ASSESSMENT OF HYDROELECTRIC POTENTIALS AT THE OWU AND ERO-OMOLA FALLS IN KWARA STATE B. F. Sule K. M. Lawal K. A. Adeniran TECHNICAL REPORT NO. 7 ISBN: 978-978-915-055-7 MAY, 2011 NATIONAL CENTRE FOR HYDROPOWER RESEARCH AND DEVELOPMENT ENERGY COMMISSION OF NIGERIA UNIVERSITY OF ILORIN, ILORIN, NIGERIA
64
Embed
Assessment of Hydroelecric Potentials of Owu and Ero-omola ...
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ASSESSMENT OF HYDROELECTRIC
POTENTIALS AT THE OWU AND ERO-OMOLA
FALLS IN KWARA STATE
B. F. Sule
K. M. Lawal
K. A. Adeniran
TECHNICAL REPORT
NO. 7
ISBN: 978-978-915-055-7
MAY, 2011
NATIONAL CENTRE FOR HYDROPOWER RESEARCH AND DEVELOPMENT
ENERGY COMMISSION OF NIGERIA UNIVERSITY OF ILORIN, ILORIN, NIGERIA
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 2
TABLE OF CONTENTS
1. EXECUTIVE SUMMARY 3
CHAPTER ONE
1.0 Introduction 5
1.1 General Introduction 5
1.2 Sources of Energy 6
1.3 Statement of Problem 6
1.4 Why Small Hydro 7
1.5 Aim of the Study 7
1.6 Objective of the Study 7
1.7 Physical Characteristics and Description of the Study Areas 7
1.8 Demographic Data 8
2. CHAPTER TWO
2.0 Theory of Hydropower Generation 10
2.1 Energy Production 11
2.2 Hydropower System 14
3. CHAPTER THREE
3.0 Study Approach and Technology 14
3.1 Data Collection 14
3.2 Determination of Energy Demand 14
3.3 River Stage Measurement 16
3.4 Measurement of Discharge 16
4. CHAPTER FOUR
4.0 Field Output and Data Analysis 17
4.1 Introduction 17
4.2 Instrumentation Details 17
4.3 Stream Discharge 19
4.4 Development of a Monthly Flood Rating Curve 19
4.5 Extension of Streamflow Data at Ero-omola Fall 23
4.6 Model Development 25
4.7 Determination of the Required Reservoir Capacity 28
4.8 Evaluation of Sediment Load or Sediment transport 29
5. CHAPTER FIVE
5.0 Potential Energy Assessment 31
5.1 Potential Energy Assessment of Ero-omola Fall 31
5.2 Potential Energy Assessment of Owu Fall 33
5.3 Hydropower Power Demand 34
6. CHAPTER SIX
6.0 Financial Justification 35
6.1 Introduction 35
6.2 Engineering Economics 35
6.3 Economics Analysis 35
6.4 Cost of Generation Per Kilowatt 36
6.5 Internal Rate of Return 36
6.6 Amortization Analysis 36
7. APPENDIX 1 40
APPENDIX 2 41
APPENDIX 3 48
APPENDIX 4 49
APPENDIX 5 55
APPENDIX 6 56
APPENDIX 7 57
APPENDIX 8 58
APPENDIX 9 59
APPENDIX 10 60
APPENDIX 11 61
8. REFERENCES 61
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 3
EXECUTIVE SUMMARY
1. General
The study for the assessment of potential hydropower development of Owu and Ero-omola Falls
commenced effectively by 20th
of June, 2009. Various site visits were undertaken to facilitate
gauge installation and hydraulic head survey. Gauge readers were recruited to monitor gauges,
with provision of a motorbike for the gauge reader at Owu Fall, due to long distance of site from
urban centre. Gauge readers were effectively engaged by 26th
of November, 2009 and have since
continued to monitor the gauge till date. Signboards were installed to indicate ownership of the
measuring instrument at both sites. Ero-Omola has recorded about 450 days (15 months) of
records while Owu Fall has about 217 days (7months) of records. The fewer months of records
were due to conflict between the gauges readers employed for the site. Discharge measurement
from both sites were evaluated to generate the discharge rating curves on excel programme and to
establish the minimum and the maximum water level.
2. Discharge Computation Method
There are different methods of determining river discharge. The choice of computation methods
depends upon the equipment and observational method used during the gauging, flow conditions
at the time of gauging, type of stream and the accuracy required. The arithmetic method is
preferred, because it offers sufficient accuracy and quicker to perform than other methods. For
the purpose of this report the Mean Section Method was utilized to evaluate the discharge. The
raw data is presented in the annexure to this report.
3. Hydropower Potential
a. Owu Fall with a hydraulic head of 95.5m has a potential hydro capacity of 8.81MW and annual
generating capacity of 15425.12MWh. The minimum flow available for about 100% of the time
from the flow duration curve is estimated at 9.9m3/s. Therefore a single pelton turbine is
recommended. The total amount of energy so generated can be sold to National grid is estimated
at N216,091,680.00 at N14.00/kWh. The internal rate of return was however negative. Owu Fall
has a difficult terrain with relatively low runoff but consistent runoff yield. It is therefore suitable
for only runoff river system as it is practically difficult to impound water behind the Fall. More so
the distance to the 33kva National Grid at Omu Aran is about 189km, while that of Ero-Omola is
just 48km.
b. Ero-Omola Fall with an averages discharge of 22.8m3/s and a hydraulic head of 59.4m has a
potential hydropower capacity of 8.64MW. The 100% flow rate from Ero-Omola may be
bifurcated by 3 unit draft tube into the turbines at 7m3/s each. The total annual energy was
estimated at 15137.28MWh at an economics cost of N211,921,820.00/annum using the NIPP
multi-year tariff order of N14.00/Kwh. The total amount derivable from the power generation
excluding other charges amount to about N213million with an internal rate of return (IRR) of
18.00%. This IRR although lower than the prevailing interest rate of 21% is still acceptable on the
premise that, the present commercial interest rate in Nigeria is relatively high. Ero-Omola water
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 4
year is between April to March with a two to three month break of hydrological cycle. It is
therefore necessary to provide a reservoir, sufficient enough to regulate flow for the turbines and
to provide domestic and irrigation water supply to the host communities downstream. This off
course is an additional cost to the investor. The benefit/cost ratio is however encouraging.
