Page 1: Allan Block Retaining Wall Specification Manual
Page 2: Allan Block Retaining Wall Specification Manual

Inside this issue:Product Standards ............................................... 2

Installation Specifications ................................... 4

Water Management ............................................. 6

ASTM Standards .................................................. 8

Design, Construction and Inspection Check Lists ......................................... 10

Design Details ...................................................... 12

Water ManagementDetails ................................................................... 13

Geogrid Details .................................................... 14

Fencing Applications ........................................... 15

Miscellaneous Details ......................................... 16

Design Methods .................................................. 18

Allowable ConstructionTolerances ............................................................ 19

Geogrid Reinforcement Specifications ...................................................... 21

List of Figures:Fig 1: AB Units - Approximate Dimensions ... 2

Fig 2: Gravity Wall Consolidation Zone .......... 3

Fig 3: Geogrid Wall Consolidation Zone ......... 5

Fig 4: Surface Water Management .................. 6

Fig 5: Construction Water Management ........ 6

Fig 6A: Internal Blanket ...................................... 7

Fig 6B: Internal Blanket and Chimney Drain .... 7

Fig 7: Freeze-Thaw Testing .............................. 9

Fig 8: Global Stability ...................................... 10

Fig 9: Elevation View ........................................ 10

Fig 10: Wall Site Components ........................... 10

Fig 11: Typical Reinforcement Configurations ....................................... 11

Fig 12: Wall Design Envelope ........................... 11

Fig 13: Vertical Control ...................................... 19

Fig 14: Differential Settlements ......................... 19

Fig 15: Horizontal Control .................................. 19

Fig 16: Rotation .................................................. 19

Table of Contents Fifth Edition

allanblock.com

List of Tables:Table 1: Embankment Protection

Fabric Specifications .......................... 7

Table 2: Strength and Absorption Requirements (ASTM) ....................... 8

Table 3: Geogrid Manufacturers Testing Results ................................... 22

The most current, up-to-date information canbe found on our website at allanblock.com.

Page 3: Allan Block Retaining Wall Specification Manual

allanblock.com

Allan Block® Corporation:

A leader in segmental retaining wall design

The following pages will provide assistance to abroad range of professional retaining wall designers.This technical specification manual will allow a walldesigner to source and reference specific informationfor use in developing project documents. Includedare: product standards, installation and water man-agement procedures, design details, industry stan-dards, allowable construction tolerances, projectdesign checklist, project installation checklist, projectinspection checklist, reference design methods, andgeogrid reinforcement options.

The goal is to provide formatted specification sheetsthat summarize information published by Allan Blockand other relevant publications, as well as provide acomprehensive document for most applicationswhich utilize mortarless concrete block as a compo-nent of a segmental retaining wall.

The document focuses on composite structures builtby combining an Allan Block facing unit with a rein-forced soil mass, and appropriate drainage details.Other methods of reinforcement will be illustrated in

Answering the question:Can segmental retaining walls satisfy the requirements of my project?

Segmental Retaining Walls (SRW’s) have evolved frombeing used in garden and landscape applications in the80’s and 90’s, to now having found their way into com-mercial projects, roadway sites, and major industrialapplications. With estimates of hundreds of millions ofAllan Blocks installed worldwide, mortarless segmentalretaining walls have proven their value and durability inthe construction marketplace.

Projects range from walls up to 50 ft (15.2 m) in heightto miles of walls used in roadway, water and otherapplications. The flexible nature of the system hasproven to eliminate the need for frost footings in north-ern climates, provide additional drainage in tropicalareas, and allow for additional flexibility in earthquakeplagued sections of the world. In short, there are veryfew site problems that cannot find a cost effective solu-tion using Allan Block Retaining Wall Products.

1

the Design Detail portion of this publication, but notpresented in great detail. The intent of this publicationis to assist the local wall design engineer, but not limittheir flexibility for any given design situation.

The specifications shown here as well as the detailedAutocad drawings are available for download on ourwebsite at allanblock.com.

allanblock.com

Page 4: Allan Block Retaining Wall Specification Manual

Specification Guidelines: Allan Block ModularRetaining Wall SystemsThe following specifications provide Allan Block Corporation's typicalrequirements and recommendations. At the engineer of record's discretion these specifications may be revised to accommodate sitespecific design requirements.

SECTION 1PART 1: GENERAL1.1 Scope

Work includes furnishing and installing modular concrete blockretaining wall units to the lines and grades designated on the con-struction drawings and as specified herein.

1.2 Applicable Sections of Related WorkGeogrid Wall Reinforcement (see Section 2, Page 4)

1.3 Reference StandardsA. ASTM C1372 Standard Specification for Segmental

Retaining Wall Units.B. ASTM C1262 Evaluating the Freeze Thaw Durability of

Manufactured CMU’s and Related Concrete UnitsC. ASTM D698 Moisture Density Relationship for Soils,

Standard MethodD. ASTM D422 Gradation of SoilsE. ASTM C140 Sample and Testing Concrete Masonry Units

1.4 Delivery, Storage, and HandlingA. Contractor shall check the materials upon delivery to assure prop-

er material has been received.B. Contractor shall prevent excessive mud, cementitious material, and

like construction debris from coming in contact with the materials.C. Contractor shall protect the materials from damage. Damaged

material shall not be incorporated in the project (ASTM C1372).

PART 2: MATERIALS2.1 Modular Wall UnitsA. Wall units shall be Allan Block

Retaining Wall units as producedby a licensed manufacturer.

B. Wall units shall have minimum 28day compressive strength of 3000psi (20.7 MPa) in accordance withASTM C1372. The concrete unitsshall have adequate freeze-thawprotection with an average absorp-tion rate in accordance with ASTMC1372 or an average absorptionrate of 7.5 lb/ft3 (120 kg/m3) fornorthern climates and 10 lb/ft3 (160kg/m3) for southern climates.

C. Exterior dimensions shall be uni-form and consistent. Maximumdimensional deviations on theheight of any two units shall be0.125 in. (3 mm).

D. Wall units shall provide a mini-mum of 110 lbs total weight persquare foot of wall face area (555 kg/m²). Fill contained within theunits may be considered 80% effective weight.

E. Exterior face shall be textured. Color as specified by owner.

2

Allan Block Product Standards

2.2 Wall RockA. Material must be well-graded compactible aggregate, 0.25

in. to 1.5 in., (6 mm - 38 mm) with no more than 10% pass-ing the #200 sieve. (ASTM D422)

B. Material behind and within the blocks may be the same material.

2.3 Infill Soil A. Infill material shall be site excavated soils when approved by

the on-site soils engineer unless otherwise specified in thedrawings. Unsuitable soils for backfill (heavy clays or organicsoils) shall not be used in the reinforced soil mass. Finegrained cohesive soils (�<31 ) may be used in wall construc-tion, but additional backfilling, compaction and water man-agement efforts are required. Poorly graded sands, expansiveclays and/or soils with a plasticity index (PI) >20 or a liquidlimit (LL) >40 should not be used in wall construction.

B. The infill soil used must meet or exceed the designed fric-tion angle and description noted on the design cross sec-tions, and must be free of debris and consist of one of thefollowing inorganic USCS soil types: GP, GW, SW, SP meet-ing the following gradation as determined in accordancewith ASTM D422.

C. Where additional fill is required, contractor shall submit sam-ple and specifications to the wall design engineer or the on-site soils engineer for approval and the approving engineermust certify that the soils proposed for use has propertiesmeeting or exceeding original design standards.

PART 3: WALL CONSTRUCTION3.1 ExcavationA. Contractor shall excavate to the lines and grades shown on

the construction drawings. Contractor shall use caution not toover-excavate beyond the lines shown, or to disturb the baseelevations beyond those shown.

B. Contractor shall verify locations of existing structures and utili-ties prior to excavation. Contractor shall ensure all surroundingstructures are protected from the effects of wall excavation.

3.2 Foundation Soil PreparationA. Foundation soil shall be defined as any soils located

beneath a wall.B. Foundation soil shall be excavated as dimensioned on the

plans and compacted to a minimum of 95% of StandardProctor (ASTM D698) prior to placement of the base material.

C. Foundation soil shall be examined by the on-site soils engineer toensure that the actual foundation soil strength meets or exceedsassumed design strength. Soil not meeting the required strengthshall be removed and replaced with acceptable material.

