8/6/2019 Amended Reply to SOC - 100511
1/72
BEFORE THE ARBITRAL TRIBUNAL OF
Shri K.K. Verma Presiding Arbitrator
Shri. V.D. Gautam Arbitrator
Shri. S.K. Jain Arbitrator
In the matter of Arbitration between:
M/s. MBL Infrastructures Limited : Claimant/Contractor
And
National Highways Authority of India : Employer/Respondent
In the matter of Arbitration under the provisions of Arbitration andConciliations Act 1996 in Short Term Improvement and RoutineMaintenance work for Chilakaluripet to Vijayawada (Km. 355.00 to Km.
434.150) and Vijaywada to Eluru (Km.3.400 to Km. 81.600) Section of NH-5
INDEX
S.No. DESCRIPTION PAGE No.
1 Statement of Defence of the Respondentincorporating amendments to the replies inrespect of Claim Nos. A-1, A-5, A-6, A-7 & A-8
1-
Filed by: EMPLOYER/RESPONDENT
Through
M. V. KINI & CO.Advocates & Solicitors
KINI HOUSE6/39, JANGUPRA B
NEW DELHI 110 014
Dated:
- 1 -
8/6/2019 Amended Reply to SOC - 100511
2/72
BEFORE THE ARBITRAL TRIBUNAL OF
1. Shri K.K. Varma, : Presiding ArbitratorAdditional Director General,(CPWD),Retd. EA-290, DDA-SFS FlatsMaya Enclave, New Delhi-110064
2. Shri. V.D. Gautam : ArbitratorIDSE, Retd.B-44, Jalvayu Vihar, Pocket 4,Plot # 8, Greater Noida 201308
3. Shri. S.K. Jain : ArbitratorJain-Lok, Kothi Gate,Hapur- 245101
IN THE MATTER OF ARBITRATION BETWEEN:-
M/s. MBL Infrastructures Limited
23A, N.S. Road,3rd Floor, Room No.14,Kolkata Claimant
AND
NATIONAL HIGHWAYS AUTHORITY OF INDIA,G-5 & G-6, Sector 10,Dwarka,New Delhi. Respondent
(ARISING OUT OF AGREEMENT DATED 24TH AUGUST, 2006)
In the matter of Arbitration under the provisions of Arbitration and
Conciliation Act, 1996 in Short Term Improvement and Routine
Maintenance work for Chilakaluripet to Vijayawada (Km. 355.00 to
Km. 434.150) and Vijayawada to Eluru (Km.3.400 to Km. 81.600)
Section of NH-5
- 2 -
8/6/2019 Amended Reply to SOC - 100511
3/72
STATEMENT OF DEFENCE OF THE RESPONDENT INCORPORATINGAMENDMENTS TO THE REPLIES IN RESPECT OF CLAIM NOS. A-1, A-5, A-6, A-7 & A-8
MOST RESPECTFULLY SHOWETH:
1. That the contents of the SOC to the extent not specifically adverted
to and replied herein shall be deemed to have been traversed in
extenso and denied by the Respondent save and except those
which are specifically admitted hereinafter.
2. That wherever applicable, the Respondent has placed copies of
correspondence/documents as annexure to the reply and reserves
its right to rely on the same and further reserves the right to file
such other correspondence/documents as may be deemed
appropriate and to make detailed submissions at an appropriate
time.
3. That the Respondent reserves its right to add, to vary, modify or
otherwise elaborate its reply, averments, contentions and
submissions and to submit further documents as may be required.
Further, the Respondent hereby reserves its right to lead oral as
well as documentary evidence as may be required in support of its
contentions.
OBJECTIONS ON THE MAINTAINABILITY & ARBITRABILITY
That the Claimant has sought to make certain alleged claims
before this Ld. Tribunal, which are either beyond the terms of the
Contract or are clearly barred by the terms of the Contract and therefore
are not maintainable or arbitrable, the details whereof are as under:
- 3 -
8/6/2019 Amended Reply to SOC - 100511
4/72
i) Claim No. A-1 Rs. 33,74,980/- towards loss on account of delay in
issue of letter to proceed (initial expenditure between 19.05.2006
to 29.08.2006).
ii) Claim No. A-5 Rs. 18,17,803/- towards losses on account of price
rise due to delays.
iii) Claim No. A-6 Rs. 5,94,88,788/- towards loss due to prolongation
of Contract period (Claim due to overheads and establishments).
iv) Claim No. A-7 Rs. 2,07,15,978/- towards loss of profit due to
reduction on account of Contract which could not be executed.
v) Claim No. A-8 Rs, 1,00,00,000/- towards loss of Goodwill,
Reputation, mental harassment etc..
The aforesaid claims are clearly de hors the Contract and for the samereason not maintainable or arbitrable before this Ld. Tribunal. This
objection may kindly be treated to have been raised u/s 16 (2) of the
Arbitration and Conciliation Act, 1996.
PRELIMINARY OBJECTIONS:
1. That the present Contract was entered into between the Claimant
and the Respondent for the purposes of short term improvement
and routine maintenance of NH-5 from Chilakaluripet to
Vijayawada and Vijayawada to Eluru. As per the terms of the
agreement, the Claimant was required to execute the work as
mentioned in the Scope of Works. According to Clause 27.1, the
Engineer shall issue the Indents of the works in stages and the
- 4 -
8/6/2019 Amended Reply to SOC - 100511
5/72
Claimant shall submit the program to the Engineer for its approval.
The language of the Clause 27.1 is reproduced herein below;
The Engineer shall issue the Indent of work instages specifying the time limit for the same asand when required. The Contractor shall submit tothe Engineer for approval a programme showingthe general methods, arrangements, order, andtiming for all the activities in the works, along withmonthly cash flow forecasts.
Thus from the above it will be clear that the Claimant was toexecute the works in accordance with the Indents issued to him by
the Engineer from time to time within the time prescribed for
completing the Indent. After execution of the Contract dated
24.08.2006, the Letter to proceed with the work was issued by the
Respondent to the Claimant on 29.08.2006. It is relevant to submit
that in accordance with Clause 27.1 of Part-I of GCC read with the
Implementation Manual and Maintenance Intervention Levels
(Section-6), it is clearly laid down under clause 6.3.1 that the
maintenance programme planning shall be in two stages, and it is
the primary responsibility of the Contractor to submit the first stage
program within 28 days of issuance of the letter of commencement
by the Employer. In spite of the said requirement under the
Contract, the Claimant failed to give any programme to the
Respondent within the stipulated period of 28 days.
2. On 11.09.2006 the Engineer, after the joint inspection and in
consultation of the Claimant issued the First Indent to the
Claimant, a copy of which has been furnished by the Claimant as
Document C-14 at pg.72 of the Statement of Claim. On
09.10.2006, a review meeting was held, which was represented by
- 5 -
8/6/2019 Amended Reply to SOC - 100511
6/72
the representatives of both the parties wherein it was pointed out
to the Claimant that the scientific laboratory to carry out various
tests had still not been established by the Claimant even though
under Clause 53(i) read with Clause 15 (a) of the Contract, the
Claimant was bound to establish a fully equipped laboratory within
a period of thirty days. Thereafter, again in a Review meeting on
09.11.2006, it was pointed out that the Claimant had again failed to
establish the laboratory. In the said meeting it was brought to the
notice of the Claimant the poor rate of execution of the work, in as
much as the Claimant had achieved only 5% against the required
67%. Copies of the minutes of the review meetings dated
09.10.2006 and 09.11.2006 are annexed hereto and marked as
Exhibit- R-1 & R-2, which will show that the Claimant initiated the
breach of the Contract right from its inception.
3. That as a matter of fact the Claimant had failed to provide even the
vehicles for routine maintenance and site management till as late
as 18.09.2006 Exhibit R-33. The claim of the Claimant that they
had mobilized the heavy machinery and other staff and labour for
commencement right from the beginning of June 2006 is totally
bereft of any truth in as much as the Claimant has miserably failed
to place any document in support thereof. Contrary to this, the
Claimant on his own admission had taken on lease an area of land
measuring 3.84 acres only on 19.01.2007 whereas the work under
the Contract had commenced on 12.09.2006 and the Contract
period was to end on 11.09.2007. The copy of Claimants letter dt.
05.02.2007 is appended hereto and marked as Exhibit R-41. As
per conditions of the Agreement, after signing of the same,
Claimant has to mobilize required machinery. As it transpired, the
- 6 -
8/6/2019 Amended Reply to SOC - 100511
7/72
Claimant failed to do so in spite of a number of notices by the
Engineer. Copies of some of the MOMs and notices are appended
hereto and marked as Exhibit -R-1 to R-6 as well as R-34 & R-35.
4. That as already submitted no equipment/machinery whatsoever
was available at site even after signing of the Contract to attend
even ordinary / routine maintenance. The failure of the Claimant in
this regard and on various other issues was brought to the
Claimants notice by the Consultant from time to time through his
letters dated 07.11.2006, 16.11.2006, 04.12.2006 and 18.12.2006,
copies whereof are appended hereto and marked as Exhibit R
-36 to R- 39.
