BANNING, CA Nexom Pilot Proposal BioPortz TM Water Resource Recovery Facility May 12, 2020
10

BANNING, CA

Apr 27, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: BANNING, CA

BANNING, CA

Nexom Pilot Proposal BioPortzTM Water Resource Recovery Facility May 12, 2020

Page 2: BANNING, CA

CD4307.02 BANNING CA 2 of 10

Executive Summary .......................................................................................................... 3

General ............................................................................................................................ 3

SECTION I: Proposed BioPortz Pilot System .................................................................. 4

1.0 / Process Description ............................................................................................... 5

BioPortz™ Moving Bed Biofilm Reactor ........................................................................... 5

2.0 / Pilot Description ..................................................................................................... 6

BioPortz™ Pilot System ................................................................................................... 6 Pilot Dimensions .............................................................................................................. 7 Pilot Requirements Provided by Site ................................................................................ 7 Project Schedule .............................................................................................................. 7

SECTION II: ........................................................................................................................ 8

Scope of Work ................................................................................................................... 8

Scope of Work ................................................................................................................. 9 Exclusions ........................................................................................................................ 9 Pricing ............................................................................................................................ 10

Questions or comments .............................................................................................. 10

Page 3: BANNING, CA

CD4307.02 BANNING CA 3 of 10

Executive Summary General Nexom is pleased to provide a BioPortz™ Pilot System to examine basis of design for

the proposed full-scale Moving Bed Biofilm Reactor (MBBR) process in Banning, CA.

The Pilot System has been designed to mirror the proposed full-scale MBBR

process. The Pilot System and the proposed full-scale system utilize reliable and robust

biological processes that requires minimal operator intervention to achieve high-quality

effluent. The BioPortz process will upgrade the existing infrastructure into a state-of-the-art

treatment facility capable of meeting discharge requirements in a small footprint.

We will use our extensive project experience from similar projects as the basis for a reliable

and sustainable system design that is cost effective, efficient, and simple to operate.

We look forward to working collaboratively with the Banning operational staff and

the project engineer to implement the BioPortz Pilot and Full-Scale Systems.

Page 4: BANNING, CA

CD4307.02 BANNING CA 4 of 10

SECTION I: Proposed BioPortz Pilot System

Page 5: BANNING, CA

CD4307.02 BANNING CA 5 of 10

1.0 / Process Description BioPortz™ Moving Bed Biofilm Reactor The BioPortzTM Moving Bed Biofilm Reactor (MBBR) is a simple

and efficient biofilm system for BOD, ammonia and nitrate removal.

Biofilms maintain a high quantity of active treatment biomass in a small

footprint. Biofilms are self-maintaining and continuously replace old

biomass with new biomass. Therefore, operator worries are eliminated

since sludge wasting is not required to maintain treatment performance.

BioPortz media are composed of HDPE with carbon black for UV

protection. The media have been designed to provide a high surface

area without compromising substrate mass transfer. Media retention

screens are constructed from stainless steel wedge wire. Media

retention screens are designed to retain media in the basins while

allowing effluent to flow through continuously without interruption.

The BioPortz MBBR reactor is constructed with the following features and benefits:

• Patented media optimized for treatment type – high-rate, low-footprint process

• Sludge recycle is not required – simplest biological process to operate

• Stainless steel wedgewire media screens

• Stainless steel aeration drop pipe

• HDPE coarse bubble diffusers – no fouling, no maintenance

• Aeration grid for optimal mixing / oxygen transfer – energy efficient

Page 6: BANNING, CA

CD4307.02 BANNING CA 6 of 10

2.0 / Pilot Description BioPortz™ Pilot System Nexom has multiple BioPortzTM Pilot Systems that can be mobilized for on-site

piloting. When the pilots are not being used for specific projects, Nexom utilizes them for

internal research and development. By continuously pushing the limit of technology, Nexom

can discern the potential successes and risks for clients and their unique systems.

