Top Banner
Appendix C Canadian Pacific Rail License of Entry Document
14

Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

Jul 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

Appendix C Canadian Pacific Rail

License of Entry Document

Page 2: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

01-13283-GG-0000-SE-RPT-0001

Trans Mountain Expansion Project

License of Entry – CP Rail

Contractor Revision Date:

2017-03-06

Contractor Revision No.:

A

Page 1 of 10

Rev No.

Prepared by/ Date

Reviewed by/ Date

Approved by/ Date

TMEP Acceptance/

Date

Pages Revised

Issued Type

A

Trans Mountain Expansion Project

License of Entry – CP Rail

KMC Document # 01-13283-GG-0000-SE-RPT-0001 RA

Page 3: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL i LICENSE OF ENTRY

TABLE OF CONTENTS Table of Contents ....................................................................................................... i

1. Westridge Marine Terminal ................................................................................... 1

1.1 Project overview .............................................................................................. 1

1.1.1 Railway crossing ........................................................................................ 2

1.1.2 Dewatering equipment ................................................................................ 3

1.1.3 Trenchless crossing .................................................................................... 3

1.1.4 Derailment protection barriers ..................................................................... 4

1.1.5 Construction traffic access and laydown ...................................................... 4

1.1.6 Road widening ............................................................................................ 4

1.1.7 WATER main tie-in ..................................................................................... 4

1.2 Reclamation .................................................................................................... 5

1.3 Construction schedule ..................................................................................... 5

1.4 Safety ............................................................................................................. 5

Appendices

Appendix 1: Westridge Design Drawings

Appendix 2: PR ROW Construction Drawings

Page 4: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 1 LICENSE OF ENTRY

1. WESTRIDGE MARINE TERMINAL

1.1 PROJECT OVERVIEW Kiewit Ledcor Trans Mountain Partnership (KLTP) is currently planning and scheduling construction activities at the Kinder Morgan Canada (KMC) Westridge Marine Terminal (WMT) for the Trans Mountain Expansion Project (TMEP).

The WMT scope of work includes a new dock complex with three berths, expansion of the foreshore to accommodate new mechanical equipment, installation of new equipment in the facility, a tunnel connecting WMT to Burnaby Terminal and underground conduit connecting the WMT facilities south of the rail to the foreshore area (refer to Figure 1-1 and Figure 1-2).

Figure 1-1: Westridge Marine Terminal Expansion

Page 5: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 2 LICENSE OF ENTRY

Figure 1-2: Westridge Marine Terminal Expansion

In order to perform the work at WMT, KLTP requires access to the Canadian Pacific Railway (CPR) right of way (ROW), both North and South of the tracks, in the area immediately adjacent to the WMT. The access is requested for the following purposes:

1) Construction traffic crossing the railway, using the existing rail crossing 2) Set-up of dewatering equipment to support under rail boring activities 3) Installation of bore pits for trenchless crossing 4) Installation of derailment protection barrier 5) Construction traffic access and temporary laydown space 6) Road widening 7) Water Main Tie-in

1.1.1 RAILWAY CROSSING Construction traffic will use the existing railway crossings to access the foreshore area. These include the primary crossing through the Westridge Marine Terminal as well as the secondary crossing accessed through North Cliff Avenue.

While it is planned to maximize bulk material deliveries via marine equipment (barge shipments), there will be an increase in equipment crossing the railway in order to perform the work as not all materials can be logistically or feasibly transported to the site via marine equipment.

Page 6: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 3 LICENSE OF ENTRY

1.1.2 DEWATERING EQUIPMENT KLTP intends to set up dewatering equipment on the CPR ROW for the duration of the project (refer to Figure 1-3). The treated water coming out from the water treatment plant will be released into ocean through exiting culverts.

Figure 1-3: Example Dewatering Equipment

1.1.3 TRENCHLESS CROSSING Two sheet pile bore pits (refer to Figure 1-4) will need to be installed on the CPR ROW to allow for the trenchless crossing. These bore pits will be constructed of sheet pile cells, excavated to the required depth from which the underground conduit will be installed. Upon completion of the work, the ROW will be returned to grade. The trenchless crossing will be performed via Guided Horizontal Auger Bore (GHAB) from one bore pit into the other.

Page 7: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 4 LICENSE OF ENTRY

Figure 1-4: Example Trenchless Bore Pit

1.1.4 DERAILMENT PROTECTION BARRIERS Two derailment protection barriers will be installed during project construction as an added safety feature for future operations. One barrier, installed north of the CPR ROW, is approximately 285 meters in length covering the full length of the expanded foreshore. The second barrier, approximately 35 meters in length, is installed south of the CPR ROW in the area of the UG railway crossing.

Both installed barriers are outside of the CPR ROW, but require excavation onto the CPR ROW to allow for their construction.

1.1.5 CONSTRUCTION TRAFFIC ACCESS AND LAYDOWN

For the duration of the project, KLTP requests use of the CPR ROW for construction equipment access and material laydown.

1.1.6 ROAD WIDENING Road widening will take place at WMT to accommodate the increase traffic flow. This road widening includes a MSE wall south of the CPR ROW and a widening of the existing railway crossing. To perform both scopes of work, KLTP will require temporary construction access from the CPR ROW for material staging and equipment placement.

1.1.7 WATER MAIN TIE-IN KLTP will need to install a tee (refer to Figure 1-5) into the fire main to provide fire water supply throughout the project. The tie-in is on CPR ROW and is planned to be a 6 inch live tap half saddle tee complete with valve. The tie-in is the only work to be completed on CPR ROW and will be connected to

Page 8: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 5 LICENSE OF ENTRY

the fire main on the existing foreshore to support the project during construction. Once the construction work has been completed, the tie-in will be removed and the ground returned to original condition.

Figure 1-5: Water Main Tie-in

1.2 RECLAMATION After construction activities are completed in way of the CPR ROW, the ROW will be returned to its original condition.

1.3 CONSTRUCTION SCHEDULE Work is scheduled to commence at WMT in late summer 2017 and continue through to April 2020.

Construction activities are planned to take place in accordance with the hours established within the City of Burnaby noise bylaw. Bulk construction activities will take place Monday to Friday, 7:00 am to 8:00pm and Saturday, 9:00am to 8:00pm. Selected work activities will be performed outside of these hours, including nightshift and Sunday work.

Work at the Burnaby Mountain Tunnel will take place 24 hours per day up to 7 days per week.

1.4 SAFETY All work performed within close proximity of the rail tracks will be performed under the direction and supervision of a CPR flag person.

Separation of the construction work from the railway will be maintained through a construction fence installed with a 4 meter offset from the tracks (refer to Figure 1-6).

Page 9: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL 6 LICENSE OF ENTRY

Figure 1-6: Example Construction Fencing

Page 10: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

TRANSMOUNTAIN EXPANSION PROJECT

CONFIDENTIAL LICENSE OF ENTRY

APPENDIX 1 Westridge Design Drawings

Page 11: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

0 20m 40m 60m

PERMIT APPLICATIONJ

a

n

3

1

2

0

1

6

Page 12: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

PERMIT APPLICATIONJ

a

n

3

1

2

0

1

6

Page 13: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

0 50M20M10M

PERMIT APPLICATIONJ

a

n

3

1

2

0

1

6

Page 14: Appendix C Canadian Pacific Rail License of Entry Document · 2017-03-06 · License of Entry – CP Rail Contractor Revision Date: 2017-03-06 Contractor Revision No.: A Page 1 of

0 10M 20M 50M30M

PERMIT APPLICATIONJ

a

n

3

1

2

0

1

6