  • 7/29/2019 AssetFactory.pdf

    1/37

    Basic ControllingReporting

    December 2012

    FINANCIALINFORMATIONSYSTEM

  • 7/29/2019 AssetFactory.pdf

    2/37

    2

    Purpose of Controlling Reporting:

    Four Key Questions to be answered

    Basic Reports used to answer Key Questions

    Cost Center (CC) Funding

    CC Funding by Allocation

    CC User

    Cost Center w/o IO: Plan & Actuals

    Cost Center with IO: Plan & Actuals

    Cost Centers: Actual/Plan/Commitments

    Internal Orders: Actual/Plan/Commitments

    Cost Centers: Actual Line Items

    Report Features

    Course Agenda

  • 7/29/2019 AssetFactory.pdf

    3/37

    3

    Controlling(CO)Controlling is used to track and plan revenue and expense activity for a specificdepartment or project.

    It is similar to FM, but with an important difference no spending control

    (i.e., Funds Availability Checking).

    The purpose of Controlling is to answer the question:

    Which department/project incurred the activity?

  • 7/29/2019 AssetFactory.pdf

    4/37

    4

    Controlling Reports answer the following questions:

    Which budget (FC or FC/Fund) was the financial transaction

    posted to?

    How does the plan compare to actual financial activity?

    What commitments are outstanding against the Cost Center/ Internal Order?

    What financial transactions have been recorded against theCost Center / Internal Order?

    Purpose of Controlling Reporting

  • 7/29/2019 AssetFactory.pdf

    5/37

    5

    Basic Reports Used to Answer Questions

    CC Funding CC Funding by

    Allocation

    CC Funding byUser

    CC w/o IO:Plans & Actuals

    CC with IO:Plans & Actuals

    CC: Actual / Plan /Commitments

    IO: Actual / Plan /Commitments

    CC: Actual LineItems

    IO: Actual LineItems

    To which budget (FC

    or FC/Fund) was thefinancial transactionposted?

    How does the plan

    compare to theactual financialactivity?

    What commitments

    are outstandingagainst the CC / IO?

    What financialtransactions havebeen recorded

    against the CC / IO?

  • 7/29/2019 AssetFactory.pdf

    6/37

    6

    Cost Center Funding Report

    Used to: View all postings to Cost Centers or Internal Orders by Cost Element (G/L

    account) and FM account (Fund Center or Fund Center/Fund)

    Provides:

    subtotals by Cost Element or FM account

    Can be run:

    for one period or a range of periods within a fiscal year for one or more:

    Cost Centers Internal Orders Cost Elements

    Funds Centers

    by exception (i.e., allows you to indicate accounts to omit)

    Enables:

    Allows drilldown to document level

  • 7/29/2019 AssetFactory.pdf

    7/37

    7

    Cost Center Funding Report (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting Information System Reports

    for Cost Center Accounting Cost Center Accounting (UofT) Cost Center Funding (Transaction Code:

    ZF06)

    A Cost Center orInternal Order is required; however, to expand or narrow thescope of report output, a Cost Element and/or CF Center may be entered.

    To subtotal byCost Elementselect CostElement SubTotals option

    Enter fiscal year and periodrange. If only one period isdesired, enter the same periodin the From and To fields.(e.g. From period 3, To period 3)

  • 7/29/2019 AssetFactory.pdf

    8/37

    8

    Cost Center Funding Report

    Out put Screen:

    If Cost ElementSub Totals option isselected, subtotalsappear here

    Subtotal byFM account

    Double click on any document line to drilldown to the Document Overview

  • 7/29/2019 AssetFactory.pdf

    9/37

    9

    Cost Center Funding by Allocation Report

    Used to:

    Organize all postings to Cost Centers or Internal Orders by Allocation(a.k.a., Assignment)

    Only useful if meaningful text or codes are used in the Assignment field of

    document line items*

    Can be run by:

    on single allocations range of allocations multiple allocations

    All other features and report layouts are similar to the Cost Center Fundingreport with the exception of subtotaling by Allocation

    *Note: The Allocation/Assignment field is case and space sensitive

  • 7/29/2019 AssetFactory.pdf

    10/37

    10

    Cost Center Funding by Allocation Report (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting InformationSystem Reports for Cost Center Accounting Cost Center Accounting (UofT) -> CostCenter Funding by Allocation (Transaction Code: ZF07)