5. That That on 22.11.2006 the Engineer placed the Second Indent
on the Claimant. It is pertinent to submit that the Claimant, in gross
violation of the requirement under Clause 6.7.3 of the Contract,
failed to install the Hot Mix plant despite notice in this behalf during
the review meeting on 14.10.2006, a copy of whose minutes is
appended hereto as Exhibit R-3. The Engineer again in letter
dated 8.11.2006 to the Claimant emphasized the need and the
urgent requirement of the Hot Mix plant at the site. A copy of the
letter dt. 08.11.2006 is annexed hereto and marked as Exhibit R-
4. Thereafter, again during the review meetings held on.
29.11.2006 and 09.12.2006, the Respondent expressed concern
over the non execution of the balance work in the First Indent. A
bare perusal of the minutes of said meeting would reveal that the
Claimant was unable even to start the work in terms of the
provisions of the agreement. Copies of the minutes of the review
meetings dt. 29.11.2006 and 09.12.2006 are annexed hereto andmarked as Exhibit- R-5 & R-6.
- 7 -
8/6/2019 Amended Reply to SOC - 100511
8/72
6. That it is submitted that the Claimant had continued with his
lackadaisical approach in executing the work and submitted only a
draft of the work program, that too belatedly after a delay of 70
days on 22.11.2006. Since the work program was only in the form
of draft, the Engineer made certain remarks vide letter dated 4th
December, 2006 annexed hereto as Exhibit R-7 and gave a
further reminder on 20th December, 2006, annexed hereto as
Exhibit R-8 regarding yearly maintenance program. Thereafter,
the Claimant resubmitted a back-dated work program on
11.12.2006 and the same was received by the Engineer only on
30th December, 2006 (at the end of the first quarter). The Engineer
in his letter dt. 06.01.2007 (Document C-34 of the Statement Of
Claim), pointed out to the Claimant his non- compliance of
submission of Work Programme to the Engineer for approval as
per the Contract. In the said letter, the Engineer further pointed out
to the Claimant about his non-compliance with the requirement of
Work Manual under Clause 6.3.1(b)-(iii) under section 6 of the
Contract, which is extracted herein below;
A comprehensive documentation shall be prepared
separately by Engineer and Contractor mentioning their
assessment of various types of defects in each km of road.
As per the above clause, the Claimant is required to prepare a
comprehensive document mentioning the assessment of various
types of defects in each KM of road, which was again not complied
with by the Claimant.
- 8 -
8/6/2019 Amended Reply to SOC - 100511
9/72
7. That right from the date of commencement of work, the Claimant
exhibited lethargy in executing the work, despite repeated notices
and reminders of the Engineer/ Respondent on numerous
occasions. Respondent vide its letter dt. 04.12.2006 (Document C-
36 in the Statement Of Claim) requested the Claimant to expedite
the work mentioned therein. Again vide letter dt. 18.12.2006
(Exhibit R-9) the Respondent pointed out to the Claimant that
despite repeated reminders through various letters and
discussions in the monthly review meetings, the Claimant had
failed to even complete the balance work under Indent No. 1 and
the value of the works executed by the Claimant was a dismal
9.79% against the required 87.91% as per the approved Work
Indent No. I/2006. In the said letter, the Respondent also listed the
failures of the Claimant in brief in executing various works. The
Respondent also sought the explanation from the Claimant as to
why LD should not be levied.
8. That though the Claimant sought to furnish reasons for their
various failures in a letter dt. 22.12.2006, the same were absolutely
imaginary and unconvincing lame excuses. The delay and
dithering in the execution of the work led to numerous complaints
from the Public regarding the deteriorating condition of the road
owing to lack of maintenance and repairs. The Respondent
through its letters from time to time had consistently apprised the
Claimant regarding the complaints and emphasized the need for
speed and expedition in the execution of the Work in a timely
manner. However, the said requests and entreaties fell on deaf
ears in as much as there was no discernible improvement in the
work performance of the Claimant. Copies of some of the
- 9 -
8/6/2019 Amended Reply to SOC - 100511
10/72
complaints received from the Public are annexed hereto and
marked as Exhibit R-10.
9. The gross negligence on the part of the Claimant will be eloquent
from the fact that the lawn in a traffic island around the Rotary at
Km. 3.460 on Visakhapatnam side caught fire in the month of
January 2007 despite the responsibility of the Claimant under the
Contract to conserve all trees, shrubs and similar plantation within
the right of the way as per provisions of clause 4.2.1. As if this was
not enough, the Claimant even failed to redevelop the lawn till
19.04.2007, which fact was brought to the notice of the Claimant in
a review meeting held on 19.04.2007. A copy of the minutes of the
review meeting dt. 19.04.2007 is annexed hereto and marked as
Exhibit R-11. The said incident of fire is a pointer to the gross
neglect on the part of the Claimant in watering, manuring, trimming
of the said area as per Contract in as much as the dry plantation
became susceptible to fire. The callous attitude of the Claimant
would be evident from the fact that instead of taking remedial steps
as requested by the Respondent time and again through number
of letters and reminders, the Claimant sought to disown their
responsibility and resort to Arbitration proceedings.
10. In the review meeting held on 09.01.2007 Exhibit R-12 the
Respondent informed the Claimant about non-compliance of
various provisions of the Contract Viz., deployment of qualified
nursing staff, deployment of Ambulances, removal of hoardings,
submission of Monthly progress reports etc. Not only did the
Claimant fail to comply with the provisions of the Contract, but also
miserably failed to fulfill the undertakings given by them in the
- 10 -
8/6/2019 Amended Reply to SOC - 100511
11/72
review meetings from time to time such as establishment of
laboratory, providing of mobile maintenance unit etc.
11. That as per the provisions of the Contract, the Claimant was
required to establish the fully operational laboratory within a period
of 30 days. However, till the date of termination of the Contract, the
Claimant failed to establish the site laboratory. Copies of various
letters on this subject from the Respondent to the Claimant are
annexed hereto and marked as Exhibit -R- 13 & R-14.
12. The Claimant was extremely lackadaisical in its approach in
executing the work. On 08.02.2007 a management meeting was
held in the office of the Project Director. In the said meeting the
Claimant was informed that the overall progress of the work was
only 1.88% against the targeted 35% until 31.01.2007. A bare
perusal of the various Minutes of the review Meetings will reveal
that the Claimant had even failed to complete the First Indent in
spite of the assurance that the same will be completed by
20.03.2007. Apart from the non-completion of the First Indent, the
Claimant did not even commence the work against Indent No.3,
the due date of which was 28.02.2007. A copy of the minutes of
the meeting dated 08.02.2007 is annexed hereto and marked as
Exhibit R-15. Again during the review meeting held on 9.03.2007Exhibit R-16 it was observed by the Respondent that the Claimant
was still to start execution of work under Indent No. 3, the due date
in respect of which had already expired on 28.02.2007.
Furthermore, despite several letters from the Respondent, the
Ambulance services were operated without the qualified staff.
From the above it will be evident that there was overall and
comprehensive failure on the part of the Claimant in executing any
- 11 -
8/6/2019 Amended Reply to SOC - 100511
12/72
work as per the terms of the Contract and the untenable claims
raised in the Statement of Claim are totally false and frivolous.
13. That despite repeated promises to execute the work in terms of the
Contract given during the various review meetings and in response
to the numerous letters from the Respondent, the Claimant
brazenly breached all such promises and undertakings, thus
leaving no options to the Respondent except to levy Liquidated
Damages on the Claimant as per terms of the Contract and
accordingly, by a letter dt.24th May 2007 (Exhibit R-17) the
Respondent conveyed the same to the Claimant. Thereafter, in the
month of June when the monsoon was already active, the
Claimant brought Hot Mix plant and Milling machinery to the site.
Notwithstanding this, the progress of work still remained dismal.
14. That a meeting was held on 29.08.2007 at NHAI Headquarters. In
the said meeting the Claimant proposed non execution of certain
BOQ items in view of a proposal for 6-laninig of the whole stretch
of road between Chilakaluripet to Gundugolanu. The Claimant
further requested the Respondent to reduce the value of the work
under the contract. The Claimant further made a request not to
recover Liquidated Damages in the future bills citing cash-flow
problems and further undertook to furnish an unconditional BankGuarantee in lieu of Liquidated Damages until finalization of
Extension of Time as well as the quantum of Liquidated Damages
to be decided by the Respondent. However, no decisions were
taken in respect of the Claimants proposals in the said meeting
and no promise was held out to the Claimant regarding any
reduction in the value of works or items except the subject of the
bank guarantees to be provided by the Claimant and extension of
- 12 -
8/6/2019 Amended Reply to SOC - 100511
13/72
BGs already provided. A copy of the Minutes of the Meeting dated
29.08.2007, which is self explanatory is appended hereto and
marked as Exhibit R-18.
