ACG Commissioning Guideline Appendix C Sample Format for System Verification and Start-Up Checklists NOTES TO APPENDIX C This appendix contains sample systems verification and start-up checklists for a selection of equipment used frequently in typical HVAC systems. There is no intention in the appendix to provide sample checklists for all possible equipment included in any design. These checklists are intended to illustrate a level of detail that is appropriate in good commissioning practice, and to suggest a practical format. As such, they contain typical items that are often required to be included in the inspections and checks carried out, and documented, prior to and during equipment start-up. The sample checklists are generic; thus they do not apply to any specific project, and so the list of check items is generic, not specific. Commissioning authorities must develop systems verification and start-up checklists for every piece of equipment within
33

Appendix C Sample Format for System Verification and Start-Up ...

Jan 01, 2017

Download

Documents

donguyet
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Appendix C Sample Format for System Verification and Start-Up ...

ACG Commissioning Guideline

Appendix C

Sample Format for System Verification andStart-Up Checklists

NOTES TO APPENDIX C

This appendix contains sample systems verification and start-up checklists for a selection of equipment used frequently in typical HVAC systems.

There is no intention in the appendix to provide sample checklists for all possible equipment included in any design. These checklists are intended to illustrate a level of detail that is appropriate in good commissioning practice, and to suggest a practical format. As such, they contain typical items that are often required to be included in the inspections and checks carried out, and documented, prior to and during equipment start-up.

The sample checklists are generic; thus they do not apply to any specific project, and so the list of check items is generic, not specific. Commissioning authorities must develop systems verification and start-up checklists for every piece of equipment within the scope of any commissioning project, and those checklists must include all items included in the specific design that require checking.

There is a Table of Contents on the next page listing the sample checklists included in this appendix.

ACG assumes no responsibility for how the material in this Appendix may be utilized by users of the Guideline; the users assume full responsibility for any and all liability that may arise from any reference to, or use of, this material.

Page 2: Appendix C Sample Format for System Verification and Start-Up ...

ACG Commissioning GuidelineAPPENDIX C

TABLE OF CONTENTS

Air Handling Unit 4Controls Air Compressor 5Hot Water Boiler 6Chiller 7Heating and Cooling Coils 8Cooling Tower 9Exhaust Fan 10Fan Powered Variable Air Volume Boxes 11Unitary Heat Pump - Water Source 12Pumps 13Return Fan 14Roof Top Unit - Gas Heat/Dx Cooling 15Supply Fan 16Variable Air Volume Boxes 17Point to Point Checks 18

Page C-2

Page 3: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

AIR HANDLING UNIT

AIR HANDLING UNIT

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationSeismic restraintsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationPlenums clean and free of loose materialTemporary start-up filtersFire & balance dampers positionedDuct system tested and cleanedAccess doors, Insulation and interior lightsLocal valving/piping (HWS, CHWS, steam, condensate, drains)Drain pansHeating and cooling coilsFailed position of heating coil valve-open to coilFailed position of cooling coil valve-closed to coilOutside air, return air and mixed air dampersHumidifierBuilding & fan room cleanlinessFilter bank, DP switch gauge and photohelicsElectrical wiring completeMotor rated for VSD serviceOverload protection (sized correctly)Disconnect switch (tested)Instrumentation (temperature, volume, pressure & humidity )Control system - point to point checks complete

START-UPVSD Start-up by manufacturer's representativeDirection of rotationElectrical interlocks - stop/startFreeze protection operationalLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual : Final operating filters installed

Page C-3

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 4: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

CONTROLS AIR COMPRESSOR

CONTROLS AIR COMPRESSOR

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationSeismic restraintsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationLocal valving/piping (air, condensate, drains)Bypass piping around dryer and filterIntake air filterInlet and outlet air silencersHigh pressure relief valveStatus indicators- local/remote.Pressure gauges.Air receiver with automatic and manual drainsDuplex oil and particle separators.Duplex Micron discharge filtersFlexible air connectionRefrigerated air dryer.Pressure reducing valveIsolation valve on each high pressure line.Electrical wiring completeOverload protection (sized correctly)Disconnect switch (tested)Local startersControl system - point to point checks complete

START-UPStart-up by manufacturer's rep. (report attached)Direction of rotationElectrical interlocks - stop/startLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual :

Page C-4

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 5: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

HOT WATER BOILER

HOT WATER BOILER

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationBoiler certificate / registration (copy attached)Mounting/support systemSeismic restraintsMaintenance clearanceLocal valving/piping correct (including expansion tanks and make-up water).Chemical cleaning and treatment (report attached)Temperature and pressure gaugesPressure relief valvePressurization and leak testsBlowdown systemSafety interlocks- low water and high temperatureCombustion air supply and ventilationInsulation/laggingStack and breachingCombustion chamber inspectionFuel system (including emergency shutdown and gas inspection certificate)Electrical wiringOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks complete

START-UPStart HWS pumps to create load.Start boiler circulation pumps.Boiler startup by supplierSupplier certificate or log provided for start-up and all specified and regulatory tests.

