Table of Contents CHAPTER ONE.................................................... 4 INTRODUCTION................................................... 4 1.1 BACKGROUND OF THE STUDY.........................................4 1.1.1 Brief Historical review of school infrastructure projects in Ghana.............................................................6 1.2 PROBLEM STATEMENT...............................................7 1.3 AIMS AND OBJECTIVES.............................................8 1.4 RESEARCH QUESTIONS..............................................8 1.5 ORGANIZATION OF THE STUDY.......................................9 CHAPTER TWO:.................................................. 10 LITERATURE REVIEW............................................. 10 2.1 INTRODUCTION...................................................10 2.2 CAUSES AND EFFECTS OF DELAYS IN MALAYSIAN CONSTRUCTION INDUSTRY 10 2.3 SIGNIFICANT CAUSES AND EFFECTS OF PROJECT DELAYS IN THE NIGER DELTA REGION, NIGERIA..............................................13 2.4 A SYSTEM THINKING APPROACH TO ELIMINATE DELAYS ON BUILDING CONSTRUCTION PROJECTS IN SOUTH AFRICA..............................17 2.5 DELAYS IN BUILDING CONSTRUCTION PROJECTS IN GHANA..............19 2.6 AN INVESTIGATION INTO CAUSES AND EFFECTS OF CONSTRUCTION DELAYS IN UAE.............................................................21 2.7 CHAPTER SUMMARY................................................23 CHAPTER THREE................................................. 25 METHODOLOGY................................................... 25 3.1 INTRODUCTION...................................................25 3.2 RESEARCH DESIGN................................................25 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Table of Contents
CHAPTER ONE....................................................4INTRODUCTION...................................................41.1 BACKGROUND OF THE STUDY.........................................4
1.1.1 Brief Historical review of school infrastructure projects in Ghana.............................................................6
1.2 PROBLEM STATEMENT...............................................71.3 AIMS AND OBJECTIVES.............................................8
1.4 RESEARCH QUESTIONS..............................................81.5 ORGANIZATION OF THE STUDY.......................................9
CHAPTER TWO:..................................................10LITERATURE REVIEW.............................................102.1 INTRODUCTION...................................................102.2 CAUSES AND EFFECTS OF DELAYS IN MALAYSIAN CONSTRUCTION INDUSTRY10
2.3 SIGNIFICANT CAUSES AND EFFECTS OF PROJECT DELAYS IN THE NIGER DELTA REGION, NIGERIA..............................................13
2.4 A SYSTEM THINKING APPROACH TO ELIMINATE DELAYS ON BUILDING CONSTRUCTION PROJECTS IN SOUTH AFRICA..............................17
2.5 DELAYS IN BUILDING CONSTRUCTION PROJECTS IN GHANA..............192.6 AN INVESTIGATION INTO CAUSES AND EFFECTS OF CONSTRUCTION DELAYS IN UAE.............................................................212.7 CHAPTER SUMMARY................................................23
CHAPTER THREE.................................................25METHODOLOGY...................................................253.1 INTRODUCTION...................................................253.2 RESEARCH DESIGN................................................25
1
3.3 TARGET POPULATION..............................................263.4 SAMPLING SIZE AND SAMPLING TECHNIQUE...........................27
3.5 SOURCES OF DATA................................................273.6 DATA COLLECTION TOOL...........................................27
3.7 DATA ANALYSIS..................................................28
CHAPTER FOUR..................................................29DATA ANALYSIS AND INTERPRETATION OF FINDINGS..................294.1 INTRODUCTION...................................................29
4.2 PERSONAL DETAILS OF RESPONDENTS................................294.2.1 Distribution of Sex of Respondents.........................29
4.2.2 Distribution of Respondents Age............................304.2.3 Respondents Qualification..................................31
4.2.4 Respondents’ Experience in Project Management..............314.2.5 Respondents Job Position...................................32
4.3 PERCEPTION OF PROJECT SUCCESS..................................334.3.1 What do you think a successful project should be?..........33
4.3.2 Do you think a project can be said to have absolute success or absolute failure rather than some degree of success or some degree of failure?...............................................344.3.3 Do you think a project involving the construction of government school infrastructure can be said to have absolute success or absolute failure rather than some degree of success or some degree of failure?..........................................35
4.4.1 Inadequate Funding.........................................364.4.2 Political Interference.....................................37
4.4.3 Increasing Cost of construction............................384.4.4 Improper planning..........................................39
2
4.4.5 Weather Condition..........................................414.4.7 inadequate contractor experience in that particular area...43
4.4.8 Shortage in material.......................................444.4.9 Do you think there are external (outside the project environment) factors that affect project success or failure?.....46
4.5.1 Management support is essential for the project to succeed 474.5.2 Skilled and experience project managers and staff is criticalfor project to be successful.....................................474.5.3 Communicating the expectation of the project to all groups involved, and roles clearly defined for each and every group will ensure a successful project......................................49
4.6 COMPOSITE RANKING OF SUCCESS FACTORS FROM ALL CATEGORIES OF RESPONDENTS........................................................50
CHAPTER FIVE..................................................55SUMMARY OF FINDINGS, CONCLUSION AND RECOMMENDATIONS...........555.1INTRODUCTION....................................................555.2 SUMMARY OF FINDINGS............................................55
during construction stage, incompetent site management, and wrong
choice of Bankers.
Labour and equipment related issues also include unskilled site
manpower, improper equipment selection and faulty equipment,
labour disputes. Material related issues also include poor
quality materials, material shortages. Consultant-related issues
include inappropriate design, poor contract management, late
identification and resolution of drawings and specification
errors and omissions, late preparation of drawings and other
contract documents, improper contract packaging or delivery
strategy, over inspection, long waiting time for inspection and
testing, inappropriate coordination of information.
The community related issues include lack of community buy-in,
delay or Non-payment of Compensation, youth unrest, Militancy and
communal crises. Contractual relationships related issues include
lack of adequate communication between the parties, major
disputes and negotiations, wrong organizational structure linking
22
to the project and external issues which include weather
conditions, change in government’s leadership and policies,
natural disasters, interference by political leaders. The effects
of project delays identified for investigation include time
overrun, budget overrun, poor quality completed project, bad
quality completed project, bad public relations, litigation,
arbitration, disputes and claims and total abandonment.
A questionnaire was appropriate for the survey and the
participants were the public sector, multinational companies and
private companies which include consultants, clients and
contractors at Port Harcourt city in Nigeria which is situated in
the Niger Delta region. Qualitative sample was used and eighty-
three (83) returned questionnaires was used for the study. The
survey was analysed using inferential statistics (factor
analysis, analysis of variance and t-test).
The study concluded that there are eleven (11) most important
factors for the cause of project delays and three (3) most
23
important effects of delays in the Niger Delta region. There are
also benefits derived from project delays by contractors.
Construction work in the Niger Delta is challenged by weather and
strict planning is required to meet project timelines.