15. That the Respondents site inspection in the month of September
revealed that the progress of work achieved by the Claimant till
then was a dismal 12.69% vis--vis the requirement of 100% as on
11.09.2007. The Claimant, in a bid to cover up his failures/
lapses unilaterally decided not to execute certain BOQ items on
the excuse that the whole stretch of road between Chilakaluripet to
Gundugolanu was proposed for six laning. It is a matter of record
that no instructions whatsoever were issued by the Respondent or
the Engineer to stop or suspend any work at any point of time.
Having failed to achieve the required progress in the work as
scheduled, the Claimant submitted a revised work programme
through a letter dated 10.09.2007 unilaterally indicating a reduction
in the scope of work under the Contract to Rs.19,60,38,117/-. As
per Clause 36.1 of Contract, the Engineer shall, having regard to
the scope of the Works and the sanctioned estimated cost, have
power to order only after approval from NHAI / as per NHAI
guidelines, in writing, Variations within the scope of the Works he
considers necessary or advisable during the progress of the
works. The above revised work programme, was not approved by
the Headquarters of the Respondent who returned the same with
the remark that the same shall have to be submitted as per Clause
36.1 of Contract as a variation proposal. Hence, the revised work
programme submitted by the Claimant is of no relevance
contractually and the value of the work to be executed under the
Contract remained as Rs.31,44,10,140.65/- only.
- 13 -
8/6/2019 Amended Reply to SOC - 100511
14/72
8/6/2019 Amended Reply to SOC - 100511
15/72
progress, bringing the case squarely within the provisions of
Clause 53.2(h) of the General Condition of Contract, there by
amounting to fundamental breach of Contract under Clause 53.2.
Clauses 53.2 and Clause 53.2(h) are reproduced herein below.
53.2: Fundamental breaches of Contract include,but shall not be limited to, the following:
53.2 (h): If the contractor has not completedatleast 30% of the value of work required to
be completed after half of the completionperiod has elapsed
19. That it is germane to state that the Engineer gave a notice vide
letter dated 07.02.2007 wherein the Engineer had recorded that
the Contractor had failed to perform the Contract as per Clause
No.53.2(h) and 15(c) of Contract Data of General Conditions of
Contract which amounted to fundamental breach of the Contract
as per Clause No.53.2(i) of General Conditions of the Contract and
demanded an explanation to show cause as to why the Contract
cannot be terminated for his default. A copy of the notice dated
07.02.2007 is enclosed as Exhibit-R-54
20. That in view of the fundamental breach of Contract committed by
the Claimant the Respondent was within its rights under the
Contract to terminate the same under Clause 53. In the present
case, the Claimant failed to complete even 30% of the total value
of work even after grant of EOT up to 31.12.2007. Furthermore,
the Claimant completely failed to setup a field laboratory with
prescribed instruments in accordance with Clause 53.1 of the
General Condition of Contract read along with Item 15 (a) of the
Contract Data. In view of the said circumstances, the Respondent
- 15 -
8/6/2019 Amended Reply to SOC - 100511
16/72
8/6/2019 Amended Reply to SOC - 100511
17/72
future interest and the cost of arbitration proceedings and such
relevant costs as may be deemed fit by this Ld. Tribunal.
PARA WISE REPLY ON MERITS
1.4 That the contents of Para 1-4 of the Statement of Claim are
matters of record and need no reply.
5. That the contents of Para 5 of the Statement of Claim, only to the
extent that the Claimant had furnished performance security in theform of bank guarantee within 10 days, are matters of record. It is
pertinent to submit here that the said performance securities
furnished by the Claimant are meant to be kept valid till the end of
the defect liability period and/or till conclusion of any arbitral
proceedings, if applicable as per provisions of clause 25.3 (e) of
the Contract. As it transpired, the Claimant has allowed the said
performance securities given by way of Bank Guarantees to lapse
and has failed and neglected to renew the same beyond the defect
liability period stipulated in the Contract, on account of which the
Respondent has already moved an application u/s 17 of the
Arbitration and Conciliation Act, 1996 before this Ld. Tribunal for
appropriate reliefs as prayed therein.
6. That the contents of Para 6 of the Statement of Claim are disputed
and denied. It is specifically denied that there was any
unreasonable delay in the issue of the letter of acceptance as
contended or at all. The tender conditions under ITB nowhere
stipulate any time limit for issue of letter of acceptance. The
contentions that the road was badly maintained by the Respondent
in the mean time is also totally unsubstantiated and false in as
- 17 -
8/6/2019 Amended Reply to SOC - 100511
18/72
much as the claimant even at the time of taking over the road after
the contract was finalized never recorded anything in writing with
respect to the alleged bad quality of the road which is being raked
up now solely with the intention to make illegal gains. It is pertinent
to submit that the complaints were received by the Respondent
regarding road condition from the road users only after arrival of
the Claimant at site on 03.10.2006. Copies of the documents are
appended hereto and marked as Exhibit R-10.
7. That the contents of Para 7 of the Statement of Claim are matter of
record and needs no reply.
8. That the contents of Para 8 of the Statement of Claim are
irrelevant and immaterial and therefore disputed and denied. The
allegations contained herein are totally unsubstantiated in as much
as the Claimant has not placed on record any document to show
that this issue was ever raised by the Claimant at the relevant point
of time. It is further submitted that signing the formal Contract was
not a mere ritual as contended by the Claimant in as much as
before signing of any such contract, it is customary for the
Respondent to seek the confirmation from the bankers who have
provided the bank guarantees towards performance securities to
ascertain the veracity of the bank guarantees provided by the
contractors. Only after satisfying itself with regard to the
genuineness of such securities, the contract is signed by the
Respondent with the concerned contractors. This step was also
followed in the instant case and only after receipt of such
confirmation from the claimants bankers the present contract was
signed between the parties. The details of other contractsexecuted by the Claimant and referred to are of relevance to
- 18 -
8/6/2019 Amended Reply to SOC - 100511
19/72
establish any standard for the time limit for execution of the
contract reckoned from the date of the letter of acceptance. It may
be added here that the said contracts referred to by the Claimant
were entered into for the purpose of maintenance wherein the
earlier contracts given to other contracts had already expired and
therefore there was urgency and priority for executing the further
contracts immediately after expiry of the earlier contracts. The
stretch under this Contract was all along being maintained by the
Respondent departmentally/ piecemeal contracts and as such
there was no urgency and priority to finalize the instant Contract. It
is also a pertinent to submit that as per terms of the ITB, the bids
invited for the subject work or to be kept valid for a period of 90
days from the date of submission as per Para 15 of the Tender
Conditions and for any further extentions of validity beyond the
said period, the same was solely at the discretion of the bidder and
it is a matter of record that the Claimant willingly extended the
validity of his bid for a period of more than 3 months.
9 & 10 That the contents of Para 9 of the Statement of Claim are
denied and disputed. As a matter of fact the Claimant had failed to
provide even the vehicles for routine maintenance and site
management till as late as 18.09.2006 Exhibit R-33. The claim of
the Claimant that they had mobilized the heavy machinery and
other staff and labour for commencement right from the beginning
of June 2006 is totally bereft of any truth in as much as the
Claimant has miserably failed to place any document in support
thereof. Contrary to this, the Claimant on his own admission had
taken on lease an area of land measuring 3.84 acres only on
19.01.2007 whereas the work under the Contract had commencedon 12.09.2006 and the Contract period was to end on 11.09.2007.
- 19 -
8/6/2019 Amended Reply to SOC - 100511
20/72
The copy of Claimants letter dt. 05.02.2007 is appended hereto
and marked as Exhibit R-41. As per conditions of the Agreement,
after signing of the same, Claimant has to mobilize required
machinery. As it transpired, the Claimant failed to do so in spite of
a number of notices by the Engineer. Copies of some of the
MOMs and notices are appended hereto and marked as Exhibit
-R-1 to R-6 as well as R-34 & R-35.
11-12. That the contents of Para 11&12 of the Statement of Claim are
disputed and denied as false and concocted. It is a matter of
record that the Claimant addressed the letter dated 2006. It is also
a matter of record that the Contract was executed between the
parties on 24.08.2006 and the letter to proceed with a work was
also issued on the same date. With regard to the empty claims of
the Claimant that they had provisioned the machinery and
equipment for executing the work even prior to the date of the
Contract, the same claims are totally divide up any proof
whatsoever regardless of the fact that even if the same were true,
the Claimant can not hold the Respondent responsible for any
action or inaction prior to the date of the Contract. As already
submitted no equipment/machinery whatsoever was available at
site even after signing of the Contract to attend even ordinary /
routine maintenance. The failure of the Claimant in this regard and
on various other issues was brought to the Claimants notice by the
Consultant from time to time through his letters dated 07.11.2006,
16.11.2006, 04.12.2006 and 18.12.2006, copies whereof are
appended hereto and marked as Exhibit R -36 to R- 39.
13. The content of Para 13 of the Statement of Claim only to the extentthey are part of the record are admitted, rest of the contentions
- 20 -
8/6/2019 Amended Reply to SOC - 100511
21/72
which are surmises of the Claimant are disputed and denied. It is
further submitted that the Respondent is not answerable to any
actions taken by the Claimant prior to the execution of the
Contract.
