  • ASHVILLE PARK LAKE HOUSE UPDATE BRIEFING

    MARCH 14, 20191

  • AGENDA▪ Drainage Patterns – Ashville Park▪ USGS Rain/Tide Gauges▪ Ashville Park Drainage Improvements – Phase I▪ Phase I Schedule & Update▪ Storm Water Quality

    2

  • PROJECTS IN RELATION TO BACK BAY

    3

  • 4

  • https://va.water.usgs.gov/webmap/precip va/

    5

    Use technology that already exists effectively USGS Tide Gauges, Rainfall Gauges Historical Storm DataMaster Drainage Plan – PCSWMM

    https://va.water.usgs.gov/webmap/precip_va/

  • • Stormwater Quality regulations and permitting are more demanding and compliance is mandatory

    • More complicated projects and regulations are increasing Operation and Maintenance requirements

    • Aging infrastructure is increasing the amount of maintenance needs

    • Existing funding in the stormwater utility is not adequate to address current and future demands

    • Recent weather events have revealed our vulnerability to flooding

    • Hurricane Matthew-2200 plus homes flooded as a result there is a need to address flooding in neighborhoods

    • Developed a program to increase CIP $300 million over the next 15 years

    STORMWATER BUDGET TRENDS AND ISSUES

    6

  • 7 | Ashville Park Stormwater March 4, 2019

    • 3 new Stormwater Ponds• Expand an Existing Pond• Channels Connecting Ponds• Regrade and Stabilization of Existing Ditches

    • Stormwater Pump Station

    • Gated Control Structure at Flanagans Lane• Ditch and Culvert Improvements at New

    Bridge/Sandbridge Road Intersection

    Phase I CIP

    Developer’s Construction and Const. Mgt. Responsibility w/ City Oversight

    City’s Construction and Const. Mgt. Responsibility

  • Ashville Park Drainage Improvements –Phase I 7-047

    3 new Stormwater Ponds Expand an Existing Pond Channels Connecting

    Ponds Regrade and

    Stabilization of Existing Ditches

    Stormwater Pump Station

    Gated Control Structure at Flanagans Lane

    Ditch and Culvert Improvements at New Bridge/Sandbridge Road Intersection

    8

  • 9

    Developer has Two Submissions:

    Grandview Villageo 1st Submittal Oct 2018o 2nd Submittal Feb 2019

    Ashville Park Drainage Improvements Phase Io 1st Submittal 2015o 2nd Submittal Oct 2018o 3rd Submittal Feb 2019

  • 10

    POTENTIAL ULTIMATE ALIGNMENT

  • 11

  • 12

    ULTIMATE CULVERT WITH LEFT TURN LANE DESIGN

  • 13

  • ASHVILLE PARK OPERATIONS PUMPING PROTOCOLS

    ▪ Temporary Plan (Until Lake #14 Weir is Built):o Manually Operating Pump generally based on a ‘significant rainfall event’ of 3-

    inches or greater expected rainfall.o As pre-emptive action, attempt drawdown water surface levels in all lakes to

    Elevation 1.0 ft ahead of a significant rainfall event.

    ▪ Permanent Plan (After Lake #14 Weir is Built):o Maintaining water surface in lakes at Elevation 2.0 ft o As pre-emptive action, drawdown water surface levels in all lakes to Elevation 1.0 ft

    ahead of a significant rainfall event.

    14

  • 15

    Gated Control Structure (Sluice Gate)

  • PW OPS - LAKE # 14 WEIR CONSTRUCTION PHOTOS

    16

  • PW OPS - LAKE # 14 WEIR CONSTRUCTION PHOTOS

    17

  • RANIER VILLAGE EMERGENCY INGRESS/EGRESS

    18

  • ASHVILLE PARK - CITY SCHEDULE OF ACTIVITIES

    19

    Ashville Park - Phase I - 7-047Schedule Item: Schedule: Current Status:Roadway and Drainage Contract:Real Estate Title Search, Appraisal & Negotiations

    No Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    Design Complete May29, 2019 * 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for Impacts Complete June 1, 2019

    * 1st Submittal for Joint Permit Application (JPA) to Obtain DEQ VWP General Permit for Linear Transportation Project (VPW-3) and USACE 17-SPGP-01 Received 3/1/19: No Mitigation Expected