4. Constraints
The Centre must collaborate with State Government to see that the only access roads to Owu Fall
are rehabilitated. The deplorable condition of the road makes it un-passable during the rainy
season and make site visit difficult. The present security situation of Owu site does not encourage
installations of expensive instrument for now, due to constant vandalization, removal or theft.
5. Financial Positions
The total budgetary provision for the two sites would have been draw down completely by the end
of April 2011. It is therefore important to provide fund for the salary and wages of the gauge
readers beginning from May 2011. The budgetary provision for the two site is estimated at
N650,000.00 each, bringing the total sum required annually to about N1,300,000.00(this includes
salary and wages of gauge readers, fuelling of motorbikes, instrument maintenance, site visits
etc.). This request becomes necessary if the centre is to continue to sustain continuous and
uninterrupted data acquisition of both sites.
6. Recommendations
a. The next phase of this study is to provide detail topography of the site and to locate position of
power house, fore bay, penstocks with detail engineering drawing and subject the overall cost to
economic analysis.
b. Thereafter this report will be publicly presented to provide the necessary information to investors
to appraise and executes the project.
c. An automatic data logger should be provided at Ero-omola. This is to minimize research cost and
expenditure on data acquisition. Self-recording gauges that maintain a continuous record of stage
are based on various types of sensors. The three most commonly used types of sensors are float-
driven, pressure, and ultrasonic. In a typical installation of a float-driven, water-level sensor, the
vertical movement of a float in a stilling basin, resulting from fluctuations in water level, is
translated by a mechanical movement or an electronic signal. Ultrasonic sensors use acoustic
pulses to sense water levels either by contact or noncontact methods. Stage-discharge relations
may have to be periodically updated due to changes in the hydraulic characteristics of a stream
reach over time, caused by erosion and sedimentation, bank vegetation, and other changes. It is
therefore extremely important to make provision for continuous regular site visits, whenever the
need arises.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 5
CHAPTER ONE
1.0 INTRODUCTION
1.1 General Introduction
Power is a very important infrastructural development of a nation. It is widely believed that
an appropriate level of energy generation has always gone hand in hand with industrialization
and economic development. Similarly a functional energy generation system often serves as
an effective tool for National Economic Development. The need for comprehensive studies of
hydropower operation of large water resources system is increasing at rapid pace because of
the increasing interest in all facets of resources use and management. Complexity of water
resource planning, design and operations studies, demand for a mathematical procedure that
will select the optimum sizes and characteristics of components to produce a desired result.
Many failures of water related projects are due to project planning on the basis of inadequate
hydrological data, due in part to two factors:
a. Data which are not accurately measured
b. Too short time series of hydrological data not allowing reliable estimates of system
performance
In the later case some scientist suggests the postponement of the project until more reliable and
accurate data are available. Although this suggestion is theoretically sound, it however lacks the
requirement and needs of engineering practice. A better way to solving the problem may be the
use of hydrological data from synoptic station within the same catchment which in combination
with available hydrological data may improve the planning results. This is the basis of the
stochastic theory approach utilized to extend flood data. The purpose of this research is to
demonstrate the value of such deficit data in the optimization process of hydropower
development. Inadequate hydrological data may lead to over or under design of the power plant.
Stochastic theory is applied in order to minimize the risk of such uncertainties. The stochastic
theory provides opportunity to forecast and extend short duration data in a planning process.
In this context we have to distinguish between two types of hydrological uncertainty.
a. The natural uncertainty due to random variation of hydro meteorological processes;
b. If hydro-power project are planned and designed on the basis of rather short time series of
observed hydrological data the danger of inaccurate solutions is high.
1.2 Sources of Energy
The three most important sources, which have become common and therefore referred to as
conventional, are:
(i) Thermal power (ii) Hydro-power (iii) Nuclear power
The other sources of power generation are also valuable but the quantum of power produced
by these sources is limited. Such other sources are: (i) Tidal power (ii) Solar energy (iii)
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 6
Geo-thermal energy (iv) Wind power (v) Magneto-hydro-dynamic plants and (VI) Biomass
Energy
The focus of this research was limited to design of potentials hydropower generation only.
Table 1.1, 1.2 and shows the status of hydropower generation and Electricity demand
Scenarios in Nigeria.
Table 1.1: Status of Hydropower Generation in Nigeria (Install Capacity)
Fresh water supplies, energy and environmental preservation are three of the most pressing
issues facing humanity. In Nigeria poor planning and under investment had created a huge
generation and supply deficit over time, despite improved routine maintenance for the
existing hydro infrastructures. There is a heavy reliance on public electricity supply while
demand for electricity keeps outstripping supply. The response to address irregular public
power generation and transmission failure was the importation of various brands of gasoline
generators into the country to augment supply, it is however obvious that a new approach and
fresh initiatives to development of energy producing resources and the implementation of
developmental plans has to be accelerated, if vision 2020 target is to be met.
1.4 Why Small Hydro
Hydroelectricity enjoys several advantages over most other sources of electrical power. These
include high levels of reliability, proven technology, high efficiency, very low operating and
maintenance cost, and the ability to easily adjust to load fluctuations. Hydropower project
often provide flood control and recreational benefits. Hydropower does not produce waste
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 7
products that contribute to air quality problems, acid rain, and green house gases; it is a
renewable resource that minimizes the use of other fuels (oil, gas and coal).
Poverty in Nigeria is associated with high unemployment, poor governance, corruption, lack
of accountability, and gross violation of human rights, nepotism and a skewed income
inordinate distribution. Additional factors include poor infrastructure and impaired access to
productive and financial assets by women and vulnerable groups. In the framework of the
Millennium Development Goals Report, the latest estimates revealed that over 70% of the
population lives below the International income poverty line of $1 a day. (World Bank, 2007)
A common belief is that guaranteeing a sustainable supply of affordable energy is one of the
best ways to address poverty, inequality and environmental degradation everywhere on the
planet. However, energy cannot be affordable unless its production and availability are
sustainable. Increasingly, energy sustainability amongst others also means: connecting the
entire urban and rural poor to reliable, sustainable economical sources of energy. This way we
can guarantee improved living standard for a better quality of life. (World Bank, 2007)
It is in response to these challenges, that the study was initiated
1.5 Aim of the Study
The main purpose of this study is to establish, explore and optimize the hydropower potentials
of Owu and Ero-omola Falls for the use of the rural communities.