Recommendations include solutions to the causes of project delays
in the Niger Delta region and they include solutions to youth
unrest, militancy and communal crises, solutions to inadequate
planning by contractors, solution to delay or non-payment of
compensation to the community, solution to wrong choice of
consultants and contractors by the clients and solutions to lack
of community buy-in.
2.4 A SYSTEM THINKING APPROACH TO ELIMINATE DELAYS ON BUILDINGCONSTRUCTION PROJECTS IN SOUTH AFRICAAiyetan, Smallwood and Shakantu, (2011) conducted a study on a
system thinking approach to eliminate delays on building
construction projects in South Africa. The study revealed that
the process of construction demand accuracy and very high
precision. The prediction of project completion time is a means
24
of realizing client satisfaction and will result in a competitive
advantage all other things being equal or constant. Lack of
project management competence could adversely affect delivery
time of a project.
Cooke-Davies (2001) indicated that project management is a tool
for project success hence project management competence level is
directly proportional to the level of success a project may
attain. The literature classifies the factors pertaining to the
subject of delay the delivery process and they include clients
understanding of the design, quality of management during
developed, quality of management during construction, motivation
of staff, site ground conditions, site access, constructability
of design, management style, management techniques used for
planning and control, physical environmental conditions, economic
policy and socio-political conditions.
Aiyetan et al. (2011) used both quantitative and qualitative
research approaches in their study. The sample consisted of
25
architects, clients, contractors, quantity surveyors and
structural engineers in South African construction industry.
Eighty-eight practitioners were surveyed during the phase one of
the study and four during the validation of the model and were
randomly sampled from samples in phase one. Background of the
respondents was collected, followed by the ranking of the
influences of factor categories on project delivery on time.
Presentation of the results and Discussion was also done on the
ranking of the influences of factor categories on project
delivery on time. The study was also introduced to systems
thinking and it was revealed that the system model for this study
is an approach to develop a holistic understanding of the
delivery process of building construction projects, the
complexity of the interrelationships of task, the actions of
professionals and the influence of environment has on the process
and delivery time of projects.
The factors that are problematic and require attention in the
delivery of projects on time is the poor performance practices in
the building construction industry hence the problem of delay is
26
mainly constructed-related. The study used a model to ensure
project delivery on time. The model is discussed in the following
sequence as basis for the model, the model flowchart, elements
constituting the model, validation of the model and summary of
the validation of the model. The study concluded that the most
important category of interventions is the construction stage. In
addition, all interventions proposed at each stage of
construction have between a moderate influences to a near major
or near major influence on the delivery of projects in South
Africa hence only pre-qualification of suppliers falls outside
the range. Furthermore, interventions at the construction stage
are deemed as most effective for the elimination of delays on
project delivery time and all the interventions proposed in the
models are important for completion of projects on time.
The study recommends a pre-qualification for suppliers; attention
should be paid to adequate briefing, confirmation of client
financial capability and design quality assurance at the brief or
design stage. In addition, things that will contribute to
eliminating delays in project should be adhered to and the study
27
indicated various strategies that should be made part of tender
documents at the tender stage.
2.5 DELAYS IN BUILDING CONSTRUCTION PROJECTS IN GHANAFugar and Agyakwah-Baah (2010) conducted a study to investigate
the causes of delays of building construction projects in Ghana.
The objectives of the study were to identify the perceptions of
the three main parties regarding the causes of delays and suggest
possible ways of eradicating or minimizing them. The study out
lined various definitions of delay. For example, Sambasivan and
Soon (2007) were of the view that delays are insidious often
resulting in time overrun, cost overrun, disputes, litigation and
complete abandonment of projects. In addition to this,
construction delay is a major problem facing the Ghanaian
construction industry.
The study revealed that the construction industry is an important
sector of the Ghanaian economy as it contributes an average of
8.5% of the Gross Domestic Product and provides means of
28
production for other industries or commodities to be consumed.
Delays in construction are caused by several factors and Ahmed et
al. (2003) grouped delays into two categories namely internal
causes and external causes. On the other hand Bolton classified
delay as excusable but non-compensable delay, compensable delay
and inexcusable delay. Other empirical reviews on the causes of
delay in construction project have been outlined in the study and
it was revealed that factors that cause delay in construction
projects are many and vary from country to country and from one
circumstance to another.
Fugar and Agyakwah-Baah (2010) study selected 130 respondents
made up of 39 contractors, 37 clients and 54 consultants.
Questionnaires were given to these respondents to aid in the
research. The study used a semi-structured interview on 15 key
players who were selected by a non-probabilistic snow ball
technique. The key players consists of 5 contractors, client’s
representatives and consultants who were interviewed essentially
to validate a preliminary set of construction delay causes
29
gleaned from the literature and to determine from their
experience other factors which cause construction delay in Ghana.
The survey data consisted of 32 causes of delay which were
analysed and grouped into nine major areas according to a
modified version of Assaf et al. (1995) classifications and they
include materials, manpower, equipment, financing, environment,
changes, government action, contractual relationships and
scheduling and controlling techniques and his seventh major
classification was Government relations’ which was substituted by
the research with Government actions. A spearman’s rank
correlation coefficient was used to show the degree of agreement
between the rankings of any two parties.
Fugar and Agyakwah-Baah (2010) study concluded that all the three
groups of respondents (clients, consultants and contractors)
agree that out of the 32 factors the top ten influencing factors
in causing delay in descending order are delay in honouring
certificates, underestimation of the costs of projects,
30
underestimation of the complexity of projects, difficulty in
assessing bank credit, poor supervision, understanding of time
for completion of projects by contractors, shortage of materials,
poor professional management, fluctuation of prices or rising
cost of materials and poor site management. In addition to this
the respondents agreed that the financing group of delay factors
was the most influential factor and material factors were
considered as the second most important factor causing delay
followed by scheduling and controlling factors.
Fugar and Agyakwah-Baah (2010) study also recommends that the
importance of adequate and timely provision of financial
resources in building construction project management cannot be
over emphasized. Furthermore, a project is not only delayed but
the morale of workers plummet because of non-payment or irregular
payment of wages. The study also gave some recommendations to the
challenge to construction managers and clients since it is to
identify ways to eliminate or at least reduce the occurrence of
financial crisis during the construction process. In addition,
31
recommendations to overcome some contractor’s ineptitude which
correlates directly with delay factors such as understanding of
cost, time of completion and complexity of projects, poor
scheduling and control and poor site management have been
indicated in this study.
