Assembly, Integration & Verification 2016 SKA Engineering Meeting Richard Lord 3 October 2016
33

Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Jun 30, 2018

Download

Documents

nguyencong
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Assembly, Integration & Verification2016 SKA Engineering Meeting

Richard Lord3 October 2016

Page 2: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Verification Planning

• Roll-Out Planning

• MeerKAT Integration Planning

Overview

Page 3: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

AIV Consortium Member Organisations

Page 4: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Stage 2 Milestones# Stage 2: Milestone Description Due Date1 Kick-off Apr 20152 Telescope Preliminary I&V Plan Jul 20153 SEMP and PMP Alignment Jun 20154 Product Hand-Over Checklist Jul 20155 Updated Cost Model Aug 20156 MeerKAT Precursor ICDs Aug 20157 Telescope Roll-Out Plan (Next Release) Sep 20158 MeerKAT Precursor Integration Plan and ICDs Oct 20169 Telescope Test Procedures (Draft) Dec 2016

10 Telescope Verification Requirements (Next Release) Feb 201611 Telescope Detailed I&V Plan Mar 201712 Telescope AIV Resource Plan Apr 201713 Product Hand-Over Checklist May 201714 AIV Review - Document Submission May 201715 AIV Review – Closure Jun 201716 Telescope Test Procedures (Final) Jun 201717 System CDR - Document Submission Jul 2017

18 System CDR - Closure System CDR+ 4 weeks

Page 5: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Verification Planning

ScienceRequirements

Telescope Requirements Specification

Element Requirements Specification

Component Specification

Design & Manufacture

ComponentAIV

ElementAIV

TelescopeAIV

ScienceValidation

Component Verification

Element Verification

System Verification

User Requirements Validation

Time

DesignVerification

Page 6: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Designs need to be qualified, before manufacturing may begin

• Manufactured products (or systems) need to be verified

• CDRs should contain Qualification Results• CDRs should contain Verification Plans

Design Qualification andProduct (System) Verification

Page 7: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Verification Model

Requirements

Verification Requirements

Verification Events

System

Test Procedures

Test Configurations

specified by

verified by

fulfilled at

employs

employs

formed by

Test EquipmentSystems Engineering Tool

High-level description ofhow to verify a requirement

Page 8: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• High-level description of how each requirement will be verified

• At what level of system integration the verification will be performed– System ITF, AA1, AA2, AA3, AA4

• Who is responsible for executing the verification– AIV Contractor, Science Validation Team

• Document release planned for mid-Nov 2016

Verification Requirements

Page 9: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Verification Events

Array Assembly

ProductHandovers

Non-FunctionalRequirements

Functional and Performance Capabilities

Page 10: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Verification Events

Page 11: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Integration & Verification Plan

I&V Plan

Verification Requirements

Roll-Out Plan

Contains:• Integration Events• Verification Events• Resources• ...

• System Requirements

• Hosting Agreements• Telescope Verification Plans• Early-Science Plans• Commissioning Plans• SKAO Input• Consortia Input