1.6 Objectives of the Study
In achieving the main aim stated above, the following objectives are covered.
a. Installation of hydrologic instruments for data collection.
b. Collection of hydrologic data and topographical maps of the two sites and adjoining
catchments.
c. Rainfall and run-off data studies.
d. Development of flood duration curve.
e. Estimation of energy generation potential with the runoff.
f. Determination of potential hydropower generation capacity of Owu Falls.
g. Economic analysis and financial assessment of both hydropower projects.
1.7 Physical Characteristics and Description of the study Areas:
Owu Fall is located at Owa Kajola in Ifelodun LGA of Kwara State near Oro-Ago about
127km from Ilorin, the state capital (figure 1 shows the LGAs of Kwara State). The run-off is
perennial from a hill of about 95.5 m high. Owu Fall lies between Latitude North N08 20 ׳
23.2״ and N08° 2023.1 ׳
״ and between Longitude East E005° 08
׳ 34.8
״and E005° 08
׳34.7
״.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 8
The rainfall is moderate with general annual average of about 1,250mm with maximum
rainfall occurring in the months of June and August and a low humidity of about 50%. The
Ero-Omola Fall is located along Osi- Isolo-Ajuba Road off Osi-Idofin road in Ekiti LGA,
(Araromi-Opin) about 116 km from Ilorin. The runoff is perennial and of higher unit
discharge than Owu-Falls. The height of the Fall is about 59.4m high. The catchment area of
Ero-omola Fall is about 45km2 with contribution from two rivers namely, Ero-river from
Iddo- Faboro near Ifaki in Ekiti state and Odo-Otun from Ajuba itself. Ero-Omola Falls lies
between Latitude North N08° 09 ׳34.6
״and N08°09
׳ 30.8
״ and between Longitude East E005°
14 ׳07.4
״ and E005° 14
׳ 06.7
״.
1.8 Demographic Data
Population is a major driver of energy demand. The most important determinant of energy
demand is the level of economic activity and its structure, measured by the Gross Domestic
Product (GDP). The evolution of the GDP was guided by the projections assumed in the
National Economic Empowerment and Development Strategy (NEEDS). The local
government areas within the catchment areas of the proposed project are listed in Table 1.4
along with other LGAs in Kwara State.
Table 1.3: Population of Kwara State (NPC, 2006)
LGAs MALES FEMALES POPULATION
Baruten
Kaiama
Moro
Edu
Pategi
*Ifelodun
Ilorin South
Ilorin East
Ilorin West
Asa
Oyun
Offa
*Irepodun
*Isin
*Oke-Ero
*Ekiti
Total
*Study Areas
108153
68240
55630
104944
62639
106056
104504
104402
181875
64982
48601
46266
75539
30833
29515
28402
1220581
101306
55924
53162
96525
49678
99986
104187
99908
182791
61453
45652
43408
73071
28905
28104
26448
1150508
209459
124164
108792
201469
112317
206042
208691
204310
364666
126435
94253
89674
148610
59738
57619
54850
2371089
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 9
Fig. 1:Map of Kwara State showing Local Government Areas. Owu and Ero-Omola Falls are located
in Ifelodun and Ekiti LGAs.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 10
CHAPTER TWO
2.0 THEORY OF POWER GENERATION
2.1 Energy Production
Hydroelectric power production from a given reservoir at any time, t depends on the installed
capacity of the turbine (generators), turbine release, generating head, the number of hours of
power generation in a period, the plant factor, the efficiency of the turbine. In hydropower,
the potential energy of the Falling water is converted to mechanical energy which is used in
rotating the turbine.
The Potential energy is given as: (Loucks et al, 1981).
PE= mgh (2.1)
where m =is the mass of the Falling water
g =is the acceleration due to gravity
h =is the Falling head
A cubic meter of water, weighing 103 kg, accelerating at a rate of 9.81m/s
2 over a distance of
one meter, results in 9.81 x 103 joules (Newton-meter) of work. The work done in one second
equals (joules per second) is of power produced in watts. Hence an average flow of tqˆ (m3/s)
Falling a height of Ht (m) in period t yields 9.81 x 103 tqˆ Ht watts or 9.81 tqˆ Ht Kilowatts.
Multiplying by the number of hours in period t yields the kilowatt-hours of energy produced
from an average flow of tqˆ in period t. The total kilowatt-hours of energy KWHt produced in
period t, assuming 100% efficiency is (Sharma, 1979)
E=KWHt =9.81 qˆ H(seconds in period t) (2.2)
3.6 x 103
Since the total flow qt in period t, in units of 106 m
3, equals the average flow rate tqˆ (m
3/s)
times the number of seconds in the period divided by 106, the total kilowatt-hours of energy
produced in period t given a plant efficiency of e is equals
E = KWHt = 2730qtHt (2.3)
Equation (2.3) implies that the kilowatt-hours of energy KWHt produced in period t, are
proportional to the product of the plant efficiency, the productive storage head Ht and the
flow qt through the turbine. The amount of electrical energy produced also depends on the
installed kilowatts of plant capacity P as well as on the plant factor Ft. The plant factor is a
measure of hydroelectric power plant use and is usually dictated by the characteristics of the
power system supply and demand.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 11
The plant factor F is given as: Ft =Average load on the plan(2.4)
Installed plant capacity
The plant factor accounts for the variability in the flow rate during each period t and this
variability is pre specified by those responsible for energy production and distribution. It may
or may not vary for different period’s t. The total energy produced cannot exceed the product
of the plant factor Ft, the number of hours in the period ht and the plant capacity P, measured
in kilowatts.
KWH = ft ht P (2.5)
FIRM ENERGY = Pdesign x x 24 x 365 kWh (2.6)
= 0.2 (A reduction factor due to streamflow fluctuations)
2.2 Hydropower system.
2.2.1 The major types of hydroelectric power development are (Sharma, 1979):
a. Run-of river development
The runoff river plant are such plant that do not substantially alter the flow regime of the
river, this implies that the river is not diverted materially away from its natural course, since
no impoundment is envisaged.
b. Pondage development (Dam toe based)
Pondage developments are reservoirs developed to provides uninterrupted or balance inflow
for day to day fluctuations in the amount of inflow available for power productions. Most
often the power plant is located at the dam toe.
c. Storage development is similar to pondage development as described above.
d. Regulating development (canal Fall based)
This are the hydropower plant fed through a regulated outlet from the reservoir.
e. Pumped storage development (diversion)
The pumped storage plant as the name implies are those plants whose inflow for power
generation is augmented through a system of pumping unit.
