What is the project success?
• scope• time• cost• quality• resources• risk
[email protected]
Page 3
DTI / Managerial Skills
[email protected]
3
Is it possible to forecast the success of a project from the
first phases ?
[email protected]
Page 4
DTI / Managerial Skills
Project’s success is decided in the first phases
[email protected]
4
© SUPSI – DTI – AS – 2015 – Advanced Project Management
[email protected]
Page 5
DTI / Managerial Skills
[email protected]
5
What are the key factors for the project’s success?
[email protected]
Page 6
DTI / Managerial Skills
Key factors for project’s success
[email protected]
6
Documentationand tracking
Experience of the Project Manager
Work Breakdown Structure
Resource estimates
Tasks assignment to professionals
Cost Estimates Time EstimatesScope
Estimates
Communication ”Culture” CommitmentCompeting Priorities
[email protected]
Rosanne Lim. “Top 10 main causes of project failure” (2016)
Page 7
DTI / Managerial Skills
[email protected]
7
What kind of tools can studythe success of a project?
[email protected]
Page 8
DTI / Managerial Skills
Design of Experiment is the tool
[email protected]
8
PROCESS
FACTORS RESPONSES
[email protected]
Page 9
DTI / Managerial Skills
Design of Experiment is the tool
[email protected]
9
PROCESS
FACTORS RESPONSES
=
=
=
+ +
k1
k2 k3 k4
k5 k6+
PROJECT
DATAWBS
COST ESTIMATE
”CULTURE”…
TIME
COSTS
QUALITY ...
X
[email protected]
Page 10
DTI / Managerial Skills
Data are collected through a survey
The survey is addressed to all PMs
PMs are invited to evaluate their projects under the identified factors
A given evaluation scale is provided to ensure consistency of data
The responses considered are: scope , time , cost , quality , resources , and risk .
[email protected]
10
[email protected]
Page 11
DTI / Managerial Skills
Survey Status
Currently data are being collected
All PMs are invited to complete the survey at this address:
[IT] http://sondaggi2.ti-edu.ch/index.php/survey/index/sid/886765/newtest/Y/lang/it
[EN] http://sondaggi2.ti-edu.ch/index.php/survey/index/sid/886765/newtest/Y/lang/en
[email protected]
11
[email protected]
Page 12
DTI / Managerial Skills
Expected Results
• A quantitative and more objective definition of what are the main success factors in a project
• a stable model for project success forecasting
• an instrument to increase awareness about project success
• an instrument to foster creativity
[email protected]