ANALISIS BIAYA PENGGUNAAN ALAT BERAT DENGAN PERBANDINGAN BIAYA DAN WAKTU PEMAKAIAN ALAT BERAT BULLDOZER DAN LOADER DIBANDINGKAN DENGAN BACKHOE LOADER PADA PEMBANGUNAN AREA PARKIR FAKULTAS TEKNIK UNS Direncanakan oleh : 1. Abdul Rohman Hadi I0112001 2. Afrinur Winursito A I0112005 3. Agung Nugroho I0113003 4. Ely Jauharotus I0113040
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
ANALISIS BIAYA PENGGUNAAN ALAT BERAT DENGAN PERBANDINGAN BIAYA DAN WAKTU PEMAKAIAN ALAT
BERAT BULLDOZER DAN LOADER DIBANDINGKAN DENGAN BACKHOE LOADER PADA PEMBANGUNAN AREA
PARKIR FAKULTAS TEKNIK UNS
Direncanakan oleh :1. Abdul Rohman Hadi I01120012. Afrinur Winursito A I01120053. Agung Nugroho I01130034. Ely Jauharotus I0113040
A. Lokasi Penelitian
• Pembangunan Area parkir terletak di Fakultas Teknik Universitas Sebelas Maret Surakarta. Luas lahan yang akan dibangun ± 748,51 m2, lokasi tersebut berada di daerah landai dengan keadaan tanahnya terdiri dari tanah asli(Tanah biasa).
Site Luas 1 = 20 x 25
= 500 m2
Luas 2 = 18 x 6= 108 m2
Luas 3 = 0,5 x 7 x 6= 21 m2
Luas Total= L1 + L2 + L3= 500 + 108 + 21= 629 m2
Volume Pekerjaan Volume Bank = Tinggi x Luas
= 1,6 x 629= 1006,4 m3
Volume Striping = Tinggi Striping x Luas= 0,2 x 629= 125,8 m3
Volume Galian = VBank –Striping= 1006,4 x 125,8= 880,6 m3
•Volume Loose (LM)
(L) Koefisien loose Tanah = 1,2
Volume Compact (CM)
(C) Koefisien compact tanah = 0,85
V.Padat
Tahapan Proyek• A. Pek. Pembersihan Lahan (stripping)• B. Pek. pemotongan tanah (cutting) • C. Pek. pemuatan (loading) • D. Pemadatan tanah (compacting)
Pekerjaan Galian- Loading
A. Dengan Bulldozer dan Wheel Loader
B. Dengan Backhoe Loader
A.Pekerjaan Stripping dan Cutting• Alat yang digunakan : Bulldozer• Volume Striping =Tinggi Striping x Luas
=0,2 x 629 = 125,8 m3
Volume Galian =VBank –Striping=1006,4 x 125,8 = 880,6 m3
• Bulldozer Komatsu D355A yang dilengkapi dengan alat garu digunakan untuk penggaruan sekaligus untuk penggusuran
• Volume total Striping+ Cutting yaitu : 1006,4 m3• Kondisi kerja :• Jarak gusur = 90 m• Ukuran Bilah = 4,32 m (panjang) x 1,68 m (tinggi)• Faktor Bilah = 0,90• Type tanah = tanah asli (biasa)• Efisiensi kerja = 0,80 (baik)• Efisiensi waktu = 0,83• Kecepatan maju = 4,78 km/jam• Kecepatan mundur = 6,54 km/jam• Waktu ganti persneling = 0,05 menit• Waktu Siklus = + + 0,05 = + + 0,05 = 1,955 menit
=
• Produktivitas Bulldozer Komatsu D355A • Q=
Dimana:Q = Kapasitas produksi m3/jamq = Kapasitas bucket m3E = efisiensi kerjaCm = Waktu siklus
-q = H2x L x k= 1,68 x 4,32 x 0,90= 6,53 m3
-Q = 6,53 x 60 x 0,8x0,8 / 1,955= 128,26 m3 / jam
Produktivitas Alat
WAKTU Stripping : = VOLUME STRIPPING / PRODUKTIVITAS ALAT= 125,8 m3 / 128,26 m3 / jam= 0,98 jam - > 1 jam
JUMLAH ALAT : 1 BUAHJumlah pekerja : 1 Operator , 1 mandor
Pek. pemuatan (loading)
ALAT : Wheel Loader W170 Kapasitas Bucket 3,5 m3