Regulating development is proposed at Ero-omola Fall, while Owu Fall is suitable for Runoff
River plant. The proposed typical schematic design diagram for the two sites is as shown in
Figure 2.1 and 2.2: The major components in the scheme are:
a) Gross head (H). The gross head is the difference of the water level in the head race and the
water level in the tail race.( for a run-off river plant)
b) Net Head (h). The net head (or effective head) is the head available for the turbine. It is equal
to the difference of total head at the point of entry and at the point of exit of the turbine.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 12
i. For a pelton wheel or impulse turbine,
h=H –Z –hf (2.7)
Where:
H =gross head (m)
Z= is the height of the pelton wheel exit above the tail race level and hf= is the loss of
head in the penstock.
ii. For a reaction turbine. h=H-(Vd)2
- hf(2.8)
2g-
Where Vd = is the exit velocity and other terms are as defined above.
c) Operating Head. The operating head is equal to the difference of the
water level in the forebay (or foreway) and that in the tail race.
FIGURE 2.1: OWU FALL
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 13
FIGURE 2.2: ERO-OMOLA FALL
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 14
CHAPTER THREE
3.0 STUDY APPROACH AND METHODOLOGY
3.1 Data Collection
Topographical map, Stream flow, hydraulic head and pipeline length must be estimated or
measured, before one can calculate the power that could be developed from a stream. Stream
flow is the most difficult to measure or estimate. Understanding of its sources, its fluctuations
and flow measurements is important.
3.2 Determination of Energy Demand
A constant monthly energy demand is defined from an assumed installed capacity and chosen
plant factor. The monthly energy demand as follows:
FE (t) = IC * n hours * PF(t) (3.1)
Where FE (t) is the target monthly firm energy demand (MWh) and other variables are
previously defined.
IC=installed capacity MW
N =no of operating hours
PF=Plant factor
Monthly firm energy demand was computed from the above equation: Owu Fall with installed
capacity of 8.81MW over assumed 8 hours of operation and plant factor of 0.25 is estimated
at 17.62MWh or 211.14MWh/annum, while Ero-omola Fall with installed capacity of
19.93MW over an assumed 8 hours of operations and plant factor of 0.25 is estimated at
39.86MWh or 478.32MWh/annum.
a) Population Estimate
Population is a major driver of energy demand. From the demographic data, the projected
population figure was deployed in the estimation of energy demand of the communities.
The project catchment areas comprises of about five local government areas namely;
Ekiti,Oke-ero, Isin, Irepodun, and Ifelodun LGAs with a combined population of 526,859
by the 2006 population census. This is projected to 2036 at a National population growth
rate of 2.83% and in consideration of 25 years life span of the proposed project. The
projection was achieved with the relation:
Pn =Po (1 + r)n (3.2)
526,859 X (1.0283)25
= 1,058,499
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 15
b.) Electricity Demand per Capital
The electricity demand per capital of 321.59Kwh published by Energy Commission
of Nigeria (2006) was adopted for this study.
c.) Peak Domestic Electric Load demand
Using the annual electric energy demand, load factor of 0.75, transmission and
distribution losses; approximate estimates of the peak load demand was obtained. The
highest growth scenarios gives a peak demand 0f 3157MW.(NERC, 2009)
d.) Projected Electricity Demand
In accordance with the National Energy Policy (2003), access to electricity by
household is expected to increase to 75% by year 2020 for urban centre while that of
rural was put at 55%. This study assumed an average projected electricity demand of
the community to grow by about 55% due to development of many small agro
businesses within the project area.
3.3 River Stage Measurement
The river stage is the height of the water surface above the mean sea level (msl). For
convenience, the datum was arbitrarily selected at the lowest point on the river bed. The river
stage was measured to compute the cross-sectional area of the river so that the discharge can
be determined using the OTT current metre obtained from Lower Niger River basin
Development Authority.
3.4 Measurement of Discharge
A river discharge is the rate at which water flows through a cross section and is expressed as
volume per unit time.
The following methods are commonly used for the measurement of discharge in a river.
1. Area-velocity method 2. Slope-area method
3. Salt-concentration 4. Moving-boat method
5. Electromagnetic and ultrasonic 6. Indirect methods
A relationship between stage and discharge is required to convert stage measurements to flow
rates. Measurements of head were converted to flow rates. In this report the velocity-area
method was used for measuring the discharge of both sites.
3.4.1 In this method, the discharge is determined from the area of cross section and the mean
velocity. The area of cross section of the stream is determined from the profile of the stream
bed obtained by survey.(Appendix 1) The river cross section was divided in to a suitable
number of vertical segments (or strips).About 10 segments were taken in the case of Owu,
while Ero-omola had about 15 segments. The total discharge in the river is the total sum of
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 16
various segments. The discharge in each segment is equal to the area of the segment
multiplied by the mean velocity of flow. The mean section method was used to estimate the
discharge, in this method; the segment is taken between two vertical lines on which the
velocity and depth are measured. The velocity in the segment is taken as the average of the
mean velocities V1and V2 determined at the two adjacent verticals. Similarly the depth is also
taken as the average of two depth d1and d2. Thus the discharge in the segment is given by
∆𝑄 = 𝑏 𝑑1+ 𝑑2
2
𝑉1+ 𝑉2
2 (3.3)
𝑇𝑜𝑡𝑎𝑙𝑑𝑖𝑠𝑐ℎ𝑎𝑟𝑔𝑒 𝑄 = 𝑄 (3.4)
3.4.2 Determination of Velocity (V): For the measurement of discharge, the mean velocity (V) is
required at various vertical lines as stated above. The following methods were used for the
sites.
1. Floats Method
2. Current Meter Method
both float and current metre method was undertaken on the field for accuracy checks.
a.) Floats method: In this method, a straight and uniform reach of the river was selected for the
float to travel. The time t taken by a float to travel a certain distance L is measured. There are three types of floats commonly used in practice. (i) Surface floats, (ii) Double floats (iii) Velocity rods. The
study adopted surface floats. The surface floats are generally made of wood (or any other light
material) so that they can float. Wooden discs of 7 – 15 cm diameters were used. As the surface floats travel at the water surface, they give the surface velocity. The mean velocity is usually taken as 0.85
times the surface velocity.
b.) Current Meter
A current meter is generally used for the measurement of velocity in a river. The current
meters are basically of two types.
(ii). Cup-type current meter (iii). Propeller-type current meter.
