or overlapping triangles but in this case,

    position is determined by measuring all the distances in the network instead of the angles.

    However, to enable station coordinate to be computed, the measured distances are combined

    with angle values derived from the side length s of each triangle.

    Until the advent of EDM, the measurement of distances in a trilateration scheme with

    sufficient accuracy was a very difficult and time consuming process and because of this

    trilateration techniques were seldom used for establishing horizontal control. Traversing

    techniques were also limited since it was not possible

    to maintain a uniformly high accuracy when traversing over long distances. As a result

    of that, triangulation was used extensively in the past to provide control for survey covering

    large areas.

    However, nowadays, because of the high precision, and accuracy of modern

    equipment, traversing, triangulation and trilateration can all be used as methods of

    establishing horizontal control. Although traversing is the most popular method for providing

    control on site, combined triangulation and trilateration is often used; this involves the

  • 8/11/2019 Basic_Surveying.pdf

    64/66

    64

    measurements of angles and distances through out a network rather than between selected

    stations as in traversing. On construction sites, combined network are used where horizontal

    control is required to be spread over large areas and they are also used to provide reference

    points for control extension, for monitoring and for precise engineering work.

    The reconnaissance for a network is the most important aspect of the survey and is

    carried out to determine the positions of the control stations. Since this is linked to the size

    and shape of the figure to be used in the scheme and to the number of measurements to be

    taken, the reconnaissance will determine the amount of fieldwork that will have to be

    undertaken.

    To start the reconnaissance, information relevant to the survey area should e gathered,

    especially that relating to any previous survey. Such information may include existing maps,

    aerial photographs and any site surveys already prepared for the construction project.

    From this information, a network diagram should be prepared, approximately to scale,

    showing proposed locations for the stations. It is also important that the survey area is visited,

    at which time the final positions for the stations are chosen.

    Many guidelines for reconnaissance when traversing are also applicable here, but

    particular attention must be paid to the establishing the station points, the layout of stations in

    relation to the survey work and the precision and reliability of the network must be assessed.

    Based on the reconnaissance, decisions regarding the measurements to be

    taken are made and the instruments to be used for the survey are specified. Most

    importantly, a check should be made to ensure that the survey meets its specifications

  • 8/11/2019 Basic_Surveying.pdf

    65/66

    65

    WEEK FIFTEEN

    7.3 DISTANCE MEASUREMENT.

    During the observation of a network, the lengths of as of the triangles sides as possible are

    measured using some sort of EDM equipment. When using the EDM equipment, the

    meteorological conditions at the time of measurements must be monitored carefully and

    suitable corrections made; also, any systematic instrument errors present in the equipment

    must be allowed for by careful calibration of the of the equipment. For National Grid based

    surveys, the scale factor is applied to each measured distance and, if the distance has been

    measured at an appreciable elevation, a height correction must be applied since mean sea

    level is the datum height for the National Grid.

    7.4 ANGLE MEASUREMENT.

    The instrument normally required for measurement of the angles in networks is a 0.1/0.2

    or 1 double reading optical micrometer theodolite or an electronic theodolite of similar

    precision.

    The theodolite is set up and angles are observed and booked. Very often, a total station or

    theodolite mounted EDM system is used to observe a network and distances and angles are

    measured simultaneously at each station.

  • 8/11/2019 Basic_Surveying.pdf

    66/66

    Figure 15.1 :Distance measuring Instrument.