Annex H: RECLAMATION DISTRICTS Sacramento County (Reclamation Districts) Annex H.1 Multi-Hazard Mitigation Plan Update September 2011 H.1 Introduction This Annex details the hazard mitigation planning elements specific to Reclamation District 341, 800, and 1000, participating jurisdictions to the Sacramento County LHMP Update. This annex is not intended to be a standalone document, but appends to and supplements the information contained in the base plan document. As such, all sections of the base plan, including the planning process and other procedural requirements apply to and were met by the Reclamation Districts. This annex provides additional information specific to each district, with a focus on providing additional details on the risk assessment and mitigation strategy for this community. H.2 Planning Process As described above, the reclamation districts followed the planning process detailed in Section 3.0 of the base plan. In addition to providing representation on the Sacramento County Hazard Mitigation Planning Committee (HMPC), the District formulated their own internal planning team to support the broader planning process requirements. Internal planning participants included staff from the following District departments: Reclamation District 1000 General Manager Wagner & Bonsignore Engineering (for RD 341 and RD 800) Additional details on plan participation and district representatives are included in Appendix A. H.3 Community Profile The community profile for the reclamation districts in Sacramento County is detailed in the following sections. Figure H.1 displays a map and the location of the reclamation districts within Sacramento County. RD 341 is circled in red, RD 800 is circled in yellow, RD 1000 is circled in green. A more detailed map provided by RD 341 is shown in Figure H.2.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Annex H: RECLAMATION DISTRICTS
Sacramento County (Reclamation Districts) Annex H.1 Multi-Hazard Mitigation Plan Update
September 2011
H.1 Introduction
This Annex details the hazard mitigation planning elements specific to Reclamation District 341,
800, and 1000, participating jurisdictions to the Sacramento County LHMP Update. This annex
is not intended to be a standalone document, but appends to and supplements the information
contained in the base plan document. As such, all sections of the base plan, including the
planning process and other procedural requirements apply to and were met by the Reclamation
Districts. This annex provides additional information specific to each district, with a focus on
providing additional details on the risk assessment and mitigation strategy for this community.
H.2 Planning Process
As described above, the reclamation districts followed the planning process detailed in Section
3.0 of the base plan. In addition to providing representation on the Sacramento County Hazard
Mitigation Planning Committee (HMPC), the District formulated their own internal planning
team to support the broader planning process requirements. Internal planning participants
included staff from the following District departments:
Reclamation District 1000 General Manager
Wagner & Bonsignore Engineering (for RD 341 and RD 800)
Additional details on plan participation and district representatives are included in Appendix A.
H.3 Community Profile
The community profile for the reclamation districts in Sacramento County is detailed in the
following sections. Figure H.1 displays a map and the location of the reclamation districts
within Sacramento County. RD 341 is circled in red, RD 800 is circled in yellow, RD 1000 is
circled in green. A more detailed map provided by RD 341 is shown in Figure H.2.
Sacramento County (Reclamation Districts) Annex H.2 Multi-Hazard Mitigation Plan Update
September 2011
Figure H.1. Reclamation Districts in Sacramento County
Source: Sacramento County LAFCO
Sacramento County (Reclamation Districts) Annex H.3 Multi-Hazard Mitigation Plan Update
September 2011
Figure H.2. RD 341 Boundaries
Source: RD 341
Sacramento County (Reclamation Districts) Annex H.4 Multi-Hazard Mitigation Plan Update
September 2011
H.3.1 History
RD 341
In the Delta, for the last 5,000 years to the 1850s, relative sea-level rise was balanced by vertical
marsh growth through biomass accumulation and sediment deposition. A transition from
deposition of organic silt-clay to peat formation in the Delta largely reflects the decline in
inundation frequency and the maturation of the marsh plain towards mean higher high water
elevations. The resulting freshwater tidal marshes developed because a relatively large
freshwater inflow compared to the size of the tidal prism sustained a low salinity, which
supported highly productive organic peat formation through tule growth. The large roots of the
tule created an organic fabric that supported and aided rapid vertical growth. The living surface
was maintained within the intertidal zone (natural habitat), and marsh organic accretion
(injection of roots and rhizomes, and incorporation of surface litter) was able to sustain vertical
growth at rates in excess of relative sea-level rise. The gradual accumulation of the organic and
inorganic sediment must have also offset the loss and compaction of existing peat.
The development of today’s Delta began in late 1850 when the Swamp and Overflow Land Act
conveyed ownership of tall swamp and overflow land, including Delta marshes from the federal
government to the State of California. Reclamation of Sherman Island began shortly thereafter,
and by 1859, local property owners had constructed small peat levees of three to four feet in
height, with a base width of about eight feet, along the banks of the Sacramento River and
Mayberry Slough.
Today, Sherman Island is protected by approximately 18-miles of levee which encompass
approximately 9,937 acres of land, according to the 1995 Sacramento Delta San Joaquin Atlas.