2.6 AN INVESTIGATION INTO CAUSES AND EFFECTS OF CONSTRUCTION
DELAYS IN UAE
Motaled and Kishk (2010) conducted a study to investigate into
the causes and effects of construction delays in United Arab,
Emirates (UAE). The main objective of this study is to identify
the main causes and effects of construction project delays in
UAE. The study revealed that a UAE construction company is the
growing rate of delays in project delivery. Assaf and Al-Hajji
(2006) described construction delay as the time overrun either
beyond the contract date or beyond the date that the parties
agree upon for delivery and it is one of the most recurring
problems in the construction industry. Project can be delayed as
a result of a large number of factors hence different authors
from Ghana by Frimpong (2003), Vietnam by Long et al. (2004),
Kuwait by Koushki et al. (2005), Saudi Arabia by Assaf and Al-
Hejji (2006) and in Jordan by Sweis et al. (2008). Delays also
have an adverse impact on project success in terms of time, cost,
quality and safety hence the effect of construction delays are
32
not confined to construction companies but can however influence
the overall economy of a country where construction plays a major
role in its development and contribute the gross domestic product
(GDP). In the UAE, half of construction projects encounter delays
(Faridi and El-Sayegh, 2006).
The study was based on literature review of the various causes
and effects of project delay. A questionnaire survey was used to
investigate 42 potential delay factors. The questionnaire was
designed in such a way that the first section was intended
generate information about the respondents profile whiles the
second and third sections was related to questions on the causes
and effects of construction projects delays respectively. The
Questionnaire was distributed to a random sample of 50 experts
working in the local consulting, project management and
contracting companies in UAE. The data analysis was carried out
using SPSS for windows and Microsoft excel.
Forty two potential causes of construction projects delay were
identified and it was categorized into contractor, consultant,
project managers, client, financial and unforeseen categories.
33
Fifteen top causes of delay include 6 client related factors, 4
project manager-related factors, 3 financial factors and 2
contractor related factors. The client related factors was more
significant cause of delay which is followed by project team or
management related factors and various financial factors faced by
contractors. Time and cost overrun was identified as the two most
important effects. Hence the study recommended the need for
training clients and their representatives and the project teams.
The study also recommends for a further future work on conducting
a well-grounded survey of construction delays in the UAE to
triangulate the initial approach adopted in this research
findings which will in turn address the limitations of the study
considering the sample size and methodology adopted.
2.7BRIEF HISTORICAL REVIEW OF SCHOOL INFRASTRUCTURE PROJECTS IN GHANASchools infrastructure projects dates back to the pre-colonial
era. When the Gold Coast was colonized, the colonial masters
sought to educate Ghanaians and as such built churches and
schools. As early as 1848, the first college of education
34
(training college) was established in Akuapem-Akropog by the
Presbyterian/Basel missionaries and later transferred under
government’s control. The construction of schools continued
through independence period until now. The issue was that, each
government had its own approach to building schools. This
continued till the establishment of Ghana Educational Trust Fund
(GET fund) in 2000 by an Act of parliament Act 581 which
formalized the procedures leading to the implementation of
government schools infrastructure projects.
There have been reports of blunders committed especially in
supervising the execution of projects as found in the Auditor
General’s reports for 2010. Since many of projects considered in
this study are mostly funded by GET Fund, challenges found will
be beneficial to policy makers at GET Fund as well.
2.8 CHAPTER SUMMARYIt is refreshing to know that, the subject area of this study is
not virgin, thus a number of authors in Ghana and around the
world have research on similar issues in their respective
35
countries. While Sambasivan and Soon (2007) conducted a study on
causes and effect of delays in Malaysian construction industry,
Sunjka and Jacob (2013) conducted a study on the significant
causes and effects of project delays in the Niger delta region,
Nigeria. Also, Aiyetan, Smallwood and Shakantu, (2011) conducted
a study on a system thinking approach to eliminate delays on
building construction projects in South Africa while Motaled and
Kishk (2010) conducteda study to investigate into the causes and
effects of construction delays in United Arab, Emirates (UAE).
One of the major indigenous works which was reviewed was by Fugar
and Agyakwah-Baah (2010). They conducted a study to investigate
the causes of delays of building construction projects in Ghana.
The main theme that runs through all five articles is project
delays while the research setting is the major difference among
all major articles reviewed. In relation to this study, one can
see a relatively new approach being presented, thus though the
causes of project delay is common to all research works
conducted, none of them focused on school infrastructure
36
projects. This indeed places this study in a position that makes
it capable on adding something valuable to extant literature.
The methodological approaches used by all papers reviewed were
similar, thus all of them used a survey approach among certain
person who are contractors, consultants or clients. In the data
gathering process, they are presented a list of possible causes
of project delays from which respondents were to rank which ones
were most frequent or dominant in accounting for the overall
project delays.
It has been seen that, the causes of project delays were quite
similar across all papers except that the factors that were
attributable to the public sector inefficiencies were only common
to the African countries like Nigeria and Ghana. These factors
include delay in honouring certificates and fund disbursements.
The other causes of project delay that were revealed include
underestimation of the costs of projects, underestimation of the
complexity of projects, difficulty in assessing bank credit, poor
37
supervision, understanding of time for completion of projects by
contractors, shortage of materials, poor professional management,
fluctuation of prices or rising cost of materials and poor site
management among others.
CHAPTER THREE
METHODOLOGY
3.1 INTRODUCTION This chapter deals with the methods used in the research to help
answer the research questions. It covers the research design to
38
be used, the population to sample, sample size and sampling
technique, research instrument and instrumentation, and data
analysis procedure. The research design is discussed first since
it partly explains all or some of other items mentioned above.
3.2 RESEARCH DESIGNThe research was designed to use only primary data and secondary
sources of data. The research administered questionnaire for the
collection of primary data. Two types of questions defined the
questionnaire: close-ended and open-ended questions. The Close-
ended questions had predetermined options from which respondents
will select from. On the other hand the open-ended questions
allowed respondents to express their opinion about the subject
being investigated or is understudy.
The primary data was gathered through administering a survey
questionnaire to project managers (contractors), consultants and
the district/municipal/metropolitan assembly engineer who in most
cases have an oversight responsibility over government awarded
39
contracts being implemented in their locality. Both qualitative
and quantitative data were used obtained for analysis towards
answering the research objectives. Therefore descriptive
qualitative and quantitative designs were used to guide the data
collection for analysis. The design was descriptive since the
researcher tried to identify and describe the factors that limit
project managers or contractors’ ability to complete government
projects on time especially those which involved the construction
of school infrastructure.
Descriptive research design is a scientific method involving the
description of the behavior of a subject without influencing it
in any way (Shuttleworth, 2008). Also qualitative and
quantitative design is used since the study will rely on both
qualitative and quantitative data are good and such data can be
analyzed using descriptive analysis.
The data gathered from the questionnaires and analyzed with
content analysis and descriptive analysis. The Descriptive
40
analysis was conducted using Microsoft Excel 2007 and SPSS
(Statistical Product and Services Solutions). The research design
was informed mainly by the works of Sambasivan and Soon (2007)
and Fugar and Agyakwah-Baah (2010).
3.3 TARGET POPULATIONThe study’s target population consisted of all constructing
firms, government agencies and consultant in the greater Accra
region. The study used a stratified sampling to select a sample
of 50 respondents from each strata, three stratum constituting
respondents from constructing firms, government agencies and
consultants, the purpose for stratified sampling is because the
population consist of a number of distinctive components, it is a
useful method of sampling since we are sampling a relatively
small sample from the extremely large and diverse heterogeneous
population.