    Private Utilities Adjustments Utility Pole affectedAdvertise for Construction June 15, 2019 - July 15, 2019Contractor Procurement & NTP Begin Sept. 15, 2019Construction ( Projected 18 months) Complete March 31, 2020

    * SCHEDULE CONTINGENT ON US ARMY CORPS OF ENGINEERS, VMRC & DEQ PERMITTING APPROVAL

    *

    ***

    Sheet1

    Ashville Park - Phase I - 7-047

    Schedule Item:Schedule:Current Status:

    Roadway and Drainage Contract:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignComplete May29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsComplete June 1, 2019* 1st Submittal for Joint Permit Application (JPA) to Obtain DEQ VWP General Permit for Linear Transportation Project (VPW-3) and USACE 17-SPGP-01 Received 3/1/19: No Mitigation Expected

    Private Utilities AdjustmentsUtility Pole affected

    Advertise for ConstructionJune 15, 2019 - July 15, 2019

    Contractor Procurement & NTPBegin Sept. 15, 2019

    Construction ( Projected 18 months)Complete March 31, 2020

    Pump Station:

    Real Estate Title Search, Appraisal & NegotiationsDedication of property by HOFD Ashville Park LLC for Pump Station needs to be executedPrelim Plat submitted 2/8/19 with comments received by Real Estate

    DesignMay 29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsJune 1, 2019* 1st Submittal for Pre-Construction Notification (PCN) NWP #43 Received 3/1/19: No mitigation Expected

    Private Utilities AdjustmentsConnect to Roadside Power Pole after Load Letter ProcessedCoordination with Dom. Power for Load Letter and inclusion of Lake #14 Dominion Energy Esmt on Plat

    A/E Advertise        June 15, 2019

    Contractor Procurement & NTPSeptember 15, 2019

    Construction ( Projected 18 months)March 15, 2021

    Flanagans Lane/Sandbridge Road Outfall Channel Maintenance:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignApril 15, 2019* Final Design Submission 2/8/19 - Awaiting Comments; SWPPP Prepared

    Permitting for ImpactsMay 1, 2019* Coordination with PW OPS for Coverage under Mx.

    Private Utilities AdjustmentsNone

    Submit to CONTRACTS for ASCC ExecutionJune 15, 2019

    NTPJuly 30, 2019

    Construction ( Projected 9 months)April 28, 2020

    Detailed-20180917-Ashville Park Schedule.xlsxLink to Overall Program Schedule

    Detailed GANT-Ashville Park Program-Schedule.xlsxLink to Overall Program Schedule (GANT)

    Detailed%20GANT-Ashville%20Park%20Program-Schedule.xlsxDetailed-20180917-Ashville%20Park%20Schedule.xlsx

    bvanderwarkerLine

    bvanderwarkerTypewritten Text2021

  • ASHVILLE PARK - CITY SCHEDULE OF ACTIVITIES

    20

    Schedule Item: Schedule: Current Status:Pump Station:

    Real Estate Title Search, Appraisal & NegotiationsDedication of property by HOFD Ashville Park LLC for Pump Station needs to be executed

    Prelim Plat submitted 2/8/19 with comments received by Real Estate

    Design Complete May 29, 2019 * 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for Impacts Complete June 1, 2019* 1st Submittal for Pre-Construction Notification (PCN) NWP #43 Received 3/1/19: No mitigation Expected

    Private Utilities AdjustmentsConnect to Roadside Power Pole after Load Letter Processed

    Coordination with Dom. Power for Load Letter and inclusion of Lake #14 Dominion Energy Esmt on Plat

    Advertise for Construction June 15, 2019 - July 15, 2019Contractor Procurement & NTP Begin Sept. 15, 2019Construction ( Projected 18 months) Complete March 31, 2021

    *

    *

    **

    * SCHEDULE CONTINGENT ON US ARMY CORPS OF ENGINEERS, VMRC & DEQ PERMITTING APPROVAL

    Sheet1

    Ashville Park - Phase I - 7-047

    Schedule Item:Schedule:Current Status:

    Roadway and Drainage Contract:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignMay 29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsJune 1, 2019* 1st Submittal for Joint Permit Application (JPA) to Obtain DEQ VWP General Permit for Linear Transportation Project (VPW-3) and USACE 17-SPGP-01 Received 3/1/19: No Mitigation Expected

