Ann Arbor Station Environmental Review PUBLIC MEETING
33

Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

May 14, 2018

Download

Documents

ledang
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

Ann Arbor Station Environmental Review PUBLIC MEETING

Page 2: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

AGENDA

1. Purpose of the Meeting

2. Project Update

3. Alternatives Analysis Phase I

4. Alternatives Analysis Phase II

5. Next Steps

6. Questions

7. Public Comment

Page 3: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

PURPOSE OF THE MEETING - Present DRAFT findings - Receive comments - Complete questionnaire

Page 4: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

PROJECT UPDATE

Page 5: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

EXISTING STATION

Page 6: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

PROJECT ACTIVITY SINCE MAY 2015

– Coordination with MDOT and FRA

– Project Alignment with Corridor-wide Tier I EIS

– Reduced parking requirement

– Reduced station size

– FRA Project Manager change

Page 7: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

PROJECT UPDATE

Page 8: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase 1

Page 9: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

PHASE I ALTERNATIVES

Page 10: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase I

ALTERNATIVES ELIMINATED: 1, 2, 6, 7, 8

Page 11: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES CARRIED FORWARD: 3, 4, 5

ALTERNATIVES ANALYSIS Phase I

Page 12: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

Page 13: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

Screening Criteria

– Location Within the Community

– Accessibility

– Site Assessment

Page 14: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

Site Assessment – Environmental Factors

– Floodplain

– Hazardous Materials

– Cultural/Historic Resources

– Recreational Lands

– Property Ownership

Page 15: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

ALTERNATIVES ELIMINATED North Main, 3B, 3C, 3D

Page 16: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

ALTERNATIVES CARRIED FORWARD

Page 17: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

ALTERNATIVE 2A

Page 18: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2A

Page 19: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2A

– Elevated station at Depot Street

– New Traffic Signal

– Buses on Broadway and Depot

– DTE Property

Page 20: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

ALTERNATIVE 2B

Page 21: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2B

Page 22: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2B

– Ground station at Depot Street

– New Traffic Signal

– Buses on Broadway and Depot

– DTE Property

Page 23: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVES ANALYSIS Phase II

ALTERNATIVE 2C

Page 24: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2C

Page 25: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 2C

– Re-use of the Michigan Central Station

– New Traffic Signal

– Buses on Broadway and Depot

– DTE Property

– Michigan Central Depot

Page 26: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

Alternatives Analysis Phase II

Alternative 3A

Page 27: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 3A

Page 28: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

ALTERNATIVE 3A

– West Fuller

– Elevated Station

– Buses on first level of parking structure

– Park Property

Page 29: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

MEETING QUESTIONNAIRE/Survey

We’ve developed a

written and an

online version of a

survey related to

the Alternatives

Analysis

Page 30: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

NEXT STEPS

Page 31: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

NEXT STEPS - TIMELINE

Page 32: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

NEXT STEPS - TIMELINE

– Public comments - Phase II Alternatives Analysis finalized

– Remaining alternatives reviewed under NEPA Regulations through EA process

– EA process includes No-Build and Remaining Alternatives

– Impacts documented and Preferred/Recommended Alternative identified in EA

document

– The EA document approved/signed for Public Review by FRA and MDOT

– A 30-day review period

– A public hearing held during the 30-day review period

– Comments received and addressed

– If no significant impacts are associated with the Preferred/Recommended

Alternative, FRA prepares the Finding of No Significant Impacts (FONSI)

document.

Page 33: Ann Arbor Station Environmental Review questionnaire . PROJECT UPDATE . ... –Re-use of the Michigan Central Station ... Manager City of Ann Arbor

Eli Cooper, AICP

Transportation Program

Manager

City of Ann Arbor

[email protected]

734-794-6430 x.43710

Robert Gorski, PE

Project Manager

AECOM

[email protected]

313-961-3418

www.a2gov.org/annarborstation

THANK YOU