Approximately 9 miles of levee are project levee, constructed by the US Army Corps of
Engineers, and approximately 9 miles of levee are non-project levee. The entire levee system is
maintained by RD 341. RD 341 maintains and operates five modern pumping stations on
Sherman Island: three on the San Joaquin River (south) side; one on the Sacramento River
(north) side; and one on Sherman Island’s northwest corner. The pumps are part of a larger
system of pumps, siphons irrigation ditches and canals used to circulate water and drain the
Island
RD 800
Reclamation District No. 800 is an area within Sacramento County lying along the Cosumnes
River and was originally created by action of the California State Legislature in 1907 (Statutes
1907,Ch 213). This original District, comprised of 2,136 acres, is located between Deer Creek
and the Cosumnes River east of Elk Grove in Sacramento County. In January 1997, a flood of
extraordinary size occurred on the Cosumnes River between Sloughhouse and Wilton requiring
considerable construction work to levees along the river. However, no levee breaks occurred on
those maintained by Reclamation District 800.
Sacramento County (Reclamation Districts) Annex H.5 Multi-Hazard Mitigation Plan Update
September 2011
As a result of the 1997 flood on the Cosumnes River, it became apparent that a public agency
was needed to maintain the levees and facilities along the river between Sloughhouse and Wilton
areas, outside the boundaries of Reclamation District 800. At the request of landowners along
the Cosumnes River whose lands were not included within Reclamation District 800, the
Trustees of the District sought an amendment to the act under which the District was formed, in
order to modify the boundaries and incorporate additional lands on the right bank of the
Cosumnes River and to include, for the first time, lands on the left bank of the river down to the
vicinity of Wilton.
To accommodate the above additions of land, SB 437 (Senator Patrick Johnston) was introduced
and adopted by the Legislature and signed by the Governor as Chapter 191, Statutes of 1997.
This action provided for the increase in District acreage from 2,136 to 25,435 acres. The total
potential levee length is 34.05 miles with 17.65 miles along the right (or north) bank and 16.40
miles along the left (or south) bank.
Since the 1997 flood, with assistance from the County of Sacramento and funding by the U.S.
Department of Agriculture, repairs were completed to levees along the Cosumnes River.
RD 1000
Reclamation District No. 1000 was created by an act of the State Legislature on April 8, 1911.
The purpose was to allow for the reclamation of what was then known as the American Basin for
agricultural purposes. The American Basin historically flooded from the Sacramento and
American Rivers overflowing their banks due to winter rains and runoff from the foothills giving
it the rich fertile soil to support the agriculture which dominated the early years in Natomas.
Much of the land was owned by the Natomas Company of California. The Act gave the District
authority and responsibility for flood control and drainage in what has become the Natomas
Basin.
Reclamation of Natomas began in 1913 with construction of the perimeter levee system which
was completed in 1915. The original cost was approximately $2 million and was financed by the
sale of bonds. Some of these original bonds are still in the possession of the District. Following
completion of the levees, an interior drainage system consisting canals, ditches and drains was
constructed to collect both stormwater runoff from precipitation that falls within the leveed area
as well as agricultural runoff from irrigated farm land. The original system conveyed all the
runoff to a large pumping plant constructed in 1915 at the terminus of Second Bannon Slough
(Plant 1A). This plant still exists and is used today. It is located directly across the Garden
Highway from the District Office. A second pumping plant (Plant 2) was added at Pritchard
Lake in 1920 along the Sacramento River north of Elvertal Road, and a third plant (Plant 3) was
added in 1939 also located on the Sacramento River just north of San Juan Road. Eventually
five more pump plants were added at various locations in the District to accommodate more
development and relieve pressure on the original plants.
Sacramento County (Reclamation Districts) Annex H.6 Multi-Hazard Mitigation Plan Update
September 2011
The drainage system stayed in this configuration for a number of years. In the 1950’s and 1960’s
urbanization of the Natomas Basin began, predominantly because of its close proximity to
downtown Sacramento and the construction of the interstate highway system. The first area to
develop was the Gardenland area in the southern extremity of the basin tucked up against the
American River and Natomas East Main Drain Canal. In the 1960’s Sacramento Metropolitan
Airport was developed. A new pumping plant paid for by the County was constructed to handle
the increased runoff from the newly constructed airport.
Through the decades more development occurred starting with the South Natomas Community,
Arco Arena, and the surrounding areas. In the 1990’s North Natomas began developing bringing
thousands of new residents, businesses and supporting infrastructure. Industrial and commercial
development also expanded in the vicinity of the airport to support its growing needs. And the
airport itself has undergone and continues to undergo significant expansion to support the
growing passenger demands. In each case, the District worked with the appropriate agency to
insure the impacts of the development and increased runoff are mitigated and do not overburden
the existing drainage system. In most cases, large detention storage basins have been
incorporated into new development to temporarily store the increased urban runoff and allow it
to be bled back into our system at a rate similar to the pre-development condition. These
detention basins are augmented by improvements to the existing pumping plants to assist in
handling the increased urban runoff.
H.4 Hazard Identification and Summary
This section details how the risk varies across the Sacramento County planning area. Each
district’s planning team identified the hazards that affect the District and summarized their
frequency of occurrence, spatial extent, potential magnitude, and significance specific to each
district (see Table H.1). In the context of the plan’s planning area, there are no hazards that are
unique to the districts.
Information on past occurrences and the likelihood of future occurrences is detailed in Section 4,
Risk Assessment, of the base plan. Additional information for high and medium significant
hazards for the District is included in the Vulnerability Assessment section of this annex.
