Aleksandra RAKOWSKA Aleksandra RAKOWSKA J J o o zef LORENC zef LORENC Witold HOPPEL Witold HOPPEL Poznań University of Technology Institute of Electrical Power Engineering DISTURBANCES IN POLISH DISTURBANCES IN POLISH 15 KV NETWORK BY GROUND 15 KV NETWORK BY GROUND SHORT-CIRCUITS SHORT-CIRCUITS
14
Embed
Aleksandra RAKOWSKA Jozef LORENC Witold HOPPEL Poznań University of Technology Institute of Electrical Power Engineering DISTURBANCES IN POLISH 15 KV NETWORK.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Aleksandra Aleksandra RAKOWSKARAKOWSKAJJoozef LORENCzef LORENCWitold HOPPELWitold HOPPELPoznań University of TechnologyInstitute of Electrical Power Engineering
DISTURBANCES IN POLISH DISTURBANCES IN POLISH 15 KV NETWORK BY 15 KV NETWORK BY
GROUND SHORT-CIRCUITSGROUND SHORT-CIRCUITS
DISTURBANCES IN POLISH DISTURBANCES IN POLISH 15 KV NETWORK BY 15 KV NETWORK BY
GROUND SHORT-CIRCUITSGROUND SHORT-CIRCUITS
Polish MV network contains mainly overhead
lines but every year the percentage share of
cables
in electrical power network is increasing.
This tendency can be observed especially for
medium voltage system.
MV power lines serviced by Utilities
at the end of 2001:
OHL- 169 629 km (76%)
CL- 54 345 km (24%)
The percentage share of various types of cable insulation
in the total length of MV cables in Polish network
1989 1991 1993 1995 1997 1999
tota
l len
gth
[ %]
year
20
40
60
80
70
50
30
10
Relative failure rate
Overhead lines
Cable lines
Average 1,0 3,7
Maximum 2,5 7,4
Minimum 0,45 1,3
Relative failure rate for MV overhead and cable lines – data for all Utilities
Types of MV lines for 5 exemplary utilities
0
20
40
60
80
100
1 2 3 4 5
Utility
Per
cen
tag
e sh
are
of
MV
lin
es [
%] OHL
CL
* Five Polish Utilities participate in survey on failuresfor cable (11 308 km) and overhead (47 929 km) lines
PAP77%
PE10%
XLPE13%
Shares of cable types installed in the MV network and cable failures for different type of insulation
in 5 exemplary Utilities at the end of 2000
PE63%
PAP36% XLPE
1%
The first generation of design – taped screen
0
20
40
60
80
100
1 2 3 4 5
Utility
Fai
lure
rat
e [%
]
Wu OHL
Wu CL
Percentage share of cable and overhead lines failure rates – total for 5 Utilities
The 90’s saw the admittance criteria, developed
in the Institute of Electric Power Engineering of
Poznan University of Technology become
commonly operated.
Large part of them are in analog technique
(90’s),
but for new substations - there are always
digital admittance earth fault protection
systems.
With admittance earth fault protection systems
some Utilities achieved that described
protection systems allow to detect at least 95%
of all earth faults .
The admittance earth fault protection systems can be divided with respect to criteria on which they rely:
- excess admittance Yo>,
- excess conductance Go>,
- conductance-directional Gok,
- susceptance-directional Bok,
- comparative-admittance Yyo.
Admitance criteria were described during CIRED Conference Birmingham - IEE Publication No 438,
1997
Near 80% of Polish HV/MV power substations work with neutral point, using Petersen coil (about 2000 substations).
There is a need to assure proper conditions for good protection function – shunting of Petersen coil with resistor during protection operation. It is the most popular configuration.
There are configurations with resistor switched on permanently, too.
Transient switching on means current about 15-25 A on primary winding – better service conditions for protection system.
Resistor switched on permanently means also additional suppression of overvoltages (it is important especially for cable lines, with aged insulation or with first generation of extruded insulation). That’s why some Utilities use such configuration but it has to be said, that it lowers protection conditions in OH lines – risk of electric shock.
Based on service experiences – it was found that
admittance earth fault protection are very
effective for
intermittent fault, too.
In present time – for a new substation – all
equipment suppliers are asked by Utilities to use
the admittance earth fault protection (now
foreign well-known companies have been asked
to put also this element additionally to their
systems).
Widely carried out research and construction works,
having resulted in analogue and modern digital
solutions, combined with providing professional
training and expertise made admittance protections -
a widely used protection system, implemented in
nearly 10 thousand MV line fields in Polish
distribution networks.
Based on service experience achieved in the power
substations we can conclude, that described
protection systems allow to detect at least 95% of all