Annexure: A DETAILS OF CONTRACTS PLACED BY OPEN TENDER (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works) (Status for the Month of APRIL 2013-MARCH 2014) Works Awarded : APRIL 2013 S. N. Tende r No. Date of opening Description of Item/ Work LOA No. and date Contractor’s Name and address Quantity (for supply contract)/ Estimated Cost (For Engg./Elect. /S&T/ Mech. etc Works) Rate (for supply contract)/ Tendered Cost (For Engg./Elect./S&T/Mec h. etc Works) Value of Contract Scheduled completion date (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) 1 IRCON/ MECH/102 9/ RCF.RBL- II/Induction Heating Machine/18 5 dtd. 30.10.12 23.11.2012 Supply of 01 No. Induction Heating Machine for mounting of fork on anti-roll bar at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA) IRCON/MECH/1029/ RCF.RBL- II/Induction Heating Machine/185 dtd.01.04.13 M/s Unitech Instruments , Unit No.: 24, Dewan & Shah, Industrial Estate No.: 7, Navghar, Vasai East, Thane - 401210 (01 no.) `4.45 Lacs (01 no.) `3,90,171/- `3,90,171/- 03-months from the date of issue of LOA 2 IRCON/ MECH/102 9/ RCF.RBL- II/Load Lifting & Turning Device/RE T-I/119 Dtd. 30.10.12 10.01.2013 Supply of 01 No. Load Lifting & Turning Device at Rail Coach Factory, Lalganj, Raebareli, UP- (INDIA) IRCON/MECH/ 1029/RCF-RBL- II/Multiple station/RET-I/119 dtd 05.04.13 M/s Vikrant Special Machines Pvt. Ltd, 90, Nayapatty Road, Kolkata – 700055 Tel.:033-2551-3070 Email: [email protected]1 set (02 nos.) `55.60 Lacs 1 set (02 nos.) `39,79,656/- `39,79,656/- 24-weeks from the date of issue of LOA 3 IRCON/ MECH/10 29/RCF.R BL-II/EOT Crane/44 dtd. 25.12.201 2 24.01.2013 Supply of (05 Nos.) 10/3 Ton Electric Overhead Travelling Cranes at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA) IRCON/MECH/ 1029/RCF-RBL- II/EOT Crane/44/2262 dtd 15.04.13 M/s Unique Industrial Handlers Pvt. Ltd., 206-207, Nahar & Seth Ind. Estate Chakala, Andheri (East), Mumbai-400 099 (05 nos.) `962.00 Lacs (05 nos.) `8,62,46,984/- `8,62,46,984/- 180-days from the date of issue of LOA 4 IRCON/ MECH/ 1029/ RCF.RBL- II/ Multiple Station/RE T/ 96 dtd. 11.01.2013 08.02.2013 Supply of 01 No. Multiple Station Machine (Combined Shearing, Punching, Cropping & Notching Machine) at Rail Coach Factory, Lalganj, Raebareli, UP IRCON/MECH/ 1029/RCF.RBL- II/Multiple Station/RET/96 dtd. 23.04.2013 M/s United Engineering Corpn., B-96, Mayapur Industrial Area, Phase-I, New Delhi-110 064 (01 no.) `46.44 Lacs (01 no.) `22,07,415/- `22,07,415/- 120-days from the date of issue of LOA
47
Embed
Annexure: A DETAILS OF CONTRACTS PLACED BY .... Annex.A Apr13-March14.pdfAnnexure: A DETAILS OF CONTRACTS PLACED BY OPEN TENDER (For Civil Engg. /Elect. Engg. /S & T/Mech. etc works)
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Annexure: ADETAILS OF CONTRACTS PLACED BY OPEN TENDER
(For Civil Engg. /Elect. Engg. /S & T/Mech. etc works)(Status for the Month of APRIL 2013-MARCH 2014)
27.02.2013 Supply of Hand Tools at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/ 1029/RCF.RBL-
II/Hand Tools/190/3000 dtd.
02.05.2013
M/s Machinery Marketing
Associates Pvt. Ltd, 2E/24,
Jhandewalan Extension, New Delhi – 110 055,
Fax: 011-23629909
`19.78 Lacs `17,56,630/- `17,56,630/- 30-days from the date of issue of PO
2 IRCON/MECH/1029/RCF-RBL-II/ Pipelines/ 028B dtd
30.10.2012
05.02.2013 Pipelines for Compressed Air, Argo mix, Nitrogen & Oxygen Gas Supply and Storage System in Shell & Bogie Shops
IRCON/MECH/ 1029/RCF-RBL-II/ Pipelines/028B dtd
10.05.2013
M/s Legris India Pvt. Ltd., Plot No.: 99, Pace City-1,
Sector-37, Gurgaon-122 001
Fax:0124-66173708
`1607.00 Lacs `17,21,50,978/- `17,21,50,978/-+
AMC for 5 years
`2,59,91,027/-
210-days from GAD approval
3 IRCON/MECH/1029/RCF. RBL-II/
Tapping Machine, Jig Saw
Machine & Hot Air
Welding Gun/192
dtd. 31.01.2013
25.02.2013 Supply of Tapping/Drilling Machine, Jig Saw (100 nos.) & Hot Air Gun (20 nos.) at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/ 1029/RCF.RBL-
II/Tapping Machine, Jig Saw Machine &
Hot Air Welding Gun/192 dtd. 13.05.2013
M/s Machinery Marketing
Associates Pvt. Ltd, 2E/24,
Jhandewalan Extension, New Delhi – 110 055,
Fax: 011-23629909
`24.55 Lacsincluding
Tapping, Drilling Machines and `17.80 Lacs
excluding Tapping, Drilling
Machine
`15,64,900/- for Jig Saw (100 nos.) & `1,75,980/- for Hot Air Gun (20
nos.) & Tapping & Drilling not ordered
`17,40,880/- 30-days from the date of issue of PO
4 IRCON/MECH/
1029/RCF. RBL-
II/Road Mobile
Crane/RET-I/53 dtd.
22.02.2013
18.03.2013 Supply of 02 Nos. Road Mobile Crane Capacity 10 MT at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/ 1029/RCF.RBL-II/Road Mobile
Crane/RET-I/53 dtd. 13.05.2013
M/s Escort Limited Construction
Equipment, 603, 6th Floor,
Vishal Bhawan, 95 Nehru Place,
New Delhi-110 019Tel.:011-26444821,Fax: 011-26444873
`18.00 Lacs (01 no.)`10,34,274/-
(02 nos.)`20,68,548/-
03-months from the date of issue of LOA
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)5 IRCON/
MECH/1029/RCF.RBL-II/Carline
Fab & Roof Acceptanc
e Fixtures/18
8/2809 dated
25.12.2013
08.02.2013 Supply of Roof Bearer, Side Wall & Carline Fabrication and Roof Acceptance Fixtures For LHB Coach at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/1029/RCF.RBL-II/Carline
Fab & Roof Acceptance
Fixtures/188/2809 dated 14.05.2013
M/s Steel Craft (India), Vill.: Kutbi
Nangal Road, Opp. 132 KV Power House, Batala-143 505
`9.90 Lacs `4,36,023/- `13,08,069/- 04-months from the date of issue of LOA
7 IRCON/J&K-
Cell/JAT/14/7004/1
7 Dtd.09.03
.13
02.04.2013 Construction of Passenger Amenities Center and other allied works including demolition of existing structures in connection with Multi Functional Complex (MFC) at Jammu Railway Station, J&K
IRCON/J&K-Cell/JAT/14/7004/17
Dtd.15.05.13
M/s Zeal Construction Co.,
J&K Bank Building, Pantha Chowk,
srinagar, Kashmir – 191 101
Mob.:0941900388309419060731
`211.06 Lacs 7.74% above `227.39 Lacs 06-months from the date of issue of LOA
8 IRCON/J&K-
Cell/JAT/14/1014/
Q-B/Hiring-
Veh-SINA-
NR/VH-10/256
Dtd.15.04.13
'03.05.2013 Hiring of Vehicles for Officers and Staff of Northern Railway associated with the Project works in connection with construction of Q-B Section of USBRL New Rail Link Project (J&K)
IRCON/J&K-SGR/Hiring Vehicle-
Srinagar/VH-10/450/240
Dtd.20.05.13
M/s Shabir Transporters,
Sagina Shopping Complex, Gogli Bagh, Srinagar
`15.78 Lacs 33% above `20.92 Lacs 12-months from the date of issue of LOA
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
9 IRCON/MECH/1029/RCF. RBL-II/
Portable Air
Compressor/ 118/RET
15.03.2013 Supply of 03 Nos. Portable Air Compressor at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/ 1029/RCF.RBL-II/Portable Air
Compressor/118/RET dtd. 21.05.2013
M/s Emprise Marketing, B-1/31 Sector-H, Aligarh, Lucknow-226 024
`12,96,000/- `23,59,090/- `23,59,090/- 03-months from the date of issue of LOA
11 IRCON/2049/ROB-
II-BIHAR/TENDER/L
C-3SPL/I/20
13/13 Dtd.
