SUBSEA UMBILICAL, RISER FLOWLINE INSTALLATION Submitted by: YOHANEST CHANDRA (A0065919R) OT 5304 – SUBSEA CONSTRUCTION AND OPERATIONAL SUPPORT DEPARTMENT OF MECHANICAL ENGINEERING NATIONAL UNVERSITY OF SINGAPORE October 2012
Oct 30, 2014
SUBSEA UMBILICAL, RISER FLOWLINE
INSTALLATION
Submitted by:
YOHANEST CHANDRA (A0065919R)
OT 5304 – SUBSEA CONSTRUCTION AND OPERATIONAL SUPPORT
DEPARTMENT OF MECHANICAL ENGINEERING
NATIONAL UNVERSITY OF SINGAPORE October 2012
2
TABLE OF CONTENT
1 INTRODUCTION ………………………………………………………….. 3
2 UMBILICAL ……………………………………………………………….. 4
2.1 TYPE OF UMBILICAL ………………………………………………. 4
2.2 INSTALLATION METHOD …………………………………………. 6
3 RISER ……………………………………………………………………….. 7
3.1 TYPE OF RISER ……………………………………………………… 7
3.1.1 COUPLED RISER …………………………………………….. 7
3.1.2 UN-COUPLED RISER ………………………………………... 10
4 FLOWLINE ………………………………………………………………… 13
4.1 TYPE OF FLOWLINE ……………………………………………….. 13
4.2 FLOWLINE INSTALLATION METHOD …………………………. 14
4.2.1 TOWING METHOD ………………………………………….. 15
4.2.1.1 BOTTOM TOW METHOD ………………………… 17
4.2.1.2 OFF-BOTTOM TOWING METHOD ……………… 19
4.2.1.3 CONTROLED DEPTH TOWING METHOD ……… 21
4.2.1.4 CATENARY TOWING METHOD …………………. 22
4.2.1.5 SURFACE TOW METHOD ………………………… 23
4.2.2 S-LAY METHOD ……………………………………………… 24
4.2.3 J-LAY METHOD ……………………………………………… 27
4.2.4 REEL-LAY METHOD ………………………………………… 29
4.3 EVALUATION OF SURF INSTALLATION METHOD …………… 32
4.4 OFFSHORE VESSEL SELECTION …………………………………. 35
CONCLUSION …………………………………………………………………... 36
REFFERENCES …………………………………………………………………. 37
3
SUBSEA UMBILICAL-RISER-FLOWLINE (SURF)
INSTALLATION METHOD
1 INTRODUCTION
Under-water facilities for oil and gas production are generally referred to using a
subsea prefix. Subsea umbilical’s, risers, and flowline is often abbreviated as
“SURF”. SURF is hardware elements that are required to connect the subsea
systems to top- side systems of a floating production unit. Umbilical, flow-line
and riser installation operations are an essential part of subsea construction.
Compared with fixed platform solutions, development solutions applying floaters
and or SURF solutions will be increasingly important. There will be a doubling
of the offshore oil service market from 2010 to 2016 and offshore E&P spending
will reach US$ 1 trillion in 2030. Today, development solutions containing
floaters and SURF (subsea) covers roughly 40% of offshore field developments –
increasing to 60% in 2030 when tie-backs will drive growth in the subsea market
by 4 times in the period 2012–2030. [1] The below graph shows some major
trends in the development of offshore oil and gas fields.
4
Figure 1: Major trend in the development of offshore oil and gas fields. [1]
There are various installation methods and techniques in common use in the
subsea industry and each method has advantages and disadvantages. A subsea
engineer has to ale to provide the best technical solution to the client that is best
suits the specific project.
2 UMBILICAL
Subsea umbilical is basically a pipe connecting subsea wells to surface structures.
It may contain electrical conduits, other pipes, and so on. It is used to operate and
maintain subsea wells or other subsea equipment. Umbilical is also used for gas
lift operation, chemical injection and annulus bleeds.
2.1 TYPE OF UMBILICAL
There are typically 2 types of umbilical. They are static and dynamic
umbilical. The static umbilical has to be designed to be stable on the seabed.
It means there is enough ballast to ensure the umbilical does not move
5
around. The dynamic umbilical shall have the capability to withstand
dynamic tension and bending load.
