Arbor Hills Landfill Public Meeting September 6, 2017 Larry Bean, Waste Management and Radiological Protection. Jackson and Lansing District Supervisor Scott Miller, Air Quality Division, Jackson District Supervisor
29

Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

May 24, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Arbor Hills Landfill Public MeetingSeptember 6, 2017

Larry Bean, Waste Management and Radiological Protection. Jackson and Lansing District Supervisor

Scott Miller, Air Quality Division, Jackson District Supervisor

Page 2: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

MDEQ Landfill Roles and Responsibilities

Waste Management and Radiological Protection Division

• Permitting

• Licensing

• Operations

• Inspections

• Monitoring

Air Quality Division

• Oversee operation of Gas Collection and Control System

• Federal Requirements• NSPS WWW

• NESHAP AAAA

• Title V Operating Permit

Page 3: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

www.michigan.gov/deqarborhills

Page 4: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Larry Bean: 517-416-4375

Scott Miller: 517-780-7481

Diane Kavanaugh-Vetort: 517-780-7864

Website and Contact Information

Page 6: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Monitoring Efforts

• DEQ Monitoring

• RK and Associates

• Surface Methane and Well Head Monitoring

Page 7: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will
Page 8: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Monitoring Efforts

• DEQ Monitoring

• RK and Associates

• Surface Methane and Well Head Monitoring

Page 9: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Original Cell 6 Permit Location Vs. Modification

Page 10: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Cell Excavation

In mid-June 2017, Arbor Hills submitted to the MDEQ for approval a minor permit modification to the west portion of Cell 6. The modification includes changing the west portion of Cell 6 to flow into Cell 4, with the changed area to be referred to as Cell 4E. The proposed modification will minimize waste removed from Arbor Hills East to approximately 40,000 cubic yards (cy) from 500,000 cy – a 92 percent reduction. The modification will reduce the potential for offsite odors.

Page 11: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of Cell ExcavationArea of Cell 4E

Page 12: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Original Cell 6 Permit Location Vs. Modification

Area originally

permitted for excavation

Modification would only

allow excavation of this area. This

would significantly

decrease area to be excavated.

Page 13: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of Cell Excavation and Liner System Detail

Page 14: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Odor Controls during Cell Excavation

• Arbor Hills Odor Control Plan

• Test Digs

• Excavation from 8-5pm

• Daily Cover

• Odor Observations

• Leachate Capture

• Gas Capture

Page 15: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Status of Corrective Actions as Established by EPA Enforcement Action

• Compliance Plan to address violations

• Construction work and deadlines

• Gas System and Flares

• Leachate System Enhancements

• Landfill Enhancements

Page 16: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Flares

Temporary Flare: In March of 2017, Arbor Hills began utilizing a temporary flare at the northwest corner of the landfill to increase vacuum and to aid in odor control. This flare will operate into 2018.

Permanent Flare: A high-capacity flare is currently going through the permitting process for installation in 2018.

Page 17: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of FlaresTemporary flare

(Installed March 2017)

Permanent backup flare (planned for 2018)

Page 18: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Perimeter Header

Arbor Hills this summer began installing a new, 24-inch diameter pipe around the perimeter of the landfill. The project is scheduled to be completed in 2018. Completion includes the railroad crossing and final tie-in to the gas-to-energy plant with a 36-inch diameter pipe.

Page 19: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of Perimeter Header24-inch header pipe along north, toward northwest corner (present construction)

24-inch header pipe along west & south, toward power plant (this fall)

36-inch header pipe under railroad track, to power plant (2018)

Page 20: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

New & Replacement Wells

This summer, Arbor Hills installed 14 new gas collection wells and 11 re-drilled wells within the landfill. The wells were installed along the south and west sides, where Arbor Hills determined where landfill gas collection most needed to be improved.

Page 21: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Leachate Tank

Arbor Hills this summer installed a new, glass-lined leachate storage tank at the southeast corner of the landfill. The new tank is equipped with carbon filtering to help prevent odors. It went into use in July. The existing leachate tank will replaced in 2018.

Page 22: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of New Leachate Tank

New leachate tank with carbon filtration (installed)

Page 23: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Final CoverArbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will conclude this fall. Closure entails covering this area with a liner system, which is covered with soil and planted with grass.

Page 24: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of South Slope Final Cover

Final Cover Location (present construction)

Page 25: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Odor Neutralization System

Arbor Hills has installed an odor neutralizing system to help mitigate odors. The system operates around the perimeter of the active area of the landfill, drawing air and infusing it with odor neutralizer as it expels it. It is safe for human health and the environment, quiet, unscented and requires no water.

Page 26: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Temporary CoverTo more efficiently collect landfill gas in the “bowl area” and prevent off-site odors approximately ten acres on the landfill’s north face was covered with a synthetic liner.

An additional seven acres will be covered this fall with the same style of synthetic liner. The new covering will extend above the present temporary cover.

Page 27: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Location of Synthetic Coverings

Location of present synthetic liner

Location of additional synthetic liner(scheduled for this year)

Page 28: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Odor Surveillance Location Map

Page 29: Arbor Hills Landfill Public Meeting Presentation · Final Cover Arbor Hills has begun to place final cover on a 20-acre portion of the south side of the landfill. This project will

Questions??

800-662-9278

www.michigan.gov/deq

Sign up for email updates

Follow us on YouTube

Follow us on Twitter @MichiganDEQ