Top Banner

of 40

AP n MPS- final

Apr 07, 2018

Download

Documents

Kunwar Ravi
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/3/2019 AP n MPS- final

    1/40

    AGGREGATE PLANNING &MASTER PRODUCTION

    SCHEDULING

    Submitted To:- Submitted By:

    Dr. SUMEET SINGH JASIAL Kakul Jain (16)Sahiba Singh (20)

    Ravi Malik (37)

    Piyush Dwivedi (47)

  • 8/3/2019 AP n MPS- final

    2/40

    DEFINITION

    Aggregate planning is the process of

    developing, analyzing, and maintaining apreliminary, approximate schedule of the

    overall operations of an organization.

  • 8/3/2019 AP n MPS- final

    3/40

    Determine the resource capacity needed tomeet demand over an intermediate timehorizon

    Aggregaterefers to product lines or familiesAggregate planning matches supply and demand

    Objectives

    Establish a company wide game plan forallocating resources

    Develop an economic strategy for meetingdemand

  • 8/3/2019 AP n MPS- final

    4/40

    FLOW CHART OF AP

  • 8/3/2019 AP n MPS- final

    5/40

    AGGREGATE PLANNING

    STRATEGIES

    Level Strategy

    Chase Strategy

    Hybrid Strategy

  • 8/3/2019 AP n MPS- final

    6/40

    CHASE STRATEGY

    Capacities (workforce levels, output rates, etc.) are adjusted

    to match demand requirements over the planning horizon.

    Advantages:Investment in inventory is low, Labor utilization

    is kept high

    Disadvantage: The cost of adjusting output rates and/or

    workforce levels

  • 8/3/2019 AP n MPS- final

    7/40

    LEVEL STRATEGY

    Capacities (workforce levels, output rates, etc.) are kept

    constant over the planning horizon.

    Advantage: Stable output rates and workforce levels

    Disadvantages: Greater inventory costs, Increased overtime and

    idle time, Resource utilizations that vary over time

  • 8/3/2019 AP n MPS- final

    8/40

    A General procedure for aggregate planning consists ofthe following steps:

    1. Determine demand for each period.

    2. Determine capacities (regular time, overtime,subcontracting) for each period.

    3. Identify company or departmental policies that arepertinent (e.g., maintain a safety stock of 5 percent ofdemand, maintain a reasonably stable workforce).

    4. Determine unit costs for regular time, overtime,subcontracting, holding inventories, back orders,

    layoffs, and other relevant costs.5. Develop alternative plans and compute the cost for

    each.

    6. If satisfactory plans emerge, select the one that bestsatisfies objectives. Otherwise, return to step 5.

  • 8/3/2019 AP n MPS- final

    9/40

    LINEAR APPROACH TO AGGREGATE PLANNING

  • 8/3/2019 AP n MPS- final

    10/40

    AGGREGATE PLANNING USING LEVELSTRATEGY

  • 8/3/2019 AP n MPS- final

    11/40

    Planners for a company that makes several models of skateboards areabout to prepare the aggregate plan that will cover six periods. They

    have assembled the following information:They now want to evaluate a plan that calls for a steady rate of regular-time output, mainly using inventory to absorb the uneven demand butallowing some backlog. Overtime and subcontracting are not usedbecause they want steady output. They intend to start with zeroinventory on hand in the first period. Prepare an aggregate plan and

    determine its cost using the preceding information. Assume a leveloutput rate of 300 units (skateboards) per period with regular time (i.e.,1,8006 = 300). Note that the planned ending inventory is zero. Thereare 15 workers, and each can produce 20 skateboards per period.

  • 8/3/2019 AP n MPS- final

    12/40

  • 8/3/2019 AP n MPS- final

    13/40

    AGGREGATE PLANNING USING CHASESTRATEGY

  • 8/3/2019 AP n MPS- final

    14/40

    After reviewing the plan developed in the precedingexample, planners have decided to develop analternative plan. They have learned that one person isabout to retire from the company. Rather than replace

    that person, they would like to stay with the smallerworkforce and use overtime to make up for the lostoutput. The reduced regular-time output is 280 units perperiod. The maximum amount of overtime output per

    period is 40 units. Develop a plan and compare it to theprevious one.