    Private Utilities AdjustmentsUtility Pole affected

    A/E Advertise        June 15, 2019

    Contractor Procurement & NTPSeptember 15, 2019

    Construction ( Projected 18 months)March 15, 2021

    Pump Station:

    Real Estate Title Search, Appraisal & NegotiationsDedication of property by HOFD Ashville Park LLC for Pump Station needs to be executedPrelim Plat submitted 2/8/19 with comments received by Real Estate

    DesignComplete May 29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsComplete June 1, 2019* 1st Submittal for Pre-Construction Notification (PCN) NWP #43 Received 3/1/19: No mitigation Expected

    Private Utilities AdjustmentsConnect to Roadside Power Pole after Load Letter ProcessedCoordination with Dom. Power for Load Letter and inclusion of Lake #14 Dominion Energy Esmt on Plat

    Advertise for Construction        June 15, 2019 - July 15, 2019

    Contractor Procurement & NTPBegin Sept. 15, 2019

    Construction ( Projected 18 months)Complete March 31, 2021

    Flanagans Lane/Sandbridge Road Outfall Channel Maintenance:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignApril 15, 2019* Final Design Submission 2/8/19 - Awaiting Comments; SWPPP Prepared

    Permitting for ImpactsMay 1, 2019* Coordination with PW OPS for Coverage under Mx.

    Private Utilities AdjustmentsNone

    Submit to CONTRACTS for ASCC ExecutionJune 15, 2019

    NTPJuly 30, 2019

    Construction ( Projected 9 months)April 28, 2020

    Detailed-20180917-Ashville Park Schedule.xlsxLink to Overall Program Schedule

    Detailed GANT-Ashville Park Program-Schedule.xlsxLink to Overall Program Schedule (GANT)

    Detailed%20GANT-Ashville%20Park%20Program-Schedule.xlsxDetailed-20180917-Ashville%20Park%20Schedule.xlsx

  • ASHVILLE PARK - CITY SCHEDULE OF ACTIVITIES

    21

    Schedule Item: Schedule: Current Status:Flanagans Lane/Sandbridge Road Outfall Channel Maintenance:Real Estate Title Search, Appraisal & Negotiations

    No Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    Design Complete April 15, 2019* Final Design Submission 2/8/19 - Awaiting Comments; SWPPP Prepared

    Permitting for Impacts Complete May 1, 2019 * Coordination with PW OPS for Coverage under Mx.Private Utilities Adjustments NoneSubmit to CONTRACTS for ASCC Execution Begin June 15, 2019NTP Begin July 30, 2019Construction ( Projected 9 months) Complete Aril 30, 2020*

    **

    *

    * SCHEDULE CONTINGENT ON US ARMY CORPS OF ENGINEERS, VMRC & DEQ PERMITTING APPROVAL

    Sheet1

    Ashville Park - Phase I - 7-047

    Schedule Item:Schedule:Current Status:

    Roadway and Drainage Contract:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignMay 29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsJune 1, 2019* 1st Submittal for Joint Permit Application (JPA) to Obtain DEQ VWP General Permit for Linear Transportation Project (VPW-3) and USACE 17-SPGP-01 Received 3/1/19: No Mitigation Expected

    Private Utilities AdjustmentsUtility Pole affected

    A/E Advertise        June 15, 2019

    Contractor Procurement & NTPSeptember 15, 2019

    Construction ( Projected 18 months)March 15, 2021

    Pump Station:

    Real Estate Title Search, Appraisal & NegotiationsDedication of property by HOFD Ashville Park LLC for Pump Station needs to be executedPrelim Plat submitted 2/8/19 with comments received by Real Estate

    DesignMay 29, 2019* 90% Design Submission 2/8/19 - Awaiting Comments

    Permitting for ImpactsJune 1, 2019* 1st Submittal for Pre-Construction Notification (PCN) NWP #43 Received 3/1/19: No mitigation Expected

    Private Utilities AdjustmentsConnect to Roadside Power Pole after Load Letter ProcessedCoordination with Dom. Power for Load Letter and inclusion of Lake #14 Dominion Energy Esmt on Plat

    A/E Advertise        June 15, 2019

    Contractor Procurement & NTPSeptember 15, 2019

    Construction ( Projected 18 months)March 15, 2021

    Flanagans Lane/Sandbridge Road Outfall Channel Maintenance:

    Real Estate Title Search, Appraisal & NegotiationsNo Acquisition or Easement Impacts per Prior Detailed Coordination with USF&W

    DesignComplete April 15, 2019* Final Design Submission 2/8/19 - Awaiting Comments; SWPPP Prepared

    Permitting for ImpactsComplete May 1, 2019* Coordination with PW OPS for Coverage under Mx.