Sacramento County (Reclamation Districts) Annex H.7 Multi-Hazard Mitigation Plan Update
September 2011
Table H.1. RD 341 Hazard Summary
Hazard Frequency of Occurrence Spatial Extent
Potential Magnitude Significance
Agricultural Hazards: Insect Pests
Bird Strike
Dam Failure
Drought
Earthquake
Flood: 100/200/500-year Occasional Extensive Catastrophic High
Flood: Localized/Stormwater
Landslide
Levee Failure Occasional Extensive Catastrophic High
River/Stream/Creek Bank Erosion
Severe Weather: Extreme Heat
Severe Weather: Fog
Severe Weather: Freeze
Severe Weather: Heavy Rain and Storms
Likely Significant Critical Medium
Severe Weather: Tornadoes
Subsidence
Volcano
Wildfire
Guidelines for Hazard Rankings: Frequency of Occurrence: Highly Likely-Near 100 percent probability in next year Likely-Between 10 and 100 percent probability in next year or at least one chance in ten years Occasional-Between 1 and 10 percent probability in next year or at least one chance in next 100 years Unlikely-Less than 1 percent probability in next 100 years Spatial Extent: Limited-Less than 10 percent of planning area Significant-10-50 percent of planning area Extensive-50-100 percent of planning area
Potential Magnitude: Catastrophic-More than 50 percent of area
affected Critical-25 to 50 percent Limited-10 to 25 percent Negligible-Less than 10 percent
Significance (subjective): Low, Medium, High
Source: AMEC Data Collection Guide
Sacramento County (Reclamation Districts) Annex H.8 Multi-Hazard Mitigation Plan Update
September 2011
Table H.2. RD 800 Hazard Summary
Hazard Frequency of Occurrence Spatial Extent
Potential Magnitude Significance
Agricultural Hazards: Insect Pests
Bird Strike
Dam Failure
Drought
Earthquake
Earthquake: Liquefaction
Flood: 100/200/500-year Occasional Significant Catastrophic High
Flood: Localized/Stormwater
Landslide
Levee Failure Occasional Significant Catastrophic High
River/Stream/Creek Bank Erosion
Highly Likely Significant Catastrophic High
Severe Weather: Extreme Heat
Severe Weather: Fog
Severe Weather: Freeze
Severe Weather: Heavy Rain and Storms
Severe Weather: Tornadoes
Subsidence
Volcano
Wildfire
Guidelines for Hazard Rankings: Frequency of Occurrence: Highly Likely-Near 100 percent probability in next year Likely-Between 10 and 100 percent probability in next year or at least one chance in ten years Occasional-Between 1 and 10 percent probability in next year or at least one chance in next 100 years Unlikely-Less than 1 percent probability in next 100 years Spatial Extent: Limited-Less than 10 percent of planning area Significant-10-50 percent of planning area Extensive-50-100 percent of planning area
Potential Magnitude: Catastrophic-More than 50 percent of area affected Critical-25 to 50 percent Limited-10 to 25 percent Negligible-Less than 10 percent Significance (subjective):
Low, Medium, High
Source: AMEC Data Collection Guide
Sacramento County (Reclamation Districts) Annex H.9 Multi-Hazard Mitigation Plan Update
Flood: 100/200/500-year Likely Extensive Catastrophic High
Flood: Localized/Stormwater Occasional Limited Limited Medium
Landslide
Levee Failure Occasional Extensive Catastrophic Medium
River/Stream/Creek Bank Erosion
Likely Significant Critical High
Severe Weather: Extreme Heat
Severe Weather: Fog
Severe Weather: Freeze
Severe Weather: Heavy Rain and Storms
Likely Limited Critical Medium
Severe Weather: Tornadoes
Subsidence
Volcano
Wildfire
Guidelines for Hazard Rankings: Frequency of Occurrence: Highly Likely-Near 100 percent probability in next year Likely-Between 10 and 100 percent probability in next year or at least one chance in ten years Occasional-Between 1 and 10 percent probability in next year or at least one chance in next 100 years Unlikely-Less than 1 percent probability in next 100 years Spatial Extent: Limited-Less than 10 percent of planning area Significant-10-50 percent of planning area Extensive-50-100 percent of planning area
Potential Magnitude: Catastrophic-More than 50 percent of area affected Critical-25 to 50 percent Limited-10 to 25 percent Negligible-Less than 10 percent Significance (subjective):
Low, Medium, High
Source: AMEC Data Collection Guide
Sacramento County (Reclamation Districts) Annex H.10 Multi-Hazard Mitigation Plan Update
September 2011
H.5 Vulnerability Assessment
The intent of this section is to assess each district’s vulnerability separate from that of the
planning area as a whole, which has already been assessed in Section 4.3 Vulnerability
Assessment of the base plan. This vulnerability assessment provides an inventory of the
population, property, and other assets located within the District and further analyzes those assets
at risk to identified hazards ranked of medium or high significance (as listed in Table H.1) to the
community. For more information about how hazards affect the County as a whole, see Chapter
4 Risk Assessment in the main plan.
H.5.1 Total Assets at Risk
This section identifies each district’s total assets at risk, including values at risk, critical
facilities, and infrastructure. Growth and development trends are also presented for the
community. This data is not hazard specific, but is representative of total assets at risk within a
community.