There are a lot of umbilical available in the market. Some of them are:
• Steel Tube Umbilical
The main considerations for steel tubes in umbilical service are
tensile strength, corrosion resistance (both internal and external), and
operating temperature. Materials available for umbilical construction
include a range of materials from carbon steel to super duplex.
External corrosion protection, afforded by a bonded polymer or zinc
sheath, is available when required. Insulation and thermal shielding
are also available upon request.
Figure 2: Steel Tube Umbilical [2]
• Integrated Production Umbilical (IPU)
The IPU design is based on proven technology and qualified for both
static and dynamic application in shallow and deep water. The design
is ideal for contributing to a stronger umbilical and a better protected
flow line. IPU reduces complexity of the field layout, as well as cost
and time in manufacturing and installation.
6
Figure 3: Integrated Production Umbilical [2]
• Power Distribution Umbilical (PDU)
PDU is suitable for static and dynamic application. It gives complete
dynamic and electric analysis.
Figure 4: Power Distribution Umbilical [2]
2.2 INSTALLATION METHOD
Umbilical is usually installed in one continuous length. It can weigh as much
as 7000 tons or may be more. As umbilical is in one continuous length, the
possible laying methods is reeling method. After umbilical is laid on seabed,
7
usually it is buried to 2 meters depth for protection. Then the umbilical is
terminated at the subsea end using an Umbilical Termination Assembly
(UTA)
Figure 5: One Continuous Umbilical in the Reel [1]
3 RISER
3.1 TYPE OF RISER
A Riser is a conducting pipe connecting subsea wellheads, templates or
pipelines to equipment located on a Floating Production Installation or fixed
offshore structure. [3]. Riser systems are classified into two big categories.
The first category is those that coupled directly to the host facility and the
other category is the un-coupled systems, which in most cases are connected
by flexible jumpers.
3.1.1 COUPLED RISER
• Steel catenary Risers (SCRs)
Steel catenary riser (SCR) technology has emerged as a potential
8
solution for subsea field development in deep-water. The
advantage of SCR is the reliability and integrity of such a system
over the life of a field at a relatively lower cost. Steel Catenary
Risers (SCRs) can be installed by all three methods of
installation. J-lay, reel-lay and S-lay. One of the main challenges
in any SCR design is the fatigue performance of the weld, and,
with its extensive welding technology. [4]
Figure 6: Catenary Riser System [5]
• Weight-Distributed SCRs
Weight Distributed SCR’s concept enhances the applicability of
SCRs to harsher environments. In this concept, well-qualified
ballast elements are attached at certain sections of the SCR to
reduce the stresses around the touchdown point and enhance the
fatigue performance of the SCR.
9
Figure 7: Weight-Distributed Steel Catenary Riser [6]
• Lazy-Wave SCRs
Lazy Wave SCR has attracted more attention in recent years due
to ts good motion isolation effect between Touch Down Point
and hang off. The main challenges for Lazy Wave SCRs are
high-specification welds and installation issues when all the
heavy buoyancies are attached to the SCR.
Figure 7: Lazy-Wave SCR configuration [6]
10
• Flexible riser systems
Flexible riser capable in extending to 800-1800m water depth
depending on diameter and pressure. It is normally assembled
and tested onshore. It usually comes in a reel configuration.
Flexible riser is good for shallow water as motions are decoupled
and reduced fatigue. However, the back draw is that damage can
be occurred and inspection is not easy.
Figure 8: Flexible Riser [5]
3.1.2 UN-COUPLED RISER
• Grouped Single Line Offset Riser (SLOR)
The SLOR offers an attractive solution due to its excellent
fatigue performance and ability for pre-installation, thus taking it
off the field development critical path. The SLOR is typically
situated around 100m away from the vessel or turret depending
on water depth. Connection between the two is achieved using a
flexible jumper via a steel gooseneck assembly connected to the
11
top of the riser pipe. The flexible jumper is then connected to the
vessel through an I-tube or J-tube assembly with bend stiffener.
At the base, the SLOR is connected to a foundation pile (suction,
driven, gravity or drilled) and terminated with an off-take
assembly that facilitates connection to the flowline with a rigid
spool. Connection to the foundation pile is achieved via a roto-
latch (articulation joint) or a stress joint.
Figure 8: Grouped SLOR Arrangement [7]
Installation of Grouped SLOR system is by towing, reel laying
and J-laying. It is to confirm the flexibility and the feasibility of
the riser.