14. With respect to Para 14 of the Statement of Claim it is submitted
that the actual monsoon Seasons in the area of works starts from
June to September and dry season will start from the October. In
as much as the Contract was signed on 28.08.2006, the monsoon
was already coming to an end by that date and the dry season was
to start by October. It is also a matter of record that the first indent
of items to be completed by Claimant related to simple
maintenance of the stretch and had no nexus or connection with a
monsoon and therefore, it is denied that the Claimant could not
commence the works due to the Monsoon season. Moreover the
actual rainfall data as obtained from the Meteorological
Department would substantiate the fact that most of the month of
September 2006 was without rainfall and there was ample scope
for the Claimant to carry out the work. The copy of rainfall data as
obtained from Meteorological Department is annexed as Exhibit
R-40. The Exhibits of Claimant i.e., C10 & C11 are matters of
record and have no nexus or connection with the allegations
contained therein.
15. With respect to Para 15 of the Statement of Claim it is submitted
that as per the agreement entered into between the parties, Clause
27.1 of Part-I of GCC and Section-6 implementation manual and
maintenance intervention levels under clause 6.3.1, the
maintenance program planning shall be in two stages, where it isvery clearly specified and it is the primary responsibility of the
- 21 -
8/6/2019 Amended Reply to SOC - 100511
22/72
Contractor to submit the first stage program within 28 days of
issuance of the letter of commencement by the Respondent.
However, the Claimant admittedly failed to provide any program to
the Respondent, therefore, any plea of the Claimant disputing the
program is mischievous and mala fide.
Further it is submitted that the first indent was finalized by the
Engineer after a joint inspection of the site by the contractor and
consultant. After the joint inspection the Engineer had even
requested the contractor for his comments and suggestions as
substantiated by the copy of the Engineer letter dt. 15.09.2006
appended hereto as Exhibit R-42
16. That the contents of Para 16 of the Statement of Claim are totally
devoid of any substance and hence disputed and denied.
17-18. That with respect to the contents of Paras 17 & 18, the
same are disputed and denied for the reasons that they have no
nexus or connection with the work undertaken by the Claimant
under the Contract. In as much as the actions on the part of the
Respondent referred to in the said paragraphs are concerned, they
were no way connected with the work performance under the
Contract and the Respondent was totally at liberty to take whatever
action with respect under the Contract beyond the Contract period
and for the same reasons the contents thereof deserve to be
dismissed summarily.
19. That the contents of Para 19 of the Statement of Claim are
disputed and denied. Further, it is submitted that the Respondent
has already explained the failure of the Claimant and the othercommissions and omissions on the part of the Claimant in the
- 22 -
8/6/2019 Amended Reply to SOC - 100511
23/72
Preliminary Submissions, which are not repeated here for the sake
of brevity. As it transpired, the Claimant himself submitted the
revised the work programme and requested for deletion of certain
works from the Claimants scope on the plea that the same are not
required due to the proposed 6-lanning of the stretch. The said
request of the Claimant was forwarded by the Engineer to the
Project Director of the Respondent, who in turn had forwarded the
same to NHAI Headquarters, New Delhi for necessary approval as
laid down in the Contract under Clause 36.1 of the Contract. In
furtherance of the said request vide Exhibit R-48, the Claimant
held out an undertaking that he will complete the balance work as
per his revised work programme for a value of Rs.19,43,90,225.2
by 31.12.2007, which was forwarded by the then Project Director
to NHAI Headquarters. As it transpired, the Claimant miserably
failed to execute the work even to the promised reduced value as
undertaken by them. Even otherwise, the said proposal of the
Claimant (referred Exhibit R-48) was rejected by NHAI
headquarters which clearly pointed out that any variations to the
work under the Contract can be considered only after completion
of the work under the Contract as enjoined therein and there was
no scope to accede to the request of the Claimant. As such
request for reduction of the Contract value to Rs. 19,43,90,225.2
did not have the approval of NHAI as enjoined by Clause 36.1
referred to above and the Engineer did not have any authority
whatsoever to approve the same and the Claimants reliance
thereon is contractually invalid.
20. That the contents of Para 20 of the Statement of Claim are
baseless and preposterous and therefore strongly disputed anddenied. It is submitted at the cost of prolixity that the stand of the
- 23 -
8/6/2019 Amended Reply to SOC - 100511
24/72
NHAI headquarters had been consistent right from the beginning
that in the scheme of the Contract and under the circumstances at
that point of time, there was no question of accepting any revised
work programme from the Claimant as sought to be made out by
the Claimant. It was emphasized by the NHAI headquarters that
the Claimant was bound to complete the work under the different
indents and upon completion thereof, make a request to the
Engineer/Respondent for extension of time, which may be granted
with or without levy of Liquidated Damages as the case may be. In
view of the aforesaid consistent stand of the Respondent, there
was no need for submission of any revised work programme by the
Claimant or its approval by the Respondent. Thus the alleged
delay complained of by the Claimant on the part of the Respondent
is without any basis whatsoever. Respondent reserves its rights to
make further detailed submissions at an appropriate time in
rebuttal of the contents of Para 20.
It is further submitted that the Claimants letter dt. ______(Exhibit
C-58) that the work could be completed only to the extent stated
therein itself is an admission on their part to the Claimants
inefficiency to perform the work in accordance with the terms of the
Contract, their bald denials notwithstanding. In as much as the said
failure of the Claimant qualified for termination of the Contract by
the Respondent, the Respondent was constrained to do so vide its
letter dt. 31.12.2007 (Exhibit R-32). The inefficiency of the
Claimant is compounded by the fact that all the activities stated in
the Claimants letter Dt. 22.12.2007 (Exhibit C-58) are very simple
and minor maintenance works which can be done by even a petty
contractor through simple planning. The very fact the Claimant was
- 24 -
8/6/2019 Amended Reply to SOC - 100511
25/72
unable to do so deservedly called for termination of their services
which was done by the Respondent.
21. That the contents of Para 21 of the Statement of Claim are
disputed and denied. As already stated, the failure on the part of
the Claimant to execute the work in accordance of the terms of the
Contract amounted to Fundamental Breach of the terms thereof
and therefore the respondent rightly terminated the Contract on
31.12.2007. As admitted by the Claimant in C-60, the only dispute
which remained to be settled between the Claimant and the
Respondent as on 29.12.2007 was limited to adjustment of
payment for variations in the actual percentage of bitumen in terms
of Clause 507.9 & 509.9 of MORT & H specifications. This
tantamounts to show that the claims as made by the Claimant
under the SOC under reply are false, concocted and imaginary.
The said claims, though are admissible as per terms of the
contract have been kept in abeyance in as much as the Claimant
invoked arbitration even before settlement of the same.
22. That the contents of Para 22 of the statement of claim are admitted
only to the extent they are matters of record and anything which is
not part of the record is disputed and denied. It is a matter of
record that the Claimant failed to submit any inventory of items
executed by them or any as built drawings as mandated by
clause 52.1 of the Contract pursuant to termination of the Contract.
In the absence thereof, the Engineer was constrained to measure
the work and determine the inventory and made recoveries from
the claimants dues accordingly, which are final and binding on the
Claimant. With regard to the contentions of the Claimant that thetermination notice dated 31.12.2007 is illegal, null and void, it is
- 25 -
8/6/2019 Amended Reply to SOC - 100511
26/72
submitted that under Clause 53 which has been quoted by the
Claimant, the Employer is within his rights to terminate the
Contract if the Contractor causes a Fundamental Breach of the
Contract. The contents of notice dated 11.12.2007 (Exhibit R-55)
from the Engineer to the Claimant is explicit enough to forewarn
the Claimant that if the Claimant claimed to complete the work by
31.12.2007, the same will invite the consequences under Clause
53 of the Contract, which dealt with the conditions under which the
Contract can be terminated. Not only the Claimant failed to
complete the work as stipulated but also failed to take any
cognizance of the said warning and even failed to address the said
subject in any of his letters subsequent thereto. The termination of
the Contract was accordingly resorted to by the Respondent and it
is also a matter of record that the Claimant did not seek to
challenge the said action before the Engineer at any point of time
thereafter. The failure of the Claimant to raise any dispute in
respect thereof shall tantamount to a waiver and the Claimant is
estopped from raising any incostinent dispute pertaining thereto
before this Ld. Tribunal.