12.04.2013
03.05.2013 Construction of Road over Bridge both railway span and adjacent approaches span including Reinforced Earth wall/ Retaining wall in lieu of LC No 3SPL at Km. 51/09-10 between Hajipur- Muzaffarpur section on Barauni-Gorakphur Route in Sonepur Division of East Central Railway,Bihar
IRCON/2049/ROB-II-BIHAR/LC-
3SPL/LOA/104/1239 Dtd.27.05.2013
M/s BSC-C&C JV Plot No.:70, Sector-32,
Gurgaon – 122 001,Haryana
`3044.70 Lacs 12.50% above `34,25,29,193/-
15-months including the monsoon period
from the date of issue of LOA
12 IRCON/MECH/
1029/RCF. RBL-II/ Hyd.
Platform (3 Axis)/RET/
83
18.02.2013 Supply of 01 No. Hydraulic Platform with 3 Axis movement at Rail Coach Factory, Lalganj, Raebareli, UP-(INDIA)
09.04.2013 Construction of two nos. Road Under Bridges (RUB) by Cut & Cover technique comprising box of approximate opening sixe 7.0 x 3.65 m and 20 m length along with its approaches, drainage and allied road works etc. complete for RCF, Raebareli at Lalganj
30.04.2013 Construction of Road over Bridge both railway span and adjacent approaches span including Reinforced Earth wall/ Retaining wall in lieu of LC No 45 AB at Km. 324/13-14 between Chapra Kacheri-Goldengunj section in Varanasi Division of North Eastern Railway,Bihar
IRCON/2049/ ROB-II-BIHAR/LC-45AB/LOA/
105/1316 Dtd. 07.06.2013
M/s Tribeni Construction Ltd.,
New Town Square,
Office No.: 4M,Chinar Park,New Town,
Rajarhat, Kolkata – 700 136
`2430.44 Lacs Schedule-A : 3.00% above
Schedule-B : 3.00% above
Total amount:
Schedule-A : `2,04,81,796/-
Schedule-B : `22,98,53,968/-
`25,03,35,764/-
15-months including the
monsoon period from the date of
issue of LOA
2 IRCON/2044/GANGA BRIDGE
PATNA/ 16/24 Dtd. 27.04.13
30.04.2013 Casting RCC road deck on erected steel truss of rail cum road bridge across river ganga at Patna, for span 1 to 19 from Dighaghat end (1no.x64m + 18nos.X123m)
LOA No.: IRCON/2044/ Ganga
Bridge/Patna/16/ 24/2213/DIGHA Dtd.
13/14.06.2013
M/s BSC-C&C (JV),
Plot No.: 70,Sector-32,Gurgaon
PIN:122001Fax: 0124-4536799
E-mail: candc@candcinfra
structure.com
`2665.00 Lacs `30,49,93,362.70 `30,49,93,362.70 16-months from the date
of issue of LOA.
3 RCON/2044/
GANGA BRIDGE PATNA/ 16/25 Dtd.
27.04.13
21.05.2013 Casting RCC road deck on erected steel truss of rail cum road bridge across river Ganga at Patna, for span 20 to 38 from Pahleja Ghat end (1no.x64m + 18nos.x123m).
21.05.2013 Construction of Balance Work (Balance Portion of Railway Triangular Portion, Pun-Pun Arm & Mithapur Arm) For Road Over Bridge in Lieu of LC- 79 At Mithapur, Patna (Bihar) Including Railway Span of Mithapur Arm, Reinforced Earth Wall/ Retaining Wall
IRCON/2034/ ROB-I-BIHAR/LC-79/LOA/ 110/1408
Date:21.06.13
M/s Mehar Foundations & Civil Engineers
Pvt. Ltd.,31, Dun Shoping
Centre,Lallubhai Amichand
Compound, Tardeo Road, Mumbai – 400
007
`2502.93 Lacs 8.50% above `27,15,67,756/- 15-months including the
monsoon period from the date of
issue of LOA
6 IRCON/MECH/1029/RCF.RBL-II/Fixture for Bogie/198 dtd.:22.03.20
13
22.04.2013 Pressing Fixture for Anti Roll bar, Bogie Frame Lifting Tackle cum Bolster Fixing Fixture
IRCON/MECH/1029/RCF.RBL-II/Fixture for
Bogie/198/3071 dtd.:21.06.2013
M/s Vikrant Special Machines
Pvt. Ltd, 90, Nayapatty Road, Kolkata – 700055
Tel.:033-2551-3070 Email: vikrantspecial@r
ediffmail.com
`19,00,000/- `13,32,927/- `13,32,927/- 04-months including the
28.05.2013 Construction of Third leg of Road over Bridge including foundation, substructure, superstructure, slip road, Reinforced Earth wall, Retaining wall etc. in lieu of LC- 72 at Km 536 between Gulzarbagh and Patna Saheb Section in Danapur Division of E C Railway , Bihar
IRCON/2049/ ROB-II-BIHAR/LC-72
(3leg)/LOA/109/1400 Dtd.21.06.2013
M/s Naraindas Construction Pvt.
Ltd., 14/441, Vinodpur, Katihar
(Bihar)PIN-854105
`893.39 Lacs 8.96% above `9,73,43,754/- 15-months including the
monsoon period from the date of
issue of LOA
8 IRCON/2049/ ROB-II-
BIHAR/TENDER /LC-
159/I/2013/2 Date:11.01.1
3
01.02.2013 Construction of Road over Bridge both railway span and adjacent approaches span including Reinforced Earth wall/ Retaining wall in lieu of LC No:159 A/SPL at Km.164/15-16 between Jivdhara-Motihari Section on Barauni-Gorakhpur Route in Samastipur Division of East Central Railway – New ROB
IRCON/2049/ROB-II-BIHAR/LC-
159A/LOA/112/1422 Date:24.06.2013
M/s TRG Industries Pvt.
Ltd.,E-461, Greater
Kailash-II, Delhi-110 048
`5112.03 Lacs Schedule-A : 8.80% above
Schedule-B : 8.80% above
Total amount:
Schedule-A : `2,37,86,997/-
Schedule-B : `53,24,01,511/-
`55,61,88,508/-
15-months including the
monsoon period from the date of
issue of LOA
9 IRCON/MECH/
1029/RCF.RBL-II/Electrical Tampering
Furnace/RET/99 Dtd
24.01.2013
20.02.2013 01 No. Electrical Pre Heat Treatment Tempering Furnace
IRCON/MECH/1029/ RCF.RBL-II/Electrical
Tempering Furnace/RET/99/2955
dtd.:25.06.2013
M/s Kashyap Brothers, Pratap Ganj, Kalpi road, Kanpur – 208012
Ph.:0512-2237897Email:kashyapbros
@gmail.com
`10,80,000/- `8,74,502/- `8,74,502/- 03-months including the
`2,11,56,0000/- `1,30,43,043/- `1,30,43,043/- 02-months including
the monsoon
period from the date of
issue of LOA
11 IRCON/J&K
Cell/JAT/14/1014/DQ/Support-Services-
DQ-Section/M-19R/252
dtd.24.04.201
3
06.05.2013 Providing services for maintenance of IRCON's establishments and also providing services by way of assisting IRCON's Engineers during supervision of work and services for office up-keep and other miscellaneous work as required at various locations along the project alignment from Dharam to Banihal covering Ramban, Sangaldhan, Khari, Sumber, Kholi, Dharam, etc. in connection with Dharam Qazigund section of USBRL Project
IRCON/J&K Cell/JAT/14/1014/
DQ/Support-Services-DQ-
Section/M-19R/252
dtd.27.06.2013
M/s Star Constructions,
1st Floor, AI-Noor Complex,
Hyderpora, Bypass (West),
Kashmir, Srinagar –
190014 (J&K)Mob.:094190011
4509419006074Email: mail@
starconstructions. com
`172.23 Lacs 5.45% below `162.83 Lacs 12-months from the date
Construction of Balance work of Station Building & other associated miscellaneous work at Jaynagar Railway Station Yard in connection with Gauge conversion & construction of new B.G. Railway Line from Jaynagar (India) to Bardibas (Nepal)
LOA No.: IRCON/2050/BGL.JB
B/Tender/Pkg-01 (India)/255 Dtd.
