“All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Dec 18, 2015

Download

Documents

Rodney Crawford
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 2: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 1 : 1.”

( 45 degrees )

Type B may be simply sloped or benched.

Page 3: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 1 : 1.”

( 45 degrees )

Type B may be simply sloped or benched.

The blue slope represents 1: 1 (45 degrees)

Page 4: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 1 : 1.”

( 45 degrees )

Type B may be benched.

Page 5: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 1 : 1.”

( 45 degrees )

Type B may be benched.

Page 6: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Will this work?

No benching in Type C soil.

If the soil was Type A, the degree of these benched slopes would be too steep.

Page 7: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 3/4 : 1.”

( 53 degrees )

Type A may be simply sloped or benched.

Page 8: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 3/4 : 1.”

( 53 degrees )

Type A may be simply sloped or benched.

The blue slope represents 1: 1 (45 degrees)

Page 9: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“Simple slope excavations which are open 24 hours or less (short term) and which are 12 feet or less in

depth...

...shall have a maximum allowable slope of 1/2 : 1.”

( 63 degrees )

Type A (short term dig)

The blue slope represents 1: 1 (45 degrees)

Page 10: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Sloping & Benching Tips

The maximum allowable slopes apply when above a shield, too.

Page 11: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Sloping & Benching Tips

The top of the shield needs to be at least 18 inches above the soil.

Page 12: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Type C soil cannot be benched.

(even if incorrectly identified as Type B)

No sloping or benching when deeper than 20 feet.

Unless a Registered Professional Engineer designs the sloping or benching system.

The maximum allowable slopes are maximums.

Many factors can reduce the maximum allowable.

Sloping and Benching Tips

Page 13: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Sloping and Benching

Page 14: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 15: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Working in the Affected Zone

Page 16: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Use 45 degrees to determine the affected zone.

(Some say the Affected Zoneshould be even bigger)

Where is the Affected Zone?

Page 17: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Most cave-ins occur in the affected zone

(that’s where the hole is)

Cave-ins strike the Affected Zone.

Page 18: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Improper sloping or benching

Mass of spoil pile or equipment

Vibrations from traffic, equipment, etc.

How long the excavation is open

Rain

What are some causes of cave-ins?

Cave-ins happen in the Affected Zone...

Page 19: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Improper sloping or benching

Mass of spoil pile or equipment

Vibrations from traffic, equipment, etc.

How long the excavation is open

Rain

What are some causes of cave-ins?

These are the factors we can control.

Page 20: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 21: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Greenwood rescuers pull injured worker from trench

“The construction crew hadn’t built a trench box to prevent the sides of the trench from collapsing, so firefighters were forced to spend about an hour shoring up the sides of the ditch before they were able to give assistance. The man was rescued about 80 minutes after the accident...” These guys will not

enter an unprotected trench.

(It caved in)

Page 22: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Dealing with Spoil Piles

Page 23: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Keep any pile two feet from the excavation.

Ideally, keep them farther away.

Is the spoil pile near the hole in the ground?

If so, the maximum height should be two or three feet.

More liberty may be taken the farther the spoil pile is from the excavation.

Registered Professional Engineers (RPEs) will include the height of spoil piles in their tabulated data.

Dealing with Spoil Piles

Page 24: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“ When surcharge loads from stored material or equipment, operating equipment, or traffic are present...

Spoil, Equipment, and Slopes

Page 25: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“All simple slope excavations 20 feet or less in depth...

...shall have a maximum allowable slope of 1 ½ : 1.”

( 34 degrees )

Remember this?

The blue slope represents 1: 1 (45 degrees)

Page 26: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

“ When surcharge loads from stored material or equipment, operating equipment, or traffic are present...

... a competent person shall determine the degree to which the actual slope must be reduced below the maximum slope. ”

Spoil, Equipment, and Slopes

Page 27: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Sloping the spoil pile may reducethe likelihood of cave-ins.