• Single Hybrid Riser Tower / Hybrid Riser Tower
Hybrid Riser Towers (HRTs) is field proven has significant
benefits for deep-water riser applications in terms of flow
12
assurance, thermal performance and robustness of layout. This is
especially significant when a large number of risers are
considered. An HRT provides the required flexibility by avoiding
a crowded layout and allowing a progressive deployment. The
idea is applicable to deep-water and ultra-deep-water, and to
spread- moored and turret-moored FPSO installations.
Figure 9: Single Hybrid Riser Tower / Hybrid Riser Tower [7]
• Buoyancy Supported Risers (BSR)
The BSR concept consists of a large sub-surface buoy, which is
anchored to the seabed by eight chains, two on each corner of the
buoy. The buoy supports multiple SCRs, which are connected to
the FPSO by non-bonded flexible jumpers. This BSR systems
absorbs the dynamics from the FPSO, resulting in almost no
dynamic stresses on the SCRs, making them behave like a long
free-spanning pipe line with the major fatigue response coming
13
from the Vortex Induced Vibration due to the local currents.
Since there is very little dynamic response for the SCRs,
mechanical-lined pipe is used for the SCR section, thereby
optimizing the riser design.
Figure 10: Buoyancy Supported Riser [4]
4 FLOWLINE
4.1 TYPE OF FLOWLINE
The first pipeline was built in the United States in 1859 to transport crude oil.
[8] Through the one-and-a-half century of pipeline operating practice, the
petroleum industry has proven that pipelines are by far the most economical
means of large scale overland transportation for crude oil, natural gas, and
their products. Pipelines have demonstrated an ability to adapt to a wide
variety of environments including remote areas and hostile environments.
Transporting petroleum fluids with pipelines is a continuous and reliable
operation.
Flexible pipes have been introduced in the oil industry since 1972, when
14
Coflexip was awarded a patent to build a high pressure, flexible steel pipe.
The first application of flexible pipeline was used in drilling as a 15,000 psi
Kill and Choke line. [9] Since then, flexible pipe designs have improved to
produce the flowlines and risers that are now used in the offshore oil
industry.
For deepwater, the flexible pipes are used mainly for dynamic risers from a
subsea pipeline end manifold (PLEM) or riser tower to a floating production
system such as an FSO, FPSO, and TLPs. The other uses are static risers,
static flowlines, subsea jumpers, topside jumpers, and expansion joints.
Flexible pipes are used for versatile offshore oil and gas applications
including production, gas lift, gas injection, water injection, and various
ancillary lines including potable water and liquid chemical lines.
4.2 FLOWLINE INSTALLATION METHOD
Pipe-laying encompass installation methods whereby the pipe string is
welded together from pipe joints, before the welds are inspected for defects
and coated, all onboard a specialized pipelay vessel as it is installed on the
seabed. [10] Pipe-laying method is used not only to install pipeline
(Flowline) but also umbilical and riser as these items are grouped together.
There are several types of SURF installation method that being used until
now. They are: Towing Method, S–Lay, J–Lay, and reeling. Here we will
discuss further for each method of SURF installation method.
4.2.1 TOWING METHOD
Tow method is one of the installation method that still being used
until now. In the tow methods, the pipeline is normally constructed at
15
an onshore site with access to the water (sea-front). These methods
can be used for installing pipelines across inland lakes, across wide
rivers, and offshore.
In the case of an offshore pipeline, the pipeline is welded onshore
with an onshore pipeline spread. Once the pipeline is fabricated and
hydro-tested, the pipeline is dewatered and moved into the water,
while being attached to a tow vessel. It is then towed to a location
offshore where each end is connected to pre-installed facilities. This
method could be cheaper than using a lay barge spread to install the
pipeline offshore. The advantage occurs mainly if several small lines
need to be laid and can be bundled inside a larger pipe.
The pipeline can be made up either perpendicular or parallel to the
shoreline. For a perpendicular launched pipeline, a land area that can
accommodate the longest section of the fabricated pipeline must be
leased. A launch way consisting of a line of rollers or rail system
needs to be installed leading from the shore end right into the water.
Launching Method
A good arrangement of pipeline fabrication should be made prior
pulling it into the seawater. After all the sections of pipeline are
fabricated and tested, the first section of pipeline is lifted by side
booms and placed on the rollers on the launch way. The cable from
the tow vessel is attached and the section is pulled into the water,
leaving sufficient length onshore to make a welded tie-in to the next
section. In this manner, the whole single pipeline is fabricated and
pulled into the water. A holdback winch is always used during these
16
pulls to maintain control the direction of pull.