3.4 SAMPLING SIZE AND SAMPLING TECHNIQUEData or information for the study was obtained by administering
fifty (50) questionnaires to project managers, contractors and
41
government agencies respectively from the target population. Thus
a total of One Hundred and Fifty (150) questionnaires were given
out to the total respondents. Simple Random sampling formed the
sampling technique for the selection of the hundred respondents.
By this technique, the researcher hoped to eliminate biasness in
the selection of potential respondents. Teddlie and Yu (2007)
state that simple random sampling is a probability sampling
technique where each unit (e.g., persons, cases) in the
accessible population has an equal chance of being included in
the sample, and the probability of a unit being selected is
independent of the selection of other units in the population.
3.5 SOURCES OF DATAAs stated in the design the researcher relied on both primary and
secondary sources. The primary form of data was obtained from the
questionnaires that were administered to respondents. The
secondary data was obtained from sources such as journals,
articles and newspapers.
42
3.6 DATA COLLECTION TOOLThe study used carefully designed questionnaires made up of
mostly closed ended questions with a table that had thirty-five
(35) possible causes of project delays learnt from the literature
reviewed in the previous chapter. These possible causes of
project delay were presented in a tabular schedule and
respondents were then required to indicate the extent to which
they agreed to any of the named factors as a cause of overall
project delay in the construction of school infrastructure as
appendixed to this chapter.
3.7 DATA ANALYSISData analysis is the process of planning, organizing,
transforming and modeling data to arrive at useful information
for decision making and in the case of research to address the
research objectives. The researcher used content and descriptive
analysis to achieve the research objectives. The close-ended
questions were analyzed using descriptive methods such as tables,
charts and graphs. Content analysis was carried out the open-
43
ended questions to identify and group similar responses on main
themes the responses carry.
Content analysis or textual analysis is a methodology used to
study the content of communication or textual information.
Responses to open-ended questions when grouped under themes will
be analyzed using descriptive analysis. Descriptive analysis will
be conducted using Microsoft Excel 2007 and SPSS.
44
CHAPTER FOUR
DATA ANALYSIS AND INTERPRETATION OF FINDINGS
4.1 INTRODUCTIONThis chapter deals with making a statistical sense out of the
data. It compresses the data and attempts to bring the
statistical meaning out of it. This chapter considers descriptive
and inferential method of analysis. It also discusses the
relevant issues to answer the research objectives. The population
was divided into three strata and a random sampling of 50
respondents was taken from each stratum and interviewed.
4.2 PERSONAL DETAILS OF RESPONDENTSThe part of the analysis examines the demographic data such as
age, sex, qualification and work experience and job description
of the respondents. The reliability of data gathered in a survey
to a large extent depends on the facts available to the
respondent to the time of the survey. Hence, it makes logical
sense to examine the biographical data on the respondent before
assessing the implications of their responses on the research
questions raised.
45
4.2.1 Distribution of Sex of RespondentsTable 4.1 below depicts that out of the 150 respondents sampled
from the three strata in the Greater Accra metropolis, 76.67% of
the total sampled population were males whiles 23.33% of the
total sampled population were female. . The incidence of more
number of males than females may be explained by the nature of
Ghanaian traditional working environment which encourage more
males than females to take professional careers, for the purpose
of the research, the responses from both sexes will be given
equal consideration as there is no distinct correlation between
gender and the perception of the subject of study.
Table 4.1: The sex of the respondents
Frequency Valid
Percent
Valid male 115 76.67
female 35 23.33
Total 150 100.00
Source: Data Survey
46
4.2.2 Distribution of Respondents AgeFrom figure 4.1 it could be seen that out of the 150 respondents
sampled 3.3% of them were between the age of 20 to 29 years,37
constituting 25% of the total sampled population were between the
age of 30 to 39 year,53 representing 35% of the sampled
population were between the age of 40 to 49 years, also those
between the age of 50 to 59 years made up of 37 respondents
constituting 25% of the total sampled population, furthermore 18
respondents constituting 11.67% of the total sampled population
were 60 years and above
20-29 30-39 40-49 50-59 60 and above
0
10
20
30
40
50
60
Ages
numb
er o
f re
spon
dent
s
47
Figure 4.1: Age of Respondents
Source: Data Survey
4.2.3 Respondents QualificationFrom table 4.2 below show that out of the 150 respondents 5
constituting 3.3% are Diploma and HND holders, 47 constituting
31.67% of the total population sampled are Bachelor degree
holders, 55 constituting 36.67% of the total sampled population
are masters degree holders, also those who hold PHD make up of 10
respondents constituting of 6.67% of the total sampled
population. Lastly 33 constituting of 21.67% of the total sampled
population are professional degree.
Table 4.2: Qualification of Respondents
Qualificat
ion
Frequen
cy
Valid
Percent
Diploma/
HND5 3.333333
Bachelor’s
Degree47 31.66667
48
Master’s
Degree55 36.66667
PHD 10 6.666667
Profession
al33 21.66667
Total 150 100
Source: Data Survey
4.2.4 Respondents’ Experience in Project ManagementFrom figure 4.2 below it could be seen that those whose project
management experience is less than 5 year are 18 constituting
11.67% of the total sampled population,55 constituting 36.675 of
the total sampled population has a project management experience
between the years of 6 t0 10,40 constituting 26.67% of the
respondents are those with project management experience between
11 to 15 years,8.33% respondents said they have manage project
between 16 to 20 years, another 8.33% said they have also managed
projects between 21 to 25 years, furthermore 8respondents
constituting 5% of the total sampled population said they have
49
managed project between 26 to 30 years, lastly those who said
they have managed project for more than 30 years made up of 5
respondents representing 3.33% of the total sampled population.
0204060
years of experience
numb
er o
f re
spon
dent
s
Figure 4.2: Experience gained by respondents in project
management
Source: Data Survey
4.2.5 Respondents Job PositionIt could be seen from table 4.3 below that 77 out of the total
sampled population were project managers or civil engineers, 45
constituting 30% of the total sampled population are site
engineers, 25 respondent representing 16.67% of the total sampled
50
population are site engineers, lastly 3 respondents constituting
1.67% of the total sampled population are those with other job
positions.
Table 4.3: Respondents Job Position
Frequen
cy
Valid
Percent
Project
manager/civil
engineer
77 51.66667
Site engineer 45 30
Site supervisor 25 16.66667
Other 3 1.666667
Total 60 100
Source: Data Survey
4.3 PERCEPTION OF PROJECT SUCCESSThis part of the data analysis ascertains the perception of the
respondent on the success of the school infrastructure project in
the Greater Accra metropolis.
