Top Banner

of 40

BanksOKI24FEB12

Apr 06, 2018

Download

Documents

OKIRPF
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/3/2019 BanksOKI24FEB12

    1/40

    The Banks Public Partnership

  • 8/3/2019 BanksOKI24FEB12

    2/40

    FORT WASHINGTON WAY 2000The first step

    A project managed by the City of Cincinnati with thecooperation of thousands

    OKI had major role and brought regionalism to project

    1998 2000

  • 8/3/2019 BanksOKI24FEB12

    3/40

    3

    From the South

    From the West

    From the North

    From the East

    Flooding: The developments designchallenge1997 Flood: The Crisis that defined that design

    http://www.cincinnati-transit.net/zsuspension-hist10.jpghttp://www.cincinnati-transit.net/zsuspension-hist10.jpg
  • 8/3/2019 BanksOKI24FEB12

    4/40

    Cross-Section Of The Design ConceptA floodable Intermodal Transit Facility with a flood-proofdevelopment podium and excellent transportation connections.

  • 8/3/2019 BanksOKI24FEB12

    5/40

    Master Development Plan

  • 8/3/2019 BanksOKI24FEB12

    6/40

    Phase 1 June 2008

  • 8/3/2019 BanksOKI24FEB12

    7/40

    Phase 1 October 2011

  • 8/3/2019 BanksOKI24FEB12

    8/40

    Phase 2a

    Block 2 Site Work/ Parking Facility Construction June2010 to November 2011. Any remaining work forPublic Parties will be done along with the Developerswork.

  • 8/3/2019 BanksOKI24FEB12

    9/40

    So where are we now?

    A d f P j t R t

  • 8/3/2019 BanksOKI24FEB12

    10/40

    Agenda of Project ReportFebruary 13, 2012 Staff Meeting for the Boardof County Commission

    1. Project update2. Local Public Agency (LPA) Agreement for

    balance of federal monies awarded the

    project3. Trade Contract -28, Public SafetyTechnology recommendation for award

    4. Recommendation for award of the design

    contract for replacement of the temporarypedestrian bridge over Pete Rose Way

    5. Working with the Developer to supportcontinued build-out of the Master Plan.

  • 8/3/2019 BanksOKI24FEB12

    11/40

    Summary

    1. The block 2 addition to the Central RiverfrontIntermodal Garage and the Riverfront Street Grid withits underlying utility network are all complete and inservice. A minor punch list remains. The electronic

    system to support both the event management andvalet parking is in operation.

  • 8/3/2019 BanksOKI24FEB12

    12/40

    Phase 2aParking 1/31/12

    New Second St Entrance

  • 8/3/2019 BanksOKI24FEB12

    13/40

    19 17

    Lot20

    Lot22

    Lot21

    LOT

    27

    LOT

    28

    LOT

    25

    1

    2

    3

    4

    VALET PARKINGLOCATIONS

    Approved Valet Parking Locations

  • 8/3/2019 BanksOKI24FEB12

    14/40

    Summary

    2. All Public Parties work envisioned by the Public

    Parties as Phase 1 and the additional Phase 2aconstruction made possible by the ARRA program iscomplete. Work underway with the Developer for

    next phases.

  • 8/3/2019 BanksOKI24FEB12

    15/40

    Summary

    3. Both construction phases of the PublicParties work continue to be within approvedbudgets and on target to meet SBE, DBE andsafety goals and should remain so through all

    contract closeouts in March. The projectcontinues to have no lost time accidents.

  • 8/3/2019 BanksOKI24FEB12

    16/40

    Summary4. Through cooperation with OKI and ODOT, all grant monies,

    primarily OKI STP money, not projected to be spent in currentwork have been re-programmed into the two parts of BidPackage 12.

  • 8/3/2019 BanksOKI24FEB12

    17/40

    Summary5. Carter-Dawson reports that Phase 1a residential

    is 99% leased and that the retail is 80% leased.