08.07.2013
M/s Trishul Engicon Pvt. Ltd. ,
Shyam Savitri Enclave,
Main Road,Rajiv Nagar,
Post-Kesari Nagar,Patna-24
`106.12 Lacs 15.4% above estimated cost
`1,22,46,807.00 07.07.2014
2 IRCON/MECH/1029/RCF.RBL-II/lab Equipments/105
dtd 22.03.13
16.04.2013 Supply and Erection, Installation & Commissioning of Shore A&D Testing Equipment, Multy Cell Ageing Oven, Digital Melting Point Apparatus & Deep Freezer (04 nos.) 01-no. Each at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No.: IRCON/MECH/1029/
RCF/RBL-II/Lab Equipments/
105/3230 Dtd. 10.07.2013
M/s Innovative Electronics &
Systems, Lucknow
`23.19 Lacs Cost of Deep Freezer is
`3,93,250/- + Cost of Digital Melting Point Aparatus is `10,02,250/-
`13,95,500/- 20 weeks from the date of issue of PO
3 IRCON/MECH/1029/RCF.RBL-II/Bogie Frame
Machining Centre/73/RET-II dtd 22.03.13
22.04.2013 Supply and Erection, Installation & Commissioning of Bogie Frame Machining Centre (02 nos.) at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No.: IRCON/MECH/1029/RCF/ RBL-II/Bogie Frame Machining Centre/73/RET-
II/3286 Dtd. 16.07.13
M/s Shin Nippon Koki Co. Ltd., Tokyo, Japan
`6325.00 Lacs Cost of Machine is JPY
245,000,000.00(EXCLUDING
Custom duty) + AMC for 5 years is JPY 10,000,000.00
JPY 490,000,000.00
240 days from the date of opening of
LC
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
4 IRCON/MECH/1029/RCF.RBL
-I/ASRS/86/RET-1
dtd 17.04.13
24.05.2013 Supply and Erection, Installation & Commissioning of ASRS (06 nos.) at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No.: IRCON/MECH/1029/
RCF.RBL-I/ASRS/86/RET-
1/3300 Dtd. 17.07.2013
M/s Godrej Efacec Automation & Robotics Ltd,
Mumbai
`2678.40 Lacs `.27,00,68,311/- `27,00,68,311/- 180 to 240 days from LOA
5 IRCON/J&K-
Cell/JAT/14/Q-B
Housekeeping-SINA-
ORH/M-23/Dtd.
16.05.13
06.06.13 Providing housekeeping services for up keeping, watch & ward and maintenance of Officers Rest House (ORH) at Srinagar on Q-B New BG Rail Line Project
IRCON/J&K-Cell/JAT/14/1014/Q-
B/Housekeeping-SINA ORH/M-
23/Dtd. 18.07.2013
M/s Wani Construction,
Kursoo Padahahi Bagh, Srinagar, Kashmir, J&K
`37.96 Lacs 20.20% below `30.29 Lacs 12 Months from 20.07.2013
6 IRCON/CC/TN/GBSS-Patna/13/ 686 Dated 03/06/2013
24.06.2013 Assembly, erection/ launching of (7x123m) span from pier No.-19 to pier No.-26 and (1x64m)span between pier No.-37 to abutment A2, triangulated steel girders for new rail-cum-road bridge across river Ganga at Patna from Pahlejaghat (North island End) including transportation of fabricated components of (7x123m) span from fabrication workshop at Pahlejaghat end and (1x64m) span from fabrication workshop at Dighaghat End of river Ganga to launching site including casting of bed blocks and final coat of painting
LOA No.: IRCON/2044/Ganga Bridge/Patna/16/18/ 2975A/Digha/1633
21.06.2013 Disposal of 40mm size Aggregates and Boulder from Pirauna Camp at Km. 175+000 and 40mm Aggregate from Badagaon Camp at km.203+600 UP-05 Road Project
LOA No.IRCON/1020/NHAI/
UP-05/NIT/221/LOA/644
Dtd 03.08.2013
M/s Azad Earthmovers, Jhansi
35740 MT 350.00 per MT `1,31,86,950/- 18.08.2013
2 NIT-222
21.06.2013 Dismantling and/or removal of temporary structures at Badagaon, Orai & reclamation of the area of Badagaon Camp and Office by excavating unsuitable soil and filling suitable soil for cultivation purpose
LOA No.IRCON/1020/NHAI/
UP-05/NIT/222/LOA/642
Dtd 03.08.2013
M/s Mahendra Pal Singh, Orai
`20.50 Lacs `19.5 Lacs for dismantling and `10.35 Lacs for
reclamation
`29.85 Lacs 03.10.2013
3 NIT-223
21.06.2013 Dismantling and/or removal of Temporary structures at Badagaon, Orai & reclamation of the area of Badagaon Workshop and plant by excavating unsuitable soil and filling suitable soil for cultivation purpose
LOA No.IRCON/1020/NHAI/
UP-05/NIT/223/LOA/643
Dtd 03.08.2013
M/s Malkhan Singh, Orai
`13.50 Lacs `4.00 Lacs for dismantling and `8.02 Lacs for
reclamation
`12.02 Lacs 03.10.2013
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
4 e-Tender JH-18-XI-WB-IRCON
-05
03.07.2013 Construction & Maintenance of Road (1) Chiur To Hesla-3.971 Km (2) Cherwadag To Erahatu – 2.771 Km (3) Tungaon To Bartoli - 3.124 Km. (4) Burka To Jabra-3.957Km (5) Sotiya To Hutub-5.503Km (6) Jamhar To Kasira-5.112 Km(7) Sardula To Kasira-3.669 Km(8) Burhiroma To Jhapra - 3.393 Km. (9) Kurse To Kedli - 6.012 Km (10) Kedli To Bargani - 2.974 Km. (11) Padampur To Ronhe - 4.456 Km. (Total Length: 44.942 Km, Block: Karra, District: Khunti, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-18-XI-WB-IRCON-05/66 Date
05.08.2013
M/s Altima Infrastructure Pvt. Ltd.(AIPL), First
Floor, 351 A, Road No.5, Ashok Nagar Ranchi, Jharkhand
(Cost put to tender=1653+
190=`1843Lacs
`1843.30 Lacs `18,43,29,618.79 05.02.2015
5 IRCON/JK Cell/JAT/14
/1014/D-Q/Hiring-
Veh-Jammu/VH
-07/254 dtd.
17.06.13
05.07.2013 Hiring vehicles for IRCON Officers & Staff for J&K cell, Jammu in connection with USBRL Project work (J&K)
IRCON/JK-Cell/JAT/14/1014/DQ
/Hiring-Veh-Jammu/VH-07/3463/
dtd. 14.08.2013
M/s Fair Deal Tour & Travels, 75-A,
Last Morh, Gandhi Nagar, Jammu
J&K
20.16 Lacs 10.2% above 22.21 Lacs 12 Months from the date of issue
of LOA
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
6 e-Tender JH-18-XI-WB-IRCON
-06
03.07.2013 Construction & Maintenance of Road (1) Hakaduba To Bundu Sima via Buruhatu - 3.834 Km. (2) Landup To Bandi - 4.299 Km. (3) Landup To Buruhatu - 1.573 Km. (4) Landup To kera - 6.786 Km. (5) Jojohatu To pirihtu - 2.003 Km. (6)Suukriserang To Budhudih-3.36 Km (7) Tirla To Budhudih - 2.562 Km. (8) Rewa To Manhu - 3.052 Km. (9) Aani dih To Takra - 1.67 Km. (10) Chukru To Namkom Block Sima via Karge - 3.492 Km. (11) Potamgara To Chitramu - 2.678 Km. (12) Siladon To Dasgaua - 3.75 Km. (13) Ganeor To Remta - 1.774 Km. (14) T09 To Dokar - 3.373 Km. Km. (15) Chikor To Somatoli - 1.099 Km. Km. (16) Taro To Barbanda - 3.023 Km. Km. (17) Sarasom To Putidag - 1.046 Km. (Total Length : 49.374 Km, Block: Khunti, District: Khunti, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-18-XI-WB-IRCON-06/82 Date
17.08.2013
M/s Vijay Kumar Sahu, Parmath
Nagar, Tupudana, Ranchi 834003
(Cost put to tender
=1779+200 = `1979 Lacs)
`1979.06 Lacs `19,79,00,001.00 17.02.2015
7 e-Tender JH-18-XI-WB-IRCON-
29
06.07.2013 Construction & Maintenance of Road : 1) Dumbatoli Pitch Road to Chete via Jogitoli, 3.13Km 2) Tongritoli to Bhandratoli 3.08Km 3) Kumbatoli More to Dumertoli, 4.735Km., 4) Katcrpa More to Chhota Khunta, 2.80Km., 5) Piska Railway Station Bhagalpur to Tusmu, 2.30Km 6) Daladali Bagichatoli to Satish Chowk NH23, 2.77Km 7) Bandhya to Badka Khunta Road, 3.27Km., (Total Length: 22.085 Kms,Block: Ratu-II, District: Ranchi, Jahrkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-18-XI-WB-IRCON-29/82 Date
17.08.2013
M/s Sambhu Singh, Aryapuri,
Ratu Road, Ranchi, Jharkhand
(Cost put to tender
= 882+100 = Rs.982.00
Lacs)
Rs.982.42 Lacs `9,31,68,433.01 17.02.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
8 IRCON/MECH/1029/RCF.RBL-II/Heavy
Duty Turret Lathe/RET-1/3502 dtd 14.05.2013
06.06.2013 Supply and Erection, Installation & Commissioning of Heavy Duty Turret Lathe Machines – 02 no. at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No. IRCON/MECH/1029/RCF. RBL-II/Heavy Duty Turret Lathe/ RET-1/3502 dated
19.08.2013
M/s Sahil Alloy & Machine Tools (P)
Limited, Batala
`170.00 Lacs `1,00,00,000/- `2,00,00,000/- 04 months from the date of issue
of LOA.