51
4.3.1 What do you think a successful project should be?From figure 4.3 it could be seen that out of the 150 respondents
sampled 27 constituting 18.33% said the completed project should
at least meet the expectation of all stakeholders,33 respondent
representing 22.33% of the total respondents said the project
should deliver what is expected with the minimum cost possible,
those who said projects should be completed within the timescale
set out for the completion were 34 constituting 22.67% of the
total sampled population, also 30 constituting 19.67% of the
total sampled population said completed projects should meet all
the functional requirements, lastly those who said completed
project should deliver sustained and actual benefits to the
stakeholders are 26 constituting 17% of the total sampled
population.
52
010203040
characteristics of project success
numb
er o
f re
spon
dent
s
Figure 4.3 what do you think a successful project should be?
Source: Data Survey
4.3.2 Do you think a project can be said to have absolute successor absolute failure rather than some degree of success or somedegree of failure?From table 4.4 below, out of the 150 respondents sampled 145
constituting 96.67% of the total sampled population said yes,
projects should either be evaluated as absolute success or
absolute failure whiles 5 respondents constituting 3.335 of the
total sampled population said no, projects should rather be
evaluated as some degree of success or some degree of failure.
53
Table 4.4 Do you think a project can be said to have absolute
success or absolute failure rather than some degree of success or
some degree of failure
Frequen
cy
Valid
Percen
t
Yes it should either be evaluated as
absolute success or absolute failure145
96.666
67
No it should rather be evaluated as
some degree of success or some degree
of failure
53.3333
33
Total 150
Source: Data Survey
54
4.3.3 Do you think a project involving the construction ofgovernment school infrastructure can be said to have absolutesuccess or absolute failure rather than some degree of success orsome degree of failure?From figure 4.4 below it could be seen that out of 150
respondents, 140 respondents constituting 93.33% said “Yes”,
project involving the construction of government school
infrastructure can be said to have absolute success or absolute
failure, 10 respondents constituting 6.67% of the total sampled
population responded “No”, project involving the construction of
government school infrastructure should rather be said to have
some degree of success or some degree of failure.
04080120160
response
numb
er o
f re
spon
dent
s
55
Figure 4.4 Do you think a project involving the construction of
government school infrastructure can be said to have absolute
success or absolute failure rather than some degree of success or
some degree of failure?
4.4 CRITICAL FACTORS INFLUENCING PROJECT DELAYSThis part of the data analysis is to deal with the critical
factors that influence the delay on the construction of
government school infrastructure in the greater Accra metropolis.
4.4.1 Inadequate FundingFrom Table 4.5, it could be seen that out of the 150 sampled for
the purpose of the research,110 constituting 73.33% said they
strongly agree that inadequate funding contribute to the delay in
the completion of construction of the school infrastructure,35
constituting 23.335 of the total respondents said they agree that
inadequate funding influences the delay in the delays in the
completion of the construction of the school project,5
constituting 3.33% of the total respondents said they are not
sure if inadequate funding influences the delay in the
construction of the school project.
Table 4.5 Inadequate Funding
56
Frequen
cy
Valid
Percent
not sure 5 3.333333
agree 35 23.33333
strongly
agree110 73.33333
Total 150 100
Source: Data Survey
4.4.2 Political InterferenceIt could be depicted from figure 4.5 that out of the 150
respondents,90 respondents constituting 60% said they strongly
agree that political interference influences the delay in the
construction of the school infrastructure project, 45
constituting 30% of the total sampled population said they agree
that political interference influences the delay in the
construction of the school infrastructure project by the
government,15 respondents constituting 10% of the total
respondents said that they are not sure if political interference
57
influences the delay in the construction of the school
infrastructure project by government in the greater Accra.
not sure agree strongly agree0102030405060708090100
response for factor contributing to project failure
numb
er o
f re
spon
dents
Figure 4.5 Political Interference
Source: Data Survey
4.4.3 Increasing Cost of constructionFrom table 4.6,it could be seen that out of the total sampled
population of 150 respondents,57 respondents constituting 38.33%
said they strongly agree that increasing cost of construction
influences the delay in completion of the construction of the
school infrastructure project by the government in Greater
Accra,50 constituting 33.33% of the total respondents said they
58
that increasing cost of production influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater accra,33 respondents
constituting 21.67% of the total respondents said they are not
sure that increasing cost of construction influences the delay
in completion of the construction of the school infrastructure
project by the government in Greater Accra, also 5 constituting
3.33% of the total respondents said they disagree that increasing
cost of production influences the delay in completion of the
construction of the school infrastructure project by the
government in Greater Accra, lastly 5 constituting of 3.33% of
the total sampled population said that they strongly disagree
that increasing cost of production influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra.
Table 4.6 increasing cost of production
Frequen
cy
Valid Percent
59
strongly
disagree5 3.333333
disagree 5 3.333333
not sure 33 21.66667
agree 50 33.33333
strongly agree 57 38.33333
Total 150 100
Source: Data Survey
4.4.4 Improper planningfrom figure 4.5,it could be seen that out of the sampled
population of 150 respondents,55 respondents constituting 37% of
the total sampled population said they agree that improper
planning influences the delay in completion of the construction
of the school infrastructure project by the government in Greater
Accra,50 constituting 33% of the total sampled population said
they strongly agree that improper planning influences the delay
in completion of the construction of the school infrastructure
project by the government in Greater Accra,25 of the respondents
constituting 17% of the total sampled population said they are
60
not sure that improper planning influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra,12 respondents
representing 8% of the total sampled population said they
disagree that improper planning influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra,5 constituting 3% of
the total respondents said they strongly disagree that improper
planning influences the delay in completion of the construction
of the school infrastructure project by the government in Greater
Accra, lastly 3 respondents constituting 2% of the total sampled
population said it is not applicable that improper planning
influences the delay in completion of the construction of the
school infrastructure project by the government in Greater Accra.
61
0
20
40
60
response to factors contributing to project failure
numb
er o
f re
spon
se
Figure 4.6 Improper Planning
Source: Data Survey
4.4.5 Weather ConditionFrom table 4.8 below it could be that 55 respondents constituting
37% of the total sampled population agree that weather condition
influences the delay in completion of the construction of the
school infrastructure project by the government in Greater Accra,
40 constituting 27% of the total sampled population said that
they strongly agree that weather condition influences the delay
in completion of the construction of the school infrastructure
project by the government in Greater Accra, also another 40
62
respondents constituting 27% of the total respondents said they
were not sure that weather condition influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra,10 respondents
constituting 6% of the total sampled population said it was not
applicable that weather condition influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra, lastly 5 constituting
3% of the total sampled population said they strongly disagree
that weather condition influences the delay in completion of the
construction of the school infrastructure.
