Top Banner
Risk Management Basics and Benefits 5 Years of Learning
24
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Basic risk management presentation 17th june 2015

Risk Management Basics and

Benefits 5 Years of Learning

Page 2: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

2

About us

Applied Analytics Integrator providing

information management & analytics services for

Asset and Enterprise Performance Management

200+ people across 3 key locations and numerous

customer sites

We help our customers do more with their data –

enabling better decisions

Working with asset intensive and mission

critical industries including Defence, Energy, Rail,

Infrastructure, Transport and Utilities

Babcock Analytic Solutions

Page 3: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 3

Definitions

Risk

APM PRAM: “A risk event is an uncertain event or set of circumstances

that, should it occur, will have an effect on achievement of one or more of

the project’s objectives.”

Uncertainty

APM BOK: “Uncertainty is the inherent variability that it is impossible to

predict how long an activity will take.”

Issue

APM BOK: “An issue is a threat to project objectives that cannot be

resolved by the project manager. Issues have already occurred and are

therefore certain.”

Page 4: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 4

Project Risk Management

The purpose of risk management is to manage a project’s exposure to

risk (Impact and Probability).

Projects need to take risks to be profitable and maximise benefits.

Good risk management goes unnoticed.

Page 5: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 5

APM Risk Process

Initiate

Identify

Assess

Plan Responses

Implement Responses

Manage P

rocess

Page 6: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 6

Establish the Context (Initiate)

Outputs

An understanding of the project.

Assumptions.

Risk scoring scheme.

What risk information is required?

To what detail is this information required?

Is a risk register required?

Is a risk register tool required?

Page 7: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 7

Establish the Context Understanding the project

What are the projects objectives/benefits?

How does this project affect the customer and the company delivering it?

How big will the project be?

• Scope

• Cost

• Resource

What assumptions have been made so far?

Not understanding the context will result in poor risk data.

Project

Company

Company's

Environment

Customer

Customer’s

Environment

Page 8: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 8

Establish Context

Risk Requirements

Clear set of objectives.

• Defines risk appetite

Each project requires an agreed risk scoring scheme.

• Qualitative risk scoring

Each project may require a different scoring scheme.

• How many risks will be recorded and in how much detail?

‒ Is a risk register required?

– Is a specific risk tool required?

Management understanding and buy in.

Very

High 5 10 15 20 25

High 4 8 12 16 20

Mod

erate 3 6 9 12 15

Low 2 4 6 8 10

Very

Low 1 2 3 4 5

Very

Low

Low Moder

ate

High Very

High

Impact

Pro

bab

ilit

y

Page 9: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 9

Risk Identification 1

This will take more than a one hour meeting!

Output

Risk statements with a cause and an effect.

A list of uncertainties to the project.

At the bidding phase or start of the project a top down approach to risk identification allows for a better structure.

Pitfalls

Dominant personalities

Work owners being offended by risk

Group think

Identifying non-risks (issues)

Competition to identify the most risks.

Trying to identify risk with no context.

Page 10: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 10

Risk Identification 2

There are two types of risk:

Uncertainty

This is the inherent variability that it is impossible to predict how long an

activity will take. 3 point estimates (Minimum, Most likely and Maximum)

are used for activity durations and costs.

Risk Events

Discrete events that are separate from an activity. These are contained

within the Risk register.

Uncertainty + Risk Events = Total Risk Exposure

Page 11: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 11

Risk Identification 3

Identification Techniques

Review of WBS

for potential inconsistencies

Checklists

One-to-one Interviews

Systematic Searches

Review Assumptions

Learning from Experience

(LFE)

Prompt Lists

Brainstorming

Page 12: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 12

Risk Identification 4

Cause

• A tangible and concise explanation of a definitive event or set of

circumstances that exist in the project or its environment.

• Due to / Caused by………..

Risk Description / Uncertainty

• A description of the actual uncertainty describing what may / could occur.

• There is a risk that……………….

Effect

• (Threat) The unplanned variations from project objectives that will arise as

a result of the risk occurring/impacting.

• (Opportunity) The currently unplanned alterations to the project to increase

the likelihood of achieving the project objectives.