Values at Risk
Significant assets directly within the each district include a range of properties and infrastructure.
These may include District-owned property, critical facilities and infrastructure, cultural and
natural resources and others. An inventory of key district assets is provided in Table H.4, Table
H.5, and Table H.6. Total value of these assets exceeds $11.5 million for RD 341 (without the
value of the levees), $100 million for RD 800, and $2,061 for RD 1000.
Table H.4. Key Assets in RD 341
Name of Asset Facility Type Replacement Value Hazard Info
Agricultural High Potential Loss Facilities $6,132,830 Flood, Levee Failure
Agricultural-Irrigated from District Facilities
High Potential Loss Facilities $4,003,440 Flood, Levee Failure
Marina-Recreation High Potential Loss Facilities $14,980 Flood, Levee Failure
Urban High Potential Loss Facilities $79,510 Flood, Levee Failure
Commercial High Potential Loss Facilities $7,520 Flood, Levee Failure
Utilities (Including easements)
Transportation and Lifeline $558,300 Flood, Levee Failure
Source: RD 341
Table H.5. Key Assets in RD 800
Name of Asset Facility Type Replacement Value Hazard Info
RD 800 levees Levee In excess of $100,000,000 Flood
Source: RD 800
Sacramento County (Reclamation Districts) Annex H.11 Multi-Hazard Mitigation Plan Update
September 2011
Table H.6. Key Assets in RD 1000
Name of Asset Facility Type Replacement Value Hazard Info
RD 1000 Plant 1A and 1B Essential $20 million Flood
RD 1000 Plant 2 Essential $5 million Flood
RD 1000 Plant 3 Essential $10 million Flood
RD 1000 Plant 4 Essential $5 million Flood
RD 1000 Plant 5 Essential $4 million Flood
RD 1000 Plant 6 Essential $5 million Flood
RD 1000 Plant 8 Essential $12 million Flood
RD 1000 Levee system Essential $2 billion Flood
Sacramento International Airport
Transportation County Flood
City of Sacramento River Pump Stations (3)
Essential City Flood
City of Sacramento Drainage Pump Stations
Essential City Flood
Schools (2 high schools, middle and elementary
High Potential Natomas USD Flood
Fire Stations Essential City Flood
Senior Housing High Potential City Flood
Interstate 5 and 80 Highway 99
Transportation Caltrans Flood
Day Care Centers High Potential City Flood
Hazardous Material Sites High Potential City Flood
Source: RD 1000
H.5.2 Priority Hazards: Vulnerability Assessment
This section provides the vulnerability assessment, including any quantifiable loss estimates, for
those hazards identified above in Table H.1 as high or medium significance hazards. Impacts of
past events and vulnerability of the District to specific hazards are further discussed below (see
Section 4.1 Hazard Identification for more detailed information about these hazards and their
impacts on the Sacramento County planning area). Methodologies for calculating loss estimates
are the same as those described in Section 4.3 of the base plan. In general, the most vulnerable
structures are those located within the floodplain or within levee and dam inundation areas,
unreinforced masonry buildings, and buildings built prior to the introduction of modern building
codes.
Sacramento County (Reclamation Districts) Annex H.12 Multi-Hazard Mitigation Plan Update
September 2011
Flood
RD 341
Through discussion of the visual inspections, the District Board members, District
superintendent and District engineer have determined that Sherman Island levees are most
vulnerable to failure cause by flooding. Should a high water flood event cause levees to
collapse, Sherman Island would be fully inundated, risking the $11 million in district assets
discussed in Table H.4.
Areas of the existing levee system most susceptible to overtopping are those which do not meet
the PL 84-99 height standard. An inventory of levee sections and their respective heights is
maintained by the District. Analysis of this inventory shows that the levee along the San Joaquin
River from about levee station 330+00 to 510+00 contains stretches which are below the HMP
height standard (1 foot above 1:100 year flood event) and therefore are susceptible to
overtopping. Figure H.3 depicts levee flood protection levels for each individual section of the
Sherman Island levees.
Figure H.3. Level of Levee Flood Protection in Reclamation District 341
Source: Reclamation District 341 Five Year Plan (2009)
Sacramento County (Reclamation Districts) Annex H.13 Multi-Hazard Mitigation Plan Update
September 2011
RD 800
Flooding would occur as a result of levee failure or overtopping. Levee failure from either
breaching or overtopping would result in the total loss of levee embankment material, as was the
case in the 1997 flood event. Levee embankment failure within the current District boundary
from the 1997 event resulted in multiple levee failure sites along the Cosumnes River. The
resulting damage to agricultural lands was extensive, with the most damage occurring
immediately adjacent to the levee breach causing severe erosion to agricultural lands, deposition
of sands and debris and the complete destruction of adjacent vineyards and irrigation systems.
RD 1000
Currently no new development is allowed within Natomas due do the recent de-certification of
the perimeter levee system by FEMA. Levee improvements are under construction to restore the
levee system which would allow for additional development. The current general plans for the
City of Sacramento, Sacramento County, and Sutter County all anticipate significant future
development within Natomas pending completion of the levee improvements and improvements
in the economy.
