8/3/2019 AP n MPS- final
1/40
AGGREGATE PLANNING &MASTER PRODUCTION
SCHEDULING
Submitted To:- Submitted By:
Dr. SUMEET SINGH JASIAL Kakul Jain (16)Sahiba Singh (20)
Ravi Malik (37)
Piyush Dwivedi (47)
8/3/2019 AP n MPS- final
2/40
DEFINITION
Aggregate planning is the process of
developing, analyzing, and maintaining apreliminary, approximate schedule of the
overall operations of an organization.
8/3/2019 AP n MPS- final
3/40
Determine the resource capacity needed tomeet demand over an intermediate timehorizon
Aggregaterefers to product lines or familiesAggregate planning matches supply and demand
Objectives
Establish a company wide game plan forallocating resources
Develop an economic strategy for meetingdemand
8/3/2019 AP n MPS- final
4/40
FLOW CHART OF AP
8/3/2019 AP n MPS- final
5/40
AGGREGATE PLANNING
STRATEGIES
Level Strategy
Chase Strategy
Hybrid Strategy
8/3/2019 AP n MPS- final
6/40
CHASE STRATEGY
Capacities (workforce levels, output rates, etc.) are adjusted
to match demand requirements over the planning horizon.
Advantages:Investment in inventory is low, Labor utilization
is kept high
Disadvantage: The cost of adjusting output rates and/or
workforce levels
8/3/2019 AP n MPS- final
7/40
LEVEL STRATEGY
Capacities (workforce levels, output rates, etc.) are kept
constant over the planning horizon.
Advantage: Stable output rates and workforce levels
Disadvantages: Greater inventory costs, Increased overtime and
idle time, Resource utilizations that vary over time
8/3/2019 AP n MPS- final
8/40
A General procedure for aggregate planning consists ofthe following steps:
1. Determine demand for each period.
2. Determine capacities (regular time, overtime,subcontracting) for each period.
3. Identify company or departmental policies that arepertinent (e.g., maintain a safety stock of 5 percent ofdemand, maintain a reasonably stable workforce).
4. Determine unit costs for regular time, overtime,subcontracting, holding inventories, back orders,
layoffs, and other relevant costs.5. Develop alternative plans and compute the cost for
each.
6. If satisfactory plans emerge, select the one that bestsatisfies objectives. Otherwise, return to step 5.
8/3/2019 AP n MPS- final
9/40
LINEAR APPROACH TO AGGREGATE PLANNING
8/3/2019 AP n MPS- final
10/40
AGGREGATE PLANNING USING LEVELSTRATEGY
8/3/2019 AP n MPS- final
11/40
Planners for a company that makes several models of skateboards areabout to prepare the aggregate plan that will cover six periods. They
have assembled the following information:They now want to evaluate a plan that calls for a steady rate of regular-time output, mainly using inventory to absorb the uneven demand butallowing some backlog. Overtime and subcontracting are not usedbecause they want steady output. They intend to start with zeroinventory on hand in the first period. Prepare an aggregate plan and
determine its cost using the preceding information. Assume a leveloutput rate of 300 units (skateboards) per period with regular time (i.e.,1,8006 = 300). Note that the planned ending inventory is zero. Thereare 15 workers, and each can produce 20 skateboards per period.
8/3/2019 AP n MPS- final
12/40
8/3/2019 AP n MPS- final
13/40
AGGREGATE PLANNING USING CHASESTRATEGY
8/3/2019 AP n MPS- final
14/40
After reviewing the plan developed in the precedingexample, planners have decided to develop analternative plan. They have learned that one person isabout to retire from the company. Rather than replace
that person, they would like to stay with the smallerworkforce and use overtime to make up for the lostoutput. The reduced regular-time output is 280 units perperiod. The maximum amount of overtime output per
period is 40 units. Develop a plan and compare it to theprevious one.
8/3/2019 AP n MPS- final
15/40
8/3/2019 AP n MPS- final
16/40
TRANSPORTATION NOTATION FORAGGREGATE PLANNING
8/3/2019 AP n MPS- final
17/40
8/3/2019 AP n MPS- final
18/40
8/3/2019 AP n MPS- final
19/40
DISAGGREGATING THE AGGREGATE
PLANMoving from the aggregate plan to a master schedule
8/3/2019 AP n MPS- final
20/40
WHAT IS MASTER PRODUCTION
SCHEDULING?
Start with Aggregate plan
Aggregate Sales Output level designed to meet targets
Disaggregates
Converts into specific schedule for each item
8/3/2019 AP n MPS- final
21/40
MASTER PRODUCTION SCHEDULE
Provides basis for:
Making good use of manufacturing resources
Making customer delivery promises
Resolving tradeoffs between sales andmanufacturing
Attaining strategic objectives in the sales and
operations plan
8/3/2019 AP n MPS- final
22/40
THE MASTER SCHEDULING PROCESS
8/3/2019 AP n MPS- final
23/40
No Change
+/- 5%
Change
+/- 10%
Change
+/- 20%
ChangeFrozen
FirmFull
Open
1-2
weeks2-4
weeks
4-6
weeks6+weeks
MPS TIME FENCES
Time to due
date
8/3/2019 AP n MPS- final
24/40
MASTER PRODUCTION SCHEDULING
TECHNIQUES
Available = inventory position at end of week
= starting inventory + MPS
forecast
Plan to have positive inventory level
Buffer in case production below plan
Or demand higher than anticipated MPS row is amount to make, MRP system has to
figure out how to make it
A ailable
8/3/2019 AP n MPS- final
25/40
MPS TECHNIQUES EXAMPLE
Week
1 2 3 4 5 6 7 8 9 10 11 12Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 25 30 35 40 45 50 45 40 35 30 25 20
MPS 10 10 10 10 10 10 10 10 10 10 10 10
On hand 20
Lot size Q = 10; OH1 = 20 is from previous periods
A level production MPS:
Available:
Period 1: 20+10-5 = 25
Period 2: 25+10-5 = 30
etc.