The accuracy of the cup-type current meter is about 0.3% for the velocity greater than 1 m/s. The
main disadvantage of a cup-type current meter is that its accuracy is low when there is an
appreciable vertical component of the velocity.
The basic principle of both types of current meters is the same; namely, when a current meter is
inserted in flowing water, there is an unbalanced drag on the rotating element (cup or propeller) which
starts rotating. As the velocity increases, the speed of rotation increases. The current meter is calibrated to give the velocity corresponding to different speeds of rotation. Manufacturers also
provide the calibration chart which gives the relationship between the velocity and the number of
revolutions per second. Generally, it follows a linear relationship,
𝑣 = 𝑎𝑁 + 𝑏 (3.5)
where v is the velocity at the instrument location, N is the number of revolutions per second, and a
and b are the constants of meter obtained by calibration. These constants are determined by towing the
instrument in a towing tank in the laboratory. The current meter gives the velocity (v) at a point. For
determination of the discharge in the river, the mean velocity (V) along a vertical line is required.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 17
CHAPTER FOUR
4.0 FIELD WORK OUTPUT AND DATA ANALYSIS
4.1 Introduction
Several visits were undertaken by the research team to Ero-omola and Owu Falls project
between September 2009 and March 2011. The purpose of the visit was to obtain stage-
discharge relation and preliminary peak discharge data for the two sites. Stream flow
measurement were undertaken to determine the extent and dependability of the flow. 2 Nos.
metric steel gauges were installed at the bottom of Fall at Owu and Ero-omola site as well.
Table 4.1: Details of Gauge at Owu and Ero-omola Falls
1. Item Owu Fall Ero-omola Fall
2. Purpose River Stage River Stage
3. Type Self illuminated steel gauge Self illuminated steel gauge
4. Station Bench
Mark
+455.51m +451.60m
5. Datum Nigeria Ordinance Datum/Universal Traverse
Mercator (UTM)
Nigeria Ordinance Datum/Universal Traverse
Mercator (UTM)
6. Gauge
Elevation(m)
+480.7m +449.996m
7. Water level
(m)
+426.2m +449.8m
8. Gauge Height
(m)
3 4
9. Location N080 20’ 40’’ and E05
0 08’ 56’’ N08
0 09’ 48’’ and E05
0 13’ 09’’
10 Date
Established
12th September 2009 11
th September 2009
4.2 Instrumentation Details
An OTT current metre obtained from the Lower Niger River Basin Development Authority
was deployed for the streamflow measurement. The instrument specification is as indicated
below:
Type: Propeller Current Metres (OTT-C31-BAREL 17929)
Propeller Diameter: 125mm
Impulse: 1
Error: +/- 0.25
The calibration equation of the instrument is given as;
V = 0.2483 n +0.011 for n=< 0.59 where n revolution per seconds
V = 0.2619 n + 0.003 for n= < 9.21
Discharge measurement trials were carried out with the instrument on both sites to determine its level
of accuracy. The float method was equally carried out as a check on the calibrated instrument. The
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 18
float method involves the use of floating material moving under the drag of the river flow, so as to
evaluate or compute the speed or velocity of the river-flow. The float method trials result at Ero-
Omola Fall is as indicated in Table 4.2.The float method was carried out over a uniform distance of
5m along the stream. Stop watch was used to determine the time of travel of the float along the
stream. The computation of the discharge is as follows:
T=Time lapse (in seconds)
Velocity =Distance (L)/Time
Discharge=Area x Velocity
Table 4.2: Discharge computation of float method Trials at Ero-omola Fall from 21-26th October
The time travel by the float along subdivision of 5m segment on the stream was determined with a
stop watch. The total discharge of 35.084m3/s was obtained during the trials. Similar trials were also
carried out with the current metre. The trials result is as indicated in Table 4.3
Table 4.3: Result of Current Metre Trials at Ero-omola Fall
Date 18/10/2009 19/10/2009 20/10/2009 21/10/2009 22/10/2009
Water level(m) 1.98 1.98 1.95 1.89 1.87
Discharge 48.79 48.60 47.31 41.75 35.4
Similar trials carried out at Owu Fall are indicated in Table 4.4 and 4.5 respectively.
Table 4.4: Results of trial of float method at Owu Fall from11
th-15
th November 2009
Distance(m) 3 3 3 3 3 3
Segment Area
(m2)
6.8 6.8 6.4 5.35 6.8 6.5
T(Time)(S) 12.13 11.97 7.60 5.53 12.00 24.9
V(m/s) 0.25 0.25 0.39 0.54 0.25 0.12
Q(m3/s 1.70 1.70 2.50 2.89 1.70 0.78 11.27
Total Discharge = 11.27m3/s (November Peak)
Table 4.5Result of Current Metre Trials at Owu Fall
Date 11/9/2009 12/9/2009 13/9/2009 14/9/2009 15/9/2009
Water level(m) 0.98 0.97 0.95 0.92 0.89
Discharge 11.02 10.88 10.58 10.14 9.703
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 19
Subsequent discharge measurements were carried out each month in order to have a relatively spread
of the flood discharge throughout the year. The rating curve equations were developed from the discharge so obtained each month.
4.3 Stream Discharge
Subsequent discharge measurement at Ero-Omola and Owu Falls were computed on the bases of
arithmetic method using the current meter measurements provided. The horizontal distance across the
stream was measured from the edge of the water at one bank. Depths were measured from the water surface.
The cross-section at Owu Fallis shown in Figure 4.1, with the location of each of the current meter measurements of point velocity. The Qi for each of the ten 1.0-m wide flow subareas are estimated
and summed to obtain the total flow. The cross-section area Ai for each subarea is estimated as depth
multiplied by 1-m width. The mean velocity in each subarea is estimated as the average of the flows at measured depth. The measured value is as indicated in Table 4.6
Table 4.6: Result of discharge measurement carried out at Owu Fall
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 33
Annual Firm Energy = 8.64 x 24 x 365x 0.2 = 15137.28MWh (Analytical)
Also from the Power Duration Curve in Figure 5.2 the firm energy or plant capacity at 100% of time
is computed as 12794.9976kw or 12.794MW
Annual Firm Energy =12.794 x 0.68 x 24 x 365 x 0.2=15242.26MWh.(Graphical)
Using the new NIPP, Multi Year Tariff Order (MYTO) of Nigeria Regulatory Energy Commission
(Appendix 9) of N14.00/kWh. The total cost of bulk energy, excluding other charges is estimated at
15137280Kwh x N14.00/kWh = N211,921,920/Annum
5.2 Potential Energy Assessment of Owu Fall
The streamflow discharge data (Appendix 5) generated from the rating equation at owu was utilized to
develop the Flow Duration Curve (FDC) as well as Power Duration Curve (PDC). The minimum flow
available for 100% of the time from the FDC/PDC curve(Figure 5.3 and 5.4) amount to 9.9m3/s over
an hydraulic head of 95.5m. The computational procedures is shown in Table 5.2
Hydropower potentials for Owu Fall= 95.5m x 9.9m3/s x 9.81 x 0.95 = 8,811.12 kW or 8.81 MW
(with 95% efficiency plans).