23-25. That the contents of Para 23-25 of the statement of claim
save and except those which are already matters of record are
disputed and denied. The Engineers notice dated 11.12.2007
(Exhibit R-55) was itself a prior warning to the Claimant of the
impending termination. The Claimant was also given an
opportunity by the said notice to improve his performance, which
he failed to do. The Contract does not make any stipulations as to
the timing of the termination and therefore the Contractors
contention to the contrary are de hors the Contract and
inadmissible. As already stated if the Claimant wanted to challenge
- 26 -
8/6/2019 Amended Reply to SOC - 100511
27/72
the said termination, the Claimant had all the opportunities to raise
the said objections before the Engineer soon after the termination
which the Claimant failed to do. It is the scheme of the Contract
under Clause 53 that the Contract can be terminated for
Fundamental Breaches on the part of the Claimant, which subject
matter, by virtue of the language of the said Clause is entirely
within the domain of the Engineer and it is a matter of record that
the Claimant did not care to raise any dispute in respect thereof
before the Engineer at the relevant point of time. In as much as a
dispute, duly raised under the Contract is amenable for arbitration
under the terms of Clause 25.3 of the Contract, the present alleged
dispute sought to be raised by the Claimant is clearly not
maintainable. As already stated the said failure to raise a dispute in
respect thereof amounts to a waiver and the Claimant is estopped
from raising any dispute with respect thereto. It is a matter of
record that by a letter dated 03.03.2008 (Exhibit C-67) after a
lapse of 2 months, the Claimant elected to call the said termination
in question address to the Project Director of the Respondent
whereas in accordance with the Contract, it ought to have been
addressed to the Engineer. The said letter even otherwise can not
be taken cognizance of in as much as the same was not signed by
an authorized signatory as enjoined by the Contract.
26. That the contents of Para 26 of the Statement of Claim are
disputed and denied. After termination of the Contract, the
Claimant submitted the bill on 13.02.2008 to Engineer and the
Engineer, in turn submitted the same to Respondent on
29.02.2008 Exhibit R-51. However, even while the said bill was
under scrutiny, the Claimant initiated proceedings under section 9of the arbitration and Conciliation Act, 1996 before the Honble
- 27 -
8/6/2019 Amended Reply to SOC - 100511
28/72
High court of Calcutta and despite the orders for maintaining status
quo given by the Honble Court, illegally allowed the Bank
Guarantees provided by way of Performance Security to lapse. In
view of the said directions of the court to maintain status Quo, the
said bills of the Claimant were not processed. It is a matter of
record that subsequent thereto, the present Ld. Tribunal was also
constituted on 06.06.2008 pursuant to invocation of arbitration by
the Claimant. In view thereof, the allegations of the Claimant to the
effect that the Respondent has acted unfairly, unreasonably and
illegally do not hold water.
27. In view of the above explained facts, the claims raised by the
Claimant are not eligible and reasons are placed also in further
paras.
Claim No.A-1 :
Claim No. Description Amountclaimed
(Rs.)
Claim No.A-1
a) Loss on account of delay in issue ofletter to proceed (Initial expenditurebetween 19.05.2006 to 29.08.2006)
2650158.00
b) Additional Bank Guarantee Charge
due to delay
460847.00
c) Differential interest on Margin Moneyof BG
263975.00
Total 3374980.00
1. That the averments of the Claimant, being in a narrative form, are
not capable of any para-wise replies. It is therefore submitted that
the contents whereof, save and except those which are already
- 28 -
8/6/2019 Amended Reply to SOC - 100511
29/72
matters of record, may be deemed to have been traversed in
extenso and rebutted by the Respondent.
2. That the above alleged claim, by the Claimants own showing,
pertains to certain alleged losses purported to have been incurred
by the Claimant during a period prior to the execution of the
Contract. In as much as the Contract was executed on 24.08.2006,
any claim which is prior to the said date is de hors the Contract
and for the same reason is not maintainable before this Ld.
Tribunal.
3. That the present untenable claim has been built-up purportedly on
account of costs and expenses incurred on account of (i) idle plant
& machinery, (ii) idle manpower, (iii) extra charges for bank
guarantees due to delay and (iv) extra differential interest on
margin money for issuance of bank guarantees, totally devoid of
any contemporary documents in support thereof and is entirely
based on the Claimants bald claim that in expectation of the Letter
to Proceed, beginning from June 2006, the Claimant had mobilized
all the plant, machinery and manpower at the site and owing to the
delay on the part of the Respondent to issue the Letter to Proceed,
they had to be demobilized and redeployed at considerable costs
and expenses, which are being claimed.
4. That the very fact that such a claim has been set up totally in the
absence of any contemporary correspondences, log books, way
leaves and permits issued by concerned Govt. authorities for
movement of such heavy machinery, payment receipts etc., in
support thereof, militates against its veracity and credibility of thealleged claim. Since the onus of proving the claim is squarely on
- 29 -
8/6/2019 Amended Reply to SOC - 100511
30/72
the Claimant, the Claimant has failed to discharge the said
onerous obligation.
5. The agreement provisions are as under :
(i) Clause 15.2 In exceptional circumstances, prior to expiry of the
original time limit, the Employer may request that the bidders may
extend the period of validity for a specified additional period. The
request and the bidders responses shall be made in writing or by
cable. A bidder may refuse the request without forfeiting his bid
security. A bidder agreeing to the request will not be required or
permitted to modify his bid, but will be required to extend the
validity of his bid security for a period of the extension and in
compliance with Clause 16 in all respects.
(ii) Clause 31.1 : Notwithstanding Clause 30, the Employer reserves
the right to accept or reject any Bid, and to cancel the bidding
process and reject all bids, at any time prior to the award of
Contract, without thereby incurring any liability to the affected
Bidder or bidders or any obligation to inform the affected Bidder or
bidders of the grounds for the Employers action.
(iii) Unless and until a formal Agreement is prepared and executed this
Bid, together with your written acceptance thereof, shall constitute a
binding contract between us (Item No.4 of P-80 of Agreement).
6. That the partial reliance placed by the Claimant on Clause 32 of
the ITB in general and Sub- Clause 32.2 in particular is misplaced
in as the said provision imposes a further condition for effective
implementation of work under the Contract. To be more explicit,
the said sub- Clause reads as The notification of award will
constitute the formation of the Contract, subject only to the
furnishing of a performance security in accordance with the
provisions of Clause 33. Clause 33 referred in Sub-Clause32.2
enjoins the successful bidder to provide the performance security
within 10 (Ten) days after receipt of the Letter of Acceptance.
Whether the Claimant complied with the said requirement or not
- 30 -
8/6/2019 Amended Reply to SOC - 100511
31/72
will be elucidated by the chronology of events as detailed
hereinafter:
(i) Bid was submitted by Contractor in the name of
Maheshwari Brothers Ltd on 24.12.2005 Refer pages
80 & 81 of Contract.
(ii) Maheshwari Brothers Ltd offered a rebate of 1.7% during
evaluation of bid on 03.05.2006 Refer page 105 of the
Contract.
(iii) Letter of Acceptance was issued by NHAI in the name of
Maheshwari Brothers Ltd on 19.05.2006 Refer page 05
of the Contract.
(iv) Under para-33, sub-para 33.1 of the ITB, the successful
bidder is required to furnish Performance Security within
10 days after receipt of the LOA. Refer page 18, para
33 of ITB.
(v) Performance Security in the form of Bank Guarantee was
provided by the Contractor on 27.05.2006 in the name of
Maheshwari Brothers Ltd and confirmed by the bank by
letter dated 06.06.2006 and received by NHAI on
12.06.2006 Refer page 116 of the Contract.
(vi) As per internal correspondence in NHAI Headquarters
the Competent Authority discussed for the above subject
work and it was decided to keep the file pending till
- 31 -
8/6/2019 Amended Reply to SOC - 100511
32/72
obtaining legal opinion in respect of the work of
Barwadda-Panagarh Section of NH-2 Package-II.
(vii) On the request of the Claimant, the issue, whether in the
light of the change in the name of the bidder i.e.,
Maheshwari Brothers Ltd to MBL Infrastructures Ltd, it
would be appropriate for the Respondent to enter into
Agreement with MBL Infrastructures Ltd was referred for
legal opinion by the Respondent vide letter dated
30.06.2006 Ref Exhibit- R-67.
(viii) Legal Opinion was received from M.V.Kini & Co.,
Advocates, vide letter dated 25.07.2006 Ref Exhibit-R-
68.
(ix) After receival of legal opinion, the file was put up for
signing of the Contract Agreement with M/s. Maheswari
Brothers Ltd., on 26.07.2006 by the concerned Manager
in Headquarters. The same was discussed by the then
Chairman on 31.07.2006, it has been desired by the
Chairman that the file be submitted to his successor. The
new Chairman has discussed and approved to sign the
Contract on 17.08.2006.
(x) By a letter dated 07.08.2006, Contractor formally
informed NHAI regarding the change of name of the
company with relevant documents from the ROC.- Refer
pages 120, 121 & 122 of the Contract.
- 32 -
8/6/2019 Amended Reply to SOC - 100511
33/72
(xi) On 19.08.2006 Bank issued amendment to the BG dated
27.05.2006 in the name of MBL Refer page 112 of the
Contract.
(xii) On 22.08.2006 the Bank confirmed the Amended Bank
Guarantee Refer page 118 of the contract.
(xiii) On 23.08.2006, Contractor wrote in continuation of earlier
letters dated 07.08.2006 and 21.08.2006 enclosing
copies of MOA & AOA of MBL and Maheshwari Brothers
Ltd Refer page 124 of the Contract.