    Enter fiscal year and period rangeSame

    selectioncriteria asthe Cost

    CenterFunding

    Report

    Enter Allocation (assignment) criteria inthis field. You can enter: A single allocation

    range of allocations, OR multiple allocations

  • 7/29/2019 AssetFactory.pdf

    11/37

    11

    Cost Center Funding by Allocation Report (contd)

    Output Screen:

    Subtotaling byallocation

    Double click anywhere on document line to drilldown to Document Overview

  • 7/29/2019 AssetFactory.pdf

    12/37

    12

    Cost Center User Report

    Used to: Organize all postings to Cost Centers or Internal Orders by the AMS

    User ID of the person who entered the document/transaction

    Can by run by: single user id range of user ids multiple user ids

    Provides: subtotals by Fund Center or Fund Center/Fund (i.e., funding source)

    All other features and report layouts are similar to the Cost CenterFunding report, but adds the user id column.

  • 7/29/2019 AssetFactory.pdf

    13/37

    13

    Cost Center User Report (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting Information SystemReports for Cost Center Accounting Cost Center Accounting (UofT)

    Cost Center User (Transaction Code: ZF08)

    Sameselectioncriteria asthe Cost

    CenterFundingReport

    Enter user criteria in these fields.You can enter: a single User ID range of User IDs, and/or

    multiple Users IDs

    Enter fiscal year and period range.

  • 7/29/2019 AssetFactory.pdf

    14/37

    14

    Cost Center User Report (contd)

    Output Screen:

    Subtotalsby FC orFC/Fcombo

    Double click document line to drilldown to Document Overview

  • 7/29/2019 AssetFactory.pdf

    15/37

    15

    Reports Used to Answer Questions

    CC Funding

    CC Funding by Allocation

    CC Funding by User

    Which budget (FC or FC/Fund)

    was the financial transactionposted to?

    How does the plan compare tothe actual financial activity

    recorded on a summary anddetailed level?

    What commitments areoutstanding against the CC / IO?

    What financial transactions havebeen recorded against the CC /IO?

  • 7/29/2019 AssetFactory.pdf

    16/37

    16

    Cost Center Without Internal Orders:Plan & Actuals Report

    Used to: Compare CO Plans to Actual Revenues and Expenses (both summary

    or detailed view)

    Can be run by: a single period or range of periods Cost Center Group or Node single, range or multiple CCs

    Specific plan versions (e.g., 0 for the current plan or 1 for the originalplan)

    Enables:

    drilldown to line item details download to Excel

    Does not include:

    Commitments

  • 7/29/2019 AssetFactory.pdf

    17/37

    17

    Cost Center Without Internal Orders:Plan & Actuals Report (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting InformationSystem Reports for Cost Center Accounting Cost Center Accounting (UofT)UofT: CC w/o IO: Plan & Actuals (Transaction Code: ZSO3)

    Default is UofT

    Enter fiscal year and period range

    Expand or narrowdesired output byselecting:

    Groups

    single values a range of CCsand/or

    multiple CCsand/or CostElements

    0 for the currentplan (default)

    1 for the originalplan

  • 7/29/2019 AssetFactory.pdf

    18/37

    18

    Cost Center Without Internal Orders:Plan & Actuals Report (contd)

    Out put Screen:

    Default view isPlan/ Act /

    Variance byCost Element &Cost Center.

    Click here todisplayalternate viewof summarytotals byCostElement forthe entirerange of CostCentersselected.

    Double click on any Cost Element item todrill down to the Detailed Line Items

    Expand orcollapse eachgroup of CostElements

    Data can be sorted.

    Data can be downloaded to Excel via Office Integration.

  • 7/29/2019 AssetFactory.pdf

    19/37

    19

    Cost Center With Internal Orders:Plan & Actuals Report

    Used to:

    compare CO Plan and Actual revenues and expenses in a summary or detailed view

    Can be run by:

    a single period or range of periods Cost Center Group or Node single, range or multiple CCs Cost Element Group single Internal Order Order Group

    Specific plan versions (e.g., 0 for the current plan or 1 for the original plan)

    Enables: Provides drilldown to line item details Download to Excel

    Does not include: Commitments

    IMPORTANT: ALL UofT Cost Centers or Internal Orders will be included in the report if theselection criteria is not defined correctly.