Annual Firm Energy =8.81MW x 24 x 365 x 0.2 = 15435.12MWh
Using the NIPP tariff order of N14.00/Kwh. Annual energy generated is estimated at
N216,091,680.00/Annum.
Table 5.2 : Owu FDC/PDC Computation
No. Year Flow(m3/s
Flow in Ascending Order
Power=9.8 x 59.4 x F(kw)
% of time of availability
N +1 -n %
N
1 JANUARY 4.1856 10.955
3917.3133 100
2 FEBRUARY
0 91.667
3 MARCH
3.6371 10.342
3403.958 83.333
4 APRIL
3.6414 10.237
3407.9883
5 MAY
3.8497 4.1856
3602.9737 66.667 6 JUNE
3.5605 4.1856
3332.2596 58.333
7 JULY
0
8 AUGUST 10.237 3.8497
9580.4755 41.667 9 SEPTEMBER 4.1856 3.6414
3917.3133 33.333
10 OCTOBER
0
11 NOVEMBER 10.955 3.6371
10252.694 16.667
12 DECEMBER 10.342 3.5605
9679.3501 8.3333
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 34
Figure 5.3: Owu Flow Duration Curve
Figure 5.4:Owu Fall Power Duration Curve
5.3 Hydropower Water Demand
From the flow duration curve(Ero-omola) the peak hydropower demand was estimated at 21.80m3/s,
hence 7m3/s is expected to be drafted by draft tube into bifurcated penstocks making a total of 7 x 24
x 3600 x 365 =220.752 MCM or 662.256mcm for the three turbines annually.
The storage capacity required to meet the peak hydropower demand of 21.80m3/s throughout the year
is given thus;
Yearly demand = 31.536 x 21.80 = 687.48mcm
0
2
4
6
8
10
12
14
0 20 40 60 80 100 120
FLO
W (
Qm
3/S)
PERCENTAGE OF EXCEDENCE
OWU FLOW DURATION CURVE
0
2000
4000
6000
8000
10000
12000
0 20 40 60 80 100 120
PO
WER
(kw
)
PERCENTAGE OF EXCEEDENCE
OWU POWER DURATION CURVE
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 35
CHAPTER SIX
6.0 FINANCIAL JUSTIFICATION
6.1 Introduction
Economic feasibility and optimality represent just one of many considerations in the decision-
making process. However, economic analysis does play an important central role in decision-
making at many levels, in various settings. Economic evaluation of hydropower development
plans combines basic methods of engineering economics with benefit estimation procedures.
Analyses of economic costs and benefits provide important information for use, along with
various other forms of information, in making a myriad of decisions in planning, design,
operations, and other water resources engineering activities. (Printinger, 1972)
The economic objectives for comparing alternative plans may be in either of the following alternative forms:
Maximize net benefits, which are benefits less costs
Minimize cost required to provide a specified level of service
Maximize benefits derived from fixed resources.
In this study, both benefits and costs are relevant and are included in the analysis.
6.2 Engineering Economics
Engineering economics is a set of principles applied in comparing alternative plans to
determine the economically optimal design. Equivalence of kind and equivalence of time are
required so that all relevant costs and benefits of each alternative are comparable.
Equivalence of kind is achieved by expressing all benefits and costs included in the analysis
in both local and foreign currencies. Equivalence of time is achieved through discounting
techniques using compound interest formulas. Having a Naira today is worth more than
obtaining a Naira at some future time, because the Naira in hand today can be invested to
accrue interest.
6.3 Economic Analysis
Benefits and costs associated with water projects occur at various times, Initial investment
costs occurring at the beginning of the project life are associated with construction or
implementation. Operation and maintenance costs continue throughout the life of the project.
Major replacement and rehabilitation costs may occur periodically. Benefits typically accrue
over long periods of time. Time streams of benefits and costs may be converted to other
equivalent cash flows for purposes of comparison using discounting formulas, with a special
fixed discount rate. The discount rate is often linked to the concept of marginal internal rate of
return in National Integrated Power Project or National Independent Power Project industry.
If funds were committed to the project yielding the highest return first, and then to subsequent
projects in order of rate of return, the rate of return of the last project selected before funds
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 36
ran out would be the marginal internal rate of return. The discount rate used by the National
Economic Planning Department is based on the market interest rate for risk free investment,
with the limitation that the rate may not be changed too rapidly. The financial analysis in this
study shall be limited to only Ero Omola project due to its obvious advantage of Owu Fall
Project.
6.4 Hydro Power Generation Benefit
The entire benefit envisaged from this project is generation of Hydro-power electricity. The
peak power generation contemplated of the project is 8638.15kw or 8.64 MW. This power
would be utilized for electrifying five LGAs town and neighboring villages.
The total capability of hydropower generation (number of Kilowatt hour units) in a year of
90% dependability would be 15137.28MWh. With 70% load factor, the total units generated
would be 0.7 x 15137.28 = 10596.096MWh.
6.5 Cost of generation per Kilowatt
The total cost of the project, except for the equivalent cost of 48 Km. long 133 KVA High Tension
Transmission line, equipments & distribution system, which is entirely for power generation works
out to 1809 million Naira. (Abstractive Cost) With the above investment, the installed capacity to be
provided is 8638.15kw; hence the cost per kW installed capacity works out to N209,419.84\kW
6.6 Internal Rate Return.
Internal rate of return is that discount rate that makes the net present value of a net benefit or
cash flow equal zero or is the maximum interest rate that a project could pay on invested
capital, if the project is to recover its investments and operating costs and still break even. It
could also be defined as the rate of return on capital outstanding per period while it is invested
in the project.
