Barranca Parkway Access Road IRVINE VALLEY COLLEGE South Orange County Community College District Bi-Weekly Progress Update Through November 15, 2016 PROJECT STATUS: • The irrigation controller was installed. • The mow curb along both sides of the access road was placed. • The asphalt patching was competed on Barranca. • Potholing was complete at the Shadow Oaks entry to locate the existing utilities. • Scheduled completion date: January 19, 2017. Project currently on schedule. • Project is 70% complete overall. Barranca Median Asphalt Patch Back