Figure 11: Pipeline Launching [5]
In the parallel launch method, it is required to have a land area along
the shore as long as the total length of the pipeline to be towed. This
could be longer than that acquired during perpendicular launch.
Parallel launch does not require any launch way. After the sections of
the pipeline are welded and tested, the sections are strung along the
shoreline. The pipeline sections are welded together to make up the
length of pipeline to be towed. The completed pipeline is moved into
the water using side-boom tractors and crawler cranes for the end
structures. The front end is attached to the tow vessel, while the rear
end is attached to a hold back anchor. The anchored tow vessel
winches in the tow cable in such a manner that it gradually moves the
pipeline laterally into the water, while the curvature is continuously
monitored. When the whole length of pipeline and its end structures
make one straight line, the tow vessel begins to tow the pipeline along
the predetermined tow route.
For pipelines that are to be towed into deep water, pressurized
nitrogen can be introduced into the pipeline to prevent collapse or
17
buckling under external hydrostatic pressure. A depth of 3000 feet
can be achieved. Greater depths would require a stop for another
recharge of pressurized nitrogen from the surface.[11] This has never
been done.
Maintenance
Maintenance for towing method can be varies. For shallow depth
water, the maintenance is still can be done by diver. But for very deep
water, It will require Remote Operating Vehicle (ROV). It all goes
the same for any very deep water application.
Towing Method
Towing method can be classified into 5 types. They are Bottom Tow
Method, Off-Bottom Tow Method, Controlled Depth Tow Method,
Catenary Tow Method and Surface Method. The choice of method is
dependent on the submerged weight of the pipeline, length of the
pipeline and the seabed environment or presence of existing pipelines
along the selected tow route.
4.2.1.1 BOTTOM TOW METHOD
The bottom tow method is pulling the pipeline along the
seabed to its final location. The length of a single section of
pipeline is limited by the available bollard pull of the vessel
used. The bollard pull must be greater than the total
submerged weight of the pipeline plus the friction. Two to
three vessels can be used in tandem to obtain additional
bollard pull capability.
18
Figure 12: Bottom Tow Method [12]
A thorough sea-bottom survey of the pipeline all the way
from the shoreline to the pipeline’s final resting place
offshore shall be conducted prior pulling it into its final
location. An abrasion-resistant coating is required on the
bottom half of the pipeline to protect the normal corrosion-
resistant coating like FBE. However, abrasion testing may be
required to select the appropriate coating. A slick coating on
the bottom half of the pipe can reduce friction and reduce the
bollard pull requirement during tow. If concrete weight
coating is required for stability, then this can be that coating.
An additional thickness may be required to allow for
abrasion.
For pipelines in shallow water, a trench may be required due
to regulatory requirements or for pipeline stability. In this
19
case, a subsea trenching plow can be prepared and attached
ahead of the pipeline prior to pulling it into its final location.
In bottom tow method, it is difficult to pull the pipelines into
a curved trench. This will require additional bollard pull.
The ends of a bottom-towed pipeline are normally connected
by deflect-to-connect method. In this method, the end
sections of the pipeline are made to float a few feet above
the seabed by providing additional buoyancy for this length
and attaching anchor chains at discrete spacing along this
length. The buoyancy and chains are attached onshore with
chains strapped over the buoyancy pipe during towing and
deployed at the pipeline’s final location. This length can then
be pulled laterally by attaching cables to the end of the
pipeline from the facility. Once the pipeline end structure is
secured at the facility, the connection can be made by
flanges (in diving depth) or by hydraulically activated
connectors (in deepwater).
4.2.1.2 OFF-BOTTOM TOWING METHOD
In the off-bottom tow method, the submerged pipeline is
buoyant and floats above the seabed at a predetermined
height during the towing. The connection at the ends of
bottom-towed pipeline is achieved in the similar method as
Bottom tow method. The buoyancy and chains are attached
in discrete modules for the length of the pipeline.
In Off-Bottom Tow Method, no extensive protection
20
structure is required and existing pipelines can be crossed by
placing concrete mats placed over these pipelines and
allowing the hanging chains to drag over the mats..
However, buoyancy and chains are required for the entire
length of the pipeline. If several pipelines are needed for
field development, the buoyancy and chains can be
recovered and used again.
