Top Banner
Balancing Procedure CBAV 1. Waterside Commissioning 1) Fully purge the complete hydronic system of air prior to commissioning. 2) Carefully inspect the system for leaks, paying particular attention to the connections. 3) Carefully inspect flexible hose, if applicable, for leaks. 4) Use system balancing valves to adjust water flow rate to specified values. Note. The chilled beam is not provided with any water flow control or measuring devices, therefore the pipe work system should be fitted with sufficient balancing aids to enable adjustment of the flow rate. 2a. Airside Commissioning — Preparation Check that the ductwork between main supply air ducts and chilled beams is airtight. Connections and fittings should be sealed to SMACNA class B standard up to 2 in. w.g. Ductwork pressure testing is recommended to identify leaks before the chilled beams are balanced. Final duct connections should be straight immediately upstream of the chilled beam units. Ductwork should have at least THREE duct diameters length of straight duct before the first system bends. Twisted or kinked flexible duct final connections or bends immediately upstream of the beam will result in incorrect pressure port readings on the beam. 2b. Airside Commissioning — Airflow Measuring & Balancing Procedure Note. Do not attempt to read the total discharge airflow rate using a hood or any other device that adds downstream pressure to the beam as it will reduce the amount of induction and give false readings. The total air flow (primary + induced) cannot be measured! The pitot-traverse method must not be used to measure the airflow in the small primary air ducts serving the chilled beam, this will result in inaccurate readings, the only accurate method is to measure the static pressure in the primary air plenum as described in the next section. The primary air flow rate is determined by measuring the static pressure in the primary air chamber and referring to the calibration chart label provided on each beam or the charts shown at the end of this document. Alternatively use the static pressures listed on the Titus chilled beam schedule provided in the submittal drawing set.
8

Balancing Procedure CBAV - Titus HVAC

Apr 01, 2023

Download

Documents

Khang Minh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Balancing Procedure CBAV - Titus HVAC

Balancing Procedure

CBAV

1. Waterside Commissioning

1) Fully purge the complete hydronic system of air prior to commissioning.

2) Carefully inspect the system for leaks, paying particular attention to the connections.

3) Carefully inspect flexible hose, if applicable, for leaks.

4) Use system balancing valves to adjust water flow rate to specified values.

Note.

The chilled beam is not provided with any water flow control or measuring devices, therefore the pipe work

system should be fitted with sufficient balancing aids to enable adjustment of the flow rate.

2a. Airside Commissioning — Preparation

Check that the ductwork between main supply air ducts and chilled beams is airtight. Connections and

fittings should be sealed to SMACNA class B standard up to 2 in. w.g. Ductwork pressure testing is

recommended to identify leaks before the chilled beams are balanced.

Final duct connections should be straight immediately upstream of the chilled beam units. Ductwork should

have at least THREE duct diameters length of straight duct before the first system bends. Twisted or kinked

flexible duct final connections or bends immediately upstream of the beam will result in incorrect pressure

port readings on the beam.

2b. Airside Commissioning — Airflow Measuring & Balancing Procedure

Note.

Do not attempt to read the total discharge airflow rate using a hood or any other device that adds downstream

pressure to the beam as it will reduce the amount of induction and give false readings. The total air flow

(primary + induced) cannot be measured!

The pitot-traverse method must not be used to measure the airflow in the small primary air ducts serving the

chilled beam, this will result in inaccurate readings, the only accurate method is to measure the static pressure in

the primary air plenum as described in the next section.

The primary air flow rate is determined by measuring the static pressure in the primary air chamber and

referring to the calibration chart label provided on each beam or the charts shown at the end of this

document. Alternatively use the static pressures listed on the Titus chilled beam schedule provided in the

submittal drawing set.

Page 2: Balancing Procedure CBAV - Titus HVAC

To measure static pressure:

Locate the pressure port located in the supply air slot near the end of the beam (see image). Access above or through field installed supply grille will be required. Remove cap and attach a static pressure measuring

gauge.

Pressure Port

Balancing Procedure

CBAV

2b. Airside Commissioning — Airflow Measuring & Balancing Procedure

Air Balancing

Adjust the branch balancing dampers to change the pressure in the chilled beam primary air plenum so the

pressure measured matches the pressure shown on the Titus chilled beam submittal schedule or the airflow

read from the commissioning charts shown on the next section. Branch balancing dampers should be used

for trimming only, excessive throttling of pressure may result in excessive noise.

Page 3: Balancing Procedure CBAV - Titus HVAC

3. Airside Commissioning Charts

Balancing Procedure

CBAV

Page 4: Balancing Procedure CBAV - Titus HVAC

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

0 5 10 15 20 25 30 35

Plen

um Pressure (in

. H²O)

Airflow (CFM)

CBAV Commissioning Chart2' Long

B3

B4

B2B1

Page 5: Balancing Procedure CBAV - Titus HVAC

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

0 5 10 15 20 25 30 35 40 45 50 55 60 65

Plen

um Pressure (in

. H²O)

Airflow (CFM)

CBAV Commissioning Chart3' Long

B3 B4B2B1

Page 6: Balancing Procedure CBAV - Titus HVAC

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80

Plen

um Pressure (in

. H²O)

Airflow (CFM)

CBAV Commissioning Chart4' Long

B2 B3 B4B1

Page 7: Balancing Procedure CBAV - Titus HVAC

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120

Plen

um Pressure (in

. H²O)

Airflow (CFM)

CBAV Commissioning Chart6' Long

B1 B2 B3 B4

Page 8: Balancing Procedure CBAV - Titus HVAC

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0.70

0.80

0.90

1.00

10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 165

Plen

um Pressure (in

. H²O)

Airflow (CFM)

CBAV Commissioning Chart8' Long

B1 B2 B3 B4