Page C-5

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 6: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

CHILLER

CHILLER

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support systemSeismic restraintsMaintenance clearanceLocal valving/piping correct (including expansion tanks, make-up water and identification).Pressurization and leak testsSupplier pre-start (including charging the system) (report attached)Chemical cleaning and treatment (report attached)Insulation/laggingRefrigerant relief valveTemperature and pressure gaugesFlow switches - safety interlocksTemperature sensors - safety interlocksUL and ASME approvalsControl/diagnostic/programmable moduleDDC interface with specified points e.g. chilled water setpoint and demand limiter analogue inputs, and % load, run status and alarm outputsElectrical wiringOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks complete

START-UPStart condenser water systemStart chilled water system to create loadChiller startup by supplierModulation through specified rangeSafety interlocksSupplier certificate or log provided for start-up and all specified and regulatory tests

Page C-6

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 7: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

HEATING AND COOLING COILS

HEATING AND COOLING COILS

ITEM COMMENTSPRE-START-UP INSPECTION

Mounting/support systemSeismic restraintsBuilding & fan room cleanlinessPlenums clean and free of loose materialDuct system tested and cleanedFire & balance dampers positionedLocal valving/piping (HWS, CHWS, steam, condensate, drains)Drain pansCoils clean, fins straight and not damaged or corroded.Water system cleaned & treated (report attached)Strainers - construction screens removed.Failed position of heating coil valve-open to coilFailed position of cooling coil valve-closed to coilControl system - point to point checks complete

START-UPFreeze protection operationalUse Point-to-Point Checklist to record:

Water inlet temperature: __________FWater discharge temperature: __________FAir inlet temperature: __________FAir discharge temperature: __________F

Page C-7

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 8: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

COOLING TOWER

COOLING TOWER

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system/vibration isolationSeismic restraintsMaintenance clearance and access panelsLocal valving/piping correct (including make-up water, meter, back flow preventer and identification).Cooling tower leak testSump clean and free of loose materialBlowdown, drain and overflow systemChemical cleaning & treatment (report attached)Temperature gaugesTemperature sensorsVibration sensorSump heater aquastat.Sump heater, low water and high temp. cutout.LubricationVanes or dampersHigh and low speed motors (or VSD)Motor guards.Sheaves and belts, alignment and tensionFreedom of rotationElectrical wiring (complete)Overload protection (sized correctly)Disconnect switch (tested)Local control panel with DDC interfaceControl system - point to point checks complete

START-UPStart cooling tower fansDirection of rotationMotor Amps - Rated: Actual : Motor Volts - Rated: Actual : Start condenser water pumpsModulate or stage cooling tower fans and/or vanesVibration & noise level acceptable

Page C-8

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 9: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION /START-UP CHECKLIST

EXHAUST FAN

EXHAUST FAN

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationFlexible connectionsSeismic restraintsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationPlenum/volute clean and free of loose materialDuct system tested and cleanedFire & balance dampers positionedExhaust louvers tested (gravity or motorized) Building & fan room cleanlinessElectrical wiringMotor rated for VSD serviceOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks complete

START-UPStart-up by manufacturer's rep. (report attached)Direction of rotationElectrical interlocks - stop/startLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual :

Page C-9

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 10: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION /START-UP CHECKLISTFAN POWERED VARIABLE AIR VOLUME BOXES

FAN POWERED VARIABLE AIR VOLUME BOXES

PRE-START-UP INSPECTIONCheck the following equipment for: VAV 1 VAV 2 VAV 3 VAV 4 VAV 5

Local valving and pipingLocal ductworkMounting support and seismic systemMaintenance access, access doors and insulationValve operation (reheat coil)Damper operationSensor location and operationFan freedom of rotationElectrical wiring completeOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks completeBuilding cleanliness

START-UPStart air handling system (see separate checklist)Local fan direction of rotationElectrical interlocks - stop/startSpeed selector switchLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated: Actual: Motor Volts - Rated : Actual : Final operating filters installed

Page C-10

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 11: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

UNITARY HEAT PUMP - WATER SOURCE

UNITARY HEAT PUMP - WATER SOURCE

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationSeismic restraintsLubricationTemporary start-up filterAccess doors and insulationDuct system completed and cleanedFire & balance dampers positionedD/X coil, water/refrigerant heat exchanger, reversing valve, compressorWater supply pipingStrainer, isolation and balance valve(s)Drain pipingDrain panFan freedom of rotationBuilding cleanlinessElectrical wiring completeOverload protection (sized correctly)Disconnect switch (tested)Local heating/cooling thermostat