9 IRCON/ELECT/102
9/RCF-RBL/Ind. Lights/49
31.05.2013 Supply of 200W, 230V AC, 50Hz, highway induction light fittings for new Rail Coach Factory, Rae Bareli (U.P.)
LOA No. IRCON/ELECT/1029
/RCF-RBL/ Ind. Lights/49 dtd 27.08.2013
M/s Crompton Greaves Ltd., 3rd Floor, Express Building, 9-10, Bahadur Shah Zafar Marg, Near
ITO Crossing, New Delhi-110002
`388.00 Lacs Supply only at unit rate of
`10092.90 each
`1,89,14,094.60 3 months
10 e-Tender JH-15-XI-WB-IRCON-
39
22.07.2013 Construction of Bridge over Goitha River on T03 to Kadwa road,Block: Dhurki, District: Garhwa, Jharkhand
LOA No.: IRCON/2054/PMGSY-JKR/JH-15-XI-WB-IRCON-39/126 Date
25.06.2013 Design, Supply, Installation, Testing, Commissioning and Handing Over of 2 x 750 KVA 11/0.433 KV Sub-station for KaTPS Railway Siding at Jhalawar
LOA No. IRCON/3014/RRVUNL.RS/SS/System Electric/02/1241
dated 31.08.2013
M/s System Electric Works, 244, Shopping
Centre, Kota – 7 Tel:0744-2363804
Email: systemselectricals@g
mail.com
`161.29 Lacs `128.79 Lacs Three Month from date of Issue of LOA
i.e. 30.11.2013
12 IRCON/3014/RRVUNL.RS/Tender/High
Rise Mast/03 Dated
28.06.2013
19.07.2013 Design, Supply, Installation, Testing, Commissioning and Handing Over of High Rise Mast for KaTPS Railway Siding at Jhalawar
LOA No. IRCON/3014/RRVUNL.RS/SS/High Rise Mast/REW/03/1238 dated 31.08.2013
M/s REW Constructions Pvt. Ltd, D-5, Industrial
Area Site-A, Mathura (U.P) -
281004
`162.66 Lacs `147.14 Lacs Four Month from date of issue of
`30.78 Lacs `25,46,962/- `25,46,962/- 90 days from LOA
2 IRCON/MECH/1029/RCF.RBL-
II/Lab Equipment
s/111 dated
07.03.2013
05.04.2013 Supply and Erection, Installation & Commissioning of (01 No.) Accelerated Weathering Tester, Toxcity Tester & (01 No.) Motorized Digital Rockwell Hardness Tester at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No. CON/MECH/1029/R
CF .RBL-II/Lab Equipments/111/
3889 dated 04.09.2013
M/s A.S.I Sales Pvt. Ltd., New
Delhi
`18.36 Lacs (01 NO.) Accelerated Weathering
Tester `6,06,900/-
+(01 No.)
Motorised Digital Rockwell
Hardness Tester `1,98,900/-
`8,05,800/- 2 months from LOA/PO for Accelerated
Weathering Tester and 3 months from LOA for Motorized Digital Rockwell Hardness Tester
3 IRCON/MECH/1029/RCF.RBL-II/Shell
Assembly line/117/RE
T dated 31.01.2013
09.03.2013 Supply and Erection, Installation & Commissioning of Integrated Shell Assemblies and Assembly Lines -01 no.at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No. IRCON/MECH/1029/
RCF. RBL-II/Shell Assembly
line/117/RET/ 3624 dated 16.09.2013
M/s SIS Corporation, Korea
`20000.00 Lacs Cost of Full System: USD
26,999,240.00 + INR
2,39,36,491.25/-
USD 26,999,240.00 + `2,39,36.491.25
365 days from LC
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)4 IRCON/3
015/TN/ROB-
RAJ/SGNR-
119/RT-2/13/44
03.5.2013 Construction of four lane Road over Bridge (ROB) with approaches as per specifications & Quality Control Standards etc. complete including detailed design & drawings in Lieu of LC-119 at Sri Ganganagar in Rajasthan State.
29.11.2012 Design, Supply, Installation, testing & commissioning of Grid connected Solar power plant of 2MW capacity with all the electrical and associated equipments including civil works at New Rail Coach Factory, Rae Bareli (U.P.)
No. IRCON/ ELECT/1029/RCF-
RBL/ SOLAR PLANT/ 44B dated
20.09.2013
M/s Tata Power Solar Systems
Ltd., 78, Electronics City, Phase I, Hosur
Road, Bangalore - 560 100
`22.40 Cr SITC Contract `15.60Cr. 8 months
6 IRCON/MECH/1029/RCF.R
BL-II/WHEEL
AXLE ASSLY
LINE/RET-I Dtd.
27.03.13
23.04.2012 Supply and Erection, Installation & Commissioning of Integrated Wheel & Axle Machining and Assembly Line with Synchronized and Automated Material Handling System for Wheel Shop at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No. IRCON/MECH/1029/ RCF.RBL-II/WHEEL
AXLE ASSLY LINE/95/RET-I/3673
dtd 25.09.2013
M/s Danobat Group, Spain
`15657.00 Lacs Cost of Imported supply portion of machines with concomitant
accessories Euro 15,664,299/-
+ Cost of Indigenous supply Rs.68,503,496/- +
Cost of Spares Euro 235,285
Euro 15,899,584 + `68,503,496/-
300 days from approval of GADs
7 NIT-225
28.06.2013 Disposal of laboratory equipments, survey instruments and Hydraulic jacks from IRCON's laboratory/store situated at Badagaon Camp at km 203+600 UP-05 Road Project
05.08.2013 Construction of Bridge over Khutisruti River on Sulumdag to Ursela road, Package: JH18JB006A, Block: Bishrampur, District: Palamau, Jharkhand
16.08.2013 Construction & Maintenance of Road : (1) REO Road To Kanaidih- 3.288 Km (2) REO Road To Kairasol - 2.091 Km (3) REO Road To Chirudih - 1.33 Km. (4) REO Road To Kumirkatta-2.57 Km (5) REO road To Taldih - 2.516 Km. (6) REO Road To Musabil - 2.483 Km. REO Road To Jangla - 3.845 Km. (Total Length: 18.123 Kms, Block: Kathikund-I, Dist- Dumka, Jharkhand).
LOA No.: IRCON/2054/LOA/P
KG-63/233 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=864.94+102.65= `967.59 Lacs
`967.04 Lacs `9,64,91,389.00 04.10.2014
5 e-Tender JH-05-XI-WB-IRCON-
64
16.08.2013 Construction & Maintenance of Road : (1) REO Road To Ledapathar-3.144 Km (2) Nayadih To Makrachattar- 2.75 Km (3)REO Road To Phitkoria- 3.214 Km (4) REO Road To Kulkat - 4.527 Km. (Total Length: 13.635 Kms, Block: Kathikund-II, Dist- Dumka, Jharkhand).
