Assessing Resources

Apr 09, 2018

Download

Documents

allahmahdiali
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 1/28

Page 2: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 2/28

Page 3: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 3/28

In considering the duration of an activity

it is essential to consider the availability

of resources for that activity

Assessment of resources is vital

Aggregation charts are one of the tools

to assess resources

Page 4: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 4/28

Time-limited problems

¾ Project must me completed by a specific

date Resource-limited problems

¾ The project must be completed with limited

resources although this might mean

extending the project deadline

Page 5: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 5/28

Page 6: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 6/28

By doing time analysis, minimum time

possible for completing the project is

obtained Take minimum time as the time limit

Adjust the timing of any activity that may

affect resource requirement within thetotal float of activity (TF= LFT-EST-

Duration)

Page 7: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 7/28

Prepare a list of activities ranked in order of their EST

Produce a resource aggregation chart (shows all theresources required when all activities start as soon aspossible)

Prepare a list of activities ranked in order of their  LST

(=LFT-Duration)

Produce a resource aggregation chart (shows all the

resources required when all activities start as late aspossible)

Compare the two obtained aggregation charts andfind compromise between these two extreme

situations

Page 8: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 8/28

Page 9: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 9/28

Page 10: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 10/28

Page 11: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 11/28

Page 12: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 12/28

Page 13: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 13/28

Similar to unlimited resource aggregation

chart

If the total demand exceed the supplythat activity must be delayed

Activity orders are based on priorities

For activities with same start time sortingis based on their total float (less total

float comes first)

Page 14: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 14/28

Earliest activities are given resources first

Not all activities can receive their 

resources at their earliest start time sothey need to be delayed until resources

become available

Page 15: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 15/28

From unlimited resource

aggregation

Page 16: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 16/28

Page 17: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 17/28

Consider the following time and resourcedata for a small project subject toresource constraint of 2 men only. How

do you manage resources to finish the

project on time?Activity Preceding

activity

Duration Labour

requirement

A - 1 2 men

B - 2 1 man

C A 1 1 man

D - 5 1 man

E B 1 1 man

F C 1 1 man

Page 18: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 18/28

Establish precedence diagram (AOA)

1

1 3

0

0 0

3

2 4

2

2 4

4

5 5

A

C

F

D

EB

1

1

1

1

2

5

Page 19: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 19/28

Find the critical path

1

1 3

0

0 0

3

2 4

2

2 4

4

5 5

A

C

F

D

EB

1

1

1

1

2

5

Page 20: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 20/28

Arrange activities based on EST and

obtain TF for each activity

Activity Duration EST LST EFT LFT TF Labour

requirements

A 1 0 0 1 3 2 2 men

B 2 0 0 2 4 2 1 man

D 5 0 0 5 5 0 1 man

C 1 1 3 2 4 2 1 man

E 1 2 4 5 5 2 1 man

F 1 2 4 5 5 2 1 man

Page 21: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 21/28

Establish aggregation chart based on

sorted EST

Number of

men required

Time

scale indaysD

0 54321

B

4

3

2

1

E

FCA Resourceavailability

Page 22: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 22/28

Sort activities based on LST

Activity Duration EST LST EFT LFT TF Labour

requirements

A 1 0 0 1 3 2 2 men

B 2 0 0 2 4 2 1 man

D 5 0 0 5 5 0 1 man

C 1 1 3 2 4 2 1 man

E 1 2 4 5 5 2 1 man

F 1 2 4 5 5 2 1 man

Page 23: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 23/28

Draw aggregation chart based on LST 

(similar to EST!!!)

Number of

men required

Time

scale indaysD

0 54321

B

4

3

2

1

E

FCA Resourceavailability

Page 24: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 24/28

At anytime we need more than 2 men to

get the job done

Based on the current resources the delayis inevitable

Lets assume we cannot increase our 

resources then we definitely need todelay the project; how do you do it?

Page 25: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 25/28

We stick to two men and the job is

delayed for 1 day

Number of

men required

tD

0 54321

B

4

3

2

1

E FC

A

Resourceavailability

6

Page 26: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 26/28

Assume that the management states

that the duration of 5 days must be

maintained and he increase theresources from 2 men to 3 men. How do

you allocate resources?

Page 27: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 27/28

It shows that from day 2 to day 4 we

need to have 3 men available

Number of

men required

Time

scale indaysD

0 54321

B

4

3

2

1

E F

C

A

Resourceavailability

Page 28: Assessing Resources

8/7/2019 Assessing Resources

http://slidepdf.com/reader/full/assessing-resources 28/28

Resource requirements for each activitymust be specified in order to performreliable scheduling

Resources must be classified and theavailability and constraints specified

A Resource Aggregation Profile(s) is anessential tool for resource management

If the resource aggregation indicates that aconstraint is being exceeded, and float isavailable the resource usage is 'smoothed'

i.e. the start of activities is delayed