• This will lead to/ result in…………………

Page 13: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Risk Assessment 1

Footer 13

Threat

• Schedule loss

• Cost increase

• Reduction in performance of product

Opportunity

• Schedule saving

• Cost saving

• Increase in performance of product

Outputs

The creation and justification of the impacts of the risk:

• Probability of occurrence

• Impact on the project’s objectives

• Recorded in 3 point estimates

Current (pre-mitigation) – can be done immediately

Target (post-mitigation) – can only be done once mitigation plans

have been identified and agreed

Page 14: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Risk Assessment 2

Footer 14

Pitfalls

Estimating

• People’s personality and personal experience will be drivers at this

point in the process

• Humans are naturally poor at estimating

• Affect – substitution of what you feel when asked a difficult

question

• Availability – a mental shortcut that relies on immediate examples

that come to a given person's mind when evaluating a specific

topic, concept, method or decision

• Anchoring – a heavy reliance on the first piece of information

offered (the "anchor") when making decisions

Page 15: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Risk Assessment 3

Footer 15

Threat

Scenario creation

Analysing plans

- Increase in work scope

- Delay to start dates

Analysing cost models

- Increase in costs

Analysing the product

- Decrease in benefits

Opportunity

Plan out and agree the benefits to

the programme.

Agree with Subject Matter Experts

(SMEs) and Suitably Qualified and

Experienced Personnel (SQEP)

- Reductions in schedule

- Cost savings

- Increase in benefits

Techniques

Page 16: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 16

Plan Responses (Threats)

Outputs

• Threat – a set of mitigation actions that reduce the impacts or the

probability of those impacts

Types of responses

• Mitigate – undertake specific actions to reduce probability and / or

impact

• Avoid – take a different course of action that stops the risk occurring

• Transfer – transfer of risk to another party better placed to manage the

threat

• Accept – accept the risk impact on the programme and establish a

fallback plan

• Fallback – strategy to be implemented if the risk materialises, to

overcome the impacts of the risk

Page 17: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 17

Plan Responses (Opportunities)

Outputs

• Opportunity – a set of actions that maximise the impacts or increase

the probability of realising the opportunity

Type of realisations:

• Exploit – Increase the probability of the opportunity occurring

• Enhance – Increase the positive effects of the opportunity

• Share – Share the opportunity with another party better placed to

manage the threat

• Accept – Being willing to take advantage of it if it comes along, but not

actively pursuing it

Page 18: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 18

Plan Responses 1

Responses and Realisations should be:

• Specific

• Measureable

• Action orientated

• Realistic

• Time-bound

Responses should also contain how they are going to affect the risks probability or impacts and by how much.

Once Mitigations have been agreed, the Target risk score can be calculated.

Pitfalls

• Decision around treatment strategy

• Cost benefit of strategy

• Try to mitigate everything and not focussed on the priorities

• Inconsistent use of the words “by” and “to” in mitigation actions

Page 19: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 19

Plan Responses 2 Very

High 5 10 15 20 25

High 4 8 12 16 20

Mod

erate 3 6 9 12 15

Low 2 4 6 8 10

Very

Low 1 2 3 4 5

Very

Low

Low Moder

ate

High Very

High

Very

High 5 10 15 20 25

High 4 8 12 16 20

Mod

erate 3 6 9 12 15

Low 2 4 6 8 10

Very

Low 1 2 3 4 5

Very

Low

Low Moder

ate

High Very

High

At the initial risk assessment

(before and responses were

identified) the risk was

qualitatively scored at 20.

Once responses have been

agreed and opened, the target

score can be reduced to the

sum of the reductions in the

mitigations.

Page 20: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 20

Implement Responses and Manage

Process 1

Outputs

• A risk set that is relevant and up to date

• High quality of data within the risks

• Reductions in threat exposure

• Increase in opportunity realisation

Techniques

• Pro-active approach to risk

• Regular risk reviews with the risk owners

• Reviewing status of proposed, ongoing mitigation plans and responses

• Reviewing, developing and approving new risks

Page 21: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 21

Implement Responses & Manage

Process 2

When Reviewing Risks

• Has the mitigation had the desired effect?

• Is the “real” current threat/opportunity impact still valid?

• Are there new mitigations responses?

• What effect will the late delivery of the Response have on the

Risk / Opportunity?

Pitfalls

• Reviewing everything with everyone

Page 22: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 22

Risk & Project Processes

The risk process must have close ties to the other processes being

utilised in the project.

The risk register holds the data that the other processes will use.

Integrating mitigations into the project.

Opportunity realisation

Threat realisation

Risk Change

Process Responses

Other

Project

Processes

Page 23: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 23

Cause Based or Risk Based

Multiple causes for a single risk statement. (Bow Tie method)

Multiple risk events due to

a single cause.

Multiple causes against multiple risk events, this is no long a risk! It is

UNCERTAINTY.

To give these methods the best chance of succeeding, the risk manager must

code the causes, effects and responses so it is obvious which response is

affecting which cause, effect or risk event.

Page 24: Basic risk management presentation 17th june 2015

www.babcockinternational.com

Strictly Private and Confidential

Footer 24

Threat and Opportunity

Perceptions on Risk