LOA No.: IRCON/2054/LOA/P
KG-64/237 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=675.14+85.3= `760.44 Lacs
`759.24 Lacs `7,57,57,041.00 04.10.2014
6 e-Tender JH-05-XI-WB-IRCON-
65
16.08.2013 Construction & Maintenance of Road : (1) Asanpahari R To Gamrah-2.929Km (2) REO Road to ERO - 4.781 Km. (3) Nargang REO Road to Balidih - 7.842 Km (Total Length: 15.552 Kms, Block: Kathikund III, Dist- Dumka, Jharkhand).
LOA No.: IRCON/2054/LOA/P
KG-65/242 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=698.99+76.38= `775.37 Lacs
`774.90 Lacs `7,73,35,854.00 04.10.2014
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)7 e-
Tender JH-05-XI-WB-IRCON-
66
16.08.2013 Construction & Maintenance of Road (1) Par Paisa more To Pakuriya via Par Paisa - 0.952 Km. (2) Jiwanpur To Bhorebadi - 1.313 Km (3) Jitara to Patusala - 1.129 Km. (4) Pakuriya To Kalakata - 4.357 Km. (5) REO Road 8th KM
To Belbuni- 3.005 Km (6) Bisundiha To Bagedar - 2.219 Km. (7) Chapuria To Sulanga - 1.164 Km. (8) REO Road Dhangara More To Dhangara - 2.912 Km. (9) Palopisa To Bhuskipahari - 3.946 Km. (Total Length: 20.997 Kms, Block: Raneshwar-I, Dist- Dumka, Jharkhand).
LOA No.: IRCON/2054/LOA/P
KG-66/240 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=995.62+139.48= `1135.10 Lacs
`1134.15 Lacs `11,32,19,287.00
04.10.2014
8 e-Tender JH-05-XI-WB-IRCON-
67
16.08.2013 Construction & Maintenance of Road : (1) Karikader To Kathalia - 2.475 Km. (2) Mohanpur To Leya - 2.658 Km. (3) PWD Road Sangrampur More To Sangrampur - 3.353 Km. (4) Patjora Road To Navgram-1.743 Km (5) Jaitara To Menhdipur - 1.6 Km. (6) Dumra Road To Harjora- 2.395 Km (7) Chotta Harkhi To Bara Harkhi - 2.345 Km (8) Manikdih To Murguni - 1.78 Km. (9) Tarni To Sunderdiha - 8.072 Km. (10) REO Road 9th KM To Bhitra - 3.361 Km. (Total Length: 29.782 Kms, Block: Raneshwar-II, Dist- Dumka, Jharkhand).
LOA No.: IRCON/2054/LOA/P
KG-67/239 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=1334.24+194.08= `1528.32 Lacs
`1527.38 Lacs `15,24,49,213.00
04.10.2014
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)9 e-
Tender JH-05-XI-WB-IRCON-
68
16.08.2013 Construction & Maintenance of Road : (1) Hathwari To Shankarpur- 3.195 Km (2) REO Road To Patranga- 3.265 Km (3) Sharpur To Porabansari - 2.15 Km. (4) Chukapari To Goradangal-1.631 Km (5) PWD Road To Makarapahari - 2.465 Km. (Total Length - 12.706 Km. Block: Shikaripara-I, Dist: Dumka).
LOA No.: IRCON/2054/LOA/P
KG-68/238 dated 04.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=604.9+78.43= `683.33 Lacs
`682.43 Lacs `6,81,27,302.00 04.10.2014
10 e-Tender JH-05-XI-WB-IRCON-
69
16.08.2013 Construction & Maintenance of Road : (1)Matyajori More To Matyajori-2.861 Km (2) Banspahari To Katpahari-3.659 Km (3)Sidhachatar More To Dhobaghat-
9.567Km (4) REO Road Birajpur To Barmasi-11.323 Km (Total Length - 27.41Km., Block: Shikaripara-II, Dist: Dumka.)
LOA No.: IRCON/2054/LOA/P
KG-69/234 dated 04.10.2013
M/s Adarsh Construction, Lal Kothi, Main Road,
Mairwa, Siwan, Bihar
=1326.16+180.21= `1506.37 Lacs
`1505.95 Lacs `14,93,82,930.00
04.10.2014
11 IRCON/ MECH/
1029/RCF.RBL-II/
Lathe Machines/62/RET-
II dtd 14.05.201
3
14.06.2013 Supply and Erection, Installation & Commissioning of 03 Nos. Lathe Machines (i.e. 01 no. for Tool Room & 02 Nos. for Mill-Wright Shop) at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
LOA No. RCON/MECH/1029/RCF. RBL-II/ Lathe Machines/62/RET-II
dtd.07.10.2013
M/s ABL Machine Tools, Nagpur
3 nos. `18.71 Lacs `40,34,300/- 90 days from LOA
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)12 IRCON/
CC/TN/JBRLP-
2050/13/685 Dt. - 20.05.20
13
12.06.2013 Construction of Civil work including Embankment, Blanketing, major & minor Bridges and other ancillary works from International Boundary (near AKAUNNHA Village) OSRAHI Section Km 2+975 to Km 27+775 (near Kapileshwar Mahuwa Village) of Nepal side alignment portion in connection with Gauge Conversion & Construction of New Broad Gauge Railway Line from JAYNAGAR(INDIA) To BARDIBAS(NEPAL)
LOA No. IRCON/2050/BJL.JBB/Embkt/Km 2+97 to km 27+77/14/1547
18 months excluding monsoon period from 1st July to 30th Sept. from
the date of issue of LOA i.e.
07.07.2015
13 IRCON/MECH/1029/RCF.R
BL-II/Overhead Tool rails/222
dtd 29.06.13
08.08.2013 Supply and Erection, Installation & Commissioning of Overhead Friction free Monorail System with Pneumatic Balancers, provision for Pneumatic & Electrical Tools and Work Lighting for seat and berth assembly station at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/1029/RCF.RBL-
II/Overhead Tool rails/22/3740 dtd
08.10.13
M/s Diya Technologies,
Lucknow
`87.66 Lacs `81,15,058/- `81,15,058/- 90 days from LOA
14 IRCON/ J&K-Cell/ JAT/14/1014/D-Q/
Hiring Veh -CAO-
NR/271
04.10.2013 Quotation for: Hiring of vehicles for Officers and Staff working in the office of the CAO, Northern Railway, USBRL Project, Jammu (J&K)
M/s Dreamland Travels, Shop No.9, Bus Stand, Jammu-180001
`4.30 Lacs 17.4% above `5.05 Lacs 3 months from the date of
deployment.