Figure 13: Off-Bottom Tow Method [12]
The seabed survey needs to consider only obstacles that are
higher than the height of the floating pipeline and sudden
steep seabed cavities. An abrasive-resistant coating is still
required in Off-Bottom Tow Method, but not as stringent as
Bottom Tow Method.
Off-bottom tow is only feasible up to a certain depth because
the buoyancy becomes more expensive as the water depth
increases.
21
4.2.1.3 CONTROLED DEPTH TOWING METHOD
In Controlled Depth Tow method, the entire length of
pipeline is controlled and kept at a considerable height above
the seabed in between the lead and trailing tow vessels
during towing. To achieve this, discrete buoyancy, chains,
and a large tension applied to the pipeline are required. The
tension is applied by two tow vessels pulling in opposite
directions at each end of the pipeline. The pipeline is
controlled at certain depth and once it reaches its desired
depth, the front tow vessel applies more thrust while the
back tow vessel cuts back on its reverse thrust. A third vessel
is required to monitor the height of the pipeline in the middle
by using a subsea transponder system. This vessel sends its
signal to the two tow vessels, which see the height in real
time and adjust their thrusts appropriately to keep the
pipeline within the desired depth range. At the design tow
speed, the pipeline will lift off from the seabed and adopt the
desired mid-depth CDTM configuration. The lift is
dependent on speed, type of chain and number of links. By
controlling the tow speed and tow wire length, the pipeline
configuration is maintained within acceptable limits, as
defined by static and dynamic tow analyses. This method is
not suited for very long pipelines (greater than 3 miles). [9]
22
Figure 14: Controlled Depth Tow Method (CDTM) [12]
In this method, only a near shore survey and final infield
pipeline route survey are required. Incase of emergency,
some discrete areas where the pipeline can be parked shall
be identified. CDTM tow speed is higher than for off-bottom
tow, and the absence of contact with the sea bottom, which
allows passing severe slopes or rocky bottom conditions.
This method is ideal for areas with extensive rocky outcrops,
many existing pipelines, or other obstructions along the tow
route.
4.2.1.4 CATENARY TOWING METHOD
In the catenary tow, the required bollard pull of the two tugs
increases as the water depth decreases. The pipeline being
towed is in a catenary configuration between the tugs. A
catenary tow is not possible in Shallow water depth since the
required horizontal bollard pull forces to keep the pipeline
23
sag-bend of the seabed are too high for conventional tugs.
The installation on site is achieved by paying out on the tug
winch wires while controlling the touchdown routing with
the vessel position.
Figure 15: Catenary Towing Method [12]
4.2.1.5 SURFACE TOW METHOD
Surface tow method is similar to mid-depth tow method but
it will not require any chains. This method required the two
vessels at each end to keep the pipeline in tension while it is
towed on the surface. Only a survey of the final pipeline
route is required. This method can be used for shallow. For
deep water, a sophisticated controlled flooding and/or
buoyancy removal system is required. Not many pipelines
are installed by this method.
24
Figure 16: Surface Tow Method [6]
4.2.2 S-LAY METHOD
S-Lay method is the most common installation method of subsea
umbilical, riser and flowline in shallow water. Typically 12 meters
long of pipe joints are manufactured and coated onshore. Then, they
are brought to the pipe lay vessel by supply vessels so that the pipe
construction can be continued without interruptions. In the S-lay
method, the welded pipeline is supported on the rollers of the vessel
and the stinger, forming the over-bend. Then it is suspended in the
water all the way to the seabed, forming the sag-bend. The over-bend
and sag-bend form the shape of an “S”. Typical S-Lay method
configuration can be seen at figure 17, below.
25
Figure 17: Schematic of S-Lay Method [13]
Onboard the S–Lay vessel, the pipe joints are welded on to the end of
the pipeline in a horizontal production facility. It is called the firing
line, which provides a sheltered environment for the workers to carry
out multiple workstations for welding, non–destructive testing of the
welds and coating. The field joint station is located after the NDE
station and the tension machines. The pipeline is held in a tensioner to
facilitate continued construction. Tensioner is a large rolling
caterpillar tracks with rubber pads that press on to the pipe going
down to the seabed. The tensioners control the speed (pay-out speed)
when the pipe that has been welded with the new pipe joints extended
from the vessel. This speed is controlled while maintaining the
tension on the pipe as the vessel moves forward. A sloping ramp
supports the pipe as it moves from the vessel and onto the stinger.