MPS is constant
Available:
8/3/2019 AP n MPS- final
26/40
MPS TECHNIQUES EXAMPLE
Week
1 2 3 4 5 6 7 8 9 10 11 12Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 20 20 20 20 20 20 20 20 20 20 20 20
MPS 5 5 5 5 5 5 15 15 15 15 15 15
On hand 20
Lot size Q = variable; OH1 = 20 is from previous periods
A chase production MPS:
MPS is variable
Available:
Period 1: 20+5-5 = 20
Period 2: 20+5-5 = 20
etc.
8/3/2019 AP n MPS- final
27/40
Week 1
Week
1 2 3 4 5 6 7 8 9 10 11 12
Forecast 5 5 5 5 5 5 15 15 15 15 15 15
Available 15 10 5 30 25 20 5 20 5 20 5 20
MPS 30 30 30 30On hand 20
Lot size Q = 30; OH1 = 20 is from previous periods
Consider the following MPS.Forecasts for weeks 1 6 wereestimated to be 5 units
Available:
Period 1: 20-5 = 15
Period 2: 15-5 = 10Period 3: 10-5 = 5
Period 4: 5-5+30 = 30
8/3/2019 AP n MPS- final
28/40
Week 2Week
2 3 4 5 6 7 8 9 10 11 12 13
Forecast 10 10 10 10 10 15 15 15 15 15 15 15
Available 0 -10 10 0 -10 -25 -10 -25 -10 -25 -10 -25
MPS 30 30 30 30
On hand 10
Lot size Q = 30; OH2
= AV1
= 10
In week 2, forecasts for weeks 2 6
were revised from 5 to 10 units.Actual demand in period 1 was 10units. As the Available row indicates,unless MPS is revised, demandfrom period 3 on will not be met,except for period 5
Available:
Period 1: 20-10 = 10Period 2: 10-10 = 0
Period 3: 0-10 = -10
Period 4: -10-10+30 = 10
etc.
Available:
8/3/2019 AP n MPS- final
29/40
Week 2Week
2 3 4 5 6 7 8 9 10 11 12 13
Forecast 10 10 10 10 10 15 15 15 15 15 15 15
Available 30 20 10 30 20 5 20 5 20 5 20 5
MPS 30 30 30 30 30
On hand 10
Lot size Q = 30; OH2 = AV1 = 10
Revised MPS meets increased demands in periods 1 6. AllAvailable quantities are nonnegative
Available:
Period 1: 20-10 = 10
Period 2: 10+30-10 = 30
Period 3: 30-10 = 20
Period 4: 20-10 = 10Period 5: 10+30-10 = 30
etc.
8/3/2019 AP n MPS- final
30/40
AVAILABLE-TO-PROMISE (ATP)
Quantity of items that can be promised tothe customer
Difference between planned production andcustomer orders already received
AT in period 1 = (On-hand quantity + MPS in period 1)
- (CO until the next period of planned production)ATP in period n = (MPS in periodn)
- (CO until the next period of planned production)
8/3/2019 AP n MPS- final
31/40
8/3/2019 AP n MPS- final
32/40
ROUGH-CUT CAPACITY PLANNING
Feasibility check of master production schedule
Historical ratios of loads placed on work centersused
Workloads assumed to fall in period and items
demanded
8/3/2019 AP n MPS- final
33/40
MANUFACTURING
ENVIRONMENTS
Production-to-Stock (PTS) Eg.- Motorcycles
Assemble-to-Order (ATO)- Eg. Fast foodrestaurants
Make-to-Order (MTO) Eg. Restaurants
How to manage
the increasing
level ofcomplexity and
uncertainty?
8/3/2019 AP n MPS- final
34/40
MARUTI SUZUKI ALTO
8/3/2019 AP n MPS- final
35/40
Maruti Suzuki produces Alto on a production-to-stock
basis.
The demand is shown as:
8/3/2019 AP n MPS- final
36/40
The safety stock for the inventory is not
fixed.
The fixed lot size is 8000.
The beginning inventory is 400.The final assembly line has a weekly
capacity of 99 hours available.
Each Alto car requires 22 seconds of final
assembly.
8/3/2019 AP n MPS- final
37/40
8/3/2019 AP n MPS- final
38/40
As the plant is already under-loaded, there can be morenumber of cars that can be manufactured during the weeks.
ROUGH- CUT CAPACITY PLANNING
8/3/2019 AP n MPS- final
39/40
CONCLUSION
The MPS unit should reflect the companys
approach to the business environment in which it
operates.
Available-to-promise information should be derivedfrom the MPS and provided to the sales
department.
A final assembly schedule should be used to convert
the anticipated build schedule into the final buildschedule.
8/3/2019 AP n MPS- final
40/40
The MPS activity & the role of the master
production scheduler must be clearly defined
organizationally.
The MPS can be usefully considered as a set of firmplanned orders.
The MPS should be evaluated with a formal
performance measurement system.