    Private Utilities AdjustmentsNone

    Submit to CONTRACTS for ASCC ExecutionBegin June 15, 2019

    NTPBegin July 30, 2019

    Construction ( Projected 9 months)Complete Aril 30, 2020

    Detailed-20180917-Ashville Park Schedule.xlsxLink to Overall Program Schedule

    Detailed GANT-Ashville Park Program-Schedule.xlsxLink to Overall Program Schedule (GANT)

    Detailed%20GANT-Ashville%20Park%20Program-Schedule.xlsxDetailed-20180917-Ashville%20Park%20Schedule.xlsx

    bvanderwarkerText BoxSince the meeting, this outfall maintenance sub-project has now been incorporated into the Roadway & Drainage Improvements Project (Slide 19) along with its wetlands permitting requirements

  • ASHVILLE PARK – DEVELOPER SCHEDULE OF ACTIVITIES

    22

    Schedule Item: Estimated Completion Date: Current Status:Ashville Park Drainage Improvements Phase IDesign May 1, 2019

    * 1st Submittal October 2018* 2nd Submittal February 2019

    Invitation to Bid End March 2019 Sent out February 27, 2019Construction August 30, 2020 ~June 2019 (soon after Plan Approval)

    Grandview Village (Village C):

    Design May 1, 2019* 1st Submittal 2015 put on hold* 2nd Submittal October 2018* 3rd Submittal February 2019

    Invitation to Bid End of March 2019 Sent out February 22, 2019Construction August 30, 2020 ~June 2019 (soon after Plan Approval)

    Sheet1

    Ashville Park - DEVELOPER SCHEDULE OF ACTIVITIES

    Schedule Item:Estimated Completion Date:Current Status:

    Ashville Park Drainage Improvements Phase I

    DesignMay 1, 2019* 1st Submittal October 2018* 2nd Submittal February 2019

    Invitation to BidEnd March 2019Sent out February 27, 2019

    ConstructionAugust 30, 2020~June 2019 (soon after Plan Approval)

    Grandview Village (Village C):

    DesignMay 1, 2019* 1st Submittal 2015 put on hold* 2nd Submittal October 2018* 3rd Submittal February 2019

    Invitation to BidEnd of March 2019Sent out February 22, 2019

    ConstructionAugust 30, 2020~June 2019 (soon after Plan Approval)

  • ASHVILLE BRIDGE CREEK WATERSHED STORMWATER QUALITY MONITORING EFFORTS

    Activity Timeframe StatusIdentify monitoring

    parameters and site selectionSeptember –October 2018 Completed

    Data collection November 2018 –February 2019 Completed

    Data analysis and report preparation

    March –May 2019 On schedule

    Potential additional data collection

    April –October 2019 TBD

    23

  • 24

    DISCUSSION

    Ashville Park �LAKE HOUSE update briefingAGENDAPROJECTS in relation to Back BaySlide Number 4Slide Number 5Stormwater Budget Trends and Issues�Phase I CIPAshville Park Drainage Improvements – Phase I 7-047Slide Number 9Slide Number 10Slide Number 11ULTIMATE CULVERT with LEFT TURN LANE DESIGNSlide Number 13Ashville Park OPERATIONS PUMPING PROTOCOLSSlide Number 15PW OPS - Lake # 14 WEIR CONSTRUCTION PHOTOSPW OPS - Lake # 14 WEIR CONSTRUCTION PHOTOSRanier Village Emergency Ingress/EgressASHVILLE PARK - CITY SCHEDULE of activitiesASHVILLE PARK - CITY SCHEDULE of activitiesASHVILLE PARK - CITY SCHEDULE of activitiesASHVILLE PARK – DEVELOPER SCHEDULE of activitiesAshville bridge creek watershed �Stormwater Quality Monitoring effortsSlide Number 24