  • 8/3/2019 AP n MPS- final

    15/40

  • 8/3/2019 AP n MPS- final

    16/40

    TRANSPORTATION NOTATION FORAGGREGATE PLANNING

  • 8/3/2019 AP n MPS- final

    17/40

  • 8/3/2019 AP n MPS- final

    18/40

  • 8/3/2019 AP n MPS- final

    19/40

    DISAGGREGATING THE AGGREGATE

    PLANMoving from the aggregate plan to a master schedule

  • 8/3/2019 AP n MPS- final

    20/40

    WHAT IS MASTER PRODUCTION

    SCHEDULING?

    Start with Aggregate plan

    Aggregate Sales Output level designed to meet targets

    Disaggregates

    Converts into specific schedule for each item

  • 8/3/2019 AP n MPS- final

    21/40

    MASTER PRODUCTION SCHEDULE

    Provides basis for:

    Making good use of manufacturing resources

    Making customer delivery promises

    Resolving tradeoffs between sales andmanufacturing

    Attaining strategic objectives in the sales and

    operations plan

  • 8/3/2019 AP n MPS- final

    22/40

    THE MASTER SCHEDULING PROCESS

  • 8/3/2019 AP n MPS- final

    23/40

    No Change

    +/- 5%

    Change

    +/- 10%

    Change

    +/- 20%

    ChangeFrozen

    FirmFull

    Open

    1-2

    weeks2-4

    weeks

    4-6

    weeks6+weeks

    MPS TIME FENCES

    Time to due

    date

  • 8/3/2019 AP n MPS- final

    24/40

    MASTER PRODUCTION SCHEDULING

    TECHNIQUES

    Available = inventory position at end of week

    = starting inventory + MPS

    forecast

    Plan to have positive inventory level

    Buffer in case production below plan

    Or demand higher than anticipated MPS row is amount to make, MRP system has to

    figure out how to make it

    A ailable

  • 8/3/2019 AP n MPS- final

    25/40

    MPS TECHNIQUES EXAMPLE

    Week

    1 2 3 4 5 6 7 8 9 10 11 12Forecast 5 5 5 5 5 5 15 15 15 15 15 15

    Available 25 30 35 40 45 50 45 40 35 30 25 20

    MPS 10 10 10 10 10 10 10 10 10 10 10 10

    On hand 20

    Lot size Q = 10; OH1 = 20 is from previous periods

    A level production MPS:

    Available:

    Period 1: 20+10-5 = 25

    Period 2: 25+10-5 = 30

    etc.

    MPS is constant

    Available:

  • 8/3/2019 AP n MPS- final

    26/40

    MPS TECHNIQUES EXAMPLE

    Week

    1 2 3 4 5 6 7 8 9 10 11 12Forecast 5 5 5 5 5 5 15 15 15 15 15 15

    Available 20 20 20 20 20 20 20 20 20 20 20 20

    MPS 5 5 5 5 5 5 15 15 15 15 15 15

    On hand 20

    Lot size Q = variable; OH1 = 20 is from previous periods

    A chase production MPS:

    MPS is variable

    Available:

    Period 1: 20+5-5 = 20

    Period 2: 20+5-5 = 20

    etc.

  • 8/3/2019 AP n MPS- final

    27/40

    Week 1

    Week

    1 2 3 4 5 6 7 8 9 10 11 12

    Forecast 5 5 5 5 5 5 15 15 15 15 15 15

    Available 15 10 5 30 25 20 5 20 5 20 5 20

    MPS 30 30 30 30On hand 20

    Lot size Q = 30; OH1 = 20 is from previous periods

    Consider the following MPS.Forecasts for weeks 1 6 wereestimated to be 5 units

    Available:

    Period 1: 20-5 = 15

    Period 2: 15-5 = 10Period 3: 10-5 = 5

    Period 4: 5-5+30 = 30

  • 8/3/2019 AP n MPS- final

    28/40

    Week 2Week

    2 3 4 5 6 7 8 9 10 11 12 13

    Forecast 10 10 10 10 10 15 15 15 15 15 15 15

    Available 0 -10 10 0 -10 -25 -10 -25 -10 -25 -10 -25

    MPS 30 30 30 30

    On hand 10

    Lot size Q = 30; OH2

    = AV1

    = 10

    In week 2, forecasts for weeks 2 6

    were revised from 5 to 10 units.Actual demand in period 1 was 10units. As the Available row indicates,unless MPS is revised, demandfrom period 3 on will not be met,except for period 5

    Available:

    Period 1: 20-10 = 10Period 2: 10-10 = 0

    Period 3: 0-10 = -10

    Period 4: -10-10+30 = 10

    etc.

    Available:

  • 8/3/2019 AP n MPS- final

    29/40

    Week 2Week

    2 3 4 5 6 7 8 9 10 11 12 13

    Forecast 10 10 10 10 10 15 15 15 15 15 15 15

    Available 30 20 10 30 20 5 20 5 20 5 20 5

    MPS 30 30 30 30 30

    On hand 10

    Lot size Q = 30; OH2 = AV1 = 10

    Revised MPS meets increased demands in periods 1 6. AllAvailable quantities are nonnegative

    Available:

    Period 1: 20-10 = 10

    Period 2: 10+30-10 = 30

    Period 3: 30-10 = 20

    Period 4: 20-10 = 10Period 5: 10+30-10 = 30

    etc.

  • 8/3/2019 AP n MPS- final

    30/40

    AVAILABLE-TO-PROMISE (ATP)

    Quantity of items that can be promised tothe customer

    Difference between planned production andcustomer orders already received

    AT in period 1 = (On-hand quantity + MPS in period 1)

    - (CO until the next period of planned production)ATP in period n = (MPS in periodn)

    - (CO until the next period of planned production)

  • 8/3/2019 AP n MPS- final

    31/40

  • 8/3/2019 AP n MPS- final

    32/40

    ROUGH-CUT CAPACITY PLANNING

    Feasibility check of master production schedule

    Historical ratios of loads placed on work centersused

    Workloads assumed to fall in period and items

    demanded

  • 8/3/2019 AP n MPS- final

    33/40

    MANUFACTURING

    ENVIRONMENTS

    Production-to-Stock (PTS) Eg.- Motorcycles

    Assemble-to-Order (ATO)- Eg. Fast foodrestaurants

    Make-to-Order (MTO) Eg. Restaurants

    How to manage

    the increasing

    level ofcomplexity and

    uncertainty?

  • 8/3/2019 AP n MPS- final

    34/40

    MARUTI SUZUKI ALTO

  • 8/3/2019 AP n MPS- final

    35/40

    Maruti Suzuki produces Alto on a production-to-stock

    basis.

    The demand is shown as:

  • 8/3/2019 AP n MPS- final

    36/40

    The safety stock for the inventory is not

    fixed.

    The fixed lot size is 8000.

    The beginning inventory is 400.The final assembly line has a weekly

    capacity of 99 hours available.

    Each Alto car requires 22 seconds of final

    assembly.

  • 8/3/2019 AP n MPS- final

    37/40

  • 8/3/2019 AP n MPS- final

    38/40

    As the plant is already under-loaded, there can be morenumber of cars that can be manufactured during the weeks.

    ROUGH- CUT CAPACITY PLANNING

  • 8/3/2019 AP n MPS- final

    39/40

    CONCLUSION

    The MPS unit should reflect the companys

    approach to the business environment in which it

    operates.

    Available-to-promise information should be derivedfrom the MPS and provided to the sales

    department.

    A final assembly schedule should be used to convert

    the anticipated build schedule into the final buildschedule.

  • 8/3/2019 AP n MPS- final

    40/40

    The MPS activity & the role of the master

    production scheduler must be clearly defined

    organizationally.

    The MPS can be usefully considered as a set of firmplanned orders.

    The MPS should be evaluated with a formal

    performance measurement system.