3.3 BaseA. The base material shall be the same as the Wall Rock material

(Section 2.2) or a low permeable granular material.B. Base material shall be placed as shown on the construction draw-

ing. Top of base shall be located to allow bottom wall units to beburied to proper depths as per wall heights and specifications.

Figure 1:Standard AB Unit -Approx. Dimensions

Sieve Size Percent Passing4 inch 100 - 75No. 4 100 - 20No. 40 0 - 60No. 200 0 - 35

allanblock.com

Standard AB FieldstoneUnit - Approx. Dimensions

Page 5: Allan Block Retaining Wall Specification Manual

allanblock.com

C. Base material shall be installed on undisturbed native soils orsuitable replacement fills compacted to a minimum of 95%Standard Proctor (ASTM D698).

D. Base shall be compacted at 95% Standard Proctor (ASTM D698)to provide a level hard surface on which to place the first courseof blocks. The base shall be constructed to ensure proper wallembedment and the final elevation shown on the plans. Well-graded sand can be used to smooth the top 1/2 in. (13 mm) onthe base material.

E. Base material shall be a 4 in. (100 mm) minimum depth for wallsunder 4 ft (1.2 m) and a 6 in. (150 mm) minimum depth for wallsover 4 ft (1.2 m).

3.4 Unit InstallationA. Install units in accordance with the manufacturer’s instructions

and recommendations for the specific concrete retaining wallunit, and as specified herein.

B. Ensure that units are in full contact with base. Proper care shallbe taken to develop straight lines and smooth curves on basecourse as per wall layout.

C. Fill all cores and cavities and a minimum of 12 in. (300 mm)behind the base course with wall rock. Use infill soils behind thewall rock and approved soils in front of the base course to firm-ly lock in place. Check again for level and alignment. Use a platecompactor to consolidate the area behind the base course. Allexcess material shall be swept from top of units.

D. Install next course of wall units on top of base course. Positionblocks to be offset from seams of blocks below. Perfect "runningbond" is not essential, but a 3 in. (75 mm) minimum offset is rec-ommended. Check each block for proper alignment and level. Fillall cavities in and around wall units and to a minimum of 12 in.(300 mm) depth behind block with wall rock. For taller wall appli-cation the depth of wall rock behind the block should be increased;walls from 15 ft (4.57 m) to 25 ft (7.62 m) should have a minimumof 2 ft (0.61 m) and walls above 25ft (7.62 m) should have a mini-mum of 3 ft (0.9 m). Spread infill soil in uniform lifts not exceed-ing 8 in. (200 mm) in uncompacted thickness and compact to 95%of Standard Proctor (ASTM D698) behind the consolidation zone.

E. The consolidation zone shall be defined as 3 ft (0.9 m) behind thewall. Compaction within the consolidation zone shall be accom-plished by using a hand operated plate compactor and shallbegin by running the plate compactor directly on the block and

then compacting in parallel paths from the wall face until theentire consolidation zone has been compacted. A minimum oftwo passes of the plate compactor are required with maximumlifts of 8 in. (200 mm). Expansive or fine-grained soils mayrequire additional compaction passes and/or specific compactionequipment such as a sheepsfoot roller. Maximum lifts of 4 in.(100 mm) may be required to achieve adequate compaction with-in the consolidation zone. Employ methods using lightweight

compaction equipment that will not disrupt thestability or batter of the wall. Final compaction requirements in theconsolidation zone shall be established by the engineer of record.

F. Install each subsequent course in like manner. Repeat procedure tothe extent of wall height.

G. As with any construction work, some deviation from constructiondrawing alignments will occur. Variability in construction of SRWs isapproximately equal to that of cast-in-place concrete retaining walls.As opposed to cast-in-place concrete walls, alignment of SRWs canbe simply corrected or modified during construction. Based uponexamination of numerous completed SRWs, the following recom-mended minimum tolerances can be achieved with good construc-tion techniques. Refer to Page 19.

Vertical Control - ±1.25 in. (32 mm) max. over 10 ft (3 m) distanceHorizontal Location Control - straight lines ±1.25 in. (32 mm) over a 10 ft (3 m) distance.Rotation - from established plan wall batter : 2.0°Bulging - 1.0 in. (25 mm) over a 10 ft (3.0 m) distance

3.5 Additional Construction NotesA. When one wall branches into two terraced walls, it is important to

note that the soil behind the lower wall is also the foundation soilbeneath the upper wall. This soil shall be compacted to a minimumof 95% of Standard Proctor (ASTM D698) prior to placement of thebase material. Achieving proper compaction in the soil beneath anupper terrace prevents settlement and deformation of the upperwall. One way is to replace the soil with wall rock and compact in 8in. (200 mm) lifts. When using on-site soils, compact in maximumlifts of 4 in. (100 mm) or as required to achieve specified compaction.

B. Filter fabric use is not suggested for use with cohesive soils.Clogging of such fabric creates unacceptable hydrostatic pressuresin soil reinforced structures. When filtration is deemed necessary incohesive soils, use a three dimensional filtration system of cleansand or filtration aggregate.

C. Embankment protection fabric is used to stabilize rip rap and foun-dation soils in water applications and to separate infill materials fromthe retained soils. This fabric should permit the passage of fines topreclude clogging of the material. Embankment protection fabricshall be a high strength polypropylene monofilament materialdesigned to meet or exceed typical Corps of Engineers plastic filterfabric specifications (CW-02215); stabilized against ultraviolet (UV)degradation and typically exceeding the values in Table 1, page 7.

D. Water management is of extreme concern during and after con-struction. Steps must be taken to ensure that drain pipes are prop-erly installed and vented to daylight and a grading plan has beendeveloped that routes water away from the retaining wall location.Site water management is required both during construction of thewall and after completion of construction.

Consult the Allan Block Engineering Department for details at 800-899-5309. A specification subject to change without notice, thiswas last updated on 08/06/2012.

Figure 2: Consolidation Zone - Gravity Wall

3

allanblock.com

Page 6: Allan Block Retaining Wall Specification Manual

allanblock.com

Allan Block Installation Specifications

PART 3: WALL CONSTRUCTION3.1 Foundation Soil PreparationA. Foundation soil shall be excavated to the lines and grades

as shown on the construction drawings, or as directed bythe on-site soils engineer.

B. Foundation soil shall be examined by the on-site soils engi-neer to assure that the actual foundation soil strength meetsor exceeds assumed design strength.

C. Over-excavated areas shall be filled with compacted backfillmaterial approved by on-site soils engineer.

D. Contractor shall verify locations of existing structures andutilities prior to excavation. Contractor shall ensure all sur-rounding structures are protected from the effects of wallexcavation.

3.2 Wall ConstructionWall construction shall be as specified under Section 1, Part 3, Wall Construction, Page 2.

3.3 Geogrid InstallationA. Install Allan Block wall to designated height of first geogrid

layer. Backfill and compact the wall rock and infill soil in lay-ers not to exceed 8 in. (200 mm) lifts behind wall to depthequal to designed grid length before grid is installed.

B. Cut geogrid to designed embedment length and place ontop of the Allan Block units to back edge of the raised frontlip or within 1 in. (25 mm) of the concrete retaining wall facewhen using AB Fieldstone. Extend away from wall approxi-mately 3% above horizontal on compacted infill soils.

C. Lay geogrid at the proper elevation and orientations shownon the construction drawings or as directed by the walldesign engineer.

4

Specification Guidelines: GeogridReinforcement SystemsThe following specifications provide Allan Block Corporation'stypical requirements and recommendations. At the engineerof record's discretion these specifications may be revised toaccommodate site specific design requirements.

SECTION 2PART 1: GENERAL1.1 Scope

Work includes furnishings and installing geogrid reinforce-ment, wall block, and backfill to the lines and grades designat-ed on the construction drawings and as specified herein.