  • 7/29/2019 AssetFactory.pdf

    20/37

    20

    Cost Center With Internal Orders:Plan & Actuals Report (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Cost Center Accounting (UofT) UofT: CC with IO: Plan & Actuals (Transaction Code: ZSO1)

    MUST specify:CC Group or

    CC value(s)

    AND

    Order Group orOrder value(s)

    Identical to the screenfor Cost Center w/oInternal Orders:Plans & Actuals

  • 7/29/2019 AssetFactory.pdf

    21/37

    21

    Cost Center With Internal Orders:Plan & Actuals Report (contd)

    Out put Screen:

    Double click any Cost Element item to

    drill down to detailed line items

    Lists the Plan/Actual

    costs and Variance datafor Cost Center

    Also providesPlan/Actuals andVariance data forInternal Orders

    Data can be downloaded toExcel via Office Integration.

  • 7/29/2019 AssetFactory.pdf

    22/37

    22

    Basic Reports Used to Answer Questions

    CC Funding

    CC Funding byAllocation

    CC Funding by User

    CC w/o IO:Plans & Actuals

    CC with IO:Plans & Actuals

    Which budget (FC or

    FC/Fund) was thefinancial transactionposted to?

    How does the plancompare to the

    actual financialactivity recorded?

    What commitmentsare outstandingagainst the CC / IO?

    What financialtransactions havebeen recordedagainst the CC / IO?

  • 7/29/2019 AssetFactory.pdf

    23/37

    23

    Cost Centers: Actual/Plan/Commitments

    Used to:

    compare CO Plan, Commitments and Actual revenues and expenses in asummary or detailed view

    Can be run by: a single period or range of periods Cost Center Group or Node single, range or multiple CCs Cost Element Group Specific plan versions (e.g., 0 for the current plan or 1 for the original plan)

    Enables: View of Commitments attached to Cost Center Provides drilldown to line item details Download to Excel

    Output is the same as the UofT: CC w/o IO: Plan & Actuals report with the addition ofCommitment transaction details

  • 7/29/2019 AssetFactory.pdf

    24/37

    24

    Cost Centers: Actual/Plan/Commitments (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Plan / Actual Comparisons Additional Key Figures

    Cost Centers: Actual/Plan/Commitments (Transaction Code: S_ALR_87013620)

    Default is UofT

    Enter fiscal year and period rangeExpand or narrowdesired output byselecting:

    Groups single

    values

    a range ofCCs and/or

    multipleCCs and/orCostElements

    0 for the

    current plan(default)

    1 for theoriginal plan

  • 7/29/2019 AssetFactory.pdf

    25/37

    25

    Cost Centers: Actual/Plan/Commitments (contd)

    Out put Screen:

    Double click any Cost Element item to drill down to detailed line items

    Actual + Commitment = Assigned

  • 7/29/2019 AssetFactory.pdf

    26/37

    26

    Orders: Actual/Plan/Commitments

    Used to:

    compare CO Plan, Commitments and Actual revenues and expenses in asummary or detailed view

    Can be run by: a single period or range of periods single, range or multiple Internal Orders Order Group single Cost Element Cost Element Group

    Specific plan versions (e.g., 0 for the current plan or 1 for the original plan)

    Enables: View of Commitments attached to Internal Order

    Provides drilldown to line item details Download to Excel

    Output is the same as the Cost Centers: Actual/Plan/Commitments but reports

    onlyon Internal Orders

  • 7/29/2019 AssetFactory.pdf

    27/37

    27

    Orders: Actual/Plan/Commitments

    SAP Menu Path: Accounting Controlling Internal Orders Information System Reportsfor Internal Orders Plan/Actual Comparisons Additional Key Figures Orders:Actual/Plan/Commitments (Transaction Code: S_ALR_87012999)

    Default is UofT

    Enter fiscal year and periodrangeExpand or narrow

    desired output byselecting:

    Order Groups Single, range

    or multipleInternalOrders

    Single CostElements

    Cost Elements

    Groups

    0 for the

    current plan(default)

    1 for theoriginal plan

  • 7/29/2019 AssetFactory.pdf

    28/37

    28

    Orders: Actual/Plan/Commitments (contd)

    Out put Screen:

    Data can be downloaded to Excel via Office Integration.