Nexom’s pilot system can be easily modified for site specific requirements. For Banning,

CA a single train system will be utilized to demonstrate the performance of the

proposed full-scale Aerobic-Aerobic-Anoxic-Aerobic process, as well as to confirm

design loading rates on the actual wastewater. The pilot process will consist of four

tanks in series. The first aerobic tank will serve to oxidize BOD. The second aerobic tank

will oxidize ammonia. The following anoxic tank, the third in series, will remove total

nitrogen. The fourth and final tank will re-aerate the water and remove any residual external

carbon from the anoxic tank. Nexom will work with Banning staff to plan and execute

regular process sampling. The anticipated sampling parameters / points are listed below:

Sampling Points

Parameter Influent Aerobic Tank

1 Aerobic Tank

2 Anoxic Tank

3 Aerobic Tank

4

Testing Parameters (by Banning Operational Staff)

TN X X Soluble TN X Ammonia X X X X X Nitrite X X X X X Nitrate X X X X X Soluble COD X X X X X Soluble P X X X X X Alkalinity X X TSS X X VSS X X

SVI30 X

Page 7: BANNING, CA

CD4307.02 BANNING CA 7 of 10

Pilot Dimensions The pilot will require level laydown area that is, at

minimum, 50 ft by 14 ft, with access for the operators on

one side and one ends. The pilot will require a source of

primary clarifier effluent to feed the MBBR process. The

pilot will also require a location to discharge MBBR effluent.

The pilot is installed in a standard ISO 40 ft high cube

shipping container:

Parameter Unit Value

Length x Width x Height ft 40 x 8 x 9.5

Weight (Shipping / Operating) lb 11,000 / 18,000

Pilot Requirements Provided by Site The pilot will require a power supply and connection of electrical service: 208 V/3-

phase/100 amps. An internet connection will be required for remote monitoring by camera

and online dissolved oxygen and temperature sensors. Remote monitoring will serve for

data logging, as well as to indicate pilot conditions. A potable / cleaning water supply, of

8 gpm minimum, will be required for cleanup. A garden hose connection is suitable for the

required water source.

Project Schedule The project schedule is based on the following major milestones and activities:

Description Anticipated Duration

Site Preparation (by others)

Pilot Mobilization and Delivery* 4-5 week

Equipment Set-Up 1 week (onsite)

Pilot Start-Up: Acclimation of Biomass 2-4 weeks (onsite)

Operation and Data Collection 8-10 weeks (onsite)

Pilot Demobilization and Removal 1 week (onsite)

Data Analysis 1 week

Report / Recommendations 2 weeks

*From date of PO.

NOTE: Some tasks in the schedule may be performed concurrently. For example, Site

Preparation may be performed during Pilot Mobilization and Delivery. Operation and Data

Collection would also be performed concurrently with Data Analysis.

Page 8: BANNING, CA

CD4307.02 BANNING CA 8 of 10

SECTION II: Scope of Work

Page 9: BANNING, CA

CD4307.02 BANNING CA 9 of 10

Scope of Work Included in the cost of the piloting study are:

• Nexom BioPortz Pilot Wastewater Treatment System

o Mobilization, delivery, and process set-up (allowance included for unloading on

site)

o External carbon source

o Start-up and training

▪ Two (2) trips for up to three (3) days on site for initial set-up / training

▪ Follow-up webinars as required

o Operational support

▪ Daily conference calls / webinars between Nexom Research and

Development Staff and Banning Operational Staff

▪ Continuous data analysis by Nexom Applications Engineering and

Research and Development Staff

o Project wrap-up, demobilization, and removal

▪ One (1) wrap-up trip, including dissemination of results to Banning

Operational Staff, for up to three (3) days on site

▪ Allowance for container loading and return shipping

• Final Report

o Summary of performance

o Updated capital and operational cost for full-scale facility

Exclusions • Offloading and secure onsite storage

• Site preparation and utility hookups for equipment, including influent, effluent, potable

water, and electrical service.

• Potable / cleaning water supply of 8 gpm minimum for cleanup: garden hose connection

• Process water within 50 ft of container (Nexom to provide pilot influent pump)

• Power supply and connection of electrical service: 208 V/3-phase/100 amps

• Operating power costs

• Analytical costs for influent, reactor, and effluent monitoring

• Manned operation of BioPortz pilot process

Page 10: BANNING, CA

CD4307.02 BANNING CA 10 of 10

Pricing

Three-Month Rental: $55,000 USD before applicable taxes

Each Additional Month: $10,000 USD before applicable taxes

Prices are valid for 30 days

Nexom Inc.

Tanner Devlin, PhD

Ph: (204) 560-0521

Email: [email protected]

Isaiah LaRue

Regional Sales Manager

Ph: (913) 444-2262

Email: [email protected]

QUESTIONS OR COMMENTS

Any questions or comments can be directed to:

Nexom

323 N. Spokane St. Suite 200 Post Falls, Idaho 83854 888-710-2583

www.nexom.com

Represented by:

Saddle Back Enviro

Steven Seymour

Mobile: (949) 291-0555

www.saddlebackenviro.com

490 Latigo Row, Encinitas, CA 92024