AstroGrid presentation to GSC 12 th Feb, 2003 London
Jan 03, 2016
AstroGrid presentation to GSC
12th Feb, 2003London
12.02.2003 AstroGrid/GSC Presentation
Introduction
Project statusGSC Issues & ResolutionIteration 01 summaryUpdated project plan
12.02.2003 AstroGrid/GSC Presentation
Project Status
Addressed GSC concernsStarted Iteration 01Developed descoped plan
First public demo software International liaisonRecruitmentTraining
12.02.2003 AstroGrid/GSC Presentation
Demo software
Joint work with AVO AstroGrid contribution : ACE
remote on-the-fly source extraction
Press demo JBO Jan 20 several other demos since small pool of beta-testers
Several other internal tech demos web service and grid service try-outs
12.02.2003 AstroGrid/GSC Presentation
Recruitment and Training
Five recruitments TechLead + 1 in place +3 interviewing this week
Substantial training programme
advanced Java courses OGSA-DAI adopters course
12.02.2003 AstroGrid/GSC Presentation
International Liaison
IVOA meeting Seattle Jan 9-10AstroGrid leading Registry/IAU demosFP6 planning Exchange visits with Aus-VO aim at niches within AstroGrid
architecture
12.02.2003 AstroGrid/GSC Presentation
12.02.2003 AstroGrid/GSC Presentation
GSC/AGOC concerns
Risk assessmentDeliverables and MilestonesTechnology choicesArchitectureUser engagement
New Oversight page for AGOC & GSC:http://oversight.astrogrid.org/
12.02.2003 AstroGrid/GSC Presentation
Risk assessment
Action has been taken to mitigate risk as indicated in Comment
12.02.2003 AstroGrid/GSC Presentation
Milestones: System Functionality
each qtr is milestone deliverables each qtrfresh WPs each qtr Document AGOCRequested similar for scientific milestonesPosted on web site
12.02.2003 AstroGrid/GSC Presentation
Milestones: Scientific
12.02.2003 AstroGrid/GSC Presentation
Project Monitoring
Milestone Plan and Risk Plan in placeReport against both each AGOCPlan allowed to evolve but only under control
12.02.2003 AstroGrid/GSC Presentation
Technology choicesmade before October
design : UML using TogetherSoft ControlCenter development language : Java SOAP web services, then OGSA IAA modelled on Globus CAS own (to standards) Registry
made since October DBMS : DB2 source control : CVS IDE/build : Eclipse/Ant Java libraries: Apache Portal : Apache Cocoon
all crucial choices made
12.02.2003 AstroGrid/GSC Presentation
ArchitectureDevelopment Process: Science problems Science use cases, sequence diagrams Component model (revised after last GSC) Component design features
see focus meeting, 22-Nov-2002 System use cases (& seq diags)
by end of Iteration-01 per-Iteration:
Detailed system design
We are here
12.02.2003 AstroGrid/GSC Presentation
Components
12.02.2003 AstroGrid/GSC Presentation
AGOC concerns
early user engagement first new sw in use already Sci.Advisory.Comm being formed beta-pool for June releases
science milestones under development
12.02.2003 AstroGrid/GSC Presentation
12.02.2003 AstroGrid/GSC Presentation
Work Plan ProcessTSP meets before each quarter first meeting Jan 6th
Agrees Work Packages for that quarter
targets, timescales, methods work group leader and team
Plan delivered before quarter start
12.02.2003 AstroGrid/GSC Presentation
Iteration 01: Jan-Mar 2003Portal Initial front end Portlet: structure Registry query portlet
Registry Schema & storage (xml, db?) WS: satisfy simple query for datasets
Grid Implement and test OGSA and OGSA-DAI Grid-based demo with Aus-VO
Cube cutout and interactive visualisation
Architecture refinement
12.02.2003 AstroGrid/GSC Presentation
12.02.2003 AstroGrid/GSC Presentation
Updated planFunctionality descopedRevised effort estimatesRevised budgetDeployment planRevised Milestone Plan
12.02.2003 AstroGrid/GSC Presentation
Component DescopeIn:
Portal Registry (simple) Community server AstroPass Workflow Process control MySpace Data centre Dataset access Tools (wrap existing)
Sextractor, IRAF, AIPS, Solarsoft, …
Out: Ontology-based
Registry Custom tools Server-based
visualisation Parsed AQL
12.02.2003 AstroGrid/GSC Presentation
Revised Estimates
12.02.2003 AstroGrid/GSC Presentation
Budget summary
12.02.2003 AstroGrid/GSC Presentation
Budget LinesTravel Calc: (10*£6K + 13*£2.5K) * 2 years Less per person than Phase A Based on actual expenditure in 2002
Outsourcing Consultancy (eg database tuning) Customisation
Existing tools web/grid services Adapt utilities for portlet use (workflow?) Adapt client tools for server-side (viz?)
12.02.2003 AstroGrid/GSC Presentation
Staff Deploymentend-2002FTEs
2003 hires2
TotalFTEs
Leicester 3.5 4.0 7.5
Cambridge 3.0 1.0 4.0
Edinburgh 1 3.0 1.0 4.0
RAL 1.5 0.7 2.2
MSSL 0.6 1.0 1.6
JBO 1 1.0 1.0 2.0
QUB 0.0 1.0 1.0
12.6 9.7 22.3
of whichnon-dev3
TotalPeople
2.5 8
1.0 4
5
4
2
1.0 1
1
4.5 25
1 At Edinburgh, 2 people are funded by AVO and 0.5 by NeSC
At JBO, 1 is funded by AVO3 Includes PM, PS, web developer, AVO interoperability RA
2 Includes Tech Lead, hired Nov-2002 + current round (3.7) + proposed (5.0)
12.02.2003 AstroGrid/GSC Presentation
Planned task deploymentLeics Cam Edin RAL MSS
LJBO QUB
Portal X X X
Registry X X
Community X X X
AstroPass X X
Workflow X X X X
Proc control X X X
MySpace X X X
Data centre X X
Data access X X
12.02.2003 AstroGrid/GSC Presentation
12.02.2003 AstroGrid/GSC Presentation
Next StepsGSC : Approve de-scoped planGSC : Approve five further developersGSC : Approve 3.7M total budgetGSC : Approve basis for monitoring projectAG : hit Q1 targetsAG : hit Q2 targets
12.02.2003 AstroGrid/GSC Presentation
ToDo: by Jun-2003First working portal, registryOGSA integrationData centre briefingSet up Science Advisory Group (AGSAG?)clarify post-AstroGrid optionsPrepare demos for IAU:
Iteration 02 s/w: Portal & data access Aus-VO: customisation of AstroGrid codebase
OGSA/OGSA-DAI demo: joint AstroGrid/Aus-VO
Scientific Roadshow (for post-IAU)IVOA standards (Registry, Data Access, …)