  • 8/3/2019 BanksOKI24FEB12

    18/40

    ECONOMIC INCLUSION

    18

  • 8/3/2019 BanksOKI24FEB12

    19/40

    The Banks Project Economic Inclusion

    As of December 25, 2011:

    I. ConstructionSBE 36%

    MBE 15.9%WBE 2.9%

    II. Professional ServicesSBE 8.0%MBE 6.8%WBE 2.1%

  • 8/3/2019 BanksOKI24FEB12

    20/40

    The Banks Project Economic InclusionFederal/ODOT Funding Disadvantaged Business Enterprise Program

    Bid Package No. ODOT DBEGoal

    ContractorCommitment

    Actual DBEParticipation

    5 8.0% 10.8% 12.0%

    7 8.0% 10.7% 11.7%

    6 5.0% 5.0% 5.4%

    Bid Package No. ODOT DBE

    Goal

    Contractor

    Commitment

    Actual DBE

    Participation

    9 4% 4.9% 2.8%

    11 8% 8.4% 7.4%

    Bid Packages 5, 6, and 7 are closed out. Substantial work isbeing completed this month by the DBE contractors on BidPackages 9 & 11, and the final billings are projected to meetODOT goals.

  • 8/3/2019 BanksOKI24FEB12

    21/40

    Combined Minority/Female Workforce participation as ofDecember 25, 2011 is 17.42%; Minority Workforce(female and male) is 16.12%

    For the one-month period ending December 25, 2011,

    nearly 89.7% of workers lived within the 15-CountyCincinnati-Middletown MSA

    Local residency analysis as of October 25, 2011 (1,397workers)

    Tri-State 97.6%Cincinnati-Middletown MSA 76.9%Hamilton County 25.6%City of Cincinnati 9.2%

    The Banks Project Economic Inclusion

  • 8/3/2019 BanksOKI24FEB12

    22/40

    Safety

    22

    Over 416,000 hours worked without a lost-timeaccident through both Public Parties construction

    phases, to date.

  • 8/3/2019 BanksOKI24FEB12

    23/40

    SCHEDULE: CONSTRUCTION

    23

    Bid Package #9 complete; closeout underwayMehring Way and Elm Street guardrails the only work remaining

    Bid Package #11 complete; closeout underwayCertificate of occupancy expected in February

    Bid Package #12 Riverfront Public Safety technology contract out to bid Part 1 to be bid Spring 2013Widening Second St. sidewalk, removal of Race St. Bridge,reconstruction of portion of Freedom Way, completion of Public Safetytechnology

    Part 2 to be bid Fall 2012Sidewalk upstream side of Roebling Bridge, steps and pedestrian bridgeover Pete Rose Way near Broadway; construction of Ohio River Trailfrom Steamboat Monument to Joe Nuxhall Way

  • 8/3/2019 BanksOKI24FEB12

    24/40

    ScheduleDevelopers Leasing

    24

    Toby Keiths prepared for opening The Tin Roof awaiting construction permit;

    opening projected for Spring 2012

    Orange Leaf beginning construction Mahoganys designing their build-out The Wine Guy executed their lease Ruths Chris signed lease; construction set to

    begin second quarter 2012

  • 8/3/2019 BanksOKI24FEB12

    25/40

    Cincinnati Park Board Progress

    25

  • 8/3/2019 BanksOKI24FEB12

    26/40

    Cincinnati Park Board ProgressPhyllis W. Smale Riverfront Park, Phases 1, 2

    substantially complete. Walnut Street Fountain & Grand Stair open to public

    in early Spring Bike Center interior design underway; expected

    opening in SpringPhase 3 work on grounds, underground utilitiescontinues.Moerlein Lager House geothermal installation, brewingtanks installation and interior finishing continues; LagerHouse will open February 27.

    Coordination with Cincinnati Parks

  • 8/3/2019 BanksOKI24FEB12

    27/40

    Coordination with Cincinnati ParksMoerlein Lager HouseOpening February 27, 2012

  • 8/3/2019 BanksOKI24FEB12

    28/40

    Coordination with Cincinnati ParksWalnut Street Fountain, Grand Stairs & Bike Center

  • 8/3/2019 BanksOKI24FEB12

    29/40

    Coordination with Cincinnati ParksWalnut Street Fountain, Grand Stairs & Bike Center

  • 8/3/2019 BanksOKI24FEB12

    30/40

    COMMUNICATIONS

    The Banks Project in the news

    30

  • 8/3/2019 BanksOKI24FEB12

    31/40

    COMMUNICATIONS

    The Banks Project in the newshttp://www.thebankspublicpartnership.com/m

    edia

    31

    http://www.thebankspublicpartnership.com/mediahttp://www.thebankspublicpartnership.com/mediahttp://www.thebankspublicpartnership.com/mediahttp://www.thebankspublicpartnership.com/media
  • 8/3/2019 BanksOKI24FEB12

    32/40

    Budget

    According to budgetprojections, local fundsremaining from theFebruary 2009 budget are

    sufficient to covernecessary match and softcosts not eligible for federalfunds. Phase 1 has just over$1m contingency remainingwhich can be moved to

    Phase 2.