Metode Operasi = pemuatan silangJarak Angkut = 10 mFaktor Bucket = 0,9Kecepatan = F = 0-7 km/jam = 7x 0,8 = 5,6 km/jam = 93,3 m/menit
R = 0-7 km/jam = 7x 0,8 = 5,6 km/jam = 93,3 m/menit Z = 0,3Produksi per siklus (q) = 3,5 m3
Efisiensi= 0,83Cycle Time (T) = + + Z = + + 0,3 = 0,51 menitProduksi per jam =
PRODUKTIVITAS : VOLUME :
WAKTU : = VOLUME LOOSE/ PRODUKTIVITAS ALAT= / 307,6 = 2,86 Jam 3 JAM (Satu hari)
JUMLAH ALAT: 1 BUAHJUMLAH PEKERJA : 1 Operator
BACK
Pekerjaan Stripping ,Cutting, Loading dengan Backhoe Loader• Backhoe Loader
Alat = PC 120-6 KomatsuPerhitungan produksi backhoe per jamVolume total pengerukan : 1006,4m3
• Produksi = X BC X JM X BF m3 / jam• T = t1+t2+t3
Dimana :• Bucket faktor untuk tanah asli = 0,8• Kapasitas bucket = 0,5 m3• JM = 0,81 (baik/sangat baik)• Kondisi sedang (t1) = 10 detik• Swing 450(t2) = 5 detik• Pembuangan (t3) = 3 detik• Waktu tetap = 12 detik
• Dapat diketahui :• T = 10 + (2 x 5) + 3 + 10
= 35 detik atau 0,58 menit• Produksi = X 0,5 X 0,8 X 0,81 m3 / jam
= 33,33 m3/jam
Produktivitas Alat = Volume Galian/ Produksi= 1006,4 m3 / 33,33 m3/jam= 30 , 195 jam / 8 jam = 3, 77 hari
Perhitungan produksi loader per jam• Volume total pemindaan : • Produksi = X BC X JM X BF m3 / jam
Cara pemuatan menggunakan metode v loading dengan rumus :• T= 2
Dimana :• Jarak = 10 meter• JM = 0,81 (baik/sangat baik)• BF = 0,8 (tabel)• Kecepatan maju= 5 km/jam• Kecepatan mundur= 5 km/jam• Cycle time
Catatan : 1 km/jam= 16,667 m/menit• F = 90 x 10 = 900 km/jam = 15000 m/menit• R = 90 x 10 = 900 km/jam = 15000 m/menit• Z = 1,1• T = 2
=1,13 menit• Produksi = X 1,2 X 0,81 X 0,8 m3 / jam
= 41,65 m3 / jam
Produktivitas Alat = Volume / Produksi= 880,6 m3/ 41,65 m3/jam= 21,14 jam / 8 jam = 2,64 hari
Kebutuhan Alat = 1 Alat Tenaga = 1 operator , 1 mandor Total Lama pekerjaan galian dan loading = 3,77+2,64 = 6,41 hari = 7 hari
C. Pek. pemuatan (loading) Dengan Dump Truck
Analisa Dump truck - Nama alat = Dump Truck - Tipe alat = FE 74 HD 125 PS 6 RODA DUMP Tahun 2010 - Kapasitas bak (c) = 6 m3 - Kondisi Alat = Baik sekali - Kondisi Operator = Baik - Efisiensi Kerja = 0.75 (tabel 2.6) - Jarak angkut = 500 m - Cycle Time backhoe = Waktu gali + (waktu putar x 2 ) + waktu buang - Kapasitas bucket backhoe = 0.9 m3 - Kecepatan rata-rata isi = 30 km/jam 1000 = 30000 1 jam = 60 menit = 30000/60 = 500 m/menit - Kecepatan rata-rata kosong = 50 km/jam = 50 x 1000 = 50000 = 1 jam = 60 menit = 50000/60
= 3,95 -> 4 unit/ hariLama Waktu PekerjaanProduksi per unit = 33,47 m3/jamJumlah Dumptruck = 4 unit dgn waktu operasi 8 jamProduksi 4 unit = 4 x 33,47 m3/jam = 133,88 m3/jamProduksi Per Hari = 8 jam x 133,88 = 1071, 04 m3/hariVolume Timbunan = 1056,71
= 1056,71 / 1071,04 = 0,98 hari ~ 1 hari
No Uraian Kode Koef Satuan
I. DUMP TRUCK
1 Jam kerja efektif per hari Tk 8 Jam
2 Kapasitas Bak V 6 M3
3 Faktor Efisiensi Alat Fa 0,81 -
4 Kecepatan Isi V1 500 m/menit