1

3

2

• SKAO Input• Consortia Input

Page 12: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Integration & Verification PlanIntegration/VerificationEvent 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20SaDT.NSDNLabver-DISH,CSP,TM,SDP I.Lab.1 *TM.TELMGMT-DISH.LMC I.Lab.2 * *TM.TELMGMT-SaDT.SAT.LMC I.Lab.3 *DISHReceiver-SaDT.SAT I.Lab.4 *TM.TELMGMT-CSP.LMC I.Lab.5 *SaDT.DDBHLabver-CSP-DISH I.Lab.6 *DISHReceiver-CSP.CBF I.Lab.7 *TM.TELMGMT-SDP.LMC I.Lab.8 *CSP.CBF-SDP.DataProc I.Lab.9 *LabSystemLineupC&M I.Lab.10 *LabSystemLineupData I.Lab.11 *LabSystem4inputVerification V.Lab.2.1 * *INFRA-DISH I.D1.1 * * *SaDT.NSDN-TM/DISH I.D1.2 *TM.TELMGMT-SaDT.SAT.LMC I.D1.3 *TM.TELMGMT-DISH.LMC I.D1.4 *DISHReceiver-SaDT.SAT I.D1.5 *SaDT.NSDN-TM/CSP I.D1.6 *TM.TELMGMT-CSP.LMC I.D1.7 *SaDT.DDBH-CSP-DISH I.D1.8 *DISHReceiver-CSP.CBF I.D1.9 *2ndDISHIntegrationtoINFRA,SaDT,CSP 2DishIntegration * *INFRAHandover V.D1.1.1 *SaDThandover V.D1.1.2 *DISHHandover V.D1.1.3 *TMHandover V.D1.1.4 *CSPHandover V.D2.1.5 *DishC&M V.D1.2.1 * *Freqrange,Sensitivity V.D1.2.2 *RFIDetection V.D1.2.3 *Channelisation V.D2.2.1 *BasicInterferometry V.D2.2.2 * *CorrelatorProducts V.D2.2.3 *Displays V.D2.2.4 *EMI/EMC V.D2.3.1 * * *Environmental V.D1.3.1 *4DISHIntegrationtoINFRA,SaDT,CSP 4DISHIntegration * * *SaDT.NSDN-TM/SDP I.D4.1 *TM.TELMGMT-SDP.LMC I.D4.2 *SaDTCSP-SDPInitiallocallink I.D4.3 * *CSP.CBF-SDP.DataProcessor I.D4.4 *INFRAHandover V.D4.1.1 *SaDThandover V.D4.1.2 *DISHHandover V.D4.1.3 *TMHandover V.D4.1.4 *CSPHandover V.D4.1.5 *SDPHandover V.D4.1.6 *Channelisation V.D4.2.1 * *BasicInterferometry V.D4.2.2 * *CorrelationProducts V.D4.2.3 *Imaging V.D4.2.4 * *EMI/EMC V.D4.3.1 * *

MonthssinceT0

Laboratory

EarlySite,1-2Dishes

Site,4Dishes

Identifies:• Integration Events• Verification Events

Each event has:• Start date• Duration• Resources• Prerequisites

Page 13: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Product Hand-Over ChecklistObjectives are to ensure that:• A well-defined development process was followed for the

product• The product meets its technical specifications,

documented by Qualification Test Results (QTRs) and Acceptance Test Results (ATRs)

• The product can be supported and maintained after hand-over

• The product is successfully installed on-site• The logistic support development for the product is in

process

• Final document release planned for May 2017

Page 14: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Installation, Integration, Verification

Acceptance Testing of Product

Integration withSKA1 Telescope

System

System Hand-Over

Operation ofSKA1 Telescope

System

ProductHand-Over

Process

no

SystemVerification

Product Hand-Over

no

yes yes

OEM Resolve Issue

AIV Contractor Responsibility

Product Contractor Responsibility Operations Team Responsibility

FactoryAcceptance and

Shipment ReadinessReview

Shipment and Installation to

ITF or Site

OEM

yes

no

Page 15: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Product Hand-Over Checklist(example)

Page 16: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Forms the basis for the delivery of products and planning of integration & verification activities

• Considers:– Sequencing of implemented functionality– Scale: How many Dishes / Stations deployed and when– Integration of MeerKAT Precursor into SKA1-MID

• Sequential process – early retirement of risks• Achieved by specifying “Array Assemblies”• Currently at Rev 5, released by Dec 2016

Roll-Out Planning

Page 17: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Described by:– Date

• When all required products have been installed, i.e. not necessarily integratedinto Telescope System

– Number of Dishes / Stations– Array Capability → Determines back-end Element functionality– Key Engineering Goals

• Array Assemblies used by AIV Contractor– Verification of Level-1 (System Level) Requirements

• Array Releases used by Science Validation Team– Validation of Science Requirements

Array Assembly

Page 18: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Multiple ITFs– At Element Level or lower

• All over the world. Rely heavily on simulators/emulators. No AIV involvement.