(xiv) Contract was signed on 24.08.2006 Refer page 03 of
Contract.
7. That the Claimants averments about massive mobilization are
hollow and without substance. Contract stipulates mobile
maintenance unit and minimum equipment to be deployed at site-
Refer pages 73 and 74 of the Contract. It is also relevant to refer to
the Claimants admission regarding its inability to mobilize heavy
equipment in Exhibit C-23 at page 116. It is a matter of record that
even the field laboratory, setting up of which was mandatory,
immediately after execution of Contract could not be set up by the
Claimant in time. Even otherwise, the work under the First Indent
did not call for mobilization of manpower, plant & equipment etc. to
the extent claimed by the Claimant. Refer page 68 of the Contract
and the First Indent (Exhibit R-70) placed on the Claimant.
8. That it is therefore submitted that there was no delay on the part ofthe Respondent to sign the Contract once the performance
- 33 -
8/6/2019 Amended Reply to SOC - 100511
34/72
security, in accordance with Clause-33 of the ITB was provided by
the Claimant and the reasons for signing the Contract on
24.08.2006 vis--vis the Letter of Acceptance dated 19.05.2006
was solely attributable to the Claimant. The alleged claim therefore
merits summary dismissal.
Claim No.A-2 (a, b, c & c1) for Rs.4,17,37,012/- :
Description Amount (Rs.)
(a) Work done accepted, certified but notpaid
(i) IPC-8 16307725.00
(ii) IPC-9 15854841.00
(iii) Work done but not certified 4924020.00
(b) Wrongful deductions for alleged non
compliances
3392964.00
(c) Amount deducted for non acceptable
recoveries
1257462.00
Total = 41737012.00
The analysis of the deductions made by the Engineer is correct
and the reasons for the said deductions are as under:
a) BOQ Item No.2.1 Recovered Amount Rs.9,37,832.64/- :
b) BOQ Item No.4.2 Recovered Amount Rs.15,40,794/- :
c) BOQ Item No.4.3 Recovered Amount Rs.9,14,337/- :
Other recoveries amount Rs.12,27,462/-
- 34 -
8/6/2019 Amended Reply to SOC - 100511
35/72
The Engineer had brought to the Claimants Notice to the said
deductions as and when the same was effected from the monthly
statements/IPCs it happens regarding various non-conformance
and recoveries were made accordingly. The recovery towards non-
conformance for BOQ Items 2.1, 4.2 & 4.3 were made as per the
Scope of Work, the documentary proof whereof have been
furnished in Exhibit-R20 to R31. The recovery calculations were
made by the Consultant Engineer is herewith enclosed as
Exhibit:R-64. The total recovery amount shown in the Exhibit:R-
50/A (Amended).
Other recoveries for an amount of Rs.12,27,462/- was
recommended by the Consultant to Respondent towards various
non-conformance of BOQ items as under.
Non lettering of distance measuring stone of BOQ item 2.2,
recovery towards surface unevenness of BC was made as
per section 6 of Agreement implementation manual and
maintenance intervention level Clause No.6.8.
Recovery towards casualties of median plantation done as
per the survey report, median plantation, survey report on
termination of the contract was prepared and submitted tothis office is herewith enclosed and based on that the
recovery was made and it is correct.
Recovery towards photographs and video graph has been
made as per the agreement conditions.
- 35 -
8/6/2019 Amended Reply to SOC - 100511
36/72
Recovery towards non-carrying out roughness measurement
has been made as per Standard Specification of
MOST/IRC/IS Specification, the Contractor has to conduct
roughness index for the work done. There is no rule that BT
has continuous stretch for conducting the roughness index,
hence it can be done even for 100m also therefore
Claimants argument is herewith denied and recovery made
by the Consultant is correct.
Claim No.A-2(c-1) :
ClaimNo.
Description Amountclaimed (Rs.)
ClaimNo.A-2(c1)
Liquidated damages accounted intotal payment due
3,14,41,014.00
The deduction of Liquidated Damages as well as deduction of 20%
from balance work to be executed as per Clause 54 of the
Agreement were resorted to by the Respondent strictly in
accordance with the provisions of the Contract. The Respondent
reserves its right to make detail submissions in support of the
same at an appropriate time.
PARA-WISE REPLIES ON MERITS:
1-2. That the contents of Paras are disputed and denied.
3. The contents of the Para 3 are disputed and denied. That as per
Clause 27.1 Part-I of GCC read along with Clause No. 6.3.1 of
Section 6 of the Contract, the contractor and the consultant within
- 36 -
8/6/2019 Amended Reply to SOC - 100511
37/72
a period 28 days from the date of issuance of letter of
commencement by the employer shall firstly, identify the activities
of routine maintenance. It is clearly mentioned that the inspection
was made on 7th & 8th September 2006 by the consultant and
contractor for finalization of the works which were undertaken
under 1st quarter only.
In view of the non submission of work programme by the Claimant,
the Engineer was constrained to finalize and issue the indents
even in the absence of the required details in the interest of work.
It is a matter of record that the Claimant eventually submitted the
work programme on 22.11.2006 i.e., after lapse of 70 days from
the date of commencement of work whereas in accordance with
Clause No. 27.1 of Para-I of GCC the same was required to be
submitted within 28 days from the date of commencement of work.
It is submitted that the Claimant was to execute the work during
the currency of the contract period which was 12 months. The work
was programmed and indents were finalized keeping in mind, the
monsoon season which will affect the work in the months of June,
July and August. Therefore, the dry spell is available from
September, 2006 to May, 2007. Based on the above, the Engineer
finalized the work program and issued the indents to the Claimant
for execution.
4-5. It is submitted the in the minutes off the meeting held on
08.09.2006 (A copy of the same is marked as Document C/12) it is
expressly mentioned that Having identified the works to be taken
up on priority in the Ist quarter, detailed discussions were held bythe Team Leader with the contractor on the work indent to be
- 37 -
8/6/2019 Amended Reply to SOC - 100511
38/72
finalized. The views of the contractor were taken into consideration
.The contractor was explained in detail about the items of works to
be executed during the Ist quarter and to ensure the safety of
traffic and to avoid inconvenience to the road users. Finally the
draft work indent was prepared and presented to the contractor
duly requesting the contractor to once again go through it and to
offer their comments any. Also the contractor was requested to
submit the methodology / method statement for the items finalized
now and to quantify the items of work.
Thus from the above it will be clear that the Ist Indent was
finalized only after detailed discussions with the contractor, infact,
the Engineer had requested the contractor to go through the Indent
again and give its suggestions. The same was accepted and
signed by the both the parties and therefore, there is no question
of any discrepancy in finalization of first indent.
It is submitted that most of the works finalized under indent No.1
for the period of 12.09.2006 to 11.12.2006 for the first quarter (3
months) are general and ordinary works and which required no
need of heavy machinery. Further it is stated that the contractor
has mentioned preparation of yearly maintenance program which
is not correct (refer the claimants document C/12) where it is
clearly mentioned that the inspection was made on 7th & 8th
September 2006 by the consultant and contractor for finalization of
the works which were undertaken under 1st quarter only.
6. The contents of Para 6 are disputed and denied. That as per
Clause 27.1 Part-I of GCC read along with Clause No. 6.3.1 ofSection 6 of the Contract, the contractor and the consultant within
- 38 -
8/6/2019 Amended Reply to SOC - 100511
39/72
8/6/2019 Amended Reply to SOC - 100511
40/72
Document C/16 in the written statement) the Engineer has
informed the Contractor about the absence of their Project
Manager and the Vice President due to which the execution of the
work was severely affected. Therefore, contents of the present
letter are sufficiently evident to prove beyond doubt that the
contractor was lackadaisical in its approach in executing the work.
10. That the contents of the Para 10 are disputed and denied. It is
submitted that the contents of letter dt. 20.12.2006 shows that the
contractor had failed to even complete the balance work of Indent
No.1 for the quarter ending with 11.12.2006. In the said letter the
consultant also recommended penalty on the contractor up to
completion. Therefore, the negligent attitude of the Claimant is
clearly borne out from the letter. It is denied that the Claimant had
brought any machinery at the site for carrying out the works as
contended. As a matter of fact the Claimant had taken the site on
Lease and Submitted the lease documents to the Respondent only
on 05.02.2007 as clearly recorded in Exhibit R-41. Thus the claim
of the Claimant with regard to mobilization of machinery at site is
clearly false and fictitious.
11. That the contents of the Para 11 are disputed and denied. It is
submitted that all the indents can not be issued at the same time in
as much as the same have to fit in the work program and
accordingly issued as and when the work under the earlier indent
is accomplished. However, a forecast of the future indents are
issued to the Claimant for the purposes of the advance planning.