The stinger is a long open frame structure fitted with rollers, which
supports the pipeline and controls its curvature from the horizontal to
26
the inclined section. The stinger is typically made out of several
hinged sections to make it articulated. Setting the segments at chosen
angles can control the stinger’s shape and curvature. The overall
stinger length depends on the pipelay vessel, but is typically in the
range of 100 meters. In shallow water depth of 100 meters, the lift off
angle will typically be in the order of 30◦ from the horizontal. For
increasing water depth, the lift off angle also increases up to 90◦ if the
tension is kept within practical limits. This is commonly known as
Steep S–lay [14], which can be performed by vessels like the
Solitaire. This stinger configuration has shown to reduce the tension
in the pipe compared to the traditional S–lay method. Furthermore,
pipeline engineers argue that it will be safe to relax the standard strain
level of the design in order to reach greater depths and handle even
heavier pipelines. [14]When the new pipe length has been laid out,
the whole process is repeated.
Figure 18: S-Lay Offshore Vessel [13]
27
The main advantage with the S–lay method is that the long firing line,
running from bow to stern, enables parallel workstations for assembly
of pipe joints, such that up to four pipe joints can be added at the
time. This makes the method fast and economical, particularly for
long pipelines.
However, for very deep water, the pipe must be supported to a near
vertical departure angle. It requires a very large stinger to avoid pipe
damage. With increasing water depths, the power that’s required to
provide lay tension increases. It is indirectly transferable to high fuel
expenses.
4.2.3 J-LAY METHOD
J-Lay installation method is a development from S-Lay installation
method and often seen as complementary methods. [14] J-Lay
installation method eliminates the over-bend region in S-Lay
installation method when installation is required in deep-water. The
configuration of the pipeline from the seabed to the pipelay vessel is
near vertical at the pipelay vessel end and this suspended pipe
resemble of letter J. The pipe leaves the pipelay vessel in a nearly
vertical position in the J–lay installation method.
28
Figure 19: Schematic of J-Lay Method [13]
The pipeline is constructed on a vertical ramp, the so–called J–lay
tower, which is fitted with tensioners and workstations. The angle of
the J–lay tower may typically vary between 0◦ and 15◦ from the
vertical. The ramp angle is chosen in such a way that it is in line with
the pipe catenary to the seabed. The pipe leaves the barge steeply
such that the total length of the free pipe is shortened and less applied
tension is required for sag bend control. The touchdown point is not
as far behind the vessel as for S–lay, due to the lower applied tension,
so that positioning of the touchdown is easier, and the pipe can be
installed more accurately. The pipeline is only bent once during
installation (at the seabed) which is advantageous for installing
pipelines that are sensitive to fatigue. Also the complexity involved
with a stinger is eliminated. The main drawback with the method is
that the tower only facilitates one workstation, making the J–lay
method inherently slower than the S–lay method, which is the price
29
paid for pipe installation at greater depths. But since the large J-lay
towers are capable of handling prefabricated quad joints (160 feet
long), the speed of pipe-laying is increased.[offshore pipelines] The
added weight high up on the vessel has an adverse effect on stability,
and semi–submersibles are frequently used to facilitate J–lay due to
their high stability. The J-lay method is very suitable for deep water
as the pipe leaves the lay system in an almost vertical position. J-Lay
installation method is not applicable in shallow water.
Figure 20: J-Lay Offshore Vessel [9]
4.2.4 REEL-LAY METHOD
Reel-Lay method is a method of installing pipelines in the ocean from
a giant reel mounted on an offshore vessel. Depending on the type of
lay vessel the spool can be designed to operate in the horizontal or the
vertical position. Pipelines are assembled at an onshore spool-base
30
facility and spooled onto a reel, which is mounted on the deck of a
pipelay barge. Reel-Lay method results in greater productivity due to
the ability to lay the pipe in a continuous manner by unwinding it
from the reel. The Reel-ay method reduces labor costs by permitting
much of the welding, x-raying, corrosion coating, and testing to be
accomplished onshore, where labor costs are generally lower than
comparable labor costs offshore. As the pipe is already spooled in the
reel, It reduces the number of personnel required to lay the pipe. Low
manpower required means lowering the risk of accidents at the same
time and providing efficiency in the availability of the pipe.