1.2 Applicable Section of Related WorkSection 1: Allan Block Modular Retaining Wall Systems. (seeSection 1, page 2)

1.3 Reference StandardsSee specific geogrid manufacturers reference standards.

Additional Standards:A. ASTM D4595 - Tensile Properties of Geotextiles by the Wide-

Width Strip MethodB. ASTM D5262 - Test Method for Evaluating the Unconfined

Creep Behavior of GeogridsC. ASTM D6638 Grid Connection Strength (SRW-U1)D. ASTM D6916 SRW Block Shear Strength (SRW-U2)E. GRI-GG4 - Grid Long Term Allowable Design Strength (LTADS)F. ASTM D6706 - Grid Pullout of Soil

1.4 Delivery, Storage, and HandlingA. Contractor shall check the geogrid upon delivery to assure that

the proper material has been received.B. Geogrid shall be stored above -10 F (-23 C).C. Contractor shall prevent excessive mud, cementitious materi-

al, or other foreign materials from coming in contact with thegeogrid material.

PART 2: MATERIALS2.1 DefinitionsA. Geogrid products shall be of high density polyethylene or

polyester yarns encapsulated in a protective coating specifi-cally fabricated for use as a soil reinforcement material.

B. Concrete retaining wall units are as detailed on the drawingsand shall be Allan Block Retaining Wall Units.

C. Drainage material is free draining granular material as definedin Section 1, 2.2 Wall Rock, Page 2.

D. Infill soil is the soil used as fill for the reinforced soil mass.E. Foundation soil is the in-situ soil.

2.2 ProductsGeogrid shall be the type as shown on the drawings having theproperty requirements as described within the manufacturers specifications.

2.3 Acceptable ManufacturersA manufacturer's product shall be approved by the wall design engineer.

Page 7: Allan Block Retaining Wall Specification Manual

D. When fill is placed and compaction cannot bedefined in terms of Standard Proctor Density, then compactionshall be performed using ordinary compaction process and com-pacted so that no deformation is observed from the compactionequipment or to the satisfaction of the engineer of record or thesite soils engineer.

E. Tracked construction equipment shall not be operated direct-ly on the geogrid. A minimum fill thickness of 6 in. (150 mm)is required prior to operation of tracked vehicles over thegeogrid. Turning of tracked vehicles should be kept to a min-imum to prevent tracks from displacing the fill and damagingthe geogrid.

F. Rubber-tired equipment may pass over the geogrid reinforce-ment at slow speeds, less than 10 mph (16 Km/h). Suddenbraking and sharp turning shall be avoided.

G. The infill soil shall be compacted to achieve 95% StandardProctor (ASTM D698). Compaction tests shall be taken at 3 ft (0.9m) behind the block and at the back of the reinforced zone. Thefrequency shall be as determined by the on-site soils engineer oras specified on the plan. Soil tests of the infill soil shall be sub-mitted to the on-site soils engineer for review and approval priorto the placement of any material. The contractor is responsiblefor achieving the specified compaction requirements. The on-site soils engineer may direct the contractor to remove, corrector amend any soil found not in compliance with these writtenspecifications.

3.5 Special ConsiderationsA. Geogrid can be interrupted by periodic penetration of a

column, pier or footing structure.B. Allan Block walls will accept vertical and horizontal reinforcing

with rebar and grout.C. If site conditions will not allow geogrid embedment length,

consider the following alternatives:• Masonry Reinforced Walls • Soil Nailing• Increased Wall Batter • Earth Anchors• Double Allan Block Wall • Rock Bolts• No-Fines Concrete See Design Details Page 16 and 17.

D. Allan Block may be used in a wide variety of water applications asindicated in Section 3, Part 1.8, Page 7.

Consult the Allan Block Engineering Department for details 800-899-5309. A specification subject to change without notice, thiswas last updated on 08/06/2012.

allanblock.com

D. Correct orientation of the geogrid shall be verified by thecontractor and on-site soils engineer. Strength direction istypically perpendicular to wall face.

E. Follow manufacturers guidelines for overlap requirements. Incurves and corners, layout shall be as specified in DesignDetail 9-12: Using Grid With Corners and Curves,Page 14.

F. Place next course of Allan Block on top of grid and fill blockcores with wall rock to lock in place. Remove slack and foldsin grid and stake to hold in place.

G. Adjacent sheets of geogrid shall be butted against eachother at the wall face to achieve 100 percent coverage.

H. Geogrid lengths shall be continuous. Splicing parallelto the wall face is not allowed.

3.4 Fill PlacementA. Infill soil shall be placed in lifts and compacted as specified

under Section 1, Part 3.4, Page 3, Unit Installation.B. Infill soil shall be placed, spread and compacted in such a

manner that minimizes the development of slack or move-ment of the geogrid.

C. Only hand-operated compaction equipment shall beallowed within 3 ft (0.9 m) behind the wall. This area shallbe defined as the consolidation zone. Compaction in thiszone shall begin by running the plate compactor directly onthe block and then compacting in parallel paths to the wallface until the entire consolidation zone has been compact-ed. A minimum of two passes of the plate compactor arerequired with maximum lifts of 8 in. (200 mm). Section 1,Part 3.4 E, Page 3.

5

Figure 3: Consolidation Zone - Reinforced Zone

allanblock.com

Page 8: Allan Block Retaining Wall Specification Manual

allanblock.com

Allan Block Water Management

Specification Guidelines:Water ManagementThe following specifications provide Allan Block Corporation's typicalrequirements and recommendations. At the engineer of record's dis-cretion these specifications may be revised to accommodate site spe-cific design requirements.

Section 3 PART 1: GENERAL DRAINAGE1.1 Surface DrainageRainfall or other water sources such as irrigation activities collectedby the ground surface atop the retaining wall can be defined as sur-face water. Retaining wall design shall take into consideration themanagement of this water.A. At the end of each day’s construction and at final completion,

grade the backfill to avoid water accumulation behind the wallor in the reinforced zone.

B. Surface water must not be allowed to pond or be trapped inthe area above the wall or at the toe of the wall.

C. Existing slopes adjacent to retaining wall or slopes createdduring the grading process shall include drainage details sothat surface water will not be allowed to drain over the top ofthe slope face and/or wall. This may require a combination ofberms and surface drainage ditches.

D. Irrigation activities at the site shall be done in a controlled andreasonable manner. If an irrigation system is employed, thedesign engineer or irrigation manufacture shall provide detailsand specification for required equipment to ensure againstover irrigation which could damage the structural integrity ofthe retaining wall system.

E. Surface water that cannot be diverted from the wall must becollected with surface drainage swales and drained laterally inorder to disperse the water around the wall structure.Construction of a typical swale system shall be in accordancewith Design Detail 5: Swales, Page 13.

1.2 GradingThe shaping and recontouring of land in order to prepare it for sitedevelopment is grading. Site grading shall be designed to routewater around the walls.

A. Establish final grade with a positive gradient away from thewall structure. Concentrations of surface water runoff shall bemanaged by providing necessary structures, such as pavedditches, drainage swales, catch basins, etc.

B. Grading designs must divert sources of concentrated surfaceflow, such as parking lots, away from the wall.

1.3 Drainage SystemThe internal drainage systems of the retaining wall can be describedas the means of eliminating the buildup of incidental water which

infiltrates the soils behind the wall. Drainage system design willbe a function of the water conditions on the site. Possibledrainage facilities include Toe and Heel drainage collection pipesand blanket or chimney rock drains or others. Design engineershall determine the required drainage facilities to completelydrain the retaining wall structure for each particular site condition.A. All walls will be constructed with a minimum of 12 in.

(300 mm) of wall rock directly behind the wall facing. Thematerial shall meet or exceed the specification for wall rockoutlined in Section 1, 2.2 Wall Rock, Page 2.

B. The drainage collection pipe, drain pipe, shall be a 4 in. (100 mm) perforated or slotted PVC, or corrugated HDPEpipe as approved by engineer of record.

C. All walls will be constructed with a 4 in. (100 mm) diameterdrain pipe placed at the lowest possible elevation within the12 in. (300 mm) of wall rock. This drain pipe is referred to asa toe drain, Section 3, 1.4 Toe Drain, Page 6.

D. Geogrid Reinforced Walls shall be constructed with an additional 4 in. (100 mm) drain pipe at the back bottom ofthe reinforced soil mass. This drain pipe is referred to as aheel drain, Section 3, 1.5 Heel Drain, Page 7.

1.4 Toe DrainA toe drain pipe should be located at the back of the wall rockbehind the wall as close to the bottom of the wall as allowed whilestill maintaining a positive gradient for drainage to daylight, or astorm water management system. Toe drains are installed forincidental water management not as a primary drainage system.