6.6.1 Assumptions:
Reservoir capital costs are given as input data and their operation and maintenance costs are
expressed as a fraction of their capital costs. Power house, penstock and forebay costs are
based on maximum draft tubes flow. Operation and maintenance costs are a fraction of this
value. Power and imported turbines spare parts costs are determined from abstractive market
value. Present worth is obtained from the actual cost (sum of the costs of actual Capital,
operation and maintenance, power, imported turbines parts, and deficit minus the
hydroelectric power benefits). The cost abstract is presented in Table 6.1.
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 37
TABLE – 6.1: Consolidated Abstract of Cost
S.No Unit Description Cost in Millions(N)
1. Unit – I Civil Works 109
2. Unit – II Electrical Works 483
3. Unit – III Compensation and Honourariums 450
4. Unit – IV Design and Construction 568
5. Unit-V Operation and Maintenance 199
Total 1809
The preliminary cost of development of Ero-omola Fall is estimated at N1,809,000,000.00 which
include the Headworks, Civil, Electrical and the mechanical component. Using the current Central
Bank of Nigeria annual interest rate of 21% at a repayment period of 25years. The Internal Rate of
Return was interpolated between 16% and 20% to guess the true Rate of Return. The details
computational procedure is indicated in Table 6.2.
𝐷𝑖𝑠𝑐𝑜𝑢𝑛𝑡 𝐹𝑎𝑐𝑡𝑜𝑟 = (1+𝑖)𝑁− 1
𝑖(1+𝑖)𝑁 = =
(1+0.16)− 1
0.16(1+0.16) =0.8620 (i=16%)
= (1+0.20)− 1
0.20(1+0.20) =0.833 (i=20%) =
(1+0.21)− 1
0.21(1+0.21) =0.8264 (i=21%)
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 38
TABLE 6.2: COMPUTATION OF INTERNAL RATE OF RETURN FROM CASH FLOW (ABSTRACTIVE COST)
METHOD:INTERPOLATION METHOD
YEAR CAPITAL O & M (N)*M GROSS(N)M VALUE OF INCREMENTAL 16%D.F 16% PW 20% D.F 20% PW
COMPONENT(N)M
INCREMENTAL NET
GROSS BENEFIT
BENEFIT(N)M CASH
FLOW(N)M
1 1.09
0
1.09
-1.09
0.862 -0.94 0.833 -0.91
2 4.83
0
4.83
-4.83
0.743 -3.59 0.694 -3.35
3 5.68
0
5.68
-5.68
0.641 -3.64 0.579 -3.29
4 4.5
0
4.5
-4.5
0.552 -2.48 0.482 -2.17
5 1.99
0
1.99
-1.99
0.476 -0.95 0.402 -0.8
6 0
0.67
0.67
1
0.41 0.41 0.335 0.34
7 0
0.97
0.97
2.37
0.354 0.84 0.279 0.66
8 0
1.3
1.3
3.7
0.305 1.13 0.233 0.86
9 0
1.62
1.62
5.06
0.263 1.33 0.194 0.98
10 0
1.95
1.95
6.43
1.57 10.1 0.948 6.1
TOTAL 18.09 6.51 24.6 0.47 6.176 2.21 4.979 -1.58
(*M=million)
Interpolation Procedures: Internal Rate of Return= Lower Discount rate +Difference Between the Discount rate x Ratio of Present Worth of Incremental benefit cash flow at Lower Discount Rate
and Sum of the Incremental Net Benefit Stream Cash flow of the two Discount rate (when the signs are ignored)
Present Worth of Benefit @ 16% = 2.21 Million Present Worth of Benefit @ 20% = 1.58 Million
The Sum of the Streams at the two Discount rates Ignoring the signs=2.21+1.58=3.79
INTERNAL RATE OF RETURN =16 (4)2.21/3.79=16 + 4(0.58) = 18.62 OR 18%
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 39
The internal rate return of 18% with an abstractive cash flow analysis suggests a promising profit
outlook. Accurate Internal Rate of Return will be achieved when both structural and non-structural
design of all hydropower components is completed and the true Bill of Engineering Measurement and
Evaluation is incorporated in the Economic Analysis. The amortization of various hydropower
components at the prevailing interest rate of 21% is computed below:
6.7 Amortization Analysis
The projected hydropower cash flow is presented in Appendix 11. The cash flow indicates that Ero-
omola project is expected to grow by 5% profit beginning from year 2015. The total Kilo Watt Hour
units available annually at 90% dependability excluding Power-Station requirement is 15137.28
MWh. Taking the estimated life span of electrical works (generation), civil, operation and
maintenance and other works as 25 years. Amortization of various component of hydropower project
outlined above was computed in consideration of prevailing interest rate of 21%. The discount factor
computed at 21% interest rate is presented thus:
𝐴 = 𝐹 𝑖
(1+𝑖)𝑁− 1 = 𝐴 = 𝐹
0.21
(1+0.21)25− 1 =0.0018 (when n=25years)
1. Amortization Cost Amount(N)
(a) Electrical Works (21% Interest, 25 yrs. life)
a) (b) Civil Works. (21% Interest, 25 yrs. life)
(c) Design and Construction
(d) Compensation and Honourariums
(a) (e)Operation and Maintenance(1.5% of Total Cost)
Total
= 0.0018 x 1090000 = N1,962.00
= 0.0018 x 4830000 = N8,694.00
= 0.0018 x 5680000 =N10,224.00
= 0.0018 x 4500000 =N8,100.00
= 0.015 x 1990000 =N29,850.00
= N58,830.00
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 40
APPENDIX 1:
CROSS-SECTION OF
ERO-OMOLA STREAM
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 41
APPENDIX 2
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 42
Streamflow Discharge Computation with Current Metre (Arithmetic Method)
The calibration equation of the instrument is given as;
V = 0.2483 n +0.011 for n=< 0.59 where n revolution per seconds
V = 0.2619 n + 0.003 for n= < 9.21
Segment 1
𝑛 = 𝑟𝑒𝑣𝑜𝑙𝑢𝑡𝑖𝑜𝑛
𝑡𝑖𝑚𝑒
= 5
40 = 0.125
𝑣1 = 0.2483 × 𝑛 + 0.011
= 0.2483 × 0.125 + 0.011 = 0.034𝑚𝑙𝑠.