As noted in this document, the current levee system does not meet the FEMA 100-year standard
and therefore the District is vulnerable to a catastrophic flood from the potential failure of the
perimeter levee system. The current population in Natomas is 100,000 based on the 2010 census
and the Corps of Engineer’s estimates total property damages (both public and private) would
likely exceed $10 billion.
The District has eight pump stations in the interior basin used to pump the stormwater and
agricultural runoff from the basin into the adjacent riverine system. A catastrophic levee failure
could eventually damage all eight of the pump stations and require their reconstruction. Table
H.6 shows the estimated replacement cost for each of the pump stations. In addition, the District
has a corporation yard and a main office in Natomas. The main office is located on top of the
existing Sacramento River levee and would likely not be physically damaged by a catastrophic
flood event though it would not be functional due to loss of utilities including power as a result
of the flood. The corporation yard would be damaged due to a flood event and could result in a
loss of the District’s equipment fleet unless it can be relocated to high ground before flood
waters affect the corporation yard. This would be dependant on the location of a levee breach in
relation to the yard.
Flood: Localized/Stormwater
RD 1000
The Natomas basin which is the jurisdiction of Reclamation District No. 1000, is a low-lying
basin surrounded on all four sides by levees. The District operates and maintains miles of canals
and drainage ditches which collect local rainfall from within the Natomas basin and transports
Sacramento County (Reclamation Districts) Annex H.14 Multi-Hazard Mitigation Plan Update
September 2011
the water to a system of eight pump stations for discharge into the adjacent river systems. The
major interior canals in the urbanized area (City of Sacramento) in the southern quarter of the
Natomas basin also have a levee system to contain the 100-year flood within the canals. If the
pump stations are not operable due to power failure in the area, the canals are at risk of
overflowing creating localized flooding. Flooding would be shallow (less than 3 feet),
significantly less than from a failure of the perimeter levee; however, it would impact emergency
response and evacuation routes should the perimeter levee system subsequently fail.
Levee Failure
Floods can threaten each reclamation district from several sources. Usually, the possibility of
flooding can be anticipated from eight to twenty hours before the “Emergency Period” is
reached. However, as demonstrated in Linda, California, in February 1986, it is possible for a
levee to collapse with little or no warning when there are still four or more feet of freeboard
available.
Generally, levees fail due to overtopping or collapse. A catastrophic levee failure resulting from
collapse probably will occur very quickly with relatively little warning. Such a failure would
occur where the levee is saturated and the high hydrostatic water pressure on the river side,
coupled with erosion of the levee from high water flows or an inherent defect in the levee, causes
an almost instant collapse of a portion of the levee. Under such circumstances, structures located
relatively near the break will suffer immediate and extensive damage. Several hundred yards
away from the break the energy of the flood waters will be dispersed sufficiently to reduce, but
not eliminate, flooding damage to structures in its path. The flood water will flow in a relatively
shallow path toward any low point in the affected area. Flood water will collect in these low
areas and the levels will rise as the flow continues. When the rivers are high, it is not possible to
close or repair a levee break until the water surface in the river and the flooded area equalize.
A major overtopping of a levee, if flow persists, will result in severe erosion of the levee crowns
on the landward side and cause levee failure over a period of minutes to several hours. A severe
levee overtopping can, therefore, be considered as a levee break for the purpose of determining
the extent of flooding that any area will suffer. Generally, overtopping can be predicted based on
river stages and the warning given depending on the source of the flood waters
RD 341
In addition to the costs incurred to repair or replace the assets destroyed by Sherman Island levee
failure, an immediate cost would be pumping out the Island. To estimate the cost of restoring
Sherman Island, the 2004 failure of the Upper Jones Tract was considered, an Island of 6,259
acres which cost approximately $120 million to restore. This equates to about $19,100 per acre,
and assuming inflation of 4% a year, would be about $22,200 in 2009. Accordingly, it would
cost approximately $221 million to pump out and restore Sherman Island (9,937 acres X $22,200
per/acre). This estimate is conservative in that it does not account for the elevations on the
interior of Sherman Island, which are up to 20 feet below sea level. Sherman will likely
Sacramento County (Reclamation Districts) Annex H.15 Multi-Hazard Mitigation Plan Update
September 2011
impound a greater volume of water per acre than Upper Jones Tract, and per acre restoration
costs will therefore be greater.
Electrical Infrastructure Affected
In addition to the dewatering costs, three major electric transmission lines (greater then 500kV)
cross Sherman Island: the California Oregon Transmission Project, operated by the Western
Area Power Administration, the Pacific Gas and Electric Company (PG&E) Table Mountain-
Tesla line, and the PG&E Vaca-Dixon-Tesla line. These lines work mainly to interconnect
California loads and generation with loads and generation in the Pacific Northwest. The three
lines through the Delta are operated as a coordinated grouping, with maximum imports or
exports limited to provide some joint redundancy to help ensure reliability.
The combined load on these three lines is typically around 4,000 MW, though under some
circumstances it can be as high as 4,800 MW (Mirzadeh 2006). This is approximately ten
percent of statewide summer loads, which is less than the required planning reserve margin of 15
percent. However, other outages may occur at the same time as this disruption, so under some
circumstances the loss of all three lines due to the failure of the Sherman Island levee system
could cause operating problems.