A. For site configurations with bottoms of the base on a levelplane it is recommended that a minimum one percent gra-dient be maintained on the placement of the pipe with out-lets on 50 ft (15 m) centers, or 100 ft (30 m) centers if pipe iscrowned between the outlets. This would provide for a max-imum height above the bottom of the base in a flat configu-ration of no more than 6 in. (150 mm).

B. For rigid drain pipes with drain holes the pipes should bepositioned with the holes located down. Allan Block does notrequire that toe drain pipes be wrapped when installed intobase rock complying with the specified wall rock material.

C. Pipes shall be routed to storm drains where appropriate orthrough or under the wall at low points when the job sitegrading and site layout allows for routing. Appropriatedetails shall be included to prevent pipes from beingcrushed, plugged, or infested with rodents.

D. On sites where the natural drop in grade exceeds the onepercent minimum, drain pipes outlets shall be on 100 foot(30 m) centers maximum. This will provide outlets in theevent that excessive water flow exceeds the capacity of pipeover long stretches.

E. When the drain pipe must be raised to accommodate out-lets through the wall face, refer to the Design Detail 4:Alternate Drain, Page 13.

Figure 5: Construction Water Management

Figure 4: Surface Water Management

6

Page 9: Allan Block Retaining Wall Specification Manual

1.5 Heel DrainThe purpose of the heel drain is to pick up any water that migratesfrom behind the retaining wall structure at the cut and route thewater away from the reinforced mass during the constructionprocess and for incidental water for the life of the structure.A. The piping used at the back of the reinforced mass shall

have a one percent minimum gradient over the length, butit is not critical for it to be positioned at the very bottom ofthe cut. Additionally the entire length of the pipe may bevented at one point and should not be tied into the toedrain.

B. The pipe may be a rigid pipe with holes at the bottom withan integral sock encasing the pipe or a corrugated perforat-ed flexible pipe with a sock to filter out fines when requiredbased on soil conditions. For infill soils with a high per-centage of sand and/or gravel the heel drain pipe does notneed to be surrounded by drainage rock. When workingwith soils containing more than fifty percent clay, one cubicfoot of drainage rock is required for each foot of pipe.

1.6 Ground WaterGround water can be defined as water that occurs within the soil.It may be present because of surface infiltration or water tablefluctuation. Ground water movement must not be allowed tocome in contact with the retaining wall.A. If water is encountered in the area of the wall during exca-

vation or construction, a drainage system (chimney, com-posite or blanket) must be installed as directed by the walldesign engineer.

B. Standard retaining wall designs do not include hydrostaticforces associated with the presence of ground water. If ade-quate drainage is not provided the retaining wall designmust consider the presence of the water.

C. When non-free draining soils are used in the retained zone,the incorporation of a chimney and blanket drain should beadded to minimize the water penetration into the reinforcedmass. Refer to Design Detail 6: Chimney and BlanketDrain, Page 13.

1.7 Concentrated Water SourcesAll collection devices such as roof downspouts, storm sewers, andcurb gutters are concentrated water sources. They must bedesigned to accommodate maximum flow rates and to vent outsideof the wall area. A. All roof downspouts of nearby structures shall be sized with

adequate capacity to carry storm water from the roof awayfrom the wall area. They shall be connected to a drainage sys-tem in closed pipe and routed around the retaining wall area.

B. Site layout must take into account locations of retaining wallstructures and all site drainage paths. Drainage paths shouldalways be away from retaining wall structures.

C. Storm sewers and catch basins shall be located away fromretaining wall structures and designed so as not to introduceany incidental water into the reinforced soil mass.

D. A path to route storm sewer overflow must be incorporatedinto the site layout to direct water away from the retaining wallstructure.

1.8 Water ApplicationRetaining walls constructed in conditions that allow standing ormoving water to come in contact with the wall face are consideredwater applications. These walls require specific design and con-struction steps to ensure performance.Refer to Design Detail 7 and 8: Water Applications, Page 13.

A. Embankment protection fabric is used to stabilize rip rap andfoundation soils in water applications and to separate infillmaterials from the retained soils. This fabric should permit thepassage of fines to preclude clogging of the material.Embankment protection fabric shall be a high strengthpolypropylene monofilament material designed to meet orexceed typical NTPEP specifications; stabilized against ultravio-let (UV) degradation and typically needs or exceeds the valuesin Table 1.

B. Infill material shall be free draining to meet the site requirementsbased on wave action and rapid draw down conditions.

C. Rip rap or alternative products such as Scourstop™ TransitionMats or articulated concrete block mats may be required as a toeprotector to eliminate scour at the base of the wall.

Consult the Allan Block Engineering Department for details 800-899-5309. A specification subject to change without notice, thiswas last updated on 09/01/2007.

Mechanical DeterminationProperty Method

Tensile Strength = 225 lbs/in (39.4 kN/m) ASTM D-4595

Puncture Strength = 950 lbs (4228 N) ASTM D-6241

Apparent Opening Size (AOS)= U.S. Sieve #70 (0.212 mm)

Trapezoidal Tear = 100 lbs (445 N) ASTM D-4533

Percent Open Area = 4% COE-02215

Permeability = 0.01 cm/sec ASTM D-4491

Table 1: Embankment Protection Fabric Specifications

allanblock.com7

Figure 6A: Internal Blanket

Figure 6B: Internal Blanket and Chimney Drain

allanblock.com

ASTM D-4751

Page 10: Allan Block Retaining Wall Specification Manual

ASTM C1372 Standard Specifications for Segmental Retaining Wall Units

Specification Guidelines:Product Specifications forSegmental Retaining Wall Units

Section 4 The following summarizes the contents of ASTM C1372 and keycomponents relevant when specifying modular concrete blockfor use in structural retaining wall designs. A copy of the fullstandard is available upon request. This summary attempts toprovide the information which is most commonly used, butAllan Block does not claim that all information contained in thestandard is represented.

1. Scope1.1 This specification covers dry-cast segmental retaining wall

units of concrete, machine–made from hydraulic cement,water, and suitable mineral aggregates with or without theinclusion of other materials. The units are intended for use inthe construction of mortarless segmental retaining walls.

5. Physical Requirements 5.1 At the time of delivery to the work site, the units shall conform

to the physical requirements of Table 2 when tested in accor-dance with 8.2.

5.2 Freeze-Thaw Durability — In areas where repeated freezingand thawing under saturated conditions occur, freeze-thawdurability shall be demonstrated by test or by proven field per-formance that the segmental retaining wall units have ade-quate durability for the intended use. When testing is requiredby the specifier to demonstrate freeze-thaw durability, theunits shall be tested in accordance with 8.3.

5.2.1 Specimens shall comply with either of the following: (1) the weight loss of each of five test specimens at the con-clusion of 100 cycles shall not exceed 1 % of its initial weight;or (2) the weight loss of each of four of the five test specimensat the conclusion of 150 cycles shall not exceed 1.5 % of its ini-tial weight.

6. Permissible Variations in Dimensions6.1 Overall dimensions for width, height, and length shall differ

by not more than ± 1/8 in. (3.2 mm) from specified standarddimensions.

6.1.1 Dimensional tolerance requirements for width shall bewaived for architectural surfaces.

7. Finish and Appearance7.1 All units shall be sound and free of cracks or other defects

that interfere with the proper placement of the unit or sig-nificantly impair the strength or permanence of the con-struction. Minor cracks incidental to the usual method ofmanufacture or minor chipping resulting from customarymethods of handling in shipment and delivery, are notgrounds for rejection.

7.2 Where units are to be used in exposed wall construction, theface or faces that are to be exposed shall not show chips orcracks, not otherwise permitted, or other imperfections whenviewed from a distance of not less than 20 ft (6.1 m) under dif-fused lighting.

7.2.1 Five percent of a shipment containing chips not largerthan 1 in. (25 mm) in any dimension, or cracks not widerthan 0.02 in. (0.5 mm) and not longer than 25 % of thenominal height of the unit is permitted.

7.3 The color and texture of units shall be specified by thepurchaser. The finished surface that will be exposed inplace shall conform to an approved sample consisting ofnot less than four units, representing the range of textureand color permitted.