Figure 21: Reeled Pipeline [15]
Each spool is designed to operate with a specific barge and can
usually handle pipe from 2" to 12". The total length capacity depends
on the spool dimensions and the diameter of the pipe. Based on a
typical design, a spool can hold up to 80 km of 2" pipe. [16]
The normal procedure used to spool the pipe on the reels consist in
welding the joints of pipe in the operations yard and winding them
31
concurrently on the spools. This procedure could be performed
directly on the docked barge since handling a full reel would require a
large crane to load the spool aboard. Therefore, at the time of
considering this method, it is necessary to clearly know that the lay
barge would have to stay docked while the pipe is being welded and
wound on the spool. Otherwise, a large enough crane is required, as
well as an adequate support and pipe-stringing track must be
provided.
The productivity Reel-Lay method depends on various factors
including the length of pipeline sections to be laid, the distance
between risers, the number of lay-barge repositioning required could
limit the production. If the wells and flow stations are close together
and the average length of this pipe laying is quite short (1500 – 2000
m), a good sequential drilling program in the surrounding areas would
be required to obtain the largest amount of laying job within the
adjacent areas and to avoid long distances mobilizations between
work sites, this method can result in a high productivity. Another
factor that affects productivity is the method used to move the barge
during the pipe lay. If the conventional method using winches and
anchors is used, the productivity is greatly reduced than using an
automated dynamic positioning system.
Reel-Lay method has some limitation where the pipeline is plastically
deformed and then straightened again, some thinning of the wall and
loss of yield strength of the material can be occurred. It also cannot
reel concrete-coated pipeline.
32
4.3 EVALUATION OF SURF INSTALLATION METHOD
After elaborating all available SURF installation method, we will try to
identify the pro and cons for each installation method. Every installation
method should have their own strong points, but they also have their own
weaknesses. Here we will try to evaluate and compare the advantages and
disadvantages for each installation method so that it can become our
guideline in choosing the best installation method for certain well.
Towing Method
Basically the main advantage of towing method is that the pipelines,
umbilical or riser can be fabricated onshore before it will be towed to the sea.
This onshore fabrication can save a huge cost compare to offshore. Actually,
Tow methods can be used for installing pipelines from shallow water depths
to deep- water depths depending on the design requirements but it has a lot
of drawbacks. The biggest drawback for Towing Method is that this method
is very dependent to weather; sea current, tide and also limited to certain
depth of 3000 feet even though pressurized nitrogen has been introduced to
the buoyancy system. The other drawbacks are different for each type of
Towing Method.
• Bottom Tow Method and Off-Bottom Tow Method
Bottom Tow and Off-Bottom Tow Method are similar and it requires
a seabed survey prior to towing to make sure that there is no
obstruction or cross pipelines on the seabed. Abrasive-resistant
coating or additional thickness for concrete pipe is required to
prevent from severe corrosion
33
• Controlled Depth Tow Method
Controlled Depth Towing Method required additional vessel to check
and control the depth of the pipeline being towed. It means additional
cost is required. CDTM is also not suitable for pipeline more that 3
miles.
• Catenary Tow Method
Catenary Tow Method is not possible for shallow water and it
requires additional bollard when doing deeper towing. It can be done
by combining few vessels to pull the pipline.
• Surface Tow Method
Surface Tow Method doesn’t require any chain, but it requires a lot of
buoyancies. As the pipeline is floating almost at surface, sea current
and weather give a huge impact to it. When the depth goes deeper, a
sophisticated controlled flooding and/or buoyancy removal system is
required. This is why this method can only be used for shallow water
and not many pipelines are installed by this method.
S-Lay Method
The main advantage with the S–lay method is that the long firing line,
running from bow to stern, enables parallel workstations for assembly of
pipe joints, such that up to four pipe joints can be added at the time. This
makes the method fast and economical, particularly for long pipelines.
However, for large water depths, the pipe must be supported to a near
vertical departure angle, which requires a very large stinger to avoid over
bending which damaging the pipe. With increasing water depths, the power
needed to provide the required lay tension increases, which is directly
34
transferable to high fuel expenses. These are the main disadvantages of the
method.
J-Lay Method
The J-lay methodology is the prime technique for laying pipelines in very
deep waters. Vertical space configuration on a J-lay vessel allows for only
one pipe joining station, hence a fast and reliable pipe-joining technique or
multiple pipe sections are prerequisite for practical use of J- lay method.
