EUGAL IN FIGURES 18 m 15 t and at At a length of a pipe is as long as an articulated bus as heavy as 3 elephants 47,000 pipes are needed for the construction Around Up to 55 Bln m 3 of natural gas can be transported annually by EUGAL. By comparison: Germany consumes around 85 billion m³ of natural gas in one year 2037 Transport through EUGAL has already been booked until this year. 140 cm EUGAL has a diameter of First String Second String Completion: end of 2019 Completion: end of 2020 The EUGAL Pipeline was approved in all three German states 2018 A market survey on gas transport needs was conducted prior to construction of EUGAL. EUGAL capacities were sold on the European capacity platform PRISMA. 2015 2017 JAGAL NET4GAS NET4GAS NEL NORD STREAM 2 EUGAL 4 is the number of network links that EUGAL has. They allow gas to be transported flexibly within Germany and to Western and Eastern Europe. long EUGAL is around 480 km FGL306 2020 2021 First gas Full capacity
2
Embed
At a length of 18 m 15 t - EUGAL · PRISMA. 2015 2017 L AS AS NEL NORD STREAM 2 EUGAL 4 is the number of network links that EUGAL has. They allow gas to be transported flexibly within
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
EUGAL IN FIGURES
18 m 15 tand atAt a length of
a pipe is as long as an articulated bus
as heavy as 3 elephants 47,000
pipesare needed for
the construction
Around
Up to
55 Bln m3
of natural gas can betransported annually byEUGAL. By comparison:
Germany consumes around 85 billion m³ of natural gas in
one year
2037Transport
through EUGAL has already been booked
until this year.
140 cm
EUGALhas a diameter of
First String Second String
Completion:end of 2019
Completion:end of 2020
The EUGAL Pipeline
was approved in all
three German
states
2018
A market survey on gas transport needs
was conducted prior to construction of EUGAL.
EUGAL capacities were sold on the European
capacity platform PRISMA.
2015
2017
JAGAL
NET4GAS
NET
4GA
S
NEL
NORD STREAM 2
EUG
AL
4is the number of network
links that EUGAL has. Theyallow gas to be transportedflexibly within Germany and
to Western and Eastern Europe.
long
EUGAL is around
480 km
FGL306
2020
2021
First gas
Full capacity
KEY
Lubmin 2 natural gas receiving station completion at the end of 2019
Compressor station Radeland 2 completion at the end of 2020
Export station Deutschneudorf completion at the end of 2019
1
2
3
Saxony
Czech Republic
Brandenburg
Mecklenburg-Western Pomerania
Berlin
Poland
Baltic Sea
JAMAL
FGL 306NETRA
JAGAL
STEGAL NET4GAS
NET
4GAS
NEL
NORD STREAM 2
1
2
3
Oder–Spreedistrict
Märkisch-Oderland district
Uckermarkdistrict
Barnimdistrict
Western PomeraniaGreifswald district
Dahme-Spreewalddistrict
Meißendistrict
Mittel-Sachsen district Sächsische
Schweiz-Osterzgebirgedistrict
Erzgebirgs- kreis district
Teltow-Flämingdistrict
Elbe-Elsterdistrict
Ober- spreewald-
Lausitz district
ABOUT GASCADE
GASCADE, formerly WINGAS TRANSPORT GmbH, has been planning, building and operating one of Germany’s largest gas networks for two decades. GASCADE thus directly connects five European countries with each other and guarantees secure energy supplies in Germany and Europe.
ABOUT THE PROJECT SHAREHOLDERS
The European gas pipeline link is a joint project between the German transmission system operators GASCADE Gastransport GmbH, Fluxys Deutschland GmbH, Gasunie Deutschland Transport Services GmbH and ONTRAS Gastransport GmbH. GASCADE, as the company in charge of the project, holds 50.5 percent of the shares. The three other shareholders each own 16.5 percent of EUGAL. GASCADE is building EUGAL and will operate in the future.
CONTACT
Would you like more Information or to learn about the current planning status for EUGAL? Then visit our website: www.eugal.de