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)15 IRCON/
MECH/1029/RCF.RBL
-II/Invert
ed Metallur
gical Microscope/RET-I/112
dtd 07.03.1
3
04.04.2013 Supply and Erection, Installation & Commissioning of Inverted Metallurgical Microscope with Image Analyser (01 no.) at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/1029/RCF.RBL-II/Inverted
Metallurgical Microscope/RET-
I/112/3778 dtd 17.10.13
M/s Banbros Engineering Pvt. Ltd, New Delhi
1 no. `30.00 Lacs `16,89,795/- 3 months from LOA
16 e-Tender JH-21-XI-WB-IRCON-
71
16.08.2013 Construction & Maintenance of Road : (1) Ambatoli Dhorhi Road to Chapabari – 5.100 Km (2)REO Main Road to Pakritoli Nawatoli Road - 1.424 Km (3) REO Main Road Kutmakachhar to Murambatoli via Jhimari - 4.600 Km (4) Gariajor Barkibiura Road To Urumkela - 6.005 Km (Total Length: 17.13 Kms, Block: Kurdeg, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-21-XI-WB-IRCON-71/280 Date 21.10.2013
M/s SK Construction, Devi
Mandap Road, Ratu Road, Ranchi
(Jharkhand)
=658.42+59.83=`718.25 Lacs
`718.24 Lacs `7,07,24,933.17 21.04.2015
17 e-Tender JH-05-XI-WB-IRCON-
01A
16.09.2013 Construction & Maintenance of Road : (1) Pipra To Amjhari - 1.89 Km. (2) Karudih To Parbatpur - 2.207 Km. (3) PWD ROAD RANGA To PAHARPUR-1.718 Km (4) Tenijor To Duaria - 2.979 Km. (Total Length: 8.800 Kms, Block: Gopikander-I, District: Dumka, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-05-XI-WB-IRCON-01A/278
Date 21.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
=539.44+57.81 = `597.25 Lacs
`598.56 Lacs `5,95,27,226.33 21.10.2014
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
18 e-Tender JH-05-XI-WB-IRCON-
01C
16.09.2013 Construction & Maintenance of Road (1) Rangamora To Kulaipura more-3.15 Km (2) Kundapahari To Mahulda bari - 6.046 Km. (Total Length: 9.20 Kms, Block: Gopikander-III, District: Dumka, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-05-XI-WB-IRCON-01C/279
Date 21.10.2013
M/s Raja Construction, Taj Colony, Panchayati
Akhara, Gaya, Bihar – 823001
`593.34 Lacs `(512.1+79.96)=`592.06 Lacs
`5,88,80,743.48 21.10.2014
19 e-tender.: IRCON/2
049/ ROB-II-
BIHAR/e-Tender/2013/23
Date:14-09-2013
07.10.2013 Supply, fabrication, assembly , erection and painting of Bowstring girder in Railway portion, steel stair case in connection to Construction of ROB at LC-35B at Danapur in state of Bihar
`154 Lakhs Schedule-A-1%(-) `15,211,163.88 6(Six) months from the date of issue of
LOA
21 e-Tender JH-17-XI-WB-IRCON-
56
05.08.2013 Construction of Bridge across Batare River on P.W.D. Road to Gahwara in 1st Km. Road, Package No. - JH 1714, Length - 52.1 m. (District - Palamau, Block - Hariharganj)
05.08.2013 Construction of A) Bridge over Nimia Nallah on PWD Road (Bara) Sighna to Lalgarwa road (JH18JB002A) and B) Bridge over Douwarpar Nallah on PWD Road (Bara) Sighna to Lalgarwa road (JH18JB002B), Block: Nodiha/Chattarpur, District: Palamau, Jharkhand
16.08.2013 Construction & Maintenance of Road : (1) Bijupara Khelari to Khashshitoli - 1.503 Km. And (2) Choriya Road to Madhukam - 3.126 Km. ( Total Length: 4.63Kms, Block: Chanho, District: Ranchi, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-18-XI-WB-IRCON-80/291 Date 23.10.2013
M/s LavKush Kumar Singh,
Lalitgram, Ratu, Ranchi
=214.48+24.61= `239.09 Lacs
`239.07 Lacs `2,37,59,044.85 23.04.2015
24 e-Tender JH-05-XI-WB-IRCON-
01B
16.09.2013 Construction & Maintenance of Road : (1) Paharpur I To Paharpur I-1.907 Km (2) Burhichhapar To Burhichhapar - 2.165 Km. (3) Purnakhor To Purnakhora - 3.4 Km. (Total Length: 7.480 Kms, Block: Gopikander-II, District: Dumka, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-05-XI-WB-IRCON-01B/293
Date 23.10.2013
M/s Raja Construction, Taj
Colony, Panchayati
Akhara, Gaya, Bihar – 823001
`(425.01+47.1) = `472.11 Lacs
`472.12 Lacs `4,69,52,214.70 23.10.2014
25 e-Tender JH-18-XI-WB-IRCON-
13B
16.09.2013 Construction & Maintenance of Road (1) HUMTA To MOISODIH-6.40 Kms, (2) NAWADIH To KUCHIDIH- 3.20 Kms, (Total Length: 9.60 Kms, Block: Bundu-II, District: Khunti, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-18-XI-WB-IRCON-13B/289
Date 23.10.2013
M/s Sanjay Singh, Harmu Road, Gadi Khana,
Ranchi
`(377.53+41.33)= `418.86 Lacs
`418.87 Lacs `4,08,92,129.27 23.04.2015
26 e-Tender JH-05-XI-WB-IRCON-
30B
16.09.2013 Construction & Maintenance of Bridge: 1) Tarni To Sunderdiha at Km. 7+612, (L078-Raneshwar), (Total No. of Bridges: 01 nos, Block:Raneshwar, Dist: Dumka, Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-05-XI-WB-IRCON-30B/288
Date 23.10.2013
M/s Asit Kumar, New Babupara, Post+ Thana-
Dumka, Jharkhand-814101
`52.10 Lacs `51.58 Lacs `51,05,568.00 23.10.2014
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)27 e-
Tender JH-02-XI-WB-IRCON-
49A
16.09.2013 Construction of Bridge over: A) Jharna Nallah on Holamgadha Khurd to Kari road (Package: JH02JB004A, Block: Chatra Sadar), B) Karam Bahua River on Holamgadha Khurd to Kari road (Package: JH02JB004B, Block: Chatra Sadar), (No. of Bridges-02, Block: Chatra sadar District: Chatra, State: Jharkhand)
LOA No.: IRCON/2054/PMGS
Y-LOA/JH-02-XI-WB-IRCON-49A/287
Date 23.10.2013
M/s Sahay Construction, Awall Mohalla, Court Road,
03.05.2013 Design & Construction of Two Lane Rail under Bridge (RUB) by Cut & cover Technique comprising two boxes, i.e One for each lane including it’s approaches, all Design, Casting & Placing box segments under traffic block, Drainage, Allied Road works & Junction Development etc. complete, as per Specifications & Drawings, Maintaining all Quality Control Standards complete near LC-119 at Sriganganagar in Rajasthan State
05.08.2013 Construction of 1) Bridge across Kawal Nala on B.T. Road to kawal in 1st km Road, Package No. - JH 1714A, Length - 39.14 m., 2) Bridge across Hariya Nala on T04 to Dagara in 2nd Km Road, Package No. - JH 1714, Length - 58.7 m., (District - Palamau, Block - Chhattarpur)
LOA No.: IRCON/2054/PMGSY-JKR/JH-17-XI-WB-IRCON-55/306 Date
03.07.2013 Supply and Erection, Installation & Commissioning of Heavy Duty Sewing Machine, Water Bath Equipment, Low & High Impedence Analyser, Chemical Balance & DFT meter (01 no.) at Rail Coach Factory at Lalganj, Raebareli, UP-(INDIA)
IRCON/MECH/1029/RCF.RBL-II/Heavy
Duty Sewing Machine & Lab
Equipment/145/3830 dated 28.10.13
M/s Matrix Eco Solutions Pvt. Ltd.,
New Delhi
1 no. `1.00 Lac `15,900/- 3 months from LOA
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)33 NIT-
23001.10.2013 Transportation of Plant
& Equipments from IRCON's UP-05 Road Project situated at Badagaon camp at Km 203+600 to CIC Noida/ Greater Noida including loading/ unloading of plant & equipments from UP-05 Road Project
14.10.2013 Supply, Installation, Testing & Commissioning of External Lighting & Power Supply System to Misc. Buildings at New Rail Coach Factory, Rae Bareli (U.P.)
LOA IRCON/ELECT/1029/RCF-RBL/BAL.EL.
Works/51 dtd 01.11.2013
M/s K V Prateek Enterprises, 301, Suneja Tower-I, District Centre, Janakpuri, New Delhi-110058
`815.39 Lacs SITC Contract `7.64 Crore 6 Months
6 IRCON/MECH/1029/RCF.RBL-II/lab
Equipment/162
dtd. 07.06.13
04.07.2013 Physical Analytical Balance, Low Load Portable Hardness Tester & Digital Hot Plate
30.10.2013 Design, Supply, Installation, Testing, Commissioning & AMC of SCADA System for display and controls of power supplies and distribution networks at New Rail Coach Factory, Rae Bareli (U.P.)
LOA No. ???issued on
12.11.2013
M/s Synergy Systems & Solutions, Faridabad
`215.39 Lacs `2.21 Crores `1.98 Crore 4 months
11 e-tender No.IRCON/J&K-
Cell/JAT/14/1014/D-Q/GRP Post etc.