It is pertinent to submit that except for the 1st
indent, the Claimantfailed and neglected to cooperate with the consultant for
- 40 -
8/6/2019 Amended Reply to SOC - 100511
41/72
finalization of further indents. Non cooperation of the Claimant was
also brought to the notice of the Claimant during various
Management meetings. However, the Claimant had deliberately
and intentionally continued with its non cooperation for reasons
best known to them.
12 & 13. That the contents of Para 12 & 13 are disputed and
denied. The Claimant never complied with the requirements of
Clause No. 27.1 of Para-I of GCC, after the first indent even
though the Consultant had initiated, finalized and issued further
indents. The Claimant failed to carry out even simple maintenance
of the reach, on account of which the Respondent received as
many as 70 complaints from the road users during the period of
Claimants services under the Contract, a list whereof is appended
hereto as Exhibit R-10.
Whit regard to the contents of sub paras a, b, c, d & e, it is
submitted that all the indents contain the details of the locations as
well. The contractor did not raise any of these issues at the
relevant point of time. It is further submitted that the details of work
to be performed as stated in C/17 (the items proposed from 1st
December, 2006 to 30th April, 2007) corresponds to the work which
was supposed to be completed by the Claimant under the 2 nd
indent. Even though the Contractor has failed to cooperate with the
Consultants in this regard, the indents were issued from time to
time in accordance with the work programme with proper notice to
the Claimant giving a forecast of future work.
14. That the contents of the Para 14 are to the extent they are matterof record are admitted. Rest of the Para is wrong and denied.
- 41 -
8/6/2019 Amended Reply to SOC - 100511
42/72
15. That the contents of the Para 15 are denied. It is submitted that 2nd
indent commencement date was fixed as 01.12.2006, 3rd indent
commencement date was fixed on 01.12.2006, 4th indent
commencement date was fixed on 20.12.2006. Therefore, all the
indents issued based on the requirement of the site condition and
available time factor. Almost all the above three indents fall in 2nd
quarter. The indents issued on various dates during the
agreement period are annexed as Exhibit R-42 to R-47.
It is submitted that after signing of agreement, the Respondent
gave the letter to proceed with the work without any delay.
Therefore, there is no delay on the part of Respondent. The
Claimant failed to plan and programme the work which was also
brought to their notice during various monthly meetings.
16. That the contents of the Para 16 are false, mischievous and denied
in entirety.
(a) The premises of the Inspection Bungalow are not meant for
establishing the Contractors work site. Hence, same cannot
be allotted.
b) As per the requirement to fulfill the agreement condition, the
Respondent had requested the Claimant to submit required
documents.
c) As per agreement condition, the crane must be 15 ton
capacity, for the same the consultant had requestedclarification.
- 42 -
8/6/2019 Amended Reply to SOC - 100511
43/72
d) The claimant has appointed i) Shri Anju Maheshwari, ii) Shri
Suryanarayana Murthy, iii) Shri Riyazuddin Pasha as
authorized persons by the Directors of its Company. But no
such power of attorney in this regard had been submitted to
Respondent. For the same the Respondent has requested to
submit the authorization duly certified with notary as the
names of above said persons are not included in the
Agreement.
e) As per the applicable Labour laws, the Consultants have
rejected to work on public holiday. If the Claimant wanted to
work on public holiday, they should have obtained
permission from Labour Department. The same was brought
to the Claimants notice. Further, it is stated that preparatory
work was to be carried out for doing specified work i.e., the
kerb painting works to be done after the repairs, are to be
carried out. Due to the said reasons, the RFI was not
approved by the Consultants which is correct as per
agreement conditions. Like wise, some of the RFIs are not
approved on the same lines and reasons were mentioned by
the Consultants there itself. Hence, it seems that the
Contractor is not carrying out the work properly as per
standards.
f) That it is a matter of record that the entire site was handed
over to the Claimant on 28.08.2006, the date from which the
work was to be proceeded with. This issue was never raised
by the Claimant during the period of contract.
- 43 -
8/6/2019 Amended Reply to SOC - 100511
44/72
17. That the contents of the Para 17 are disputed and denied. It is
denied that the Claimant was prevented by the Respondent from
executing the work. The Consultant had brought to the Claimants
notice from time to time their lapses during the management
meetings as well as through correspondence on 7th November,
2006 and 16th November, 2006 as the due date of completion. A
bare perusal of these letters would reveal that the Claimant had
failed to mobilize its machinery in time at site and as a result
thereof could not execute even the indented work in time.
18. That the contents of the Para 18, except those which are matters of
record are disputed and denied. The original date of completion of
work under Indent No.1 was 11 th December 2006 and not 2007.
Further, the Claimant had sought EOT on 02.07.2007 and
02.08.2007, but did not give any cogent reasons for non-
completion of the work within the stipulated period. In view thereof,
the request for EOT could not be finalized by the Respondent.
However on 31st October, 2007 the Claimant represented with
details and requested EOT and the same was granted up to
31.12.2007 on certain conditions as per the meeting held at the
Head Quarters of the Respondent. In the said meeting, the
Claimant had promised to complete the work within the extendedperiod. However, despite the said assurance the Claimant at the
time of request for extension of time dated 13.08.2007 marked as
Exhibit: R-56 and once again failed to execute the work as per the
terms of the Contract.
19 & 20. That the contents of paras 19 & 20, except those which are
matters of record are disputed and denied. it is submitted that dueto the inability of the Claimant to execute the work, a meeting was
- 44 -
8/6/2019 Amended Reply to SOC - 100511
45/72
held at the Respondents Head Quarters wherein the Claimant
requested for reduction in the scope of work in view of the tenure
of the Contract and to exempt certain work on account of the
prospect of 6-laning. Subsequent to the meeting, the Claimant
submitted a revised work programme dt. 10.09.2007 on account of
which the revised value of work was shown by the Claimant as
Rs.19, 60, 38,117/-. However, the said revised work programme
was rejected by the Headquarters of the Respondent and
accordingly the Claimant was requested to submit a detailed
variation proposal. Hence, the reliance of the Claimant on the
impugned revised work programme and revised value of work is
de hors the Contract and have no sanctity whatsoever. The value
of work to be executed under the Contract was
Rs.31,44,10,141.65/- and remained so till the date of termination of
the Contract. The Engineer, vide his letter dt. 31.10.2007 had
informally revised the indents as per the request of the Claimant
without seeking prior approval from the Employer and the reliance
of the Claimant on the said letter of the Engineer is totally
misplaced and inadmissible. A copy of the Contractors letter dt.
10.09.2007 is annexed hereto and marked as Exhibit - R-48.
However, the intended completion date of the work was
31.12.2007 as approved by NHAI pursuant to the request of the
Claimant subject to the Claimant submitting a revised work
programme for completion by that date and levy of Liquidated
Damages by Respondent. However, the Claimant again committed
breach of the condition to complete the works within the revised
date of completion (31.12.2007).
- 45 -
8/6/2019 Amended Reply to SOC - 100511
46/72
21. That the contents of the Para 21 are matter of record and needs no
reply.
22. That the contents of the Para 22 are false, frivolous and hence
denied. The indents 5 & 6 were issued as per site requirements
and the Claimant failed to co-operate with the Consultant for
finalization of the indents and also certain items of works which did
not need any machinery. The Claimant failed to perform even such
activities, The failure and inability of the Claimant were willful and
wanton and the Claimants efforts to foist the blame on the
Respondent are mala fide and misplaced.
23. That the contents of the Para 23 are disputed and denied as false.
The Claimant never challenged the validity of Indent nos. 5 & 6
before the Respondent. Therefore, the Claimant cannot absolve
himself from the liability to execute the work envisaged in Indent
no. 5&6, much less to claim any compensation for the work
executed.
24. That the contents of the Para 24 are disputed and denied. As a
matter of fact the Claimant never submitted any bills in time and if
submitted, they were without the necessary documents.Resultantly, the bills had to be returned to the Claimant several
times due to insufficient information. It is pertinent to state herein
that IPC 8 was submitted by the Claimant at the end of the
extended period and IPC 9 was submitted after the termination of
the Contract. Therefore, the Respondent was unable to release the
bills as the final account has to be settled and also various
recoveries are to be made.
- 46 -
8/6/2019 Amended Reply to SOC - 100511
47/72
25. That the contents of the Para 25 only to the extent they are matters
of record are admitted.
26 & 27. That the contents of the Paras 26 & 27 are disputed and denied.
The liquidated damages were imposed and calculated IPC wise as
per details given in Exhibit R-50 & 50/A (Amended) appended
hereto. However, the recovery of liquidated damages became
impossible due to the minor value of work executed by the
Claimant and the priority for recovery of mobilization advance.
Thus, the Respondent was unable to recover whatever amounts
were shown in the Measurement Books for future recovery. It is a
matter of record that the extension of time was granted on the
specific condition that the LDs would be imposed. It is emphatically
denied that the Respondent prevented the Claimant from
completing the work under the indents. In fact the Claimants did
not need anybody to prevent them from completing any work in as
much as the Claimant themselves are eminently capable of not
completing any work assigned to them on their own.