PG&E also operates two other lines with less than 500kV capacity to provide local service to
Sherman Island and nearby Delta Islands. Failure of the Sherman Island levee system would
impact the ability of PG&E to serve the local delta community. The DRMS report estimates the
cost of a two month outage of two 500 kV lines to be $42,000,000.
Oil and Gas Production Affected
Sherman Island has 60 natural gas and oil wells, and approximately 1,082 acres of gas and oil
production fields. In addition, the levees protect 145,514 feet of a natural gas pipeline which
originates in Canada and crosses Sherman Island. Failure of the Sherman Island levee system
would interrupt gas service through the pipeline and gas production and storage occurring on
Sherman Island.
Civil Infrastructure Affected
Sherman Island levees also protect State Highway 160 and the drawbridge at Three Mile Slough.
State Route 160 connects Sherman Island to the mainland Sacramento County on the northeast
corner via Threemile Slough Bridge (Bridge 24-0121), and to Contra Costa County on the
island’s west side, via the Antioch Bridge (Bridge 28-0009). Failure of the Sherman Island levee
system and resulting loss of State Route 160 and access to the Antioch Bridge would severely
impact truck and vehicular traffic relying on this roadway. The Sherman Island Five Year Plan
(2009) estimated that the closure of State Highway 160 would cost approximately $70,000 per
day.
Sacramento County (Reclamation Districts) Annex H.16 Multi-Hazard Mitigation Plan Update
September 2011
RD 800
Potential for severe damage to the Wilton Road crossing over the Cosumnes River would require
detouring of extensive daily high volume traffic of Wilton Road. Closure of the road would
severely delay public safety agency emergency response. Truck and vehicular traffic impacts
would have severe economical impacts to the local economy.
RD 1000
The levees around Natomas were designed to handle the historical “flood of record” which was
the 1907 and 1909 floods on the Sacramento River. Another large flood event occurred in 1937
which the system safely passed with only minor problems. Again, in 1955 an even larger flood
roared through the Central Valley around Christmas. The Natomas levees held with some minor
sloughing along the Sacramento River near the Sacramento/Sutter County line. However, as a
result of this flood, the Army Corps of Engineers raised the Natomas Cross Canal and Pleasant
Grove Creek Canal levees as much as two to three feet in anticipation of future even larger flood
events. In addition, by 1955 Folsom Dam was operational which provided additional flood
storage capacity along the American River on the District’s southern flank.
For the next thirty years, smaller floods came and went without incident until February 1986.
During a 10 day period starting on Valentine’s Day 1986, over 19 inches of rain fell on the
Central Valley resulting in the current “flood of record” on the Sacramento and American River
basins. The District levees were seriously challenged as large areas experienced significant
seepage causing the backside of the levees to erode. Approximately 10,000 feet of levee along
the Sacramento River west of the airport sustained major sloughing. A flood fight was initiated
by the District and eventually the Army Corps of Engineers assumed responsibility. Were it not
for the quick action by the District and the extended efforts by the Corps it is likely a levee
failure would have occurred somewhere along the Sacramento River during that flood.
Following 1986, levee repairs were constructed by the Corps of Engineers to remediate the levee
seepage problem. This work was completed in the early 1990’s. In addition, a joint powers
authority known as the Sacramento Area Flood Control Agency or SAFCA was formed to
develop a comprehensive flood control project for the entire Sacramento area. On New Year’s
day 1997 a flood eerily similar to the 1986 event hit Sacramento cresting at almost the same river
level. Because of the improvements constructed by the Corps several years earlier, the Natomas
levees safely passed this flood with some seepage but little to no levee damage. However, this
flood caused levee failures elsewhere in the Sacramento River system and has awoken a concern
about potential “underseepage” issues and their potential to cause a levee failure in the future. In
addition since these two very large flood events occurred within such a short time frame, experts
now believe we should plan our flood control system and levees for even larger floods;
especially levees protecting urban areas where damages would be extensive and the potential for
loss of life high. This was further engrained in our planning efforts by the flooding in New
Sacramento County (Reclamation Districts) Annex H.17 Multi-Hazard Mitigation Plan Update
September 2011
Orleans as the result of Hurricane Katrina in 2006 and the resulting catastrophic damages and
lives lost.
More urbanization is anticipated in Natomas including continued buildout of North Natomas,
more commercial/industrial development associated with Sacramento International Airport, and
even plans for a new large community in the south Sutter County area in the vicinity of Riego
and Sankey Roads. See the previous section for a detailed description of RD 1000 facilities that
would be affected by a flood due to a levee failure in Natomas.
River/Stream/Creek Bank Erosion
Stream bank erosion is a natural process, but acceleration of this natural process leads to a
disproportionate sediment supply, stream channel instability, land loss, habitat loss and other
adverse effects. As farmers settled the valleys in the 1800s, the Gold Rush drew prospectors to
the hills. As mining in the Sierra Nevada turned to the more “efficient” methods of hydraulic
mining, the use of environmentally destructive high-pressure water jets washed entire
mountainsides into local streams and rivers. As a result, the enormous amounts of silt deposited
in the riverbeds of the Central Valley increased flood risk. As a remedy to these rising riverbeds,
levees were built very close to the river channels to keep water velocity high and thereby scour
away the sediment. However, the design of these narrow channels has been too successful.
While the Gold Rush silt is long gone, the erosive force of the constrained river continues to eat
away at the levee system and stream banks within the districts.
