Place title here Metro North Ballymun4Business 18 th February 2011
Place title here
Metro NorthBallymun4Business18th February 2011
Metro North - Ready to Go
Metro North
St Stephen’s Green to Estuary
16.5km total length – 11 km in tunnel (City centre to Ballymun
and Airport)– 5.5 km in retained cut, at-grade or
elevated
14 stops – 9 underground stops from St. Stephen’s
Green to Ballymun and at Airport– 5 surface stops
Planning Permission Granted – 20 Conditions– Depot relocation application early 2011– Enabling Works can commence
● Estuary
● Swords
● Fosterstown
● Airport
● Dardistown
● Northwood
● Ballymun
● DCU
● Griffith Avenue
● Drumcondra
● Mater
● Parnell Square
● O’Connell Bridge
● St Stephen’s Green
Metro North - Ready to Go
Is now the time for Metro North?
Tackling traffic congestion
Tackling urban sprawl
Economic & social costs high if we do not proceed
Environmental costs high if we do not proceed
Metro North - Ready to Go
Is now the time for Metro North?
Metro serves key destinations
Metro provides world class
service
PPP is the appropriate
funding model
Capital costs are at the
bottom of the curve
Metro North - Ready to Go
Is now the time for Metro North?
Strong economic case
even with modest growth
Ireland must remain
competitive
600 jobs for enabling works Over 6,000 jobs
Metro North - Ready to Go
In Summary
Now is the time to build Metro North
• Infrastructure deficit remains
• Economics stack up
• Value in the market
• PPP model suits current conditions
• Immediate positive impact on jobs in
the sector
• Ready to go NOW!
Image of Ballymun Stop
The Works
The works are split into 2 distinct phases
1. Enabling works
2. Main Works
Metro North - Ready to Go
Enabling Works
• Work to commence in January 2012 and take 24 months to complete
• Diversion /relocation of services along Ballymun Road and at the footprint of DCU and Ballymun Stops including:
8km drainage 150 deep drainage manholes 4.5km water main 2.5km gas main 3.5km eircom
Metro North - Ready to Go
Enabling Works
• Majority of diversions within Ballymun Road & Balcurris Road
• Lighter diversions in footpaths
• Over 200 separate traffic management phases to keep disruption to a minimum
• 2 lanes traffic maintained along Ballymun Road in each direction
• Bus lanes to operate over a 24 hour day along Ballymun Road
• Pedestrian and vehicle access to businesses will be retained
Metro North - Ready to Go
Main Works Construction
• Cut & Cover tunnel through Ballymun• Stop Box
Main works 24 months (excavation and concrete works) 2013 to 2016
Equipping the Station 8 months
Testing and commissioning the system 6 months
Main works is carried out in 2 distinct phases to ensure pedestrian access maintained and two lanes open along Ballymun Main Street
Metro North - Ready to Go
stmoreland Street
The Aim
The aim for RPA is to design and construct the works without materially impacting on the existing businesses
• Keeping Ballymun open for Business
• Ensuring people in Ballymun can continue to go about their daily business safely and with as little
disruption as possible
Metro North - Ready to Go
Keeping Ballymun Open for Business
• By maintaining: Pedestrian access to all premises Access for servicing and deliveries Access to all existing car parks
• Active communication and liaison with business community and the public
All of this is achieved through • Careful planning and execution of the works
Metro North - Ready to Go
Managing our Environment
• Noise and dust limits strictly controlled and monitored
• High quality, well maintained attractive hoarding for the Main Works
• Good lighting and signage will be provided between the worksites and the shops/business premises
• Good housekeeping, plant and equipment cleaned and fully serviced, worksites kept tidy and dust free
• RPA and its contractor will work closely with you the business community throughout the construction period
Metro North - Ready to Go
RPA Commitments
RPA will:
•Have an ongoing role throughout the works•Ensure you are consulted and kept informed about the works•Arrange open forums with local businesses & residents•Run a 24/7 hotline for queries and complaints•Appoint Community Liaison Officers dedicated to Ballymun
area•Provide up to date information through meetings and other
communications channels
Metro North - Ready to Go
Contractor’s Commitments
The Contractor(s) will:• Comply with the Railway Order and all environmental
constraints set out in the EIS• Comply with the Conditions of Contract• Comply with all statutory requirements and controls imposed
by the Local Authority• Plan the works in line with best practice• Educate and brief his workforce on a regular basis• Engage with you
Metro North - Ready to Go
Summary
• The case for Metro North remains strong• Funding approval• Award Enabling Works contracts• Engage with business in planning the works• Programme of information meetings closer to the works
commencing
Ready to go
Metro North - Ready to Go
Thank You
Any Questions?
Metro North - Ready to Go