– At System Level• End-to-End line-up of Level-2 products

• System ITF used for:– System Level Design Qualification– Verification of interfaces between Level-2 products– Debugging, troubleshooting, development work, etc– Testing of hardware/firmware/software upgrades during Constr. Phase– Knowledge transfer (between contractors, engineers, AIV Team, etc)

Integration Test Facility (ITF)

Page 19: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Functional Allocation toRoll-Out Milestones

ITF AA1 AA2 AA4AA3

R1 R2 R3 R4 R5 R6

F 1 F 2 F 3

Page 20: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Functional Allocation toRoll-Out Milestones (SKA1-MID)

SystemITFAA1AA2AA3AA4

Page 21: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Functional Allocation toRoll-Out Milestones (SKA1-MID)

CSP

SystemITF

AA1

AA2

AA3

AA4

DSH

SystemITF

AA1

AA2

AA3

AA4

SDP

SystemITF

AA1

AA2

AA3

AA4

TM

SystemITF

AA1

AA2

AA3

AA4

SaDT

SystemITF

AA1

AA2

AA3

AA4

INFRA

SystemITF

AA1

AA2

AA3

AA4

Page 22: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SKA1 MID Roll-Out PlanSi

teIn

tegr

atio

n Te

st F

acili

ty (I

TF)

ITF Qualification

Event

AA4AA3AA2AA11Dish

2Dishes

4Dishes

ITF Qualification

Event2

ITF Qualification

Event3

ITF Qualification

Event4

DishPRR

Number of SKA1 Dishes deployed

MeerKAT Precursor

Front-End IntegrationINFRA, SaDT, DISH

QualityGate

ITFIntegration

Events

Dish Receiver, SaDT,CSP, TM, SDP

Page 23: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SKA1 LOW Roll-Out Plan

Page 24: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SKA1-MID Dish Roll-Out

C0Dish C0Dish + 1 C0Dish + 2 C0Dish + 3 C0Dish + 4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

0

50

100

150

200

250

MeerKAT Science Programme

Full Hand-Over toSKA1 Operations

MeerKAT Integration

New SKA1_MID Dishes

MeerKAT Dishes

1st Dish

DishPRR

C0Dish + 5

Page 25: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SKA1-LOW Station Roll-Out

T0 T0 + 1 T0 + 2 T0 + 3 T0 + 4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

0

100

200

300

400

500

Start Construction SKA1 End Construction SKA1

1st Station

T0 + 5

Page 26: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Software Release ManagementSi

teIn

tegr

atio

n Te

st F

acili

ty (I

TF)

ITFQE

AA4AA3AA2AA1

Arb

itrar

y Lo

catio

n

ITF Integration Environment(Software verified against real hardware and firmware)

Development Environment(Software qualified against simulators)

On-Site Environment(Software acceptance tested with production hardware and firmware)

Software Releases

Software Releases

Issues Issues

No Change-Control Under Change-Control

Page 27: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

MeerKAT Integration Planning

Page 28: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SKA1-MID Core Area

Blue Dots = MeerKAT DishesGreen Dots = SKA1-MID Dishes

Page 29: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

MeerKAT Digitiser to be retro-fitted with SKA1-MID Receiver Sampler

Receiver Retro-fit (ECP 150006)

Feed Indexer

MeerKATL-Band Feed

MeerKATDigitiser

Page 30: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

SaDT Equipment:• DDBH• NSDN• STFR

Dish Equipment:• Receiver Packetiser

Receiver Retro-fit (ECP 150006)

Page 31: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Rack Space inside the SDC (Shielded Drive Compartment) inside the Pedestal

• Heat Removal inside the SDC• EMI shielding requirements• Re-use of MeerKAT Masers

MeerKAT Integration Issues

Page 32: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

• Develop a culture of safety awareness• Verification of Safety Requirements• Adherence to safety regulations• Support effective communication

Safety during Construction

Page 33: Assembly, Integration & Verification · Assembly, Integration & Verification 2016 SKA Engineering Meeting ... SaDT CSP-SDPI nitial local link I.D4.3 * * ... SKA1-MID Core Area

Thank You