RD 341
Due to the public benefit provided by Sherman Island levees and the valuable local and non-local
assets they protect, District employees conduct visual inspections of the Sherman Island levee
system every day of the year. In addition, the superintendent, Board president and District
engineer survey the levee a minimum of twice a month and participate in an annual inspection of
the levee from the waterside. These inspections are invaluable for identifying issues such as
seepage, cracking, erosion and lack of splash cap and riprap.
According to the District’s Five Year Plan, levee erosion is an ongoing problem. Areas of the
existing levee system most susceptible to failure due to flooding resulting from erosion are those
areas with inadequate riprap protection. The large expanse of waterway of the Sacramento River
adjacent to Sherman Island provides the necessary distance, or fetch, when accompanied by high
winds can produce large waves. The existing rip rap protection lacks the required coverage of
the waterside slope to protect the levee from wind generated waves. The existing large
breakwater quarry stones and limited amount of rip rap are below the high tide level of the
Sacramento River exposing the unprotected levee embankment material to wind generated
erosion damage. High winds originating from the north during periods of high tide and/or high
storm runoff will seriously erode the unprotected levee slope. Accordingly, the District feels that
the lack of riprap slope protection is a critical issue which could affect the stability of the levee,
should erosion damage occur.
Sacramento County (Reclamation Districts) Annex H.18 Multi-Hazard Mitigation Plan Update
September 2011
Figure H.4. Erosion Sites in Reclamation District 341 Levees
Source: RD 341 Five Year Plan (2009)
RD 800
The waterside levee slope of the Cosumnes River is heavily vegetated and considered to be high
value habitat with an abundance of endangered species. Consequently, the vulnerability to
stream bank erosion is high, the cost to mitigate for habitat loss prevents the District from
repairing existing eroded areas.
RD 1000
RD 1000 conducted bank erosion studies in 1999 and 2004 to identify sites where erosion is of
concern and could lead to levee erosion if not addressed. The District has continued to monitor
these sites since 2004. In addition, the Army Corps of Engineers and California Department of
Water Resources undertakes annual inspections of the Sacramento River to identify erosion sites
that could impact the integrity of the adjacent levee system. Four sites both on the Corps list and
the in the District’s reports have now been repaired through contracts with the Corps of
Engineers. These sites are along the Sacrmento River adjacent to Natomas at River Miles 78.0,
77.2, 73.5 and 68.9.
During the winter of 2011, RD 1000 staff undertook emergency repairs at approximate RM 68.4
as high water during this past season eroded a significant portion of the bank and was threatening
the adjacent levee. This site is just downstream of the work done by the Corps of Engineers at
Sacramento County (Reclamation Districts) Annex H.19 Multi-Hazard Mitigation Plan Update
September 2011
RM 68.9 and is part of an approximately 5800 foot reach of eroding bank site identified in the
District’s report that is being monitored.
In addition to this site, the District’s studies in 1999 and 2004 have identified 6 additional small
erosion sites which are being monitored and are being requested to be repaired through the
Sacramento River Bank Protection Project though it currently has not been identified by the
Corps for remedial work.
Severe Weather: Heavy Rain and Storms
RD800
According to historical hazard data, severe weather is an annual occurrence in the District.
Damage and disaster declarations related to severe weather have occurred and will continue to
occur in the future. Heavy rain and thunderstorms are the most frequent type of severe weather
occurrence in the area. Wind and lightning often accompany these storms and have caused
damage in the past. Problems associated with the primary effects of severe weather include
flooding, pavement deterioration, washouts, high water crossings, landslide/mudslides, debris
flows, and downed trees. However, it is the secondary effects of heavy rain and storms that are
of concern to RD 800. Heavy rains can cause flooding, levee failure, and stream bank erosion.
Flooding, levee failure, and stream bank erosion can cost RD 800 millions in damages.
H.6 Capability Assessment
Capabilities are the programs and policies currently in use to reduce hazard impacts or that could
be used to implement hazard mitigation activities. This capability assessment is divided into five
sections: regulatory mitigation capabilities, administrative and technical mitigation capabilities,
fiscal mitigation capabilities, mitigation outreach and partnerships, and other mitigation efforts.
H.6.1 Regulatory Mitigation Capabilities
Table H.7 lists regulatory mitigation capabilities, including planning and land management tools,
typically used by local jurisdictions to implement hazard mitigation activities and indicates those
that are in place in the reclamation districts.
Table H.7. District Regulatory Mitigation Capabilities
Regulatory Tool (ordinances, codes, plans)
RD341 RD800 RD1000
Date Comments Y/N Y/N Y/N
General plan N N N
Zoning ordinance N N N
Subdivision ordinance N N N
Growth management ordinance N N N
Sacramento County (Reclamation Districts) Annex H.20 Multi-Hazard Mitigation Plan Update
September 2011
Regulatory Tool (ordinances, codes, plans)
RD341 RD800 RD1000
Date Comments Y/N Y/N Y/N
Floodplain ordinance N N N
Other special purpose ordinance (stormwater, steep slope, wildfire)
Y Y Y RD 800: Encroachment permit regulations RD 1000: Title 23 California Water Code
Building code N N N Version:
BCEGS Rating N N N
Fire department ISO rating N N N Rating:
Erosion or sediment control program Y Y Y RD 800: Erosion control implanted as needed RD 1000: Erosion control measures on levee and canal slopes as necessary
Stormwater management program N N N
Site plan review requirements N N Y RD 1000: Proposed projects which impact levees or drainage facilities require permits from District and include plan review and sign off
Capital improvements plan N N Y RD 1000: District currently developing a CIP
Economic development plan N N N
Local emergency operations plan N N Y RD 1000: Emergency Response Plan as required by State
Community Wildfire Protection Plans N N N
Flood insurance study or other engineering study for streams
Table H.9 identifies financial tools or resources that each reclamation district could potentially
use to help fund mitigation activities.