  • 7/29/2019 AssetFactory.pdf

    29/37

    29

    Basic Reports Used to Answer Questions

    CC Funding

    CC Funding byAllocation

    CC Funding by User

    CC w/o IO:Plans & Actuals

    CC with IO:Plans & Actuals

    CC: Actual / Plan /Commitments

    IO: Actual / Plan /Commitments

    Which budget (FC orFC/Fund) was thefinancial transactionposted to?

    How does the plancompare to theactual financialactivity recorded?

    What commitmentsare outstandingagainst the CC / IO?

    What financialtransactions havebeen recordedagainst the CC / IO?

  • 7/29/2019 AssetFactory.pdf

    30/37

    30

    Cost Centers: Actual Line Items

    Used to: show all Actual transaction line items posted to Cost Center

    Provides: detailed list of line items sorted by Fund Centers

    Can be run on: a single Cost Center range or multiple Cost Centers Cost Center Group or Node single Cost Element range or multiple Cost Elements Cost Element Group

    Multiple fiscal years

    Enables: Download to Excel

    Internal Order version of this line itemreport:

    SAP Menu Path: AccountingControlling Internal Order Information Systems Reports forInternal Orders Line Items Orders:Actual Line Items

    Transaction Code: KOB1

  • 7/29/2019 AssetFactory.pdf

    31/37

    31

    Cost Centers: Actual Line Items (contd)

    SAP Menu Path: Accounting Controlling Cost Center Accounting Information System Reports for Cost Center Accounting Line Items Cost Centers: Actual Line Items (Transaction Code: KSB1)

    Report singe posting

    date or over multipleyears

    Expand or narrowoutput by:

    Cost Center/CCGroup

    CostElement/CostElement Group

  • 7/29/2019 AssetFactory.pdf

    32/37

    32

    Cost Centers: Actual Line Items (contd)

    Output Screen:

    Double click anywhere on a line item to

    drill down to Document Overview

    Can be sort, filter, subtotal data

    To download to Excel

  • 7/29/2019 AssetFactory.pdf

    33/37

    33

    BasicReportsUsedtoAnswerQuestions CC Funding

    CC Funding byAllocation

    CC Funding by User

    CC w/o IO:Plans & Actuals

    CC with IO:Plans & Actuals

    CC: Actual / Plan /Commitments

    IO: Actual / Plan /Commitments

    CC: Actual Line Items(and IO: Actual Line

    Items)

    Which budget (FC orFC/Fund) was thefinancial transactionposted to?

    How does the plancompare to theactual financialactivity recorded?

    What commitmentsare outstandingagainst the CC / IO?

    What financialtransactions havebeen recordedagainst the CC / IO?

  • 7/29/2019 AssetFactory.pdf

    34/37

    34

    WEB Documentation

    Reference Guides:http://www.finance.utoronto.ca/fast/qrg.htm

    Office Integration

    http://www.finance.utoronto.ca/fast/qrg/nav/commonrptfcns/offint.htm

    FAQs:http://www.finance.utoronto.ca/faq.htm

    Financial Forms:http://www.finance.utoronto.ca/forms/processing.htm

    Policy & Documentation:http://www.finance.utoronto.ca/gtfm.htm

  • 7/29/2019 AssetFactory.pdf

    35/37

    35

    NEED HELP?

    http://www.utoronto.ca/ams/help.htm

    Help is a facility for all AMS subsystems:

    Use the WEB form found at the above address

    Select the appropriate AMS module

    (e.g., FIS: FAST Team)

    Complete all the information required on the form Click on the Send it button

    Mail box is monitored Monday to Friday9:00 a.m. - 5:00 p.m.

  • 7/29/2019 AssetFactory.pdf

    36/37

    36

    F.A.S.T. Team Contacts

    F.A.S.T Web site:http://www.finance.utoronto.ca/fast.htm

    Course Evaluation:

    http://www.finance.utoronto.ca/fast/training/fissceval.htm

    Manager Lorena Gaudio [email protected]

    Assistant Manager Chris Dimitriadis [email protected]

    Business Analyst Darshan Harrinanan [email protected]

    Business Analyst Suzanne Macintyre [email protected]

    Business Analyst Karen Jang-Leung [email protected]

    Business Analyst Rames Paramsothy 978-4675(Training Coordinator) [email protected]

  • 7/29/2019 AssetFactory.pdf

    37/37

    THEEND!