Table 4.7 Weather Condition
Frequen
cy
Valid
Percent
not
applicable10 6
strongly
disagree5 3
63
not sure 40 27
Agree 55 37
strongly
agree40 27
Total 150 100
Source: Data Survey
4.4.6 Equipment availability and failure
from figure 4.7 it could be seen that out of the 150 sampled from
the three strata,61 constituting of 41% of the total sampled
population said they are not sure that equipment availability and
failure influences the delay in completion of the construction of
the school infrastructure project by the government in Greater
Accra,31 constituting 20% of the total sampled population said
they agree and strongly agree each that equipment availability
and failure influences the delay in completion of the
construction of the school infrastructure project by the
government in Greater Accra,25 of the respondents representing
17% of the total sampled population said they disagree that
64
equipment availability and failure influences the delay in
completion of the construction of the school infrastructure
project by the government in Greater Accra, lastly 3 constituting
2%of the total sampled population for the research said it is not
applicable that equipment availability and failure influences the
delay in completion of the construction of the school
infrastructure project by the government in Greater Accra.
65
not apllicable
disagree
not sure
agree
strongly agree
0
20
40
60
response to factors contributing to project failure
numb
er o
f re
spon
dent
s
Figure 4.7 equipment availability and Failure
Source: Data Survey
4.4.7 inadequate contractor experience in that particular areaFrom table 4.8,it could be seen that out of the 150 respondent
sampled,49 constituting 33% of the total sampled population said
they agree that inadeguate contrators experience in that
particular area influences the delay in completion of the
construction of the school infrastructure project by the
government in Greater Accra,44 constituting 29% of the total
respondents said they are not sure that inadeguate contrators
experience in that particular area influences the delay in
66
completion of the construction of the school infrastructure
project by the government in Greater Accra,34 respondents
constituting 22% of the total sampled population said they
disagree that inadeguate contrators experience in that particular
area influences the delay in completion of the construction of
the school infrastructure project by the government in Greater
Accra,21 constituting 145 of the total respondents said they
strongly agree that inadeguate contrators experience in that
particular area influences the delay in completion of the
construction of the school infrastructure project by the
government in Greater Accra, lastly 3 constituting 2% of the
total sampled population said they strongly agree that inadeguate
contrators experience in that particular area influences the
delay in completion of the construction of the school
infrastructure project by the government in Greater Accra.
Table 4.8Inadequate Contractor Experience In That Particular Area
Frequen
cy
Valid
Percent
67
strongly
disagree3 2
disagree 34 22
not sure 44 29
agree 49 33
strongly
agree21 14
Total 150 100
Source: Data Survey
4.4.8 Shortage in materialFigure 4.8 depicts that out of the total sampled population of
150 respondents,53 constituting 36% were not sure that shortage
in material influences the delay in completion of the
construction of the school infrastructure project by the
government in Greater Accra,41 constituting 36% of the total
sampled population agrees that shortage in material influences
the delay in completion of the construction of the school
infrastructure project by the government,25 constituting 17% of
the total sampled respondents disagree that shortage in material
68
influences the delay in completion of the construction of the
school infrastructure project by the government,18 respondents
constituting 12% of the total respondents strongly disagree that
shortage in material influences the delay in completion of the
construction of the school infrastructure project by the
government,lastly13 constituting 8% of the total respondents
strongly agree that shortage in material influences the delay in
completion of the construction of the school infrastructure
project by the government.
strongly disagree
disagree not sure agree strongly agree
0
10
20
30
40
50
60
response to factors contributing to project failure
numb
er o
f re
spon
dent
s
Figure 4.8 Shortages in Material
69
Source: Data Survey
4.4.9 Do you think there are external (outside the projectenvironment) factors that affect project success or failure?Figure 4.9 indicate that 120 constituting 80% of the total
sampled population said yes they think there are external
(outside the project environment) factors that affect the project
success or failure whiles 30 constituting 20% of the total
sampled population said no there is don’t think there are
external factors that affects the project’s success or failure.
yes no020406080100120140
response
numb
er o
f re
spon
dent
s
70
Figure 4.9 Do you think there are external (outside the project
environment) factors that affect project success or failure?
Source: Data Survey
4.5 PROJECT SUCCESS FACTORSThis part of the data analysis deals with the factors that are
associated with project success of the school infrastructure
project by the government.
4.5.1 Management support is essential for the project to succeedFrom table 4.10 below it could be seen that 67 respondents
constituting 45% of the total sampled population strongly agree
that management support is essential for the school
infrastructure project to succed,another 67 constituing 45% of
the total respondents agree that management support is essential
for the school infrastructure project to succed,3 constituting 2%
of the total sampled poipulation said they were not sure if
management support is essential for the school infrastructure
project to succed,out of the total sampled population of 150
71
respondents 10 constituting 7%,disagree that management support
is essential for the school infrastructure project to
succed,lastly 3 constituting 2% of the total sampled population
strongly disagree that management support is essential for the
school infrastructure project to succed.
Table 4.9 Management support is essential for the project to
succed
Frequen
cy
Valid
Percent
strongly
agree67 45
agree 67 45
not sure 3 2
disagree 10 7
strongly
disagree3 2
Source: Data Survey
72
4.5.2 Skilled and experience project managers and staff iscritical for project to be successfulFigure 4.9,it could be seen that out of the total sampled
population of 150 respondents,73 constituting 48% of the total
sampled population strongly agree that skilled and experienced
project managers and staffs is critical for the success of the
school infrastructure project,65 constituting 43% of the total
sampled population agree that skilled and experienced project
managers and staffs is critical for the success of the school
infrastructure project,10 constituting 7% of the total sampled
population were not sure that skilled and experienced project
managers and staffs is critical for the success of the school
infrastructure project,3 constituting 2% of the total sampled
population disagree that skilled and experienced project managers
and staffs is critical for the success of the school
infrastructure project.
73
strongly agree
agree not sure disagree0
1020304050607080
response to project success
numb
er o
f re
spon
dent
ss
Figure 4.10 Skilled and experience project managers and staffs is
critical for project to be successful
Source: Data Survey
4.5.3 Communicating the expectation of the project to all groupsinvolved, and roles clearly defined for each and every group willensure a successful projectFrom table 4.11 below show that out of the total sample
population of 150 respondents,75 constituting 50% of the total
respondents strongly agree that communicating the expectation of
the project to all groups involved and roles clearly defined for
each and every group will ensure the success of the school
infrastructure project,53 constituting 35% of the total sampled
74
population agree that, communicating the expectation of the
project to all groups involved and roles clearly defined for each
and every group will ensure the success of the school
infrastructure project,12 respondents constituting 8% of the
total sampled population were not sure that communicating the
expectation of the project to all groups involved and roles
clearly defined for each and every group will ensure the success
of the school infrastructure project, lastly 10 constituting 7%
of the total sampled population disagree that communicating the
expectation of the project to all groups involved and roles
clearly defined for each and every group will ensure the success
of the school infrastructure project.
Table 4.10 Communicating the Expectation of the Project to All
Groups Involve, and Roles Clearly Defined for each and every
Group will ensure a Successful Project
Frequency Valid Percent
strongly agree 75 50Agree 53 35not sure 12 8
75
disagree 10 7Total 150 100
Source: Data Survey
This aspect of the data analysis deal with all critical factors
that influences the delay in the completion of the school
infrastructure project and the most relevant of the critical
factors with respect to the various strata that was randomly
sampled to select the 150 respondent, each stratum was analyzed
with respect to the critical factors and the top ten most
relevant ones was selected.