  • 8/3/2019 BanksOKI24FEB12

    33/40

    Phase 2a Budget Reallocation(Rollover of Phase 1 contingency would add $1 million)

    Phase I IA S ources May 2010 Approval S ource BP9 Projected Use

    BP11 Projected

    Use BP12 Projected Use Total Projected Use

    Existing Phase I Public Parties Source $5,692,945

    TIF Bond Proceeds $10,197,496Stimulus - State of Ohio $13,000,000 $5,000,000 $8,000,000 $13,000,000

    CMAQ Federal Grant (Stimulus) $10,200,000 $10,200,000 $10,200,000

    STP Federal Grant $7,521,071 $230,358 $1,032,592 $6,258,121 $7,521,071

    Developer Contribution** $2,000,000

    Stimulus - OKI $1,500,000 $1,500,000 $1,500,000

    Existing Federal Earmarks $1,125,116 $491,964 $625,116 $1,117,080

    OKI Enhancement Grant $1,000,000 $750,000 $750,000

    Budget Total $52,236,628

    Total Federal Use $7,222,322 $19,232,592 $7,633,237 $34,088,151

    Projected Local Use $1,492,000 $10,397,120 $5,414,540 $17,303,660

    Total Use $8,714,322 $29,629,712 $13,047,777 $51,391,811

    Phase IIA Sources December 8, 2011 Source BP9 Projected Use

    BP11 Projected

    Use BP12 Projected Use Total Projected Use

    Unallocated Funds

    Contingency Contingency

    Existing Phase I Public Parties Source $5,692,945

    TIF Bond Proceeds $10,197,496

    Stimulus - State of Ohio $13,000,000 $5,000,000 $8,000,000 $13,000,000

    CMAQ Federal Grant (Stimulus) $10,200,000 $10,200,000 $10,200,000

    STP Federal Grant* $9,261,022 $215,520 $1,702,880 $7,342,622 $9,261,022

    Developer Contribution** $2,000,000

    Stimulus - OKI $1,500,000 $1,500,000 $1,500,000

    Existing Federal Earmarks *** $1,037,062 $592,480 $444,600 $1,037,080

    OKI Enhancement Grant**** $750,000 $750,000 $750,000

    Budget Total Available $53,638,525

    Total Federal $35,748,084 $7,308,000 $19,902,880 $8,537,222 $35,748,102 -$18 $1,036,800

    Projected Local $17,890,441 $1,492,000 $10,397,120 $5,414,540 $17,303,660 $586,780 $259,200

    Total Use $8,800,000 $30,300,000 $13,951,762 $53,051,762

    *More STP available than considered in estimate of May 2010

    *** Federal budget rescission reduced the dollars available in the earmarks/grants

    ** The Developer contribution is contingent upon exercise of a Future Phase Trigger Notice as specified in the MDA and will not be available

    during construction. The Public Partie s will need to advance these funds.

    Bid P k 12

  • 8/3/2019 BanksOKI24FEB12

    34/40

    Bid Package 12Street Grid Pedestrian Improvements

    Part one: ODOT Local Public Agency Agreement

    (LPA) in place1. Traffic and Public Safety Technology2. Second Street/Transit Center Pedestrian Upgrade3. Freedom Way, Rosa Parks Street to Walnut Street4. Removal of Temporary Race Street, South of

    Freedom Way

    Part two:LPA ready for approval1. Suspension Bridge Approach Pedestrian Connection2. Riverwalk Trail3. Broadway/Pete Rose Way Pedestrian Connection

  • 8/3/2019 BanksOKI24FEB12

    35/40

    Bid Package 12, Part 2Suspension Bridge Pedestrian Connection

  • 8/3/2019 BanksOKI24FEB12

    36/40

    Before

  • 8/3/2019 BanksOKI24FEB12

    37/40

    After

    Bid P k 2 P 2

  • 8/3/2019 BanksOKI24FEB12

    38/40

    Bid Package 12, Part 2Riverwalk Joint Project with Cincinnati Parks

    Bid P k 12 P 2

  • 8/3/2019 BanksOKI24FEB12

    39/40

    Bid Package 12, Part 2Pedestrian Bridge, Stair and Staging Replacement

  • 8/3/2019 BanksOKI24FEB12

    40/40

    QUESTIONS?

    John F. Deatrick(513) [email protected]

    http://www.thebankspublicpartnership.com