28 That the contents of these Paras 28 are disputed and denied. The
Contract entered into between the parties was for maintenance
and under any maintenance contract it is unlikely that the work will
be executed only in continuous stretches. The Claimant was well
aware that the contract was for the repair and maintenance and
quoted the price accordingly. Therefore, any claim of the Claimant
regarding the additional cost is wholly misconceived and liable to
be dismissed. Further it is submitted that as perExhibit:R-43 the
stretches covered in the indents were more than 400mts and it is amatter of record that in the revised work programme, the Claimant
- 47 -
8/6/2019 Amended Reply to SOC - 100511
48/72
himself submitted his work plan for stretches varying from 100m to
400m length for BC laying as will be evident from Exhibit:R-59.
29. That the contents of the Para 29 are disputed and denied. It is
submitted that after the First Indent, the Claimant failed to
cooperate with the consultant in finalizing the Indents. However,
the Consultant has finalized indents as per site requirement as well
as the available dry spell i.e. from 12/06 to 04/07 because the
monsoon generally commences from June onwards. As regards
the 2nd indent, the commencement date was fixed as 01.12.2006,
after the lapse of 80 days of original commencement of work.
Hence the Consultant has taken in to the consideration that the
minimum period has to be given to the Claimant for mobilization of
heavy machinery and also keeping in mind that the onset monsoon
may start from June, 2007.
30-35. That the contents of the Paras 30 to 35 are based on conjecture
and surmises and therefore are disputed and denied in entirety.
The Respondent has narrated in detail the true and correct
sequence of events in the Preliminary Submissions which are
relevant to the present untenable claims and the same clearly
negate the misconceived theories sought to be advanced by the
Claimant in support of the untenable claim. The Claimant
consciously entered in to Contract with the Respondent for the
work covered therein and the extraneous considerations which are
clearly outside the Contract cannot justify the failure of the
Claimant in the faithful execution of the work. It is very obvious that
the Claimant has sought to invent reasons to cover up their
inefficiency and ineptitude to handle a contract of this magnitude.The contentions therefore merit summary rejection.
- 48 -
8/6/2019 Amended Reply to SOC - 100511
49/72
8/6/2019 Amended Reply to SOC - 100511
50/72
40. That the contents of Para 40 are baseless and preposterous and
therefore strongly disputed and denied. The averments containedin the Preliminary submissions are reiterated and reaffirmed.
41 to 43. That the contents of Para 41 to 43 are disputed and denied.
The untenable and far-fetched reasoning devoid of rationale
adverted to by the Claimant cannot negate the evident fact that the
execution of the work was too slow and the Claimant failed to
execute the work in consonance with the work program. The
Respondent in its letter dated 18.04.2007 had informed the
Claimant that the Claimant failed to achieve a minimum of 30%
progress when in fact half of the Contract period was already over.
The Respondent further informed the Claimant about its failure to
establish the lab with all the prescribed equipment.
44 & 45. That the contents of Paras 44 & 45 are disputed and denied.
The establishment of field laboratory was not only for the
bituminous works but also required as per the Contract conditions
to test and verify the quality of work of various items of works
which were under BOQ. In the Contract, it was very clearly
specified that within 30 days from commencement of work the field
laboratory was to be established.
46 & 47. That with respect to the contents of Paras 46 & 47 of the
Statement of claim it is submitted that the work was revised and
submitted by the Claimant for approval due to the failure of the
Claimant to complete the work within the time prescribed under the
Indents. It is emphatically denied that the Respondent had
extended the time frame in view of its default. It is further denied
that due to the extension of time frame the Respondent lost its
- 50 -
8/6/2019 Amended Reply to SOC - 100511
51/72
8/6/2019 Amended Reply to SOC - 100511
52/72
53-57 That the contentions contained in Paras 53 to 57 are baseless and
preposterous and therefore strongly disputed and denied. The
Respondent will refer and rely upon the Preliminary submissions
and explanations made in paras 19-20 in this claim.
58. That the contents of Para 58 are disputed and denied. The work
was not completed in time due to reasons totally attributable to the
Claimant. Therefore the Contract was terminated by the
Respondent on 31.12.2007.
59. That the contnts of the Para 59 are disputed and denied. Due to the
breach of the Contract by the Claimant, the work was terminated
on 31.12.2007.
60. That the contnts of the Para 60 are disputed and denied. That the
Claimant failed to complete the work on or before 11.09.2007,
original date of completion as per agreement condition and once
again failed to complete the revised work program within extended
time period i.e., 31.12.2007 as promised by the Claimant.
Therefore, on account of continuous and consistent failures by the
Claimant, the Contract was not extended further.
61. That the contents of Para 61 are disputed and denied. The
Liquidated Damages are imposed as per the terms of the Contract
and any contention to the contrary is emphatically repudiated. The
contents of sub-paras (a) to (j) are also candidly disputed and
denied and the Respondent reserves its right to make detailed
submissions in rebuttal thereof at an appropriate time before the
Ld. Tribunal.
Claim No.A-2(f) :
- 52 -
8/6/2019 Amended Reply to SOC - 100511
53/72
That the contentions of the Claimant with regard to their alleged
eligibility for the above misconceived claim are vebose and without
any para numbers to facilitate any point-wise or para-wise Replyby the Respondent. Suffice it would to state that the said recovery
was made by the Respondent wholly in accordance with the
Contract for the reasons and grounds already stated in the
Preliminary Submissions and para-wise replies, which are not
repeated herein for the sake of brevity. It is further submitted that
the contents of the SOC with respect to the above untenable claim,
to the extent not specifically adverted to and replied herein
specifically shall be deemed to have been traversed in extenso ,
disputed and denied by the Respondent save and except those
which are specifically admitted herein. Further, the Respondent
reserves its right to make detailed submissions in rebuttal thereof
at an appropriate time before the Ld. Tribunal.
Claim No.A-3 :
Claim No. Description Amountclaimed
(Rs.)
Claim No.A-3 Amount withheld from IPC-1 to IPC-9. 53,62,518/-
That the contents of this para are disputed and denied. After
termination of the Contract, the Claimant submitted the bill on
13.02.2008 to Engineer and the Engineer, in turn submitted the
- 53 -
Claim
No.
Description Amount claimed
(Rs.)
ClaimNo.A-2(f)
Deduction in IPC 9 on amount of20% of the balance work to becompleted
1,77,51,022.00
8/6/2019 Amended Reply to SOC - 100511
54/72
same to Respondent on 29.02.2008 Exhibit R-51. However, even
while the said bill was under scrutiny, the Claimant initiated
proceedings under section 9 of the Arbitration and Conciliation Act,
1996 before the Honble High court of Calcutta and despite the
orders for maintaining status quo given by the Honble Court,
illegally allowed the Bank Guarantees provided by way of
Performance Security to lapse. In view of the said directions of the
court to maintain status Quo, the said bills of the Claimant were not
processed. It is a matter of record that subsequent thereto, the
present Ld. Tribunal was also constituted on 06.06.2008 pursuant
to invocation of arbitration by the Claimant.
Claim No.A-4 :
ClaimNo.
Description Amountclaimed
(Rs.)
Remarks ofthe
Respondent
ClaimNo.A-4 Charges on Bank Guarantee forLDs and Differential interest onMargin Money of BG
15,49,748.00 Disallowed
That the contents of the Para are disputed and denied.
The Respondent had already withheld the amount towards
liquidated damages in running bills as a paper adjustment in
accordance with clause 45.1 of the GCC of the Contract as the
value of work done by the Claimant was meagre during the initial
period of the Contract and the amount was hardly sufficient to
recover mobilization advance. Therefore the Respondent recorded
the LDs in the Measurement Book [Exhibit R-50 & 50/A
(Amended)] to adjust the same in future bills due to negative value
of work done. However, the Claimant offered to submit
unconditional BGs in lieu thereof in as much as the Claimant was
- 54 -
8/6/2019 Amended Reply to SOC - 100511
55/72
under financial crisis and requested the Respondent not to recover
the amount of LD from the payments. The Respondent agreed in
good faith and with a view to help Claimant to complete the work,
accepted the same. Thus, the extra Bank Guarantees were
submitted by the Claimant at their own option and therefore the
above claim is clearly misconceived and untenable. Even
otherwise the present claim cannot lie against the Respondent
under the terms of the Contract.
Claim No.A-5 :
1. That the present untenable claim, which is clearly an after thought,
has also been raised on account of the alleged delay between the
date of the Letter of Acceptance and the actual date of signing of
the Contract, which has been dealt with in extenso in reply to
Claim No. A-1 and therefore is not being repeated for the sake of
brevity. The contents of the reply to the said claim, to the extent
applicable, may be treated as reply to the averments of the
Claimant contained herein.
2. That the tenure of the services under the present Contract was
limited to 12 months only and as per practice, such short-term
contracts do not qualify for price adjustments, which again, as per
- 55 -
ClaimNo.
Description Amountclaimed
(Rs.)
ClaimNo.A-5
Losses on account of price rise due todelays
18,17,803.00
8/6/2019 Amended Reply to SOC -