J-Lay Method allows the pipe to be laid in a less tension configuration. Pipe
stresses are maintained well within the linear elastic limit. J-Lay Method also
requires lower lay tension resulting in reduced on-bottom tension and free
span. As the vessel required a huge tower, it adds more weight to overall
weight of the vessel and increased its stability. Hence, It is less susceptible to
weather condition. As the J-lay method is primarily a deep-water method,
some limitations occur in shallow water.
Reeling Method
Reeling Mehod hold a huge advantages to be able to lay very long pipelines.
But, It is only limited to flexible pipelines only. This flexible pipelines
cannot be used for ultra deep water as the flexible pipelines cannot withstand
the hydrostatic pressure from seawater. Removing the buckle in reeling
method takes quite time to complete.
4.4 OFFSHORE VESSEL SELECTION
Since the first SURF installation method has been introduced, the vessel to
carry out the job has been improved to give better performance. Selection of
vessel is vital in Subsea Umbilical Riser and Flowline installation to be able
35
to perform the job. It is very important to understand the primary vessel-
capacity requirements to carry out the job. Some information like; crane-lift
capabilities, flexible-pipe lay tensions and overall deck-storage capacity have
to be identified before handling the products to be installed. There are many
types of vessel that normally used to carry out SURF installation such us:
Tug Boat, Barge, FSO/FPSO, etc. To determine the installation-vessel
requirements, some initial engineering was conducted to better understand
maximum lift and deployment loads associated with the installation program.
Figure 22: Type of Offshore Vessel [17]
36
CONCLUSION
As we know, Umbilical, flow-line and riser installation operations are an
essential part of subsea construction. Compared with fixed platform solutions,
development solutions applying floaters and or SURF solutions will be
increasingly important. There are a lot of wells in the whole world that required
subsea construction and each places are unique. It doesn’t mean that we can
apply same subsea construction design for well that has different characteristic.
Subsea engineer must understand for each characteristic, which application can
give the best result.
For shallow deep water, S-lay installation method and Towing method would be
the best choice to lay the pipeline on seabed. When doing Towing method, It
would be best if we don not use parallel launching, as it will need large of place
to launch the pipeline in parallel. In the other hand, for deep water J-Lay
installation method is the pioneer. J-Lay method requires a huge vessel with the
tower. Hence, It would be able to withstand harsh weather, as it is more stable.
For small pipeline size, Reel-Lay method could deliver good performance except
for ultra deep water. The flexible pipeline in Reel-Lay method cannot withstand
the huge hydrostatic pressure.
As for Riser, Group SLOR, Single Hybrid Riser Tower / Hybrid Riser Tower,
Steel catenary Risers and Buoyancy Supported Risers are able to be used in deep
water. Group SLOR and Single Hybrid Riser Tower / Hybrid Riser Tower are
famous in their robustness in layout. In shallow water Lazy-wave Riser
installation would perform well.
In deep water, maintenance is usually done by ROV. It has better safety compare
to Diving maintenance as in Diving maintenance, the diver are exposed directly
37
to the environment. Hence it is also advised diving maintenance can only be done
for maximum 30 meters depth only.
In overall, the choice of subsea construction will be depend on the field
characteristic, client requirement and available technology.
38
REFFERENCES
[1] INTSTOK, Equipment and systems for offshore oil & gas field developments,
2012
[2] Aker Solution, Subsea Umbilicals, 2009
[3] ABS, Subsea Riser System, 2006
[4] Subsea 7, Riser Technology, 2012
[5] Bernie Alistair, Lecture Notes -Subsea Construction and Support Operations,
2012
[6] http://www.offshore-mag.com
[7] Grouped SLOR
[8] (Wolbert, George S., Petroleum pipelines; Petroleum industry and trade;
Petroleum pipeline industry, 1952
[9] Boyun Guo, et al, Offshore Pipelines, 2004
[10] Braestrup et al., Marine Pipelines, 2005
[11] Alf Roger Hellesto, et al, Deep Water Pipeline and Riser Installation by the
Combined Tow Method, 2007
[12] http://www.bgr.bund.de
[13] Gullik Anthon Jensen, Offshore Pipelying Dynamics, 2010
[14] Dominique Perinet, Acergy France and Ian Frazer, Strain Criteria for Deep
Water Pipe Laying Operations, 2008
[15] http://www.oilonline.com
[16] http://www.welschs.cc/reel.html
[17] http://gcaptain.com/technip-begins-work-marine-containment/
39