𝐴1 = 12 𝑏𝑑
= 12 × 3 × 0.95
= 1.43𝑚3
𝑞1 = 𝑣1𝐴1
= 0.03 × 1.43
= 0.049𝑚3/𝑠
Segment 2
𝑛 = 7
43 = 0.163
𝑉2 = 0248 × 0.163 + 0.011
= 0.043𝑚/𝑠
𝐴2 = 𝑄2 + 𝑄3
2 𝑏
= 0.095 + 1.4
2 3
= 3.53𝑚2
𝑞2 = 𝑉2𝐴2
= 0.043 × 3.53
= 0.152𝑚2/𝑠
Segment 3
𝑛 = 7
52 = 0.135
𝑣3 = 0.2483 × 0.135 + 0.011
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 43
= 0.036𝑚/𝑠
𝐴3 = (𝑄3 + 𝑄4)
2 𝑏
= (1.4 + 2.0)
2
= 5.0𝑚2
𝑞3 = 𝑉3𝐴3 = 0.184𝑚3/𝑠
𝑞3 = 0.184𝑚3/𝑠
Segment 4
𝑛 = 7
40 = 0.175
𝑣4 = 0.2483 × 0.175 + 0.011
= 0.046𝑚/𝑠
𝐴4 = (2.0 + 2.1)3
2
= 6.15𝑚2
𝑞4 = 𝑉4𝐴4
= 0.046 × 6.15
= 0.283𝑚3/𝑠
Segment 5
𝑛 = 10
55 = 0.182
𝑣5 = 0.2483 × 0.182 + 0.011
= 0.048𝑚/𝑠
𝐴5 = (2.1 + 2.3)3
2
= 6.6𝑚2
𝑞5 = 𝑉5𝐴5
= 0.048 × 6.6
= 0.317𝑚3/𝑠
Segment 6
𝑛 = 10
53 = 0.189
𝑣6 = 0.2483 × 0.189 + 0.011
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 44
= 0.049𝑚/𝑠
𝐴6 = (2.3 + 2.25)3
2
= 6.83𝑚2
𝑞6 = 𝑉6𝐴6
= 0.049 × 6.83
= 0.334𝑚3/𝑠
Segment 7
𝑛 = 10
48 = 0.208
𝑣7 = 0.2483 × 0.208 + 0.011
= 0.054𝑚/𝑠
𝐴7 = (2.25 + 2.2)3
2
= 6.68𝑚2
𝑞7 = 𝑉7𝐴7
= 0.054 × 6.68
= 0.360𝑚3/𝑠
Segment 8
𝑛1 = 15
50 = 0.3 𝑉81 = 0.2483 × 0.3 + 0.011
= 0.077𝑚/𝑠
𝑛2 = 10
50 = 0.2 𝑉82 = 0.2483 × 0.2 + 0.011
= 0.0524𝑚/𝑠
𝑉8𝑎𝑣𝑔 = 0.065𝑚/𝑠
𝐴8 = (2.2 + 2.5)3
2
= 7.05𝑚2
𝑞8 = 𝑉8𝐴8
= 0.065 × 7.0
= 0.458𝑚3/𝑠
Segment 9
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 45
𝑛1 = 15
45 = 0.33 𝑉91 = 0.2483 × 0.33 + 0.011
= 0.085𝑚/𝑠
𝑛2 = 10
48 = 0.2 𝑉92 = 0.2483 × 0.21 + 0.011
= 0.054𝑚/𝑠
𝑉9𝑎𝑣𝑔 = 0.069
𝐴9 = (09 + 010 )
2𝑏 𝐴9 =
(2.5 + 2.8)
22
= 5.3𝑚2
𝑞9 = 𝑉9𝐴9
= 0.069 × 5.3
= 0.366𝑚3/𝑠
Segment 10
𝑛1 = 15
43 = 0.35 𝑉101 = 0.2483 × 0.35 + 0.011
= 0.089𝑚/𝑠
𝑛2 = 10
46 = 0.22 𝑉102 = 0.2483 × 0.22 + 0.011
= 0.057𝑚/𝑠
𝑉10𝑎𝑣𝑔 = 0.073𝑚/𝑠
𝐴10 = (010 + 04)
2𝑏 𝐴10 =
(2.8 + 3.0)
22
= 5.8𝑚2
𝑞10 = 𝑉10𝐴10
= 0.073 × 5.8
= 0.423𝑚3/𝑠
Segment 11
𝑛1 = 20
52 = 0.38 𝑉111 = 0.2483 × 0.38 + 0.011
= 0.098𝑚/𝑠
𝑛2 = 10
40 = 0.25 𝑉111 = 0.2483 × 0.25 + 0.011
= 0.065𝑚/𝑠
𝑉11𝑎𝑣𝑔 = 0.081𝑚/𝑠
𝐴11 = (011 + 012 )
2𝑏 𝐴11 =
(3.0 + 2.95
22
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria
Page 46
= 5.95𝑚2
𝑞11 = 𝑉11𝐴1
= 0.081 × 5.95
= 0.482𝑚3/𝑠
Segment 12
𝑛1 = 20
50 = 0.40 𝑉121 = 0.2483 × 0.40 + 0.011
= 0.102𝑚/𝑠
𝑛2 = 10
42 = 0.24 𝑉122 = 0.2483 × 0.24 + 0.011
= 0.062𝑚/𝑠
𝑉12𝑎𝑣𝑔 = 0.082𝑚/𝑠
𝐴12 = (012 + 013 )
2𝑏 𝐴12 =
(2.95 + 3.1
22
= 6.05𝑚2
𝑞12 = 𝑉12𝐴12
= 0.082 × 6.05
= 0.496𝑚3/𝑠
Segment 13
𝑛1 = 20
48 = 0.42 𝑉131 = 0.2483 × 0.42 + 0.011
= 0.106𝑚/𝑠
𝑛2 = 10
46 = 0.22 𝑉132 = 0.2483 × 0.22 + 0.011
= 0.057𝑚/𝑠
𝑉13𝑎𝑣𝑔 = 0.081𝑚/𝑠
𝐴13 = (013 + 014 )
2𝑏 𝐴13 =
(3.1 + 3.2 )
22
= 6.3𝑚2
𝑞13 = 𝑉13𝐴13
= 0.081 × 6.3
= 0.51𝑚3/𝑠
Segment 14
𝑛1 = 20
52 = 0.38 𝑉141 = 0.2483 × 0.38 + 0.011
Assessment of Hydroelecric Potentials of Owu and Ero-omola Falls in Kwara State, Nigeria