Table H.9. District Fiscal Mitigation Capabilities
Financial Resources
Accessible/Eligible to Use (Y/N)
Comments RD341 RD800 RD1000
Community Development Block Grants
Y Y N RD 800: Usually do not meet cost/benefit requirements
Capital improvements project funding N N Y
Sacramento County (Reclamation Districts) Annex H.22 Multi-Hazard Mitigation Plan Update
September 2011
Financial Resources
Accessible/Eligible to Use (Y/N)
Comments RD341 RD800 RD1000
Authority to levy taxes for specific purposes
Y Y Y RD 800: Requires 2/3 majority vote to increase assessments RD 1000: For increase in assessments must comply with Propositon 218 which requires vote
Fees for water, sewer, gas, or electric services
N N N
Impact fees for new development N N Y RD 1000: District requires impact fee and/or mitigation for new development
Incur debt through general obligation bonds
N N Y RD 1000: District has authority but currently has no GO Bonds outstanding
Incur debt through special tax bonds N N N
Incur debt through private activities N N N
Withhold spending in hazard prone areas
N N N
Other
Source: AMEC Data Collection Guide
H.6.4 Mitigation Outreach and Partnerships
RD 341
None at this time.
RD 800
None at this time.
RD 1000
RD 1000 has worked with other partners in the Natomas Basin including the Sacramento Area
Flood Control Agency, Natomas Central Mutual Water Company, Natomas Basin Conservancy,
Sacramento County Airports and the City of Sacramento on projects of mutual benefit that
address public safety and the District’s flood control mission.
H.6.5 Other Mitigation Projects and Efforts
RD 341
The Reclamation District 341 5 Year Plan (2009) lists may mitigation projects and efforts.
These are shown in Figure H.5 and Figure H.6.
Sacramento County (Reclamation Districts) Annex H.23 Multi-Hazard Mitigation Plan Update
September 2011
Figure H.5. Reclamation District 341 Strategy to Meet Desired Levels of Protection
Source: RD 341 Five Year Plan (2009)
Sacramento County (Reclamation Districts) Annex H.24 Multi-Hazard Mitigation Plan Update
September 2011
Figure H.6. Reclamation District 341 Strategy to Meet Desired Levels of Protection
(cont.)
Source: RD 341 Five Year Plan (2009)
Sacramento County (Reclamation Districts) Annex H.25 Multi-Hazard Mitigation Plan Update
September 2011
RD 800
Levee maintenance practices designed to protect District levee system includes annual vegetation
management and rodent control. Due to environmental protection limitations, District disaster
reduction practices are limited.
RD 1000
Efforts are currently underway to address both these potential risks with the goal of providing
Natomas at least 200 year level of flood protection (a 0.5% risk of flooding in any given year)
and looking for opportunities to improve the system even beyond this level; particularly as
urbanization of the basin continues.
As described previously, perimeter levee improvements (Natomas Levee Improvement Project)
are currently being constructed by the Sacramento Area Flood Control Agency (SAFCA) with
local assessment funds and State Bond funds. This project will only address a portion of the
perimeter levee issues. The remaining levee improvements are to subsequently be completed by
the Corps of Engineers as federal funds are appropriated
H.7 Mitigation Strategy
This section describes the mitigation strategy process and mitigation action plan for each
reclamation district’s inclusion with the Sacramento County Multi-Hazard Mitigation Plan
update.
H.7.1 Mitigation Goals and Objectives
RD 341 adopts the hazard mitigation goals and objectives developed by the HMPC and
described in Chapter 5 Mitigation Strategy of the base plan.
RD 800 adopts the hazard mitigation goals and objectives developed by the HMPC and
described in Chapter 5 Mitigation Strategy of the base plan.
RD 1000 adopts the hazard mitigation goals and objectives developed by the HMPC and
described in Chapter 5 Mitigation Strategy of the base plan.
H.7.2 Mitigation Actions
The planning team for each reclamation district identified and prioritized the following
mitigation actions based on the risk assessment and in accordance with the process outline in
Section 5, Mitigation Strategy, of the base plan. Background information and information on
how each action will be implemented and administered, such as ideas for implementation,
responsible office, potential funding, estimated cost, and timeline are also included. General
processes and information on plan implementation and maintenance of this LHMP by all
Sacramento County (Reclamation Districts) Annex H.26 Multi-Hazard Mitigation Plan Update
September 2011
participating jurisdictions is included in Section 7, Plan Implementation and Maintenance, of the
base plan.
1. RD 341 – Implement the Recommended Actions of the Sherman Island Five Year Plan