5 Kecepatan Kosong V2 833,333 m/Menit
6 Jarak Angkut- Waktu Pengangkutan (D/V1)-Waktu Kembali (D/V2)-Waktu Pemuatan (V/0,9)XfaX (34/60-Waktu Menumpah-Waktu Menunggu
Daya/Tenaga Alat : 198 HPLebar Efektif Pemadatan (W) : 1,5 meterDiameter Drum Penggilas (B) : 1,219 meterBerat Operasional : 6.670 kgBerat Drum Penggilas : 3.251 kgEffesiensi Kerja (E) : 0,8 (Baik)Jam Kerja/Hari : 8 jamJenis Tanah : Tanah biasaKecepatan Operasional Alat : 2 km/jamJumlah Lintasan (N) : 8Tebal Pemadatan (T) : 0,25 cm
Perhitungan Produksi CompactorProduksi Per Jam (Q)P = (V x 1000) x B x T x E
N = (2 x 1000) x 1,219 x 0,25 x 0,8
8= 60,95 m2/jam
Produksi Per HariP = 60,95 x 8 jam = 487,6 m2/hari Jumlah Alat yg DibutuhkanV = Volume Tanah Padat
Produksi/hari x Lama waktuV = 748,51
487,6 x 1V = 1,53 ~ 2 unit
Lama Waktu PekerjaanProduksi per unit = 60,95 m3/jamJumlah Compactor = 1 unit dgn waktu operasi 6 jamProduksi unit = 1 x 60,95 m3/jam = 60,95 m3/jamProduksi Per Hari = 6 x 60,95 = 365,7 m3/hariVolume Pemadatan = 748,51 m3
= 748,51365,7= 2,04 hari ~ 2 hari
BIAYA PELAKSANAAN
No Pekerjaan Jenis Alat Volume (m3)
Lama Kerja (jam)
Biaya (Rp/jam)
Total Biaya (Rp)
1 Galian Backhoe Loader PC 120-6 1006,4 30,195 115.000 3.472.4252 Loading Backhoe Loader PC 120-6 880,6 25,37 115.000 2.917.550 =6.389.975
Penutupa. Kesimpulan Dari analisa perbandingan perhitungan waktu dan biaya pelaksanaan pada pembangunan area parkir FT UNS menggunakan peralatan berat kombinasi antara bulldozer dengan wheel loader dan backhoe loader maka dapat diambil kesimpulan sebagai berikut: 1. Berdasarkan perbandingan waktu pelaksanaan pekerjaan, maka waktu yang diperlukan oleh kombinasi wheel loader dengan bulldozer dibantu oleh dump truck sebesar 34,86 jam sedangkan waktu untuk backhoe loader dibantu dengan alat bantu dump truck sebesar 79,725 jam. Maka waktu tercepat dengan menggunakan kombinasi antara wheel loaderr dengan bulldozer dengan selisih waktu 44,865 jam. 2. Berdasarkan perbandingan biaya pelaksanaan pekerjaan, maka biaya yang diperlukan oleh kombinasi wheel loader dengan bulldozer dibantu oleh dump truck sebesar Rp. 16.789.743,82 sedangkan biaya untuk backhoe loader dibantu dengan alat bantu dump truck sebesar Rp-20.149.975 . Maka biaya termurah dengan menggunakan Bulldozer dan Wheel Loader dibantu dengan alat bantu dump truck dengan selisih biaya Rp. 3.360.231,18
VI. Daftar Pustaka1. Ervianto,W.I,2002., Manajemen Proyek Konstruksi, Penerbit Andi Yogyakarta,2. Fatena Rostiyanti, Susy, 2008. Alat Berat Untuk Proyek kontruksi.,Penerbit Rineka Cipta.3. Rochmanhadi. 1990, Pemindahan Tanah Mekanis PTM.PenerbitPekerjaan Umum.4. Rochmanhadi. 1992., Alat-Alat Berat dan Penggunaannya.Penerbit Pekerjaan Umum. 5. Sosrodarsono Suyono, Dr, Ir, 1990, Alat-alat Berat.Penerbit Yayasan Badan Pekerjaan Umum.ISSN : 2302-7312 Vol. 11 No. 1 2013 http://jurnal.sttgarut.ac.id 10