The definition of (project)?
An-Najah National UniversityEngineering FacultyCivil Engineering
DepartmentConstruction project managementSubmitted in partial
fulfillment of construction project management for the bachelor
degree in civil engineeringPrepared by:Omar Daour Abed-Allah
SawalmehMohammad Fuad Mohannad Abu SemriSubmitted to:Dr. Barraq
Jomaa2011The project consists of two parts
Part one : Project Management Principles
Part two: The Applied ProjectPart oneProject Management
PrinciplesThe definition of (project)? A project is a temporary
endeavor undertaken to accomplish a unique product or service with
a defined start and end point and specific objectives that, when
attained, signify completion.
PMBOK
What do we mean by (Project Management)?Project management is
the discipline of planning, organizing, securing and managing
resources to bring about the successful completion of specific
project goals and objectives. It is sometimes conflated with
program management, however technically that is actually a higher
level construction: a group of related and somehow interdependent
engineering projects. Project management is the application of
knowledge, skills, tools, and techniques to project activities in
order to meet or exceed stakeholder needs and expectations from a
project.Project management is the science (and art) of organizing
the components of a project, whether the project is development of
a new product, the launch of a new service, a marketing campaign,
or a wedding. A project isn't something that's part of normal
business operations. It's typically created once, it's temporary,
and it's specific. As one expert notes, "It has a beginning and an
end." A project consumes resources (whether people, cash,
materials, or time), and it has funding limits.Project Management
basicsDefinition Planning Execution Control Closure
The triple constraint
Part Two
The Applied Project
Description of the projectThe project is a school buildingSites
in Sulfeet West BankThe owner is the ministry of education
Palestinian AuthorityThe building consists of three storiesThe area
of the school is 671m2Sequence of worksThe main steps we have
followed in our project is:Work Breakdown Structure (WBS).Quantity
surveying.Bill of quantity (BOQ) preparation; quantities, cost,
resources, and man hours.Activities durations.Project cost.Project
duration.WBSWork breakdown structure is a tool used to define and
group a project's discrete work elements in a way that helps
organize and define the total work scope of the project.WBS of the
project
Quantity surveyingWe have used M.Excel to find the quantities of
each activity due to the WBS, the calculations include (steel,
concrete, frame work,..etc).We have used the symmetry (if there),
to facilitate the calculations.For example there are five different
volumes of footings, we have calculated for one footing of each
type then multiple with its number. Sample calculation
Calculations of concrete volumes and frame work
areas:(Contd)Calculations of steel weighs:
Duration =( Mhr*total quantity) /n. of labors * no of hoursIn
this project : the labor work in crew such as civil crew included 5
workers and work 8 hours in dayExample : The steel for the first
slab = 5.7 ton and Mhr for steel in slab = 25 Duration =( 5.7 * 25
) /(5*8) = 3.56 days This means you need one crew to finish steel
work in slab in 4 days
Activities durations :Project BudgetingEstimation cost of the
material , labor and non labor, for each activity , it was collect
tha data from contractors .
And here some excel calculationCalculate the cost of resources
(Labor/Material/ equipment)
labor
Resources and costPrimavera analysisThe primavera used to :
Scheduling Project network Project budgeting Project duration
and CBM analysis Resources leveling
Result from excelResult from primavera768900.8768900.64The
result excel and primavera are the same
conclusionThe quantity surveying for each activity most be
calculated according to work breakdown structur,and then the cost
for activity must be determined to calculate total cost and total
duration on the project.
The management principle must be used to determine the early
start, early finish, free float, total float for each activity.
ContdThe scheduled project duration is 187 work days 38 % of
activities are critical . The price per meter square as total is
approximately 1383.1 NISThe project indirect cost estimated to be
10 % of cost .The profit of the project is 10 % of the total cost (
direct & indirect )
Thank you for your attention