– halt Station/M-29/268/55
12, dtd. 29.0813
17.09.13 Construction of GRP Post, electric Gazette (x-ray) Shed, 2 Nos. Morchas,Chain Link Fencing and other allied works at Hillar Shahabad Station KM 164/708 of Qazigund-Banihal Section of J&K rail Link Project (M-29)
IRCON/J&K-Cell/JAT/14/1014/D-Q/GRP Post etc. – Halt Station/M-
29/268/5512, dtd.13.11.13
M/s Inam & Co., Kaka Road, Nai Sarak, Srinagar,
J&K-190001
`65.33 Lacs 10.5% above `72.16 Lacs 4 months from the date of issue of
28.10.2013 Construction & Maintenance of Road (1) Pandripani Jaldega to Banmali Road - 4.00 km (2) NH Joram to Kahupani Pahantoli Road - 4.57 km (3)Pandripani Jaldega to Pandripani - 1.970 km (Total Length: 10.540 Kms, Block: Thethaitanger-IA, District: Simdega, Jharkhand)
IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-09A1/410 Dtd. 21.11.2013
M/s Krishna Construction
`440.40 Lacs `440.41 Lacs `439.41 Lacs 20.05.2015
15 e-Tender JH-18-XI-WB-
IRCON-31A
28.10.2013 Construction & Maintenance of Road – Phase XI : (1) Chiur To Hesla at km. 2+060 (L025-Karra), (2) Burka To Jabra at km. 2+760 (L035-Karra), (3) Burhiroma To Jhapra at km.2+460 (L053-Karra), (4) Taro To Barbanda at Km.1+575 (L045-Khunti), (Total No. Of Bridges: 04, Block: Karra & Khunti, District: Khunti, State: Jharkhand)
IRCON/2054/PMGSY/LOA/JH-18-XI-
WB-IRCON-31A/405 Dtd. 21.11.2013
M/s Mahamaya Enterprises
`281.13 Lacs `278.36 Lacs `278.36 Lacs 20.05.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)16 e-
Tender JH-05-XI-WB-
IRCON-30A1
28.10.2013 Construction & Maintenance of Road – Phase XI : 1) Asanpahari R To Gamrah at Km.1+402,(L022-Kathikund), 2) Narganj REO Road to Balidih at Km.7+050,(L054-Katikund), 3) Banspahari To Katpahari at Km.1+456, (L034-Shikaripara), 4) Sidhachatar To Dobhaghat at Km. 7+892, (L036-Shikaripara), (Total No. of Bridges: 04 nos, Dist: Dumka, Jharkhand)
IRCON/2054/PMGSY/LOA/JH-18-XI-
WB-IRCON-30A1/416 Dtd. 22.11.2013
M/s Mahamaya Enterprises
`203.91 Lacs `201.91 Lacs `199.89 Lacs 21.05.2015
17 IRCON/CC/TN/
CGRLP/JVCs Office/ 13/687, Dt. 03.06.201
3
05.07.2013 Internal finishing work, partitions, false ceiling, modification of toilets, plumbing, electrical and sanitary works etc. in connection with Setting up new office for JVCs at Raipur (Chhattisgarh)
IRCON/CGRLP/LOA/13/ JVC’s office/13/687
DT.26.11.2013
M/s VAS Nirman, 22 Maulshree
Vihar, V.I.P. Road, Puraina, Raipur,
CG
`35.85 Lacs `35.85 Lacs `31,87 Lacs 3 months
18 e-Tender JH-21-XI-WB-
IRCON-20A1
28.10.2013 Construction & Maintenance of Road- 1). Arani to Purnadih 0.500 Km. 2). Biru to pataratoli 2.1 Km. , 3). Harijantoli to telitoli 3.4km 4). Belgarh to bhnwarpani 3.90 Km. ,5). Kudrum to Bhandartoli 1.6 Km. 6). Khuntitoli to Ghosra 4.2 Km, (Total length 15.7 Km, Block- Simdega Sadar-I, District :Simdega)
IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-20A1/423 Dtd. 26.11.2013
Md. Yasin Construction
Pvt. Ltd
`693.69 Lacs 692.34 ` 692.34 Lacs 25.05.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
19 e-Tender JH-21-XI-WB-IRCON-75A
28.10.2013 Construction & Maintenance of Road : Jarket to Badomda 17.50 km. (Total Length:17.50Km, Block :Bano-III, District Simdega
IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-75A/424 Dtd. 26.11.2013
Md. Yasin Construction
Pvt. Ltd
`724.61 Lacs `724.62 Lacs `724.62Lacs 25.05.2015
20 e-Tender.
: IRCON/2049/
ROB-II- BIHAR/
e-Tender/2013/24 Date:31
-10-2013
19.11.2013 Supply, fabrication, assembly , erection and painting of Bowstring girder in connection to Construction of ROB at LC-47B at Begusarai in state of Bihar
IRCON/2049/ROB-II-Bihar/LC-
47B/Steel/LOA/131/2534,
Dtd.30.11.13
M/s. SSG Techno
Services Pvt. Limited, 29,
Ashutosh Pally, P.O: Garia,
Kolkata-700084
`365.69 Lacs 0.10% below `365.32 Lacs 06 Months from the date of issue of LOA
`17,84,532/- `14,64,169/- `14,64,169/- 30 days from PO
8 IRCON/ J&K-Cell/ JAT/14/
1014/D-Q/ Hiring
Veh-Bnhl-NR/VH-09/269,
dtd. 28.10.13
12.11.2013
Hiring of vehicles for Officers and Staff associated with the project works in Connection with the construction of Dharam-Qazigund Section of USBRL New Rail Link Project (J&K) (VH-09)
`142.00Lacs `76.65 Lacs `76.65 Lacs 90 days from the date of issue of
LOA
2 IRCON/J&K-
Cell/JAT/14/1014/
DQ/T-74R-
A/300, Dtd.25.07
.13
13.09.13 Construction of tunnel T-74R balance work from Adit between KM 127/660 to KM 130/950 (Length 3290m) on DQ Section of USBRL Project (Package: T-74R-A)
13-12-13 Supply of Power Supply System for Minor Gates for Sri Lanka Railways
IRCON/9038/SLR.S&T/PSL MX/122-1053 dt. 04.02.14
M/s. Statcon Power Controls
Ltd. Gautam Budh Nagar,
NOIDA
50 USD 3955.69 USD 19,997,784.50
6 months from date of issue of
LOA
2 e-Tender JH-21-XI-WB-IRCO
N-09B2
22.01.14 Construction & Maintenance Works of
(1)Pandripani Jaldega to Gandatoli - 4.748 km (2)
NH 23 Kereya to Dangtoli - 2.250 km
(3)NH 23 to Kurpani via Kundpani - 2.775 km
(4)NH 23 Kereyadangtoli Road to
Panginpahar Road - 0.825 km (5) Jogbahar
Ambapani to Changurbera - 2.100 km
(Total Length: 12.698 Kms, Block:
Thethaitanger-IB, District: Simdega,
Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-09B2/598 Date
07.02.2014
M/s Krishna Construction
540.11 Lac 540.22Lac 539.67 Lac 03.09.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)3 e-
Tender JH-21-XI-WB-IRCO
N-10A2
22.01.14 Construction & Maintenance Works of (1) Aurwrabahar Dumki Road To Ambatoli - 1.865 Km (2) Royantoli to Bhawandipa Road - 2.215 Km (3) Thethaitanger Bolba Road to Auwrabahar Chhuria Dumki Oriss - 10.435 Km (Total Length: 14.515 Km, Block: Thethaitanger-II A, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-10A2/596 Date
07.02.2014
M/s Krishna Construction
600.22 Lac 599.62 Lac 599.62 Lac 03.09.2015
4 e-Tender JH-21-XI-WB-IRCO
N-77A1
22.01.2014
Construction & Maintenance Works of
(1)Gobardhabasa at NH-23 to Manjhartoli 6.0
km, (2) Karmatoli SH to Karkotoli 3.30 km.,
(3)Pahantoli at Kolebira-1 Manoharpur to
Rabutoli 4.20 km, (Total Length 13.50 km., Block
Kolebira-1 , Dist. Simdega.)
LOA No.: IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-77A1/596 Date
07.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
665.89Lac 665.89Lac 665.83Lac 19.08.2015
5 e-Tender JH-18-XI-WB-IRCO
N-13A1
22.01.2014
Construction & Maintenance Works of (1) BAGHADIH TO CHOTODIH - 3.60 Kms, (2) BICHKATOLI TO PAWADHI-1.30 Kms, (3) DAMI TO KOLENGHATU-3.20 Kms, (4) EDAIHATU TO PANDRA VIA BANABURA-4.60 Kms, (Total Length: 12.70 Kms, Block: Bundu-I, District: Khunti, Jharkhand)
LOA No.: IRCON/2054/PMGSY/LOA/JH-18-XI-
WB-IRCON-13A1/602 Date
12.02.2014
M/s Adarsh Construction
`586.13Lac `586.13 Lac `575.50 Lac 03.09.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)6 e-
Tender JH-18-XI-WB-IRCON-28A
22.01.2014
Construction & Maintenance Works of 1) Bajpur to Chaulli via Hisir , 1.25Km., 2) Dahutoli Road to Doriyatoli ,3.03Km., 3) Sarnatoli to Siramtoli, 1.62Km, 4) REO Hochar to Patratoli, 1.755 Km., 5) Nawatoli More to Gangatoli, 1.60Km., 6) Tiputoli to Childag, 2.51Km., 7) REO Road Ekkaguri to Ekkaguri, 0.99Km., 8) Reo Road To Gariyatoli,, 1.56Km., 9) NH23 Satish Chowk to Nagri Bandhya, 4.97Km., (Total Length: 19.285 Kms, Block: Ratu-I, District: Ranchi, Jharkhand)
LOA No.: IRCON/2054/PMGSY/LOA/JH-18-XI-
WB-IRCON-28A/603 Date
12.02.2014
M/s Adarsh Construction
822.14 Lac 822.14 Lac 804.89 Lac 03.09.2015
7 e-Tender JH-21-XI-WB-IRCO
N-09C2
22.01.2014 Construction & Maintenance Works of (1) NH 23 to Ghattari Road - 3.500 km (2) Pandripani Jaldega to Pahartoli - 8.300 km (Total Length: 11.80 Kms, Block: Thethaitanger-IC, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-09C2/609 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd.