4.6 COMPOSITE RANKING OF SUCCESS FACTORS FROM ALL CATEGORIES OFRESPONDENTSThe study acknowledges that all three respondents groups play a
specialized role in project management; hence it will be very
importance to pool all their responses together to ascertain the
overall ranking of success factors as revealed from the study’s
total respondent group. Table 4.14 shows this below using the
Respondent Importance Index (RII).
76
Table 4.11 ranking of Delay factors and RII by Building
contractors
building contractors RII %ranking
Owner Interference 92.8 1Delay in the release of funds 92.4 2Weather condition 91.2 3Mistakes during construction stage 88.4 4Poor Site management 84.4 5Inadequate funding 84 6Improper planning 80 7High cost of funding 74.4 8Unrealistic contract duration andrequirements imposed 71.6 9Contract relationships related causes Majordisputes and negotiations 70 10
The relative importance index table above lists the building
contractor’s results of responses per factor causing delay in the
school construction project in Ghana; the table depicts that
building contractor’s rank the factor ‘owner interference’ as the
prime cause of the school construction project delay in Ghana
with a relative importance index of 92.8%,the factor ‘contract
relationships related causes major disputes and negotiations’ as
the less cause of school construction project delay in Ghana.
77
Table 4.12 ranking of Delay factors and RII by government
agencies
GOVERNMENT AGENCIES
RelativeimportanceIndex
ranking
Inadequate funding 94.4 1Political interference 91.2 2Unforeseen adverse site condition 81.6 3Poor Site management 80.8 4Poor stakeholder management 75.6 5Inappropriate overall organizationalstructure linking to the project 74.4 6Delay in the release of funds 73.2 7Material related causes Quality of material 72.4 8Quality assurance/control 71.6 9Contract related causes Change orders 66.8 10
The relative importance index table above lists the building
contractor’s results of responses per factor causing delay in the
school construction project in Ghana; the table depicts that
building contractor’s rank the factor ‘inadequate funding’ as the
prime cause of the school construction project delay in Ghana
with a relative importance index of 94.4%, the factor ‘contract
78
related causes change orders’ as the less cause of school
construction project delay in Ghana.
Table 4.13 ranking of Delay factors and RII by consultant
consultant
relativeimportanceindex
ranking
Inadequate funding 90 1political interference 86.4 2Owner Interference 73.6 3Delay in the release of funds 72 4Unrealistic contract duration andrequirements imposed 71.6 5Poor Site management 70.4 6consultant related causes contractmanagement 68.8 7material related cause qualitymaterial 68 8preparation and approval ofdrawings 67.2 9contract related causes changeorder 66.8 10
The relative importance index table above lists the building
contractor’s results of responses per factor causing delay in the
79
school construction project in Ghana; the table depicts that
building contractor’s rank the factor ‘inadequate funding’ as the
prime cause of the school construction project delay in Ghana
with a relative importance index of 92.8%,the factor ‘contract
related causes change order’ as the less cause of school
construction project delay in Ghana.
Table 4.14: Ranking of delay factors and RII
Ranking Delay factor description
Frequency
RelativeimportanceIndex RII %
1 Inadequate funding 143 952 Political interference 138 91.66673 Unforeseen adverse site condition 128 85.31074 Poor stakeholder management 127 84.7701
5Contractor related causesSubcontractors 127 84.7222
6 Inappropriate overall 127 84.4828
80
organizational structure linking tothe project
7 Increasing cost of production 127 84.44448 Owner Interference 126 84.1954
9Lack of communication between theparties 126 84.1954
10Mistakes and discrepancies incontract document 125 83.3333
11 Regulatory changes 124 82.471312 Poor Site management 123 81.920913 Weather condition 123 81.920914 Problem with neighbors 123 81.8966
Wrong timing of projectcommencement dates (like rainyseasons) 121 80.5085
17Preparation and approval ofdrawings 120 80.226
18
Conflict of interest betweencontractor’s expectation and theproject objective 120
80.1724
19Labor and equipment category causesLabor supply 120 79.8851
20 Delay in the release of funds 118 78.8889
21Waiting time for approval of testsand inspection 117 77.7778
22
Contract relationships relatedcauses Major disputes andnegotiations 116 77.381
23 Slow decision making 116 77.118624 Improper planning 113 7525 Equipment availability and failure 112 74.4253
26Consultant related causes Contractmanagement 110 73.6111
27 Labor and equipment category causes 110 73.0556
81
Labor supply28 Quality assurance/control 109 72.598929 Mistakes during construction stage 109 72.413830 Shortage in material 107 71.186431 High cost of funding 107 71.0526
32Inadequate contractor experience inthat particular area 104 69.4444
33 Labor productivity 102 68.3333
34Contract related causes Changeorders 102 68.3333
35Material related causes Quality ofmaterial 102 67.7778
The relative importance index table above lists the total
results of responses per factor causing delay in the school
construction project in Ghana, the table depicts that respondents
rank the factor “inadequate funding” as the highest cause of the
delay in the school construction project in Ghana with a relative
importance index of 95%, the respondents also ranked the factor
“Material related causes (Quality Material)” as the least cause
of the delay in the school construction project with a relative
importance index of 67.7778% .
82
CHAPTER FIVE
SUMMARY OF FINDINGS, CONCLUSION AND RECOMMENDATIONS
5.1INTRODUCTIONThis part of the study presents the final stage of the entire
work. It summarizes the findings from the data collected and
gives adequate conclusion and recommendations for policy
consideration.
5.2 SUMMARY OF FINDINGSLooking at their experience on the job, assessment of how
respondents viewed a successful project revealed that most of
them believed that a successful project should be completed
within the time scale set out for the completion of the project.
83
This was followed by the view that a successful project should
deliver what is expected within a minimum cost possible.
Meanwhile others also deemed a successful project to be able to
meet all functional requirements of the project. The remaining
views were that at least a successful project should meet the
expectations of all project stakeholders and also deliver
sustained actual benefits ti the stakeholders. This indicates
that successful projects should primarily be completed within the
time scale set out for the project.
Respondents were further probed on whether a project could be
considered as an absolute success or failure rather than some
degree of success or failure. Majority representing about 97%
believed that indeed a project can be deemed as an absolute
success or absolute failure. However, the rest thought a process
could have some elements of failure or success. They therefore
indicated that the construction of a government school
infrastructure can be deemed as either successful or failed.
84
Assessment of the factors that influenced project delays were
found to include more importantly, inadequate finance, political
interference and improper planning and increase cost of
production even though a few of them did not believe their impact
on project delays. Moreover, factors such as weather condition,
inadequate contractor experience and other external factors also
affect the success of projects undertaken. However, elements such
as shortage in material and equipment availability and failure do
not really affect the completion of projects on time.
Findings further revealed that there are various success factors
such as management support, skilled and experience project
managers and staffs as well as the communication of the
expectation of the project to all groups involve, and roles
clearly defined for each and every group will ensure a successful
project. This indicates that for a project to be successful there
should be total support for the project and project managers as
well as staff need the requisite skills and be abreast with the
expectations of the project.
85
Moreover, other critical success factors that influence project
delay from building contractors view indicate that, factor such
as unrealistic contract duration and requirements imposed,
inadequate funding and poor site management and high cost of
funding all have a strong influence on the delay of school
infrastructure in Ghana. Others also agree that contractual
relationships and improper planning contribute to delay in
completion. Others comprise of owner interference and weather
conditions. This indicates that there are myriad factors that
influence project delays in the contractors’ point of view.
However, from the consultants view, factors that causes delay in
construction include delay in the release of fund, political
interference, material related causes, quality of material and
unrealistic contract duration and requirements imposed as well as
owner interference. However, respondents were indifferent about
factors such as poor site management, consultant related clauses
in contract management and preparation and approval of drawings
in their influence on project delays.
86
Meanwhile, from the government agency perspective, factors such
as inadequate funding, delay in the release of funds and
political interference have critical influence on the delay of
construction projects. Other pressing factors include poor site
management, quality assurance, unforeseen adverse site condition,
poor stakeholder management and inappropriate overall
organizational structure linking to the project as well as
quality of materials. However, factors that were not highly
considered to influence the delay in construction projects
include contract related causes that Change orders.
5.3 CONCLUSIONThe main objective of the study was to assess the causes of
project delays in Ghana with specific emphasis on the
infrastructure government school projects in the Greater Accra
Region. Findings have been able to achieve the research
objectives and as such, it can be concluded that there are
various causes of delays in projects from the perspectives of
contractors, the government agency and the consultants. From the
building contractors’ perspective, it is evident that
87
insufficient funds needed for the construction of the projects
tend to impede the progress of the construction. Additionally,
contractors believe that contract durations are often
characterized by unrealistic contract duration that tends to make
it difficult for contractors to meet that duration. Additionally,
construction site management is essential in ensuring the
successful completion of projects. Meanwhile, high cost of
funding the projects sometimes affects the progress and
completion of the projects due to the contractors’ inability to
meet the rising cost. This finding is buttressed by Sambasivan
and Soon (2007) who indicated that delays are mainly caused by
time and cost overruns among others.
Apart from the above mentioned factors, other pressing issues
such as improper planning, mistakes during the construction stage
as well as owner interference and weather conditions all affect
the progress and completion of projects. This shows that delays
in construction projects can be caused by the constructors
themselves through poor planning on the particular project.
88
Additionally, unforeseen situations such as poor weather
conditions and owner interference also cause project delays. This
is buttressed by the findings of Kometa et al. (1994) who
indicated almost all these factors as causes of delay in
construction.
From the consultants view, it can be concluded that delay in the
release of funds from the government tend to impede the progress
of the project as funds needed for the procurement of the
construction materials tend to delay. Additionally, factors
mentioned by the contractors have also been mentioned by the
consultants. Some of these include unrealistic contact duration,
material related causes and owner interference. Other identified
issues from their perspective included consultant related clauses
in contract management that are hard to comply and the duration
of drawing preparation and approval. All these are critical
issues that tend to cause project delays. These findings are
further in accordance with the findings of [Assaf et al. (1995);
Sunjka and Jacob (2013)] who identified that issues concerning
89
materials, equipment and manpower, finance and environment as
well as government actions all contribute to project delays.
Moreover, from the government agency’s perspective, delays in
construction are mainly caused by delay in release of funds
coupled with their inadequacies as well as political interference
as stipulated by (Assaf et al. 1995). This indicates that the
government does not allow the agency to control the project
construction adequately. Also, funds are not released to the
agencies on time for prompt delivery to contractors. Other
identified issues also include poor site management as mentioned
earlier, quality assurance issues, unforeseen adverse site
condition and poor stakeholder management. All these show that
certain unplanned circumstances also contribute to the delay in
construction. Additionally, stakeholders are not properly managed
to ensure the progress of the projects. Meanwhile, the
organizational structure that links to the project tends to be
inefficient in ensuring the progress of the project.
90
In general, causes of government construction project delays
comprises of factors such as inadequate funding, political
interference, increase cost of production due to high cost of
prices on market, improper planning on the projects as well as
weather conditions and equipment availability and failure.
Additionally, the experience of the contactors assigned and
shortage of materials to a particular project also contribute to
the delay of construction.
It could be seen that all these delays can have adverse effect on
the success of the project. This is due to the fact that it will
have impact on project success in terms of time, cost, quality
and safety as indicated by (Faridi and El-Sayegh, 2006).
Meanwhile, considering the success of government construction
project, it can be concluded that communication of the
expectations of the project to all groups need to be ensured.
Additionally, management needs to provide the needed support to
equip contractors to give their best. Meanwhile, project success
91
also is highly dependent on the skills and experience of project
managers and staff who will undertake.
5.4 RECOMMENDATIONSThe study has been able to identify the various causes of delay
in construction government school projects in Ghana. It therefore
recommends among others that it is important that adequate and
timely provision of financial resources in building construction
government school projects is provided by the government to avoid
delay and subsequent failure of the projects. Furthermore,
government agencies that contract the contractors for the school
projects need to assess the competencies of the contractors to
ensure that they are capable to deliver at the right time
Stakeholders are critical to the success of every project and as
such, managers and contractors of projects need to be adequately
managed to ensure that stakeholders are abreast with the project
and its progress. The Government of Ghana needs to give
contractors and agencies the needed timeand opportunity to work
to ensure the successful completion of the projects as the
92
interference causes delay and subsequently affects the overall
success of the project.
Procurement for government school projects need to be provided on
time for prompt delivery by agencies to avoid project delay and
frustrations. Finally, contractors and staff assigned to a
particular school project need to be equipped with the requisite
skills to avoid all inadequacies on the project. This could be
done through periodic research and training on the job.
Implementation plan
Action
points
resources Responsible
agency
Time
frame
cost
Stakeholder
s meeting
for players
in the
constructio
n industry
Publicity
Venue for
meeting
Logistics/
stationary
GET Fund
and GES
3
weeks(
should
be done
by
August
To be
determi
ne by
the
respons
ible
93
like
ministry of
education,
GES and GET
Fund
so that
the
outcome
could
be
conside
red in
the
nationa
l
budget
prepara
tion
agency
Strengtheni
ng of
committees
that have
oversight
Budget
allocation
Inclusion of
prosecution
powers in the
GES,GETFUND
and
parliament
6
months
To be
determi
ned by
respons
ible
94
responsibil
ity in
supervising
government
school
project at
GES,GETFUND
and
parliament
regulatory
establishing
this committees
agency
REFERENCESAhmed, S. M., Azhar, S., Kappagntula, P. and Gollapudil, D.
(2003). “Delays in construction: a brief study of Florida
construction industry”. Proceedings of the 39th Annual ASC