START-UPStart-up by manufacturer's representative and certificate or log providedDirection of rotationElectrical interlocks - stop/startFan speed selector switchNo water or condensate leakageLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual : Final operating filters installed

Page C-11

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 12: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGPRE-START/START-UP CHECKLIST

PUMPS

PUMPS

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationPiping and valvingSeismic restraintsMounting/support system and vibration isolationFreedom of rotationLubricationElectrical wiringOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks complete

START-UPHWS or CHWS availableDirection of rotationElectrical interlocks - stop/startVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual :

Page C-12

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 13: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION /START-UP CHECKLIST

RETURN FAN

RETURN FAN

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationFlexible connectionsSeismic restraintsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationPlenums clean and free of loose materialDuct system tested and cleanedFire & balance dampers positionedBuilding & fan room cleanlinessElectrical wiringMotor rated for VSD serviceOverload protection (sized correctly)Disconnect switch (tested)Control system - point to point checks complete

START-UPStart-up by manufacturer's rep. (report attached)Direction of rotationElectrical interlocks - stop/startLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual :

Page C-13

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 14: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

ROOF TOP UNIT - GAS HEAT/DX COOLING

ROOF TOP UNIT - GAS HEAT/DX COOLING

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationMounting/support system and vibration isolationSeismic restraintsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationPlenums clean and free of loose materialTemporary start-up filtersFire & balance dampers positionedAccess doors, Insulation and interior lightsFilter bank, DP switch gauge and photohelicsLocal valving/piping (gas, condensate, pans, drains)Motorized dampersD/X expansion (cooling) coil and compressorD/X condensing coil and fansGas piping and valving completeGas inspection certificateRegulatory authority approved installation and burner control (certificate available)Building cleanlinessElectrical wiring completeOverload protection (sized correctly)Disconnect switch (tested)Local control module with DDC interfaceControl system - point to point checks complete

START-UPStart-up by manufacturer's representative with report and certificate or log providedDirection of rotationElectrical interlocks - stop/startLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual : Final operating filters installed

Page C-14

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 15: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION/START-UP CHECKLIST

SUPPLY FAN

SUPPLY FAN

ITEM COMMENTSPRE-START-UP INSPECTION

Commissioning lock-out procedures reviewedOperation and maintenance informationElectrical wiringMotor rated for VSD serviceOverload protection (sized correctly)Disconnect switch (tested)Mounting/support system and vibration isolationSeismic restraintsFlexible connectionsEquipment guardsAlignment & V-belt tensionFreedom of rotationLubricationPlenums clean and free of loose materialTemporary start-up filtersFire & balance dampers positionedInlet louvers tested (gravity or motorized)Duct system tested and cleanedAccess doors, Insulation and interior lightsBuilding & fan room cleanlinessFilter bank, DP switch gauge and photohelicsInstrumentation (temperature, volume, pressure & humidity )Control system - point to point checks complete

START-UPVSD Start-up by manufacturer's rep. (report attached)Direction of rotationElectrical interlocks - stop/startFreeze protection operationalLocal air leakage acceptableVibration & noise level acceptableMotor Amps - Rated : Actual : Motor Volts - Rated : Actual : Final operating filters installed

Page C-15

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 16: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION /START-UP CHECKLIST

VARIABLE AIR VOLUME BOXES

VARIABLE AIR VOLUME BOXES

PRE-START-UP INSPECTIONCheck the following equipment for:

local valving and pipinglocal ductworkmounting support and seismic systemmaintenance accessvalve operationdamper operationsensor location and operationControl system - point to point checks completeBuilding cleanliness

START-UPStart air handling system (see separate checklist)Local air leakage acceptable

Unit ID Room Reheat Ducting

Valving &

Piping

Mounting Support Seismic

Maint.access

Valve operation

Damper operation

Airflow Sensor

Temp. Sensor

Page C-16

PROJECT:

Equipment Name/Tag: Location:

System/Area Served: Related Equipment:

Pre-start checks by: Date: Start-up checks by: Date:

print name signature

Page 17: Appendix C Sample Format for System Verification and Start-Up ...

HVAC COMMISSIONINGSYSTEM VERIFICATION /START-UP CHECKLIST

CONTROLS POINT TO POINT CHECKS

POINT TO POINT CHECKS

Point Output Input Accept Comment

Description Name DO AI0%

AI50%

AI100% DI AI Y/N

Page C 17

PROJECT:

Equipment/System: Location:

Checked by: Date: Verified by: Date:

print name signature