8. Sampling and Testing8.1 The purchaser or authorized representative shall be

accorded proper facilities to inspect and sample units atthe place of manufacture from the lots ready for delivery.

8.2 Sample and test units for compressive strength, absorption,and dimensional tolerances in accordance with TestMethods ASTM C140.

8.3 When required, sample and test five specimens for freeze-thaw durability in water in accordance with Test MethodASTM C1262. Freeze-thaw durability shall be based on testsof units made with the same materials, concrete mix design,manufacturing process, and curing method, conducted notmore than 24 months prior to delivery.

9. Compliance9.1 If a sample fails to conform to the specified requirements, the

manufacturer shall be permitted to remove units from the ship-ment. A new sample shall be selected by the purchaser fromremaining units from the shipment with a similar configurationand dimension and tested at the expense of the manufacturer. Ifthe second sample meets the specified requirements, theremaining portion of the shipment represented by the samplemeets the specified requirements. If the second sample fails tomeet the specified requirements, the remaining portion of theshipment represented by the sample fails to meet the specifiedrequirements.

Minimum Required Net Average CompressiveStrength, psi (MPa)

Average of 3 units Individual Unit3000 (20.7) 2500 (17.2)Maximum Water Absorption Requirements,

lb/ft3 (kg/m3)Weight Classification Oven-Dry Density of Concrete lb/ft3 (kg/m3)

Light Weight Medium Weight Normal WeightLess than 105 (1680) to 125 (2000)105 (1680) less than 125 (2000) or more18 (288) 15 (240) 13 (208)

TABLE 2: Strength and Absorption Requirements (ASTM)

8allanblock.com

Page 11: Allan Block Retaining Wall Specification Manual

ASTM C1262 Standard Test Method for Evaluating the Freeze-Thaw Durabilityof Manufactured Concrete Masonry Units and Related Concrete Units

Section 5The following summarizes the contents of ASTM C1262 and keycomponents of the test methods used to determine relativefreeze thaw durability. This does not provide a comparison tofield performance but a systematic approach to testing. A copyof the full standard is available upon request. This summaryattempts to provide the information which is most commonlyused, but Allan Block does not claim that all information con-tained in the standard is represented.

1. Scope1.1 This test method covers the resistance to freezing and thawing

of dry-cast segmental retaining wall (SRW) units (seeSpecification C1372) and related concrete units. Units are test-ed in a test solution that is either water or 3 % saline solutiondepending on the intended use of the units in actual service.

Note 1— Related concrete units include units such as hollow andsolid concrete masonry units, concrete brick, and concreteroof pavers.

4. Significance and Use4.1 The procedure described in this test method is intended to

determine the effects of freezing and thawing on SRW andrelated units in the presence of water or saline solution.

4.2 The procedure is not intended to provide a quantitative meas-ure to determine an expected length of service for a specifictype of concrete unit.

6. Sampling6.1 Selection of Test Units — Select five whole SRW units rep-

resentative of the lot from which they are selected. The unitsshall be free from visible cracks or structural defects.

6.2 Number of Specimens — Test specimens shall consist ofsolid coupons saw-cut from full sized units. Do not saw-cuttest specimens from units that have been previously oven-dried. Do not subject test specimens to oven-drying prior tocompletion of freeze-thaw testing.

6.2.1 Cut one coupon from each of the five sampled units. Cut thecoupon from the exposed surface of the unit as the unit is usedin service unless the exposed surface is an architectural orother nonplanar surface (see Note 6). In the case of a unit withan exposed architectural or other nonplanar surface, cut thecoupon from another flat molded surface ideally as far as pos-sible from the architectural or other nonplanar face and in nocase less than 2 in. (50 mm) from that surface. Immediately fol-lowing saw-cutting, remove loose particles and residue fromthe coupon by rinsing in tap water and brushing with a softbristle brush. Do not fully immerse coupons in water. Eachspecimen shall be marked with a unique identification numberon the non-molded surface of the specimen.

Note 6— Split-faced surfaces are the most common surfaces usedto provide an architectural appearance to segmental retainingwalls. However, other means could be used to obtain similararchitectural effects like tumbling, grinding, and slumping.

7. Procedure7.1 Specimen Conditioning:

7.1.1 After preparation of the freeze-thaw test specimens in accordancewith Section 6, place the specimen in the container face downon the specimen supports such that the non-saw-cut surface ofthe specimen is in contact with the specimen supports. Add a

9

sufficient amount of test solution at a temperature of 60 to80°F (16 to 27°C) to the container to achieve a test solutiondepth of 1⁄2 ± 1⁄16 in. (13 ± 2 mm) (see Note 8 and Note 9). Donot pour test solution directly onto the specimen. The testsolution shall be either potable tap water or a 3 ± 0.1 % (byweight) sodium chloride saline solution (see Note 10). Closethe container lid tightly and store the container on a level sur-face in laboratory air as defined in 6.2.3.

7.2 Cyclical Testing:7.2.3 One freeze-thaw cycle is defined as a completed freezing cycle

followed by a completed thawing cycle.7.2.4 At 20 cycle intervals for those specimens tested in water and at 10

cycle intervals for those specimens tested in saline solution,remove containers from the test chamber and collect residue inaccordance with 7.3. Open containers to visually inspect the con-dition of the specimens and to adjust the test solution level tocomply with 7.1.1.

7.3 Collection of Residue:7.3.1 Weigh to the nearest 0.2 g (0.0005 lb) and record as Wf a filter

paper of high wet strength and smooth surface that has come toequilibrium temperature with the lab environment. Remove a sin-gle specimen from its container. Immediately rinse the specimenwith water (if the specimen is tested in saline solution, use salinesolution to rinse the specimen) using a squeeze bottle, being care-ful to collect in the specimen container the rinse water (or salinesolution) and all loose particles from the specimen. Consider anypieces that separated from the specimen as part of the residue.Pour the test solution from the specimen container through the fil-ter paper to collect the residue (spall) from the test specimen.Replace the specimen in the container. Using fingertips and asqueeze bottle, remove loose particles from all surfaces of thespecimen, again being careful to collect all rinse water (or salinesolution) and loose particles in the specimen container. The topsurface of the specimen shall not be immersed in test solution atanytime and the collected rinse water (or saline solution) shall notexceed a depth of 1⁄2 in. (13 mm) in the container. Remove thespecimen from the container, pour the rinse water (or saline solu-tion) through the filter paper, and rinse the specimen containeruntil all residue (spall) in the specimen container is collected onthe filter paper. Rinse the residue from specimens tested in salinesolution three times with water to remove any soluble salt.

8. Calculation and Report8.1 Determine and report the cumulative weight loss of each residue

collection interval expressed in terms of g (lb) and as a percent ofthe calculated initial weight of the specimen, Winitial, determinedin accordance with 7.3.5. Where the coupon thickness is less than1.25 in. (32 mm), the percentage and cumulative weight loss shallbe multiplied by a value equal to the actual thickness in inches(mm) divided by 1.25 in. (32 mm). Report these values for eachspecimen as well as the average of the specimens tested.

Figure 7: Test Specimen in Freeze-Thaw Container

allanblock.com

Page 12: Allan Block Retaining Wall Specification Manual

allanblock.com

Wall Design Checklist

To ensure that the basics are covered in your wall design wehave prepared the following wall design checklist. It may alsobe used by someone checking your work to provide an outlinefor a consistent review process.

Review Wall Design Plans For Special Conditions:

• Site Drainage Layout• Global Stability• Government Regulations• High Water Table• Seismic Design Requirements

Review Wall Design Plans For:• Overall Length of Wall• Station Points• Plan Layout• Elevations• Grades or Slopes Above or Below Walls• Soil Conditions

Retained Soil Friction AngleInfill Soil Friction AngleFoundation Soil Friction AngleCohesion for Foundation SoilSoil Settlement Potential

• Water ManagementAbove GradeBelow GradeExcess Irrigation

• Locations of Catch Basins and Utilities• Compliance to Specifications• Surcharges (live, dead, and location)• Temporary Construction Loads• Snow or Storage Loads• Special Provisions

Design Review:• Grid Length• Grid Spacing• Grid Placed on Consistent Courses• Design Factors of Safety

SlidingOverturningBearingGrid OverstressPullout from SoilPullout from BlockInternal CompoundGlobalSeismic

• Water Management DetailsSurface Water SourcesSubsurface Water SourcesDetails for Low Permeability SoilsLocation and Venting of Toe and Heel Drains

• Overall Quantity EstimatesBlockGridWall Rock

• Construction Details• General Notes and Specifications

Figure 8: Global Stability

Figure 9: Elevation View

Figure 10: Wall Site Components

10

Page 13: Allan Block Retaining Wall Specification Manual

allanblock.com

Construction and Inspection Checklist

Review Construction Details And Procedures:

A. Mark station points for top and bottom of wall elevations andchanges in wall direction.

B. Identify changes in grid lengths, location of grids, and types ofgrid to be used.

C. Determine and locate proper base size for each section of wall.

D. Verify that the correct type and color of block has been orderedand delivered to the job.

E. Verify that the foundation soil and retained soil conform todesign requirements.

F. Verify that infill soil meets design standards.

G. Verify that compaction testing will be performed, who isresponsible, at what intervals of locations along the wall, andwhat coordination will be required.

H. Determine what method will be used to verify constructionmaterials, methods, and sequence of construction. (ie: writtendocumentation of as built, full time inspector on site, photo-graphic documentation.)

I. Wall contractor is responsible for quality control of wall instal-lation per the approved plans. The owner or owner’s represen-tative is responsible for engineering and quality assurance ofthe project.

We have prepared the following Construction and InspectionChecklist to provide a list of items covering the basics for yourretaining wall project. It may also be used during the biddingprocess to ensure that all special provisions are complied with.Always check your local building codes, document any changesto the plan in writing and notify the wall design engineer withany concerns on water management.

Review Wall Design Plans For:

A. Compliance of Site to Latest Site Plan• Does the site plan and wall layout coincide with current Site

Conditions?• Have all slopes above and below the walls been taken into

account on the plans?• Do the section drawings match the topography of the job-site?• Have site utilities been accounted for?• Are there any recommendations for changes to the site plans

to accommodate the wall?

B. Review of Reported Soil Conditions with On-SiteSoils Engineer

• Are on-site soils consistent with soil parameters used in walldesign?

• Does the site show indications of multiple types of soil, andhas this been accounted for?

• Is there evidence of landfill areas on site?• Has the owner contracted with a geotechnical engineering

firm for overall / global stability outside of the wall designenvelope (H tall by the greater of 2H or He + L long)? SeeFigure 12.

C. Review of Above Grade Water Management withProject Civil Engineer

• Has surface runoff been accounted for in the site design?• Will this site be irrigated?• If storm drains become inoperable where will the water

migrate to?• During renovation of land will temporary drainage be an

issue?

D. Review of Below Grade Water Management withWall Design Engineer and General Contractor

• How and where will drain pipes be installed?• Is it possible to vent drain pipes to daylight?• Is venting to a storm drainage system an option?• Will outlets be located and protected from blockage or damage?

E. Surcharges• Have all surcharges been accounted for?• During construction are there any temporary surcharges that

should be accounted for?

Figure 11: Typical Reinforcement Configuration

Figure 12: Wall Design Envelope

11

allanblock.com

Page 14: Allan Block Retaining Wall Specification Manual

Design Details

Detail 2B: Typical Gravity Wall Application - AB Fieldstonewith short anchoring units (SAU)

Detail 3: Allan Block Plantable Wall

12

The following drawings are for general information and use. They are not to be relied upon for any specific project without beingreviewed by an engineer. They are not to be used for construction. It is the sole responsibility of the user to verify the applica-bility of the drawing to their specific project. The drawings are available for download in .dwg or .pdf format at allanblock.com for modifications by an engineer to be site specific to a project.

allanblock.com

Detail 1C: AB Fieldstone with long anchoring units (LAU) Detail 2: Typical Gravity Wall Application

Detail 1: Typical Reinforced Wall Application Detail 1B: Typical Reinforced Wall Application- AB Fieldstone

Page 15: Allan Block Retaining Wall Specification Manual

Detail 7: Taller Height Reinforced Water Applications Detail 8: Low Height Reinforced Water Applications

Detail 5: Swales Detail 6: Chimney and Blanket Drain

13

Detail 4: Alternate Drain

allanblock.com

allanblock.com

Page 16: Allan Block Retaining Wall Specification Manual

Design Details

Detail 13: Step Up at Base Course Detail 14: Grouted Connection

Detail 11: Inside Curve Geogrid Overlap Detail 12: Outside Curve Geogrid Overlap

Detail 9: Inside Corner Geogrid Overlap Detail 10: Outside Corner Geogrid Overlap

14allanblock.com

The following drawings are for general information and use. They are not to be relied upon for any specific project without beingreviewed by an engineer. They are not to be used for construction. It is the sole responsibility of the user to verify the applica-bility of the drawing to their specific project. The drawings are available for download in .dwg or .pdf format at allanblock.com for modifications by an engineer to be site specific to a project.

Page 17: Allan Block Retaining Wall Specification Manual

allanblock.com

Detail 19: Wind Bearing Fence or Railing, Option 2 Detail 20: Masonry Parapet

Detail 17: Alternate Fence Footing with SLEEVE-ITFooting System

Detail 18: Wind Bearing Fence or Railing, Option 1

Detail 15: Non-Wind Bearing Fence or Railing, Option 1 Detail 16: Non-Wind Bearing Fence or Railing, Option 2

15

allanblock.com

Page 18: Allan Block Retaining Wall Specification Manual

allanblock.com

Design Details

Detail 25: Concrete Collar Storm Water Pipe Outlet, Section and Elevation View

Detail 23: Impact Roadway or Parking Guard Rail Detail 24: No-Fines Concrete

Detail 21: Double Wall Parapet Detail 22: Non-Impact Parking Railing

16

The following drawings are for general information and use. They are not to be relied upon for any specific project without beingreviewed by an engineer. They are not to be used for construction. It is the sole responsibility of the user to verify the applica-bility of the drawing to their specific project. The drawings are available for download in .dwg or .pdf format at allanblock.com for modifications by an engineer to be site specific to a project.

Page 19: Allan Block Retaining Wall Specification Manual

allanblock.com

Detail 30: Allan Block Facing to Soil Nail ReinforcedShotcrete Wall

Detail 31: Allan Block Facing to Earth Anchor Tiebacks

Detail 28: Allan Block Masonry Reinforced Typical Section

Detail 29: Allan Block Veneer Typical Section

Detail 26: Terraced Section Detail 27: Allan Block Double Wall Typical Section

17

allanblock.com

Page 20: Allan Block Retaining Wall Specification Manual

Design Methods

The following information is intended to provide insight into thebasic concepts behind an Allan Block retaining wall design. Acomplete review of the methodology and the equations may befound by reviewing the Allan Block Engineering Manual.

Allan Block walls are most often designed and constructed as eithergravity walls or coherent gravity masses, but can be used in manydifferent types of retaining wall applications;

Gravity Walls are structures that resist the pressures from theretained soil with the weight of the facing. Under optimum condi-tions Allan Block gravity walls may be constructed up to 5.5 ft (1.7m).

Coherent Gravity Masses act as large composite structures.These structures are a flexible unified mass that resist the forcesfrom the retained soil in the same manner as a simple gravity wall.These composite structures are composed of geogrid reinforced soilmasses with Allan Block Retaining Walls used as a durable, aesthet-ically pleasing, facing material.

Other reinforcement options include Tie Back Walls or MasonryReinforcement. Tie Backs utilize Allan Block as a hard facing withsome type of anchor used to tie back the facing. Designs of this typedevelop loads at the face and end of the anchor and do not performas a coherent gravity mass. Masonry reinforcement applicationsuse grout and rebar through the cores of the Allan Block to create ahigh strength cantilever wall.

Allan Block Corporation has developed several tools to help thedesign engineer through the design process. Available toolsinclude:

Allan Block Engineering Manual— providing detailed calcu-lations and commentary for the methods and processes used inthe design procedure.

AB Walls 10™ — a Windows based software design programthat is a tool for the designer and allows configuration of a wallstructure that is appropriate for the site and application. Thissoftware also allows the designer to calculate multiple cross sec-tions, elevation views, plan views and material estimates thatare all coordinated and export them to a DXF CAD format.

Hand Calculations— a MathCAD based file that contains all ofthe detailed calculations for the engineer to review as well asproviding the engineer the ability to revise the equations to fitthe particular need of the job in process while providing amethod to cross check the output of AB Walls 10™.

The basic elements of the design process require an understandingof the properties of the soils to be used behind and below the retain-ing wall, terrain changes above or below the retaining structure, sur-charges located above the wall, and seismic loading if appropriate.

The design calculation process has two categories of stability to bechecked; external stability and internal stability.

External stability analysis applies to the outside of the retaining wallor reinforced mass. The forces exerted on the structure are calcu-lated by using an equation developed by Coulomb in 1776 calledactive earth pressure. The term “active” refers to the ability of thewall structure to rotate and bend in small incrementswithout adversely affecting the stability. This equation takes

into account the strength of the soil, slope of the backfill, the bat-ter of the retaining wall, and the effects of the friction between theretained soil and the retaining wall structure. When addressingexternal stability the engineer will design for adequate factors ofsafety with respect to overturning (eccentricity), sliding, bearingcapacity, and global stability.

Internal stability applies to forces and reactions within the blocksand geogrid reinforcement. Here a designer will check for ade-quacy in block to reinforcement connection strength, reinforce-ment pullout from the soil, reinforcement overstress and, InternalCompound Stability (ICS). See the AB Engineering Manual(Chapter 6) for a complete disclosure on ICS calculations. Seegeogrid reinforcement specifications section for further explana-tion of how geogrid works. Refer to Page 20.

Retaining wall designs rely heavily on the site soil properties. Atthe beginning of the design process a value is assigned to the soilthat numerically describes how much resistance to movementthis soil possesses. This resistance to movement is called theinternal friction angle (�, PHI). As the internal friction of the soilincreases it exerts less force on the retaining wall. Soils that con-tain high percentages of sands and gravel have higher frictionangles, drain away excess water more readily, and are easier touse during the construction process. For these reasons soils withsand and gravel are preferred materials to use when constructinga reinforced soil structure.

Soils exhibit another property that resists movement called cohe-sion, which is typically found in clay soils. Cohesion may be clas-sified as temporary strength because it depends greatly on mois-ture content of the soil, because of this it is not utilized in mostelements of the design process.

Water pressure is not considered in a typical design. Becausewater adversely affects the strength and weight properties of soilwithin the composite structure, primary consideration should begiven to manage water away from the retaining wall structure.These structures have been developed to drain away only inci-dental water which may infiltrate the mass during or after con-struction. The wall rock and drain pipe are included to keep thesurrounding soil at its optimum moisture content.

A designer must also consider aspects of the retaining wall thatare not solved in calculations. They must address all the elementssurrounding the structure and set construction standards.Compaction requirements, geogrid spacing, and geogrid lengthare a few of these items to consider. (See Allan Block Tech Sheet#598 – Designing Balance Into Your Retaining Wall Project for fur-ther information).

Allan Block products can be used for almost any application.Incorporating these design concepts will help any engineer createa safe, aesthetically pleasing, and cost effective retaining wall.

F = (0.5)(�)(Ka)(H)2

csc(�) sin (�-�)sin(���w) � sin(���w) sin(��i)

sin(��i)

� = Soil Unit Weight

[ ]Ka =2

18allanblock.com

Page 21: Allan Block Retaining Wall Specification Manual

allanblock.com

Allowable Construction Tolerances

19

Figure 13: Vertical Control

Figure 14: Differential Settlement

Figure 15: Horizontal Control Figure 16: Rotation

Construction Tolerances

To ensure that acceptable work standards are understood duringretaining wall installation, construction tolerances need to beestablished. These construction tolerances should consider thatthe retaining wall is designed to be a flexible structure that toler-ates horizontal and vertical variation. However, too much varia-tion can affect the structural stability of the wall.

To maintain horizontal and vertical control, adjustments may berequired during modular block installation. Even with tight qual-ity control procedures by block manufactures, modular blockunits may vary in height. Shimming a maximum of 0.125 in. (3 mm) per block is acceptable construction practice. It is recom-mended that shimming material be asphaltic or non-degradableproducts.

Acceptable construction tolerances are illustrated in Figures 13thru 16.

Differential Settlement

Foundation settlements must be estimated with great care for build-ings, bridges, towers, power plants, and similar high-cost structures.For structures such as fills, earth dams, levees, and retaining walls agreater margin of error in settlements can usually be tolerated. Theconstruction method of placing the dry-stacked mortarless Allan Blockon an aggregate leveling pad creates a flexible but stable retainingwall. Settlement errors that are acceptable while maintaining struc-tural integrity include large total wall settlement and moderate differ-ential settlement as depicted in Figure 14.

Settlement occurs when the weight of the retaining wall structureexceeds the bearing capacity of the soil. Cohesionless soils consist-ing of sands and gravels often exhibit very little settlement with mostof the settlement occurring during or shortly after wall construction.Cohesive soils with high moisture content have the potential for largetime-depended settlement because the weight of the wall can actual-ly compress the foundation soil. The settlement can be estimatedusing conventional one-dimensional consolidation calculations.When anticipated settlement is greater than the construction toler-ances, special design and construction steps need to be taken.

Post Construction Finish and Appearance

Depending on wall heights, surcharges, soil conditions and founda-tion materials, some stress cracks may occur in the wall during andafter construction. Since Allan Block walls are flexible structures,some cracking of block is likely, as are spaces between blocks as thewall moves. These openings should not exceed 0.25 in. (6 mm) anddo not affect the structural integrity of the wall.

allanblock.com

Page 22: Allan Block Retaining Wall Specification Manual

allanblock.com

Specification Guidelines: Geogrid Reinforcement

Every building we live and work in calls on various materials toblend strength and functionality to create a finished product thatprovides us with a safe living space incorporating the amenities thatwe desire. The development of geosynthetics to reinforce soil mass-es has paved the way to a new industry utilizing concrete block as afacing for these composite retaining wall structures.

Allan Block walls that cannot rely on the weight of the block alone toretain soil typically use geogrid reinforcement to develop a largermass. Geogrids are flexible synthetic meshes produced from highstrength polyester fibers encapsulated in protective coating. Theywork perfectly with on-site soils and modular retaining wall prod-ucts because of their strength, durability, workability and overalleconomy.

Soil reinforcement is a concept that dates back to the times ofBabylonia and the construction of the Great Wall of China when non-degradable tree branches were placed in between layers of com-pacted soil. Whether it is tree branches or coated synthetic fibers,these products are used to create a reinforced coherent massbehind the retaining wall by stabilizing the mass and increasing theinternal strength of the soil.

Geogrid interacts with soil by using friction as well as passive resist-ance. This interaction happens both in the infill soil and the "rock-lock" connection of the block to the geogrid. The block to geogridconnection is created when the gravel material in the hollow coresof the Allan Block units are compacted, interlocking the gravel with

Geogrid Reinforcement Specifications

the apertures of the geogrid. The gravel helps creates superiorresistance to pullout because it is a uniform, multi-point connec-tion. With over 200 million square feet of Allan Block products inthe ground we have not had one case of the retaining wall blockpulling away from the soil mass.

Most geogrid mats are stronger in one direction of orientation.The primary strength direction is commonly referred to as themachine or roll direction. Geogrid mats are typically rolled per-pendicular to the face of the wall to utilize the long term allowabledesign strength (LTADS) of the geogrid. The transverse strandsare in place to maintain consistent spacing of the load carryingstrands, and can be half the strength of the primary strands. TheLTADS value of geogrid accounts for varying soil strengths, instal-lation damage, chemical degradation, and creep.

The mechanical properties of various brands of geogrid are givenin Table 3. LTADS values are given by the geogrid manufactur-ers testing results. Allan Block connection strengths are perASTM D6638 (also explained in NCMA SRWU-1).

20

AB® Collection

AB Europa® Collection

AB Fieldstone® Collection

AB Stones AB Rocks AB Classic AB Vertical AB Jumbo Junior AB Lite Stones AB Junior Lite

AB Dover AB Palermo AB Barcelona AB Bordeaux

812 facing unitw/SAU

824 facing unitw/SAU

812 facing unitw/LAU

824 facing unitw/LAU

SAU - short anchoring unit LAU - long anchoring unit

Page 23: Allan Block Retaining Wall Specification Manual

allanblock.com21

Typical Geogrid Specifications and Connection Testing Results

AB Full-Size Units

AB Fieldstone Units

Table 3: Geogrid Engineering Properties

The information in this chart has been taken from published literature and is believed to be accurate. Consult the Allan Block EngineeringDepartment for details at 800-899-5309.

Geogrid Type

Long Term Allowable Design Strength, LTDS, lb/ft (kN/m) Reduction

Factor Creep, RFcr

Peak Connection Strength Equations, P, lb/ft (kN/m) Normal Load

Intercept lb/ft (kN/m)Sand-Silt-

ClaySand-Gravel Gravel Segment 1 Segment 2

Strata Systems, 380 Dahlonega Road, Cummings, GA 30040 800-680-7750

Strata 150 1008(14.70)

962(14.10)

882(12.90) 1.610

Tu = 930 lb/ft + Ntan(24°)(Tu = 13.5 kN/m + Ntan(24°))

- -

Strata 200 1613(23.60)

1540(22.50)

1412(20.60) 1.610

Tu = 948 lb/ft + Ntan(31°)(Tu = 13.8 kN/m + Ntan(31°))

- -

Strata 350 2259(33.00)

2156(31.50)

1976(28.90) 1.610

Tu = 900 lb/ft + Ntan(23°)(Tu = 13.1 kN/m+Ntan(23°))

- -

Strata 500 2796(40.80)

2669(39.00)

2447(35.70) 1.610

Tu = 848 lb/ft + Ntan(30°)(Tu = 12.4 kN/m + Ntan(30°))

- -

Tencate Nicolon, 365 South Holland Drive, Pendergrass, GA 30567 888-795-0808

Miragrid2XT

949(13.80)

839(12.20)

727(10.60) 1.670

Tu1 = 125.6 lb/ft + Ntan(58.48°)(Tu1 = 1.8 kN/m + Ntan(58.48°))

Tu2 = 1623.5 lb/ft(Tu2 = 23.65 kN/m)

918.6(13.40)

Miragrid3XT

1558(22.70)

1423(20.80)

1309(19.10) 1.670

Tu = 1047 lb/ft + Ntan(33°)(Tu = 15.3 kN/m + Ntan(33°))

- -

Miragrid5XT

2234(32.60)

2040(29.80)

1876(27.40) 1.670

Tu1 = 983 lb/ft + Ntan(37°)(Tu1 = 14.3 kN/m + Ntan(37°))

Tu2 = 1756 lb/ft) + Ntan(20°)(Tu2 = 25.6 kN/m + Ntan(20°))

1984.2(28.95)

Miragrid7XT

2961(43.20)

2704(39.40)

2487(36.30) 1.670

Tu = 1065.4 lb/ft + Ntan(25.62°)(Tu = 15.52 kN/m + Ntan(25.62°))

- -

Miragrid8XT

3089(45.07)

3007(43.87)

2719(39.87) 1.670

Tu1 = 1063 lb/ft + Ntan(40°)(Tu1 = 15.51 kN/m + Ntan(40°))

Tu2 = 2872 lb/ft(Tu2 = 41.90 kN/m)

2155.9(31.45)

Miragrid10XT

4116(60.05)

4006(58.45)

3622(52.84) 1.670

Tu1 = 513 lb/ft + Ntan(52°)(Tu1 = 7.48 kN/m + Ntan(52°))

Tu2 = 1426 lb/ft + Ntan(23°)(Tu2 = 20.81 kN/m + Ntan(23°))

1067.3(15.57)

Huesker - 11107 - A South Commerce Blvd, Charlotte, NC 28273 800-942-9418

Fortrac35/20-20

1322(19.30)

1300(19.00)

1243(18.10) 1.572

Tu1 = 728 lb/ft + Ntan(18°)(Tu1 = 10.6 kN/m + Ntan(18°))

Tu2 = 958 lb/ft + Ntan(8°)(Tu2 = 14.0 kN/m + Ntan(8°))

1247.4(18.20)

Fortrac55/30-20

1936(28.30)

1882(27.50)

1783(26.00) 1.655

Tu1 = 1090 lb/ft + Ntan(27°)(Tu1 = 15.9 kN/m + Ntan(27°))

Tu2 = 1906 lb/ft + Ntan(4°)(Tu2 = 27.8 kN/m + Ntan(4°))

1856.2(27.08)

Fortrac80/30-20

2815(41.10)

2815(41.10)

2615(38.20) 1.655

Tu1 = 680 lb/ft + Ntan(57°)(Tu1 = 9.92 kN/m + Ntan(57°))

Tu2 = 2143 lb/ft + Ntan(14°)(Tu2 = 31.27 kN/m + Ntan(14°))

1133.6(16.54)

Geogrid Type

Long Term Allowable Design Strength, LTDS, lb/ft (kN/m) Reduction

Factor Creep, RFcr

Peak Connection Strength Equations, P, lb/ft (kN/m) Normal Load

Intercept lb/ft (kN/m)Sand-Silt-

ClaySand-Gravel Gravel Segment 1 Segment 2

Strata Systems, 380 Dahlonega Road, Cummings, GA 30040 800-680-7750

Strata 150 1008(14.70)

962(14.10)

882(12.90) 1.610

Tu = 853 lb/ft + Ntan(10°)(Tu = 12.4 kN/m + Ntan(10°))

Tu2 = 1200 lb/ft(Tu2 = 17.5 kN/m)

-

Strata 200 1613(23.60)

1540(22.50)

1412(20.60) 1.610

Tu = 784 lb/ft + Ntan(35°)(Tu = 11.4 kN/m + Ntan(35°))

Tu2 = 1875 lb/ft)(Tu2 = 27.3 kN/m)

-

Strata 350 2259(33.00)

2156(31.50)

1976(28.90) 1.610

Tu = 761 lb/ft + Ntan(32°)(Tu = 11.1 kN/m+Ntan(32°))

Tu2 = 1908 lb/ft + Ntan(5°)(Tu2 = 27.8 kN/m + Ntan(5°))

-

Tencate Nicolon, 365 South Holland Drive, Pendergrass, GA 30567 888-795-0808

Miragrid2XT

949(13.80)

839(12.20)

727(10.60) 1.670

Tu1 = 893 lb/ft + Ntan(31°)(Tu1 = 13.0 kN/m + Ntan(31°))

Tu2 = 1516 lb/ft + Ntan(5°)(Tu2 = 22.1 kN/m) + Ntan(5°))

1213.5(17.70)

Miragrid3XT

1558(22.70)

1423(20.80)

1309(19.10) 1.670

Tu = 829 lb/ft + Ntan(39°)(Tu = 12.1 kN/m + Ntan(39°))

Tu2 = 1715 lb/ft + Ntan(6°)(Tu2 = 25.0 kN/m + Ntan(6°))

1257.3(18.34)

Miragrid5XT

2234(32.60)

2040(29.80)

1876(27.40) 1.670

Tu1 = 778 lb/ft + Ntan(43°)(Tu1 = 11.3 kN/m + Ntan(43°))

Tu2 = 2066 lb/ft + Ntan(18°)(Tu2 = 30.1 kN/m + Ntan(18°))

2119.8(30.93)

Huesker - 11107 - A South Commerce Blvd, Charlotte, NC 28273 800-942-9418

Fortrac35/20-20

1322(19.30)

1300(19.00)

1243(18.10) 1.572

Tu1 = 769 lb/ft + Ntan(6°)(Tu1 = 11.2 kN/m + Ntan(6°))

- -

Fortrac55/30-20

1936(28.30)

1882(27.50)

1783(26.00) 1.655

Tu1 = 1444 lb/ft + Ntan(3°)(Tu1 = 21.0 kN/m + Ntan(3°))

- -

allanblock.com

Page 24: Allan Block Retaining Wall Specification Manual

© 2012, 2009, 2007, 2005, 2002, 2000 Allan Block Corporation, Bloomington, MN Phone 952-835-5309 Fax 952-835-0013, DOC. #R0901-0812

This technical specification manual will allow a wall designer tosource and reference specific information for use in developingproject documents. The information contained in this manualis for use with Allan Block products only.