Walls are sloped. Spoil piles can be, too.

Page 28: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Dealing with Equipment

Page 29: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Is equipment being used near the excavation?

Probably, it’s a construction site.

But, there may be equipment not being used.

If machinery is not being used, move it away.

Are there dump trucks on site?

Are they loading or unloading materials?

If not, get them out of there ASAP.

Dealing with Equipment

Page 30: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Dealing with Equipment

Page 31: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Working in the Affected Zone

Page 32: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 33: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Shields and Shores

Page 34: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Here’s a shield.

Page 35: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

1926.652(c)

An engineer designs it and you build it according to specs.

An engineer designs it and somebody else builds it for you.

and, then you use it according to specs.

If using shores or shields, they need to be used as recommended, advised, and specified by the manufacturer.

Have the user’s manual available.

aka “Tabulated Data”

Shield Design Options

Page 36: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Here’s another shield.

Page 37: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

There’s no shield here.

Page 38: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

The rules for working in or around shields.

Stay inside it! That’s what it’s there for.

Is there a ladder within 25 feet of any worker?that means a ladder inside the box.

No moving the shield when workers are inside it.

No digging beyond two feet under the box.

Has lateral movement been restricted?

Page 39: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

A big chunk of soil moves a big box easily.

Page 40: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

When the box is snug, it can’t go anywhere.

Page 41: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

What if a shield is damaged?

It happens. In general, damaged units are not allowed.

If they’re found to be unsafe, then they’re not used.

If a shield or box is banged up...

The competent person takes a look at it.

If the CP says so, the box is back in action.

If the CP is unsure, an engineer is brought in to look at it.

The engineer will say what to do.

In the meantime, the box is not used.

Page 42: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Protect the protected workers, too.

Are there loose materials that could roll down into the protected area below?

Scrape away loose debris from sloped or benched walls. If it’s not there, it’s not a hazard.

Install protective barricades or nets along the face to stop or slow incoming debris.

Workers on slopes could become hazards to those below. Permit no work along the face without a system of protection (barricade, net) for those below.

Page 43: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Use Appendices A & C.

Not allowed when deeper than 20 feet.

Timber Shoring

Page 44: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Douglas fir or equivalent (with a bending strength not less than 1500 psi)

Depending on the application, you may use...

Mixed oak or equivalent (with a bending strength not less than 850 psi)

These materials can be expensive, one of the reasons timber shoring is not common.

Page 45: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Use Appendix D.

Not allowed when deeper than 20 feet.

Aluminum Hydraulic Shoring

Page 46: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

MacGyver it yourself in accordance with Appendix D.

Buy a kit and use it exactly the way the manufacturer says.

Aluminum Hydraulic Shoring

If going this route, there are two options

Page 47: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Shields and Shores

Page 48: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 49: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Other Matters

Page 50: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

1926.20(b)(4)

The employer shall permit only those employees qualified by training or experience to operate equipment and machinery.

Only qualified people operate equipment.

Get away from that!

Page 51: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Do an inspection before every shift.

Is that safety glass in the cab?

Wear the seat belt.

(Unless there’s no rollover protective structure)

Is there a warning or signaling system?If you can’t see the edge, use signals.Is there a reverse signal alarm?

General Safety Ideas for Equipment

Page 52: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Is the equipment unattended?

Set the parking brake (if equipped)

Use chocks or something to secure it.

If left overnight, make it visible with reflectors, flashing lights, or barricades.

Always lower the bucket to ground when not in use, even if temporarily.

Clear loose debris from dump trucks before you hit the highway and the DOT sees you.

General Safety Ideas for Equipment

Page 53: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

or, visit http://www.call811.com

Mark the locations

Check local digging laws and requirements.

Call 811

Before you dig, you should...

Page 54: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Estimating the location of utilities (by marking) isn’t enough...

Before digging starts, an exact determination must be made.

No one else can use your marking lines, and vice versa.