488.13 Lac 488.14 Lac 488.14 Lac 19.08.2015
8 e-Tender JH-21-XI-WB-IRCO
N-21A2
22.01.2014 Construction & Maintenance of Road- (1) Reo Road Garja to Kharwagarha 3.5km (2).Garja road to bhagalata 5.0 km (3) Nawatoli to meromloya 2.075 km . (Total Length 10.575 km, Block : Simdega Sadar-IIA District : Simdega.)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-21A2/608 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
444.76 Lac 444.83 Lac 444.83 Lac 19.08.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
9 e-Tender
JH-21-XI-WB-IRCO
N-72A1
22.01.2014 Construction & Maintenance Works of (1) Thethaitangar Bolba Road to Jillinga Karapani - 2.59 km (2) Bolba Road To Royantoli -1.815 km (3) Asanbera to Tukupani Road - 4.453 km (4) Thethaitangar Kurpani Road to Dumbertoli Asenbera Road - 3.600 km (5) Kurpani Road to Panripani Tukupani Road - 4.575 (Total Length: 17.033 Kms, Block: Thethaitanger-IIIA, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-72A1/607 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
788.44 Lac 788.44 Lac 788.44 Lac 12.08.2015
10 e-Tender
JH-21-XI-WB-IRCO
N-72A2
22.01.2014 Construction & Maintenance Works of (1) Rengari Road to Poraha Toli- 2.850 km (2) Shankh River to Kongsera Basartoli Road -4.15 km (3) Konpala Road to Lurkutoli -1.900 km (4)Konpala to Patra toli - 2.000 km(5) Lathkhamhan Rengari Road to Sarplata via Bhawarkhol - 5.100 km (Total Length: 16.00Kms, Block: Thethaitanger-IIIB, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-72A2/606 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
621.72 Lac 621.71 Lac 621.71 Lac 19.08.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
11 e-Tender JH-21-XI-WB-IRCO
N-73A1
22.01.2014 Construction & Maintenance Works of (1) Kevgutu to Kodhipat 1.53 Km, (2) Tembaro to Marani(5.80 Km) , (3) Borsotta to Borbera 5.6 Km (4) Paro Rajmal Path to Kawalbera 2.6 Km, (5) Kansoda Ella to Mahabang Path 4.7 Km (Total length 20.23 Km, Block: Bano-I, District : Simdega)
IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-73A1/604 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
978.37 Lac 977.63 Lac 977.63 Lac 19.08.2015
12 e-Tender JH-21-XI-WB-IRCO
N-74A1
22.01.2014 Construction & Maintenance Works of (1) PWD Road to Nawagaon via Chatuora Kusum 1.4 Km, (2) Bintuka to Tudeue 2.6 Km (3) Pangur To Khujurbahar via Jumarsoya 3.0 Km (4) Rubbai to Parro via Ramjal Sumirbora 4.4 Km. (5) Bano PWD road to Ganmer Path via Pabura nimtur Bintuka Pangur Tonia 7.25 Km. , (Total length 18.65 Km, Block: Bano-II, District : Simdega)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
21-XI-WB-IRCON-74A1/605 Date
13.02.2014
M/s Md. Yasin Construction Pvt.
Ltd
919.11Lac 918.82 Lac 918.82 Lac 19.08.2015
13 e-Tender JH-21-XI-WB-IRCO
N-10B2
22.01.2014 Construction & Maintenance Works of (1) NH 23 Joram to Masania via Sudapahar - 5.950 Km (2) NH 23 Jampani Tojoram Ambapani Deobahar Road - 2.775 Km (3) Thethaitangar Bolba Road to Dhorthibahar - 7.000 Km (Total Length: 15.725 Km, Block:Thethaitanger-II B, District: Simdega, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/JH-21-XI-
WB-IRCON-10B2/614 Date
14.02.2014
M/s Krishna Construction
662.08 Lac 662.09 Lac 661.79 Lac 03.09.2015
Contd.../-
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)14 IRCON/
JK-Cell/JAT/14/1014/DQ/Superpassage 77A-1/BR-
12, Dtd:21.1
2.13
28.02.14 Construction of Super Passage at Cut & cover No.77A-1 between KM 146.191 and KM 146.2265 under Dharam-Qazigund Section of USBRL New Rail Link Project (Jammu & Kashmir) (Package: BR-12)
IRCON/J&K-DQ/1014/Superpas
sage-77A-1/BR-12/6/27,
Dtd.15.02.2014
M/s Inam & Co, Engineers &
Contractors, Kaka Road, Nai Sarak,
Srinagar, J&K-190001
`55.84 Lacs Overall 2% below
`54.73 Lacs Within Four (4) Months from the date of issue of
LOA
15 e-Tender JH-18-XI-WB-IRCON-26A
22.01.2014
Construction & Maintenance Works of (1) Padriya to Loharakochha - 3.077 Km., (2) Tangritola to Chotkalowagarha - 2.514 Km., (3) Chaingara to Mahadeotola - 2.949 Km., (4) Baraoudi to Semratola - 1.741 Km., (5) Nawatoli to Ojhasaram - 1.700 Km., (6) Patkoi to Saram - 5.174 Km. and (7) Cholebera to Aradewar - 2.740 Km. (Total Length:19.89Kms, Block: Burmu, District: Ranchi, Jharkhand)
LOA No.: IRCON/2054/PMGSY-JKR/LOA/JH-
18-XI-WB-IRCON-26A/618 Date 18.02.2014
M/s Lions Construction
1072.88 Lac 1072.87 Lac 1048.52 Lac 27.08.2015
16 e-Tender IRCON/Elect/3014/OH
E Erectio
n/01 Dtd.
22.11.2013
16.12.2013
Design, Supply, Installation,Testing, Comissioning of Railway Electrification Works Comprising of 25 KV Overhead Line Equipment (OHE) from Jhalawar City station to Kalisindh Thermal Power Plant
Construction of Station Buildings, Passenger & Goods Platform, PF Shelter/sheds, FOB, tea stall, goods circulating area/roads works, staff quarters, guest house, Pump House, over head water tank, trolley shed & miscellaneous anciliary works for Nepal Custom Yard.
IRCON/2051/JBNRL/ Stn.
Bldg/Nepal Custom Yard/19/ 1818 dt.31.03.14
M/s Bagmati Construction Company,
Subash Chowk,
ForbesganjPIN: 854 318Araria, Bihar
Ph: 06455-225451
`1981.42 Lacs
8% Above `1491.94 Lacs 15 months from the date of issue
21.03.14 Providing Support Services dor IRCON's office and Guest Houses and other locations at USBRL Project office and establishments at Jammu. (Package: SS-3R)
IRCON/JK Cell/JAT/1014/17/
G/Support Services/SS-3R/344 (A),
Dated:01.04.2014
M/s Gh. Nabi Giri & Sons, Main
Bazar, Banihal, Distt. Ramban
(J&K).
`24.04 Lacs 0.02% below `29.42 Lacs 12 months from the date of issue
of LOA
2 Consultancy-02
(Nepal), NIT No.-706 Dtd.
30.01.2014
21.02.14 Consultancy Works for Architectural and structural design and Other Services Related to the Construction of Station Building, Staff Quarters, OH Water Tank and miscellaneous works in connection with Construction of New Broad Gauge Rail Line From Jaynagar (India) to Bardibas (Nepal). PKG: Consultancy – 02 (Nepal)
21.04.2014 `10.26 Lacs
3 Consultancy-03
(Nepal), NIT No.-707 Dtd.
30.01.2014
21.02.14 Consultancy Works for Preparation of GAD, Detailed Design & Drawing including Proof Checking of foundation, sub-structure and superstructure of Major Bridges from Km 27+775 to Km 52+336 in connection with Construction of New Broad Gauge Rail Line From Jaynagar (India) to Bardibas (Nepal). PKG: Consultancy – 03 (Nepal)