-
For Official Use NEA/SEN/NRA/WGOE(2015)1 Organisation de
Coopration et de Dveloppement conomiques Organisation for Economic
Co-operation and Development 04-May-2015
___________________________________________________________________________________________
_____________ English text only NUCLEAR ENERGY AGENCY
Committee on Nuclear Regulatory Activities
Working Group on Operating Experiences
Technical Note on Operating Experience:
Pre-Stressed Anchor Bolts Non-Compliances
JT03375546
Complete document available on OLIS in its original format
This document and any map included herein are without prejudice
to the status of or sovereignty over any territory, to the
delimitation of
international frontiers and boundaries and to the name of any
territory, city or area.
NE
A/S
EN
/NR
A/W
GO
E(2
015)1
For O
fficial U
se
En
glish
text o
nly
-
NEA/SEN/NRA/WGOE(2015)1
2
ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT
The OECD is a unique forum where the governments of 34
democracies work together to address the economic, social and
environmental challenges of globalisation. The OECD is also at
the forefront of efforts to understand and to help
governments respond to new developments and concerns, such as
corporate governance, the information economy and the
challenges of an ageing population. The Organisation provides a
setting where governments can compare policy
experiences, seek answers to common problems, identify good
practice and work to co-ordinate domestic and international
policies.
The OECD member countries are: Australia, Austria, Belgium,
Canada, Chile, the Czech Republic, Denmark, Estonia,
Finland, France, Germany, Greece, Hungary, Iceland, Ireland,
Israel, Italy, Japan, Luxembourg, Mexico, the Netherlands,
New Zealand, Norway, Poland, Portugal, the Republic of Korea,
the Slovak Republic, Slovenia, Spain, Sweden,
Switzerland, Turkey, the United Kingdom and the United States.
The European Commission takes part in the work of the
OECD.
OECD Publishing disseminates widely the results of the
Organisations statistics gathering and research on economic, social
and environmental issues, as well as the conventions, guidelines
and standards agreed by its members.
This work is published on the responsibility of the OECD
Secretary-General.
The opinions expressed and arguments employed herein do not
necessarily reflect the official views of the Organisation or of
the governments of its member countries.
NUCLEAR ENERGY AGENCY
The OECD Nuclear Energy Agency (NEA) was established on 1
February 1958. Current NEA membership consists of 31
countries: Australia, Austria, Belgium, Canada, the Czech
Republic, Denmark, Finland, France, Germany, Greece, Hungary,
Iceland, Ireland, Italy, Japan, Luxembourg, Mexico, the
Netherlands, Norway, Poland, Portugal, the Republic of Korea,
the
Russian Federation, the Slovak Republic, Slovenia, Spain,
Sweden, Switzerland, Turkey, the United Kingdom and the
United States. The European Commission also takes part in the
work of the Agency.
The mission of the NEA is:
to assist its member countries in maintaining and further
developing, through international co-operation, the scientific,
technological and legal bases required for a safe, environmentally
friendly and economical use of
nuclear energy for peaceful purposes;
to provide authoritative assessments and to forge common
understandings on key issues, as input to government decisions on
nuclear energy policy and to broader OECD policy analyses in areas
such as energy and sustainable
development.
Specific areas of competence of the NEA include the safety and
regulation of nuclear activities, radioactive waste
management, radiological protection, nuclear science, economic
and technical analyses of the nuclear fuel cycle, nuclear law
and liability, and public information.
The NEA Data Bank provides nuclear data and computer program
services for participating countries. In these and
related tasks, the NEA works in close collaboration with the
International Atomic Energy Agency in Vienna, with which it
has a Co-operation Agreement, as well as with other
international organisations in the nuclear field.
This document and any map included herein are without prejudice
to the status of or sovereignty over any territory, to the
delimitation of international frontiers and boundaries and to the
name of any territory, city or area.
Corrigenda to OECD publications may be found online at:
www.oecd.org/publishing/corrigenda.
OECD 2015
You can copy, download or print OECD content for your own use,
and you can include excerpts from OECD publications, databases and
multimedia products in your own documents, presentations, blogs,
websites and teaching materials, provided that suitable
acknowledgment of the OECD as source
and copyright owner is given. All requests for public or
commercial use and translation rights should be submitted to
[email protected]. Requests for
permission to photocopy portions of this material for public or
commercial use shall be addressed directly to the Copyright
Clearance Center (CCC) at
[email protected] or the Centre franais d'exploitation du droit
de copie (CFC) [email protected].
-
NEA/SEN/NRA/WGOE(2015)1
3
COMMITTEE ON NUCLEAR REGULATORY ACTIVITIES
The Committee on Nuclear Regulatory Activities (CNRA) shall be
responsible for the programme of
the Agency concerning the regulation, licensing and inspection
of nuclear installations with regard to
safety. The Committee shall constitute a forum for the effective
exchange of safety-relevant information
and experience among regulatory organisations. To the extent
appropriate, the Committee shall review
developments which could affect regulatory requirements with the
objective of providing members with an
understanding of the motivation for new regulatory requirements
under consideration and an opportunity to
offer suggestions that might improve them and assist in the
development of a common understanding
among member countries. In particular it shall review current
management strategies and safety
management practices and operating experiences at nuclear
facilities with a view to disseminating lessons
learnt. In accordance with the NEA Strategic Plan for 2011-2016
and the Joint CSNI/CNRA Strategic Plan
and Mandates for 2011-2016, the Committee shall promote
co-operation among member countries to use
the feedback from experience to develop measures to ensure high
standards of safety, to further enhance
efficiency and effectiveness in the regulatory process and to
maintain adequate infrastructure and
competence in the nuclear safety field.
The Committee shall promote transparency of nuclear safety work
and open public communication.
The Committee shall maintain an oversight of all NEA work that
may impinge on the development of
effective and efficient regulation.
The Committee shall focus primarily on the regulatory aspects of
existing power reactors, other
nuclear installations and the construction of new power
reactors; it may also consider the regulatory
implications of new designs of power reactors and other types of
nuclear installations. Furthermore it shall
examine any other matters referred to it by the Steering
Committee. The Committee shall collaborate with,
and assist, as appropriate, other international organisations
for co-operation among regulators and consider,
upon request, issues raised by these organisations. The
Committee shall organise its own activities. It may
sponsor specialist meetings and working groups to further its
objectives.
In implementing its programme the Committee shall establish
co-operative mechanisms with the
Committee on the Safety of Nuclear Installations in order to
work with that Committee on matters of
common interest, avoiding unnecessary duplications. The
Committee shall also co-operate with the
Committee on Radiation Protection and Public Health and the
Radioactive Waste Management Committee
on matters of common interest.
-
NEA/SEN/NRA/WGOE(2015)1
4
-
NEA/SEN/NRA/WGOE(2015)1
5
FOREWORD
The NEA Committee on Nuclear Regulatory Activities (CNRA)
believes that sharing operating
experience from the national operating experience feedback
programmes are a major element in the
industrys and regulatory bodys efforts to ensure the continued
safe operation of nuclear facilities.
Considering the importance of these issues, the Committee on the
Safety of Nuclear Installations (CSNI)
established a working group, PWG #1 (Principle Working Group
Number 1) to assess operating experience
in the late 1970s, which was later renamed the Working Group on
Operating Experience (WGOE). In
1978, the CSNI approved the establishment of a system to collect
international operating experience data.
The accident at Three Mile Island shortly after added impetus to
this and led to the start of the Incident
Reporting System (IRS). In 1983, the IRS database was moved to
the International Agency for Atomic
Energy (IAEA) to be operated as a joint database by IAEA and NEA
for the benefit of all of the member
countries of both organisations. In 2006, the WGOE was moved to
be under the umbrella of the Committee
on Nuclear Regulatory Activities (CNRA) in NEA. In 2009, the
scope of the Incident Reporting System
was expanded and re-named the International Reporting System for
Operating Experience (although, the
acronym remains the same).
The purpose of WGOE is to facilitate the exchange of
information, experience, and lessons learnt
related to operating experience between member countries. The
working group continues its mission to
identify trending and issues that should be addressed in
specialty areas of CNRA and CSNI working
groups.
-
NEA/SEN/NRA/WGOE(2015)1
6
-
NEA/SEN/NRA/WGOE(2015)1
7
TABLE OF CONTENTS
1. Introduction
................................................................................................................................................
9
2. Description of the issue
............................................................................................................................
11
3. Observations and regulatory significance
.................................................................................................
15
4. Root causes
...............................................................................................................................................
17
5. Regulatory actions and licensee corrective actions
..................................................................................
19
6. Conclusions
..............................................................................................................................................
21
Appendix A: ASN Presentation
.....................................................................................................................
23
Appendix B: WGOE Questions And Country Responses
.............................................................................
29
WGOE QUESTIONS
................................................................................................................................
29 CANADA
..................................................................................................................................................
29 CZECH REPUBLIC
..................................................................................................................................
30 FINLAND
..................................................................................................................................................
30 GERMANY
...............................................................................................................................................
31 INDIA
........................................................................................................................................................
31 JAPAN
.......................................................................................................................................................
31 SPAIN
........................................................................................................................................................
32 SLOVAKIA
...............................................................................................................................................
32 SLOVENIA
...............................................................................................................................................
32 SWEDEN
...................................................................................................................................................
32 SWITZERLAND
.......................................................................................................................................
32 UNITED KINGDOM
................................................................................................................................
32
-
NEA/SEN/NRA/WGOE(2015)1
8
-
NEA/SEN/NRA/WGOE(2015)1
9
1. INTRODUCTION
The WGOE is a network of operating experience experts that allow
countries to reach out on specific
issues to get timely feedback on practices and experience in
other countries. The primary purpose of this
type of technical note is to capture the exchange of information
for an emergent operating experience
challenge from a specific country and its resolution. Sometimes,
these issues are resolved in such a manner
that they do not rise to the level of an International Incident
Reporting System (IRS) report. This technical
note captures the operating experience.
In 2008, the presentation in Appendix A was given to the WGOE
members to introduce the issue.
Following this presentation, questions were distributed to WGOE
members to better understand
international experience and actions and to inform about ASNs
plan of action. The questions and
responses of different WGOE members are gathered in Appendix
B.
-
NEA/SEN/NRA/WGOE(2015)1
10
-
NEA/SEN/NRA/WGOE(2015)1
11
2. DESCRIPTION OF THE ISSUE
The nineteen French nuclear power plants (NPPs) currently in
operation are very similar in their design
and construction (PWR type). They each comprise from two to six
units, which in total amounts to 58
reactors. Each reactor includes a nuclear island, a conventional
island, water intake and discharge
infrastructures, and potentially a cooling tower.
The nuclear island mainly consists of the reactor vessel, the
reactor coolant system, the steam generators
and the circuits and systems ensuring reactor operation and
safety. Various support function circuits and
systems are also associated with these systems: primary effluent
treatment, ventilation and air-
conditioning
These main systems or circuits are equipped with materials which
are often attached to concrete slab with
anchor bolts. They are fixed by steel rods through the concrete
slab. These rods are prestressed, i.e. under
tension during assembly, to prevent slippage and detachment of
the support under the effect of forces
applied under normal or accidental situation, particularly in
case of earthquake or pipe break.
Approximately 1,000 anchor bolts are used in a French
reactor.
Figure 1: Anchor bolt description
In the early 1990s, several non-compliances were discovered:
- anchor bolts undersized comparing to their conception (ex:
anchor bolts of the borated water tank
of the security injection system),
- stress corrosion cracking (SCC), which may cause the failure
of the anchor bolt,
-
NEA/SEN/NRA/WGOE(2015)1
12
- and loss of tension, which is caused by delayed strains in
concrete (such as shrinkage and creep
phenomena).
Following are two examples to illustrate the extend of the
issue.
Steam generator anchor bolts
Figure 2 : Steam generator anchor bolts
Each steam generator of the French reactors is equipped with
four self-locking devices. Each device is
fixed to the concrete by four anchor bolts and designed to get
locked during an accident situation without
hindering the possible displacements of the steam generator in
normal operating situations.
-
NEA/SEN/NRA/WGOE(2015)1
13
Originally, these steam generator anchor bolts of 900 MWe CP01
reactors were not protected against
corrosion. Given their steel characteristics and their tension
value, they are listed as being susceptible to
failure by SCC.
In order to cancel this risk, the 48 original anchor bolts of
each reactor (except one) have been replaced by
protected against corrosion by a zinc layer, by the end of
2011.
Reactor vessel support anchor bolts
The concrete support of the reactor vessel is equipped with 18
to 19 devices which aim at preventing
horizontal displacement of the reactor vessel during earthquake.
Each device is composed of 8 anchor
bolts.
Anchor bolts of the 900 MWe CPY2 reactors (except one 4-unit
NPP) are affected by tension loss and
failure by SCC. The following diagram shows the evolution over
time of the number of broken anchor
bolts discovered in the three most affected reactors.
1 CP0 reactors : four reactors at Bugey (reactors 2 to 5) and
two reactors at Fessenheim
2 CPY reactors : consisting of another twenty-eight 900 MWe
reactors, that can also be subdivided into CP1 (eighteen
reactors at Blayais, Dampierre-en-Burly, Gravelines and
Tricastin) and CP2 (ten reactors at Chinon, Cruas-
Meysse and Saint-Laurent-des-Eaux)
Year
Nu
mb
er
of
bro
ken
anch
or
bolts
-
NEA/SEN/NRA/WGOE(2015)1
14
Figure 3 : reactor vessel support
-
NEA/SEN/NRA/WGOE(2015)1
15
3. OBSERVATIONS AND REGULATORY SIGNIFICANCE
These deficiencies could impact the operability of safety
materials during accidental situations, particularly
in case of earthquake or pipe break.
-
NEA/SEN/NRA/WGOE(2015)1
16
-
NEA/SEN/NRA/WGOE(2015)1
17
4. ROOT CAUSES
Initially, no maintenance was supposed to be performed on the
anchor bolts during plants lifetime. Moreover, after tensioning an
anchor, the prestressing force decreases due to the effects related
to
behaviour of the steel and concrete. These effects were
under-estimated during the conception.
Both conception deficiencies (loss of tension in anchor bolts)
and construction/operation deficiencies
(SCC) are responsible for these non-compliances.
-
NEA/SEN/NRA/WGOE(2015)1
18
-
NEA/SEN/NRA/WGOE(2015)1
19
5. REGULATORY ACTIONS AND LICENSEE CORRECTIVE ACTIONS
Since 2003, for each component equipped with anchor bolts, a
specific file has been created in order to
gather information concerning:
- the conception plan and the precise dimension of the anchor
bolt, - the minimum tension required, - the maximum tension allowed
(to prevent plastic deformation) - the last prestressed tension
applied,
Moreover, the loss of tension due to concrete shrinkage and
steel relaxation is calculated in order to
estimate the date of the next prestressing operation. In 2009,
the first results of these investigations
concluded the necessity to perform a tightening of 51,000 anchor
bolts among the 60,000 in total every ten
years.
In 2010, ASN issued a position letter requesting particularly
EDF to forward a preventive periodic
maintenance program and the demonstration of the exhaustiveness
of its strategy. The aim was to ensure
that all anchor bolts were considered.
In 2011, a specific maintenance program has been issued by EDF
in order to carry out the following
periodic checks:
- compliance with the conception design, - no failure of the
anchor, - visual control of concrete (no crack and burst), - visual
control of the anchor to detect corrosion, - sufficiency of
prestressed tension and repair if necessary.
Concerning rupture due to stress corrosion cracking, anchor
bolts have been repaired. Two main methods
are used:
- substituting the damaged anchor by another one protected
against corrosion with a zinc layer, - injecting a wax between the
metallic sheath and the anchor in order to protect the anchor
from
moisture.
ASN ensures that periodic checks and maintenance work are
actually performed in accordance with the
requirements through worksite inspections, checks during the
reactor outages and periodic technical
meetings with EDF.
-
NEA/SEN/NRA/WGOE(2015)1
20
-
NEA/SEN/NRA/WGOE(2015)1
21
6. CONCLUSIONS
Conception conformity should always be checked during plants
lifetime. Such checking should be performed on site (walkdowns) and
should also consist in reviewing the documentation.
ASN considers that actions undertaken by EDF to determine the
applicable baseline requirements for each
component equipped with anchor bolts are indispensable to
identify eventual non-compliances. Moreover,
the preventive maintenance programme provides a specific
framework to carry out examinations and
repairs. However, the non-compliances identification method and
the sufficiency of the preventive
maintenance program are currently being evaluated by ASN and its
technical support, IRSN, and a position
letter should be issued in the near future.
-
NEA/SEN/NRA/WGOE(2015)1
22
-
NEA/SEN/NRA/WGOE(2015)1
23
APPENDIX A: ASN PRESENTATION
-
NEA/SEN/NRA/WGOE(2015)1
24
-
NEA/SEN/NRA/WGOE(2015)1
25
-
NEA/SEN/NRA/WGOE(2015)1
26
-
NEA/SEN/NRA/WGOE(2015)1
27
-
NEA/SEN/NRA/WGOE(2015)1
28
-
NEA/SEN/NRA/WGOE(2015)1
29
APPENDIX B: WGOE QUESTIONS AND COUNTRY RESPONSES
WGOE QUESTIONS
Q1 - Are your NPP equipped with pre-stressed anchor bolt?
Q2 - If yes, did the operators in your country face any problem
with these equipments? How did they deal
with it?
Q3 - Do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure (...) integrity?
CANADA
Q1 - are your NPP equipped with pre-stressed anchor bolt?
Pickering NGS Vacuum Building (VB) used similar post-tensioned
rods in the concrete structure to tie the
roof slab to the wall. The anchor rods used in this case were
not through bolts but they were embedded into
the wall of the VB.
Q2 - If yes, did the operators in your country face any problem
with these equipments? How did they deal
with it?
Currently, the operator is developing the plan and the
procedures for the inspection and testing for this type
of post-tensioned rods. Inspection of the pre-stressing system
is part of the periodic inspection program
requirements for containment structures in NPPs in Canada.
Q3 - do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure (...) integrity?
Yes, the effect of degradation of the concrete structure,
including shrinkage and creep, will be expected to
be considered by the operators in the inspection and testing
methods selected, and in the evaluation of the
inspection results for the post-tensioned rods. The periodic
inspection program prepared by the operator is
required to be submitted to the regulator for review and
acceptance.
Contact : James Mok, M. Sc., P. Eng.
Specialist/Spcialiste
Operational Engineering Assessment Division | Division de
l'valuation technique de l'exploitation
Directorate of Assessment and Analysis | Direction de
l'valuation et de l'analyse
Canadian Nuclear Safety Commission | Commission canadienne de
sret nuclaire
Ottawa, Canada K1P 5S9
[email protected]
Telephone | Tlphone 613-996-7338 / Facsimile | Tlcopieur
613-943-1818
Government of Canada | Gouvernement du Canada
-
NEA/SEN/NRA/WGOE(2015)1
30
CZECH REPUBLIC
Q1: No, our NPPs are not equipped with pre-stressed anchor bolts
use at Czech NPPs. We use different
types of anchoring usually bolts fixed in concrete.
Q2: Not applicable.
Q3: Changes in the quality of concrete are taken into account in
the program of in-service periodical
inspections. Delayed strains are considered.
Quality of concrete is assessed mainly for the containment
building at the Temelin NPP and for so called
confinement at Dukovany NPP.
You can find some information on Temelin NPP containment
structure in the IRS report No. 7982.
FINLAND
Olkiluoto 1 and 2
There are no pre-stressed anchor bolts in Olkiluoto 1 and 2
units. Even machine foundations are
anchored by common grouted through bolts.
Olikiluoto 3
In Olkiluoto 3 unit steam generators and main circuit pumps as
well as certain main stream piping
anchorage have been and will be done by pre-stressed bolts.
Design solutions cover total life time
(60+5 years) of the plant by taking into account long period
behaviour of structures and materials.
Such phenomena are ex. relaxation of bolts and creeping of
concrete. Corresponding maintenance
program will be inspected during commissioning inspections after
which STUK is able to give
further information.
Loviisa 1 and 2
Below is a drawing of the Loviisa reactor containment structure
that shows (detail G) how the pre-
stressed anchor bolts are used for fastening the steel
containment into the concrete base plate. The
bolts are re-tightened and inspected via ultra sonic testing
periodically (4years) for
possible deficiences. The outer bolts are demountable and can be
replaced according to the
inspection program. So far (= 33 years of operation) no major
problems has been noticed with the
bolts.
-
NEA/SEN/NRA/WGOE(2015)1
31
Additional information considering Loviisa NPP:
Jouko Turpeinen, Manager, International Programs
Fortum Power and Heat Oy, Loviisa Power Plant
POB 23, 07901 Loviisa, FINLAND
Tel: + 358 10 4554733 (direct) or + 358 50 5446840 (mobile)
Fax: + 358 10 4554435
Email: [email protected]
GERMANY
German NPPS do not have this type of anchors. No associated
events.
INDIA
Q1 - Are your NPP equipped with prestressed anchor bolt ?
In Indian Pressurized Heavy Water Reactor (PHWR) design,
pre-stressed anchor bolts are not in use. For
heavy equipment, like DGs, compressors, transformers etc, cast
in place J bolts or grouted anchor bolts are
used. For lighter equipment like control panels, cabinets etc,
embedded plates are used to weld the
equipment base.
However, the hanger supports for calandria and steam generators
at older generation Rajasthan and Madras
atomic power station units 1&2, are pre-stressed with
external springs. The spring tension and hanger pre-
stressing is checked periodically.
Q2. If yes, did the operators in your country face any problem
with these equipment? How did they deal
with it?
No problems with existing anchors.
Q 3, do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure integrity?
In Indian NPPs, no pre-stressed anchor is used on containment
structure. Reactor
containment structure is provided with specially designed
embedded openings for routing pipes, power
cables and I&C cables etc.
JAPAN
Response to French question regarding pre-stressed anchor bolt
(Japan)
By: Shigeo TAMAO (JNES)
Q1 - are your NPP equiped with pre-stressed anchor bolt?
No.
Q2 -If yes, did the operators in your country face any problem
with these equipment?
How did they deal with it?
NA
Q3 -Do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure (...) integrity?
-
NEA/SEN/NRA/WGOE(2015)1
32
In Japan anchor bolt is not pre-stressed. The only concern of
delayed strain in concrete is the relaxation of
tendon in PCCV. But tendons are applicable to re-stress if
needed.
SPAIN
No associated events.
SLOVAKIA
The nuclear power plants (NPPS) do not have this type of
anchors. No associated events.
SLOVENIA
The answers to the questions of the pre-stressed anchor bolt
are:
1. Answer: NPP Krsko is not equipped with the pre-stressed
anchor bolts.
2. Answer: N/A.
3. Answer: N/A.
SWEDEN
NPPS do not have this type of anchors. No associated events.
SWITZERLAND
Q1 - are your NPP equiped with pre-stressed anchor bolt?
It is not very common but we have some.
Q2 - If yes, did the operators in your country face any problem
with these equipments ? How did they deal
with it ?
No problems, but the corresponding equipment is listed in the
periodic maintenance program. E.g. for pipe
supports a perodic control (readjustement) of the force is
requested. - Problematic is the use of so called
expansible anchors. There is a phenomena that reduces pre-stress
within very short time.
Q3 - do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure (...) integrity?
The mentioned phenomena are known. See also Q2.
UNITED KINGDOM
Response from UK Magnox South's 5 sites
Q1 - are your NPP equiped with pre-stressed anchor bolt?
A1 - Yes, Liebig anchor bolt installations to brackets civil
structures at Dungeness A and Bradwell. They
were installed well after original construction but over 10
years ago. MXS civil personnel also have
experience of these bolts at nuclear power stations now operated
by other licenses which inform us, but not
directly referred to here.
Q2 - If yes, did the operators in your country face any problem
with these equipments? How did they deal
with it?
-
NEA/SEN/NRA/WGOE(2015)1
33
A2 - Installation of Liebig anchors consists of drilling and
under cutting the bolt hole, inserting the bolt
assembly, torquing the bolt and re-torquing it more than 24 hrs
later. There have been very few installation
problems which are revealed before or during bolt torquing.
Appropriate training and management of the
operatives has been sufficient to deal with such matters. The
brackets are subject to routine inspections
which show the bolts remain in good condition, for some bolts
these inspections include torque checks and
these too have been satisfactory for over 10 years.
Q3 - do the operators take into account delayed strains in
concrete to ensure anchor bolt but also reactor
containment structure (...) integrity ?
A3 - Yes, delayed strains in the concrete and in the bolt are
taken account of by re-torquing the bolt after
more than 24 hrs. This is supported by tests that we are aware
of, the manufacturer's recommendations and
our operational experience in A2. The bolts referred to
contribute to reactor building structures but not to
reactor containment structures."
Response from UK Magnox North's Wylfa NPP
Reactors at Wylfa Power Station have Liebig Anchors securing the
Superheater Header Restraints and load
cell readings have been taken of about 30 of them over the last
10 years to check that the anchors retain
95% of their design load. The anchors monitored are M24 and M36
with the majority being M24 with a
design loading of 132kN. A general summary of characteristics of
these anchors, from a quick review of
the graphs plotted from the load cell readings, is that initial
load is lost over the first 2 to 3 months and
after about a year general linear behaviour is established with
losses averaging about 5% of the design
load, with a maximum of say10%, occurring over the following 9
years. If you think the detailed
information from the monitoring would be helpful to yourself or
your French colleagues please would you
request this directly from Wylfa."
I have received additional information below from one of the NII
civil engineering specialists.
The main points have been picked up by the French colleagues i.e
Stress Corrosion Cracking and Creep. I
would also make the following observations in relation to
prestressed anchorages:
1. The maintenance regime should be well documented.
2. The design should allow for checking pre-load and
re-stressing if required.
3. Continuous monitoring may be appropriate (cf rock
anchorages).
4. If practicable the design should allow for inspection of the
anchorages and the tension system (bar, or
strand etc.)
5. Through section systems are best with a positive anchorage at
each end.
6. Blind anchorages where the remote end cannot be inspected
require careful design:
a) Cast in plate give a better bearing generally with less
anchorage creep problems.
b) Drilled holes where the anchorage is formed by mechanical
means or by grouting are more
prone to creep. Hole should be undercut.
COMMITTEE ON NUCLEAR REGULATORY ACTIVITIESFOREWORDTABLE OF
CONTENTS1. INTRODUCTION2. DESCRIPTION OF THE ISSUE3. OBSERVATIONS
AND REGULATORY SIGNIFICANCE4. ROOT CAUSES5. REGULATORY ACTIONS AND
LICENSEE CORRECTIVE ACTIONS6. CONCLUSIONSAPPENDIX A: ASN
PRESENTATIONAPPENDIX B: WGOE Questions and Country ResponsesWGOE
QUESTIONSCANADACZECH
REPUBLICFINLANDGERMANYINDIAJAPANSPAINSLOVAKIASLOVENIASWEDENSWITZERLANDUNITED
KINGDOM