Underground Utilities

Page 55: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

APWA Uniform Color Code

Page 56: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

1926.651(i)(2)

Excavation below the level of the base or footing of any foundation or retaining wall that could be reasonably expected to pose a hazard to employees shall not be permitted except when:

A support system, such as underpinning, is provided to ensure the safety of employees and the stability of the structure; or

The excavation is in stable rock; or

A registered professional engineer says the structure will not be affected by activity.

The RPE says activity will not pose a hazard to employees.

Undercutting and Underpinning

Page 57: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Don’t undercut without first supporting.

Page 58: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

1926.651(i)(2)

Excavation below the level of the base or footing of any foundation or retaining wall that could be reasonably expected to pose a hazard to employees shall not be permitted except when:

A support system, such as underpinning, is provided to ensure the safety of employees and the stability of the structure; or

The excavation is in stable rock; or

A registered professional engineer says the structure will not be affected by activity.

The RPE says activity will not pose a hazard to employees.

Undercutting and Underpinning

Page 59: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

A back-up plan in case the hydrant goes.

Page 60: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

If there’s less than 19.5% oxygen in the air you’ll be breathing

or, if it’s reasonable to assume that’s the case...

... it’s time for testing.

Confined Spaces and Hazardous Atmospheres

Page 61: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

You’re going to need protection.

PPE

Ventilation

Monitors

Rescue equipment (just in case)

If it’s hazardous in there...

Page 62: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Guardrails. Fences. Barricades.

Walkways or access ramps six feet or greater above next lowest level.

A pit or well six feet or greater in depth

If foliage or other visual barrier obstructs the excavation’s edges...

Then you need to barricade the area.

Fall protection while on the ground?

Page 63: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Other Matters

Page 64: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.
Page 65: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Quick Review

Page 66: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Mass of spoil pile or equipment

Vibrations from traffic, equipment, etc.

Improper sloping or benching

How long the excavation is open

Rain

Common causes of cave-ins

Page 67: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Can identify and is authorized to remedy hazards.

Is familiar with protective systems (shields, shores, and sloping configurations), soils analysis, and standard requirements.

Does lots of inspections.

Consults with RPEs in certain situations.

A competent person...

Do you have authority?

Page 68: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Stable Rock = stable rock

Type A: pristine clay More cohesive

Type B: angular gravel

Type C: anything less Less cohesive

Soil Types

There are many downgrading conditions.

Water, vibration, prior activity, weather, stability ...

Page 69: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Let the shield protect you.

Stay inside the trench box, not a few feet from it.

Proper exit should involve the ladder...

... which is inside the box,and no more than 25 feet away.

Don’t move a shield with workers inside.

Is lateral movement of the shield minimized?

Dig as little below a box as possible. Two feet is the maximum allowed by OSHA.

Page 70: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

The maximum allowable sloping configurations are the maximums.

Any number of reasons could reduce them.

The configurations apply above shields, too.

Benching isn’t allowed in Type C soil.

Anything deeper than 20 feet must be designed by a Registered Professional Engineer (RPE).

Simple Slopes and Benches

Page 71: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Quick Review

Page 72: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Call 811 – Know what’s belowhttp://www.call811.com/

Safety and Health Topics: Trenching and Excavationhttp://www.osha.gov/SLTC/trenchingexcavation/construction.html

OSHA Construction eTool: Trenching and Excavationhttp://www.osha.gov/SLTC/etools/construction/trenching/mainpage.html

Trench Safety Version 4.0http://www.trenchsafety.org/

Page 73: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.

Excavation1926 Subpart P for construction

www.montanasafety.com

Maurizio DelcaroOccupational Health & Safety SpecialistThat’s it!

Questions, Comments?

Thanks for attending!

Page 74: “All simple slope excavations 20 feet or less in depth......shall have a maximum allowable slope of 1 : 1